Attachment 4- Bid Schedule.xlsx

XLSX spreadsheet 43 KB Posted

Attached to
Base Emergency Spills Response Federal contract opportunity
Solicitation number
FA850125R0006
Issued by
Department of the Air Force Materiel Command Air Force Sustainment Center

About this file

The document is a Bid Schedule Excel spreadsheet for a Base Emergency Spills Response contract at Robins Air Force Base. The solicitation (FA850125R0006) covers a base period from September 1, 2025, to August 31, 2026, with two optional one-year extension periods. The pricing structure includes two Contract Line Item Numbers (CLINs): CLIN 0001 is a firm fixed monthly price for defined requirements like bi-monthly boom replacements and 24/7 on-call services, priced at $384 for the base period and $432 for Option Year 1. CLIN 0002 is a to-be-determined (TBD) spill response line item where contractors must provide fully burdened labor rates for various environmental and technical positions.

The bid schedule includes detailed labor categories such as Program Manager, Environmental Scientists/Engineers at different experience levels, Environmental Technicians, Quality Control Manager, GIS Analysts, and Health & Safety Officer. The spreadsheet also captures equipment rates for response vehicles, heavy equipment, and specialized tools like vacuum trucks and pumps. A site visit is scheduled for July 10, 2025, at 10:00 AM EST, with mandatory pre-registration required by emailing specific Air Force personnel. The contract is issued by the Department of the Air Force Materiel Command Air Force Sustainment Center, with contractors expected to provide comprehensive environmental and emergency spill response services.

View the file

Other files for this federal contract opportunity

Other files attached to Base Emergency Spills Response, newest first.
File Type Posted
Base spill attendee list - 10 July.docx DOCX document
Base Emergency Spills Response-Amendment 1.docx DOCX document
Attachment 5-Robins AFB Access Affidavit (Revised 31 Oct 2022) - Final_AdriaReimer.pdf PDF
Solicitation - FA850125R0006.pdf PDF
Attachment 3- CDRLs.pdf PDF
Attachment 2- SCA Wage Determination.pdf PDF
Attachment 1- PWS.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Bid Schedule

Robins AFB Spills Bid Schedule
DescriptionFrequencyFirm Fixed Price (per month)Base Period (1Sep25 -31Aug26)Firm Fixed Price (per month)Option Year 1 (1Sep26 -31Aug27)Firm Fixed Price (per month)Option Year 2 (1Sep27 -31Aug28)Total
Month
Clin 0001Clin 0001 is to price all defined requirements within the requirement PWS/QASP. Examples are bi-monthly boom replacements, exercises, on call 24/7, etc.1232$384.0036$432.000$0.00$816.00
Year
Clin 0002Clin 0002 will be a TBD clin. However, for evaluation purposes the contracor will provide established labor rates on tab two of this excel document in order for the government to use in their total evaluated price (TEP).1 Lot(Rates filled in by contractor on tab 2 below (Clin 0002 Spill Resp. Rates) will fill in base period block.$0.00(Rates filled in by contractor on tab 2 below (Clin 0002 Spill Resp. Rates) will fill in Option year 1 block.$0.00(Rates filled in by contractor on tab 2 below (Clin 0002 Spill Resp. Rates) will fill in Option year 2 block.$0.00$0.00

Total Evaluated Price $816.00

* Clin 0001 monthly amount will be for all requirements not related to actual spill response. This clin will be a firm fixed price clin to which the contractor is paid monthly for those requirements identified within the PWS/QASP. The contractor is to input their monthly costs in the highlighted yellow sections above for each year identified.

** Clin 0002 will be a TBD clin with the amount established by the government at time of award. For evaluation purposes contractor will fill in their not to exceed labor rates found on sheet 2 (clin 0002 Spill Resp. Rates). These rates will automatically calculate against historical numbers and automatically display on this sheet. The not to exceed labor rates provided will be used to assist the government with price reasonableness during actual spill occurances.

Clin 0002 Spill Resp. Rates

Spill Response (SR) Only - Fully burdened labor rates **Estimates to be used as part of the Toltal Evaluated Price Evaluation at award
CLIN
Base Period (1Sep25 -31Aug26)Option Year 1 (1Sep26 -31Aug27)Option Year 2 (1Sep27 -31Aug28)
Labor CategoryContractor PSS Labor CategoryPSS SINProposed Labor HoursProposed Labor RateTotalProposed Labor HoursProposed Labor RateTotalProposed Labor HoursProposed Labor RateTotal
Program ManagerEngineer/Scientist 8899-118$0.0018$0.0018$0.00
Project ManagerEngineer/Scientist 7899-11$0.001$0.001$0.00
Regulatory SpecialistEngineer/Scientist 6899-115$0.0015$0.0015$0.00
Environmental Scientist/Engineer - SeniorEngineer/Scientist 7899-11$0.001$0.001$0.00
Environmental Scientist/Engineer - MidEngineer/Scientist 6899-11$0.001$0.001$0.00
Environmental Scientist/Engineer - JuniorEngineer/Scientist 4899-11$0.001$0.001$0.00
Environmental Technician - SeniorEngineer/Field Technician 3899-191$0.0091$0.0091$0.00
Environmental Technician - MidEngineer/Field Technician 2899-1210$0.00210$0.00210$0.00
Environmental Technician - JuniorEngineer/Field Technician 1899-11$0.001$0.001$0.00
Quality Control ManagerEngineer/Scientist 8899-11$0.001$0.001$0.00
GIS Analyst -SeniorBusiness Analyst 3899-11$0.001$0.001$0.00
GIS Analyst - MidBusiness Analyst 2899-11$0.001$0.001$0.00
GIS Analyst - JuniorBusiness Analyst 1899-11$0.001$0.001$0.00
Administrative SpecialistProject Support Specialist 1899-14$0.004$0.004$0.00
Health & Safety OfficerEngineer/Field Technician 3899-11$0.001$0.001$0.00
Total Direct Labor Hours348348348
Total Direct Labor Dollars$0.00$0.00$0.00

Misc Equp rates Miscelaneou Equip rates (will be used for price reasonablenes during actual spills)

Equiptment RatesBase Period (1Sep25 -31Aug26)Option Year 1 (1Sep26 -31Aug27)Option Year 2 (1Sep27 -31Aug28)
Resonse VehiclesRatePerPerPer
Crew Vehicle (trk/1ton/Dually)DayDayDay
Crew Vehicle (1/4/1ton)DayDayDay
Equipment vehicle (Flatbed)DayDayDay
Sport Utility Vehicle (4x4)DayDayDay
All Terrain vehicle (ATV)DayDayDay
Boat & TrailerDayDayDay
Emergency Response Equipment TrailerDayDayDay
Heavy Equipment TrailerDayDayDay
Rail TrailerDayDayDay
Utility Supply TrailerDayDayDay
Utility Equipment TrailerDayDayDay
* All mileage will be paid based on current IRS established rate per business mile

Heavy Equipment

King Vac Air MoverHourHourHour
SS Vacuum Tanker (up to 5,000 gal)HourHourHour
Master Vac (up to 2,500 gal)HourHourHour
Roll off truckHourHourHour
Bob truck (up to 24' encloded)HourHourHour
Backhow (rubber tire)HourHourHour
Fork attachmentsHourHourHour
Skill Looader (bobcat)HourHourHour
Drum grabber attachment (manual)HourHourHour
Drum grabber attachment (hydrolic)HourHourHour
Vacuum Cleaners
Mercury VacDay
Dual Head ElectricDay
Dual Head w/Hepa Filter
Air Operated (Venturi)
Air Operated w/Hepa Filter
Pumps
Trash Pump2" w /40'hoseDay
3" w/40' hoseDay
4" w/40' hoseDay