This document is an Addendum to FAR 52.212-1 and 52.212-2 for a Total Small Business Set-aside contract for PDO HAZMAT Building Air Conditioner Replacement. The Bureau of Land Management will award a Firm Fixed Price Contract to the lowest-priced offeror who meets all evaluation criteria, with submissions due by July 11, 2025 at 12:00 PM MDT. Offerors must provide a technical statement including equipment specifications and schedule, three references from similar projects within the past three years, and complete the quote template.
The evaluation process will rank quotes initially by price, then assess them against pass/fail criteria for Schedule, Equipment, and Past Experience. The lowest-priced quote receiving acceptable ratings will then be evaluated for Past Performance, with an "Excellent Confidence" rating determining the best value. If no offeror receives an "Excellent Confidence" rating, the award will go to the offeror with the highest past performance rating, lowest price, and acceptable ratings across all factors. Past performance will be based on references and may include information from the Department of the Interior's Contractor Performance Assessment Reporting System.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Sol_140L6425Q0021_Amd_0002.pdf | ||
| Attachment_6_Q_A_0001.pdf | ||
| Sol_140L6425Q0021_Amd_0001.pdf | ||
| Attachment_3_Wage_Determination.pdf | ||
| Combined_Synopsis_and_Solicitation.pdf | ||
| Attachment_2_Clauses_and_Provisions.pdf | ||
| Sol_140L6425Q0021.pdf | ||
| Attachment_5_Quote_Template.docx | DOCX document | |
| Attachment_1_Statement_of_Work.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Addendum to FAR 52.212-1 – Instructions to Offerors – Commercial Items
This acquisition will be solicited and awarded in accordance with Federal Acquisition Regulation (FAR) Part 12 -- Acquisition of Commercial Items and FAR Part 13 – Simplified Acquisition Procedures.
A Firm Fixed Price Contract will be awarded to the Offeror whose quote conforms to the solicitation requirements and represents the best value to the Government, in accordance with the evaluation factors defined below. Offerors must be deemed a responsible prospective contractor
IAW FAR 9.1.
This acquisition is being solicited as a Total Small Business Set-aside.
INSTRUCTIONS TO OFFERORS: All quotes must include all data and information requested and must be submitted in accordance with these instructions. Any offeror who submits an incomplete package may be considered nonresponsive. All quotes are expected to conform to the solicitation provisions and be prepared in accordance with this section.
Return the following items with your response:
a. Technical Statement: Provide a brief summary of how you intend to meet the requirements outlined in the scope of work. The Technical Statement shall include the following:
i. Equipment type and specifications.
ii. Schedule: Provide a detailed schedule consistent with the period of performance.
b. References: Submit three references for jobs completed within the last three years, which are similar in size and scope to this project. Referenced projects must demonstrate the experience, capacity, and expertise to perform the required tasks within the period of performance. References will be used to determine Past Experience and Past Performance.
c. Price: Fill out Attachment 5. Quote Template.
QUESTIONS: All questions shall be submitted in writing via email to Rachel Henriques at rhenriques@blm.gov, no later than July7, 2025, by 12:00 PM MDT.
QUOTES: All quotes shall be submitted electronically to Rachel Henriques at rhenriques@blm.gov, no later than July 11, 2025, by 12:00 PM MDT.
Addendum to FAR 52.212-2 – Evaluation – Commercial Products and Commercial Services
Basis for Contract Award: This contract will be awarded in accordance with FAR 13, and consider the following factors: Schedule, Equipment, Past Experience, Past Performance, and Price. Initially, quotes will be ranked according to total price.
Starting with the lowest priced quote, the Government will determine if the quote meets the pass/fail criteria of Schedule, Equipment, and Past Experience by rating them as acceptable or unacceptable. If the lowest priced quote receives an acceptable rating in all three categories, it will then be assigned a rating for Past Performance. If the lowest priced quote receives an “Excellent Confidence” past performance rating, then that offer represents the best value for the government and the evaluation ends. Award shall be made to that offeror without further consideration of any other quotes.
If the lowest priced quotes receives an unacceptable rating for any factor, or receives less than an “Excellent Confidence” past performance rating, the next lowest priced offeror will be evaluated, and the process will continue (in order by price) until an offeror receives an acceptable rating on all factors and an “Excellent Confidence” past performance rating, or until all offerors have been evaluated.
If no offeror receives an “Excellent Confidence” past performance rating, award will be made to the offeror with the highest past performance rating and lowest price, whose quote receives an acceptable rating for all other factors.
Evaluation Factors:
a. Factor 1 – Schedule: The schedule will receive an acceptable or unacceptable rating, defined below, based on whether or not it aligns with the period of performance in the statement of work.
Rating Description Acceptable Offeror’s proposed schedule aligns with the period of performance in the statement of work.
Unacceptable Offeror’s proposed schedule does not align with the period of performance in the statement of work.
b. Factor 2 – Equipment: The offeror’s proposed equipment will receive an acceptable or unacceptable rating, defined below, based on where it meets or exceeds the specifications outlined in the Statement of Work.
Acceptable The offeror's proposed equipment meets or exceeds the specifications outlined in the Statement of Work.
Unacceptable The offeror's proposed equipment does not meet the specifications outline in the Statement of Work.
c. Factor 3 – Past Experience: The offeror’s past experience will receive an acceptable or unacceptable rating, defined below, based on whether or not the Offeror demonstrates they have the requisite experience to complete this project.
Acceptable Offeror provided at least 2 references for projects similar in size and scope, and demonstrated experience performing the type of work outlined in the Statement of Work.
Unacceptable Offeror did not provide at least 2 references for projects similar in size and scope, or the references provided do not demonstrate experience performing the type of work outlined in the Statement of Work.
d. Factor 4 – Past Performance: Past performance will be rated based on submitted references, and any other information deemed relevant by the Contracting Officer (E.g. prior work for the Department of the Interior, Contractor Performance Assessment Reporting System). Past performance projects deemed not relevant will not be considered. Projects deemed not recent (greater than three years) will be disregarded. Offeror’s who lack recent or relevant past performance will be assigned an Unknown Confidence rating.
Excellent Confidence Based on the offeror’s performance record, the Government has a high expectation that the offeror will successfully perform the required effort.
Acceptable Confidence Based on the offeror’s performance record, the Government has an acceptable expectation that the offeror will successfully perform the required effort.
No Confidence Based on the offeror’s performance record, the Government has no expectation that the offeror will be able to successfully perform the required effort.
Unknown Confidence No performance record is identifiable, or the offeror’s performance record is so sparse that no confidence assessment rating can be reasonably assigned.
An “Unknown Confidence” past performance rating will be considered a neutral rating which will not negatively impact the offeror. However, an “Excellent Confidence” and “Acceptable Confidence” past performance rating will rank higher than an “Unknown Confidence” past performance rating.
e. Factor 5 - Total Price: Price will be evaluated for reasonableness in accordance with
FAR 13.106-3.