This document is a Statement of Work (SOW) for a federal construction project to improve parking lots and roadways at the VA Southern Oregon Rehabilitation Center and Clinics in White City, Oregon. The key details are:
The scope of work includes cleaning and resealing cracks in approximately 368,400 sq ft of parking areas, removing and replacing damaged asphalt in 22,600 sq ft of parking lots, extending a wheelchair access lane, and adding three new wheelchair access ramps. The contractor will also be responsible for providing traffic control, completing work on each parking lot within 4 days, using specified paint materials, and verifying utility locations. The work is part of the federal contract opportunity solicitation number 36C26024R0066, issued by the Department of Veterans Affairs Veterans Health Administration for the Veterans Integrated Service Network 20. The solicitation requests bids for this construction project to improve the campus parking and roadways.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
VA Southern Oregon Rehabilitation Center and Clinics. 8495 Crater Lake Highway . White City, OR 97503
STATEMENT OF WORK
692-24-103
Improve Campus Parking Lots and Roadways
A. BACKGROUND
The pavement throughout various parking area shows extensive weather damages, also lumped surfaces due to invasive roots that needs to be leveled and sealed in existing grade. Most lots and roads need to be enhanced for safer driving conditions with new base coatings, repaving, and traffic parking marks.
B. SCOPE OF WORK
B. 1. Clean and fill cracks, reseal with 2 coats and paint traffic & parking marks areas as indicated in drawings. The total areas needing this type of work is approx. 368,400 ft2.
B.2. Remove trees and roots completely which have caused heaving and damage. Install new base material and repave root damaged/lumped surface in near parking lot, K, avenue “N”. Plant new trees in median as indicated in drawings. Remove existing asphalt from lots, “M” and “M1” as shown in drawings. Prepare base in lots “M” and
“M1”and repave. The approx. total need for repaving is 22,600 ft2, including paint traffic
& parking marks. Install single wheel stops per stall at the lots “M” and “M1”.
B.3. Add drip irrigation system connecting from the closest existing irrigation line to the task B.2 as indicated in drawings.
B.4. Extend wheelchair access lane (approx. 50 ft). Details are depicted on the drawing;
LOTS E, F, O & G.
B.5. Add new wheelchair access ramps (3 each). Details are depicted on the drawing;
SOUTH-NORTH ENTRANCE & B231.
C. SPECIFIC TASKS
C.1. Provide all traffic control signs, equipment and personnel. It is the contractor’s responsibility to coordinate with the current Contracting Officer’s Representative (COR), schedule closures and provide rerouting plans.
C.2. Each continuous parking lot shall be complete and opened to regular access/traffic within 4 calendar days.
C.3. No. 97 - Traffic Marking Paint, Latex shall be used for all traffic and parking marks
B.1. & B.2.). Reflective glass or beads shall be applied when paint is still in damp.
C.4. A manual open/close valve type must be used and located within the tree island
(B.3.)
C.5. Fire extinguishers, eye wash and first-aid kits will be available at all times.
VA Southern Oregon Rehabilitation Center and Clinics. 8495 Crater Lake Highway . White City, OR 97503
C.6. It is the contractor’s responsibility to verify the Mechanical, Electrical and Plumbing
(MEP) locations provided by the VA and subject to verifications. As-builts/redlined drawings will be generated and sent to the current COR upon completion (B.3.)
C.7. Pavement shall be complete and finished grading slopes must be conforming/consistence with what is already in place.
C.8. Resealing shall be performed in a sequence of filling cracks, then 2 coatings after cleaning areas; Second coating must be applied after first coating is completely cured.