This document is a set of 100% construction documents for the Portland VA Bridge Repair project, which is contract number 648-20-113. The project involves general construction, demolition, steel repair and fireproofing, and replacement of waterproof membrane and tile assembly, as well as expansion joint work at the Portland, OR VA Medical Center. The construction period is 180 calendar days after the Phase 1 notice to proceed, with an initial 30-day period for submittals. Key requirements include maintaining occupancy of the medical center during construction, following security protocols, and properly scheduling and coordinating utility shutdowns and phased work. The contractor must provide a critical path method (CPM) project schedule, comply with testing and commissioning requirements, and provide comprehensive operations and maintenance documentation upon project completion.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PORTLAND VA BRIDGE REPAIR 100% CONSTRUCTION DOCUMENTS
PORTLAND, OR 06/16/2023
Portland, OR VA Medical Center 00 01 00 - 1 of 1
Portland VA Healthcare
Project No. 648-20-113
DEPARTMENT OF VETERANS AFFAIRS
VHA MASTER SPECIFICATIONS
TABLE OF CONTENTS
Section 00 01 10
SECTION NO. DIVISION AND SECTION TITLES DATE
DIVISION 00 - SPECIAL SECTIONS
00 01 15 List of Drawing Sheets
DIVISION 01 - GENERAL REQUIREMENTS
01 00 00 General Requirements
01 32 16.15 Project Schedules (Small Projects – Design/Bid/Build
01 33 23 Shop Drawings, Product Data, and Samples
01 35 26 Safety Requirements
01 42 19 Reference Standards
01 45 00 Quality Control
01 45 29 Testing Laboratory Services
01 74 19 Construction Waste Management
DIVISION 02 – EXISTING CONDITIONS
02 41 00 Demolition
DIVISION 03 – CONCRETE
03 30 00 Cast-in-Place Concrete
DIVISION 05 – METALS
05 12 00 Structural Steel Framing
05 50 00 Metal Fabrications
DIVISION 07 - THERMAL AND MOISTURE PROTECTION
07 81 00 Applied Fireproofing
07 92 00 Joint Sealants
07 95 13 Expansion Joint Cover Assemblies
DIVISION 09 – FINISHES
09 30 13 Ceramic/Porcelain Tiling
Portland, OR VA Medical Center 00 01 15 - 1 of 2 Portland VA Healthcare Project No. 648-20-113
SECTION 00 01 15
LIST OF DRAWING SHEETS
The drawings listed below accompanying this specification form a part of the contract.
Drawing No. Title
GI001 PROJECT INFORMATION
GI002 ICRA PLAN
ARCHITECTURAL
AE 101 DEMOLITION PLAN
AE 102 FLOOR PLANS/RCP WEST AND CENTRAL BRIDGES
AE 103 FLOOR PLANS/RCP EAST BRIDGE
AE 201 DETAILS
STRUCTURAL
S1.0 STRUCTURAL PLANS AND DETAILS
- - - END - - -
Portland, OR VA Medical Center 03 30 00 - 1 of 27
Portland VA Healthcare CAST-IN-PLACE CONCRETE
Project No. 648-20-113
01 00 00 - 1 of 27
GENERAL REQUIREMENTS
SECTION 01 00 00
GENERAL REQUIREMENTS
PART 1
1.1 SAFETY REQUIREMENTS
A. Refer to Section 01 35 26, SAFETY REQUIREMENTS for safety and infection control requirements.
1.2 GENERAL INTENTION
A. Contractor shall completely prepare site for building operations, including demolition and removal of existing structures, and furnish labor and materials and perform work for
VA Project Project 648-20-113 Structural Repair Bldg 102 and 103 Connections as required by drawings and specifications.
B. Visits to the site by Bidders may be made only by appointment with the COR.
C. GDM , of Oregon, as Architect-Engineers, will render certain technical services during construction. Such services shall be considered as advisory to the Government and shall not be construed as expressing or implying a contractual act of the
Government without affirmations by COR or a duly authorized representative.
D. Before placement and installation of work subject to tests by testing laboratories or commissioning authority testing laboratory retained by Department of Veterans Affairs or the Contractor, the Contractor shall notify the COR in sufficient time to enable testing laboratories or commissioning authority personnel to be present at the site in time for proper taking and testing of specimens and field inspection. Such prior notice shall be not less than three work days unless otherwise designated by the COR.
E. All employees of general contractor and subcontractors shall comply with VA security management program and obtain permission of the VA police, be identified by project and employer, and restricted from unauthorized access.
F. Prior to commencing work, general contractor shall provide proof that a qualified "competent person" (CP) has completed OSHA 30-hour training and will maintain a presence at the work site whenever the general or subcontractors are present.
G. Training:
1. All employees of general contractor or subcontractors shall have the 10-hour OSHA certified Construction Safety course and/or other relevant competency training, as determined by
Portland, OR VA Medical Center 03 30 00 - 2 of 27
Portland VA Healthcare CAST-IN-PLACE CONCRETE
Project No. 648-20-113
01 00 00 - 2 of 27
GENERAL REQUIREMENTS
the VA COR with input from the Infection Control Risk
Assessment (ICRA) team.
2. Submit training records of all such employees to the CO and COR for approval before the start of work.
1.3 STATEMENT OF BID ITEM(S)
A. ITEM I, General Construction:
1. Work includes general construction, alterations, necessary removal and/or modifications of existing structures and construction, patching and finishing work, site work, and certain other items.
B. ITEM II, demolition
D. ITEM III, Steel repair and fireproofing
E. ITEM V, Replacement of waterproof membrane and tile assembly, and expansion joint
1.4 SPECIFICATIONS AND DRAWINGS FOR CONTRACTOR
A. Drawings and contract documents may be obtained upon request.
1.5 CONSTRUCTION SECURITY REQUIREMENTS
A. Security Management Plan:
1. General Contractor shall provide a Security Management Plan that defines both physical and administrative security procedures for the project.
2. The General Contractor is responsible for assuring that all sub-contractors working on the project and their employees also comply with these regulations.
B. Security Procedures:
1. General Contractor’s employees shall not enter the project site without appropriate badge. They may also be subject to inspection of their personal effects when entering or leaving the project site.
2. Before starting work the General Contractor shall give one week’s notice to the COR so that security escort or arrangements can be provided for the employees. This notice is separate from any notices required for utility shutdown described later in this section.
H. Qualified firestopping, refer to Specification 07 84 00.
Portland, OR VA Medical Center 03 30 00 - 3 of 27
Portland VA Healthcare CAST-IN-PLACE CONCRETE
Project No. 648-20-113
01 00 00 - 3 of 27
GENERAL REQUIREMENTS
3. No photography of VA premises is allowed without written permission of the COR.
4. VA reserves the right to close down or shut down the project site and order General Contractor’s employees off the premises in the event of a national emergency. The General
Contractor may return to the site only with the written approval from the Contracting Officer (CO).
C. Key Control:
1. The General Contractor shall provide duplicate keys and lock combinations to the Contracting Officer's Representative (COR) for the purpose of security inspections of every area of the project including tool boxes and parked machines in order to take emergency action.
2. The General Contractor shall install all cylinders at completion of the contract work. The VA Locksmith will obtain and install all permanent key cores after the General Contractor receives acceptance on their door and/or hardware installation from the COR.
CI. Document Control:
1. Before starting any work, the General Contractor/Sub Contractors shall submit an electronic security memorandum describing the approach to following goals and maintaining confidentiality of project information, including project documentation and drawings on paper and hard drives. This can be included as part of the General Contractor's "Security Management Plan."
2. The General Contractor is responsible for safekeeping of all drawings, project manual and other project information. This information shall be shared only with those with a specific need to accomplish the project.
3. All paper waste or electronic media, such as CD’s, shall be shredded and destroyed in a manner acceptable to the VA.
4. Notify the CO and COR immediately when there is a loss or compromise of project documentation or drawings.
Portland, OR VA Medical Center 03 30 00 - 4 of 27
Portland VA Healthcare CAST-IN-PLACE CONCRETE
Project No. 648-20-113
01 00 00 - 4 of 27
GENERAL REQUIREMENTS
5. All electronic information shall be stored in specified location following VA standards and procedures using an Engineering Document Management Software (EDMS).
6. Security, access and maintenance of all project drawings, both scanned and electronic shall be performed and tracked through the EDMS system.
E. Motor Vehicle Restrictions
1. Vehicle authorization request shall be required for any vehicle entering the site and such request shall be submitted 24 hours before the date and time of access.
Access shall be restricted to picking up and dropping off materials and supplies.
F. Personal Conduct:
1. Every person who enters the Medical Center’s grounds is expected to conduct themselves in a professional responsible manner without the need to enumerate every expected or prohibited behavior.
2. Weapons, ammunition, explosives, and alcoholic beverages are prohibited on the Medical Center’s grounds.
3. There shall be no solicitations or sales of any kind on the Medical Center’s grounds.
4. The Government reserves the right to refuse to permit employment on the Work or require dismissal from the Work of any subcontractor who, by reason of previous unsatisfactory work on Department of Veterans Affairs project or for any other reason, is considered by the COR to be incompetent or otherwise objectionable.
1.6 OPERATIONS AND STORAGE AREAS
A. The Contractor shall confine all operations (including storage of materials) on Government premises to areas authorized or approved by the COR. The Contractor shall hold and save the
Government, its officers and agents, free and harmless from liability of any nature occasioned by the Contractor's performance.
Portland, OR VA Medical Center 03 30 00 - 5 of 27
Portland VA Healthcare CAST-IN-PLACE CONCRETE
Project No. 648-20-113
01 00 00 - 5 of 27
GENERAL REQUIREMENTS
B. Temporary buildings (e.g., storage sheds, shops, offices) and utilities may be erected by the Contractor only with the approval of the COR and shall be built with labor and materials furnished by the Contractor without expense to the Government. The temporary buildings and utilities shall remain the property of the Contractor and shall be removed by the Contractor at its expense upon completion of the work. With the written consent of the COR, the buildings and utilities may be abandoned and need not be removed.
C. The Contractor shall, under regulations prescribed by the COR, use only established roadways, or use temporary roadways constructed by the Contractor when and as authorized by the COR.
When materials are transported in prosecuting the work, vehicles shall not be loaded beyond the loading capacity recommended by the manufacturer of the vehicle or prescribed by any Federal, State, or local law or regulation. When it is necessary to cross curbs or sidewalks, the Contractor shall protect them from damage. The Contractor shall repair or pay for the repair of any damaged curbs, sidewalks, or roads.
D. Working space and space available for storing materials shall be as shown on the drawings.
E. Workers are subject to rules of Medical Center applicable to their conduct.
F. Execute work so as to interfere as little as possible with normal functioning of Medical Center as a whole, including operations of utility services, fire protection systems and any existing equipment, and with work being done by others.
1. Keep roads clear of construction materials, debris, standing construction equipment and vehicles at all times.
2. Use of equipment and tools that transmit vibrations and noises through the building structure are not permitted in buildings that are occupied jointly by patients or medical personnel and Contractor's personnel during construction, except as permitted by the COR where required by limited working space.
3. Do not store materials and equipment in other than assigned areas.
4. When scheduling delivery of materials and equipment to VA buildings, communicate qualities and delivery times with the COR in advance of delivery date in order for the COR to coordinate and provide approval of delivery. Do overburden the the VA Buildings with material quantities that can not be used or stored at the job site immediately.
Portland, OR VA Medical Center 03 30 00 - 6 of 27
Portland VA Healthcare CAST-IN-PLACE CONCRETE
Project No. 648-20-113
01 00 00 - 6 of 27
GENERAL REQUIREMENTS
a. Provide unobstructed access to Medical Center areas required to remain in operation.
5. Storage of Contractor's materials and equipment may be permitted by the COR in vacated portions of buildings where access by Medical Center personnel is not required, subject to fire & life safety requirements.
I. Utilities Services: Where necessary to cut existing pipes, electrical wires, conduits, cables, etc., of utility services, or of fire protection systems or communications systems (except telephone), they shall be cut and capped at suitable places where shown; or, in absence of such indication, where directed by COR. All such actions shall be coordinated with the COR and the Utility Company involved.
J. Phasing:
1. The Medical Center must maintain its operation 24 hours a day 7 days a week. Therefore, any interruption in service must be scheduled and coordinated with the COR to ensure that no lapses in operation occur. It is the Contractor's responsibility to develop a work plan and schedule detailing, at a minimum, the procedures to be employed, the equipment and materials to be used, the interim life safety measure to be used during the work, and a schedule defining the duration of the work with milestone subtasks.
2. To ensure such executions, Contractor shall furnish the COR with a schedule of approximate phasing dates on which the
Contractor intends to accomplish work in each specific area of site, building or portion thereof. In addition, Contractor shall notify the COR 2 weeks in advance of the proposed date of starting work in each specific area of site, building or portion thereof. Arrange such phasing dates to ensure accomplishment of this work in successive phases mutually agreeable to the COR and Contractor.
K. All buildings on the campus will be occupied during performance of work but immediate areas of alterations will be vacated.
1. Contractor shall take all measures and provide all material necessary for protecting existing equipment and property in affected areas of construction against dust and debris, so that equipment and affected areas to be used in the Medical
Centers operations will not be hindered. Contractor shall permit access to Department of Veterans Affairs personnel and patients through other construction areas which serve as routes of access to such affected areas and equipment.
These routes whether access or egress shall be isolated from the construction area by temporary partitions and have walking surfaces, lighting etc to facilitate patient and
Portland, OR VA Medical Center 03 30 00 - 7 of 27
Portland VA Healthcare CAST-IN-PLACE CONCRETE
Project No. 648-20-113
01 00 00 - 7 of 27
GENERAL REQUIREMENTS
staff access. Coordinate alteration work in areas occupied by Department of Veterans Affairs so that Medical Center operations will continue during the construction period.
L. Construction Fence: Before construction operations begin, Contractor shall provide a chain link construction fence, 2.1m (seven feet) minimum height, around the construction area indicated on the drawings. Provide gates as required for access with necessary hardware, including hasps and padlocks. Fasten fence fabric to terminal posts with tension bands and line posts and top and bottom rails with tie wires spaced at maximum 375mm (15 inches). Bottom of fences shall extend to 25mm (one inch) above grade. Remove the fence when directed by the COR.
M. When a building and/or construction site is turned over to
Contractor, Contractor shall accept entire responsibility including upkeep and maintenance therefore:
1. Contractor shall maintain a minimum temperature of 18 degrees C (65 degrees F) at all times, except as otherwise specified.
2. Contractor shall maintain in operating condition existing fire protection and alarm equipment. In connection with fire alarm equipment, Contractor shall make arrangements for pre-inspection of site with Fire Department or Company
(Department of Veterans Affairs or municipal) whichever will be required to respond to an alarm from Contractor's employee or watchman.
N. Utilities Services: Maintain existing utility services for
Medical Center at all times. Provide temporary facilities, labor, materials, equipment, connections, and utilities to assure uninterrupted services. Where necessary to cut existing water, steam, gases, sewer or air pipes, or conduits, wires, cables, etc. of utility services or of fire protection systems and communications systems (including telephone), they shall be cut and capped at suitable places where shown; or, in absence of such indication, where directed by the COR.
1. No utility service such as water, gas, steam, sewers or electricity, or fire protection systems and communications systems may be interrupted without prior approval of the
COR. Electrical work shall be accomplished with all affected circuits or equipment de-energized. When an electrical outage cannot be accomplished, work on any energized circuits or equipment shall not commence without a detailed work plan, the Medical Center Director’s prior knowledge and written approval.
2. Contractor shall submit a request to interrupt any such services to the COR, in writing, 7 days in advance of
Portland, OR VA Medical Center 03 30 00 - 8 of 27
Portland VA Healthcare CAST-IN-PLACE CONCRETE
Project No. 648-20-113
01 00 00 - 8 of 27
GENERAL REQUIREMENTS
proposed interruption. Request shall state reason, date, exact time of, and approximate duration of such interruption.
3. Contractor will be advised (in writing) of approval of request, or of which other date and/or time such interruption will cause least inconvenience to operations of
Medical Center. Interruption time approved by Medical Center may occur at other than Contractor's normal working hours.
4. Major interruptions of any system must be requested, in writing, at least 15 calendar days prior to the desired time and shall be performed as directed by the COR.
5. In case of a contract construction emergency, service will be interrupted on approval of the COR. Such approval will be confirmed in writing as soon as practical.
O. All services to be abandoned such as wires, cables, raceways, ducts, pipes, and the like and their hangers or supports, are to be removed entirely back to the point of connection to the active utility (i.e. piping and ductwork back to active mains, electrical wires and cables back to active circuitry, and all empty raceways). If items are noted to be abandoned in place, they are to be sealed, capped, or plugged.
P. To minimize interference of construction activities with flow of
Medical Center traffic, comply with the following:
1. Keep roads, walks and entrances to grounds, to parking and to occupied areas of buildings clear of construction materials, debris and standing construction equipment and vehicles.
Wherever excavation for new utility lines cross existing roads, at least one lane must be open to traffic at all times with approval.
2. Method and scheduling of required cutting, altering and removal of existing roads, walks and entrances must be approved by the COR.
Q. Coordinate the work for this contract with other construction operations as directed by the COR. This includes the scheduling of traffic and the use of roadways, as specified in Article, USE
OF ROADWAYS.
1.7 ALTERATIONS
A. Survey: Before any work is started, the Contractor shall make a thorough survey with the COR, of areas of building(s) in which alterations shall occur and areas which are anticipated routes of access, and furnish a report, signed by both, to the COR.
This report shall list by rooms and spaces:
Portland, OR VA Medical Center 03 30 00 - 9 of 27
Portland VA Healthcare CAST-IN-PLACE CONCRETE
Project No. 648-20-113
01 00 00 - 9 of 27
GENERAL REQUIREMENTS
1. Existing condition and types of resilient flooring, doors, windows, walls and other surfaces not required to be altered throughout affected area(s) of building.
2. Existence and conditions of items such as plumbing fixtures and accessories, electrical fixtures, equipment, venetian blinds, shades, etc., required by drawings to be either reused or relocated, or both.
3. Shall note any discrepancies between drawings and existing conditions at site.
4. Shall designate areas for working space, materials storage and routes of access to areas within buildings where alterations shall occur and which have been agreed upon by Contractor and the COR.
B. Any items required by drawings to be either reused or relocated or both, found during this survey to be nonexistent, or in the opinion of the COR, to be in such condition that their use is impossible or impractical, shall be furnished and/or replaced by
Contractor with new items in accordance with specifications which will be furnished by Government. Provided the contract work is changed by reason of this subparagraph B, the contract will be modified accordingly, per FAR 52.236-2 DIFFERING SITE CONDITIONS and FAR 52.243-4 CHANGES.
C. Re-Survey: Thirty calendar days before expected partial or final inspection date, the Contractor and COR together shall make a thorough re-survey of the areas of buildings involved. They shall furnish a report on conditions then existing, of resilient flooring, doors, windows, walls and other surfaces as compared with conditions of same as noted in first condition survey report:
1. Re-survey report shall also list any damage caused by
Contractor to such flooring and other surfaces, despite protection measures; and, will form basis for determining extent of repair work required of Contractor to restore damage caused by Contractor's workers in executing work of this contract.
D. Protection: Provide the following protective measures:
1. Wherever existing roof surfaces are disturbed they shall be protected against water infiltration. In case of leaks, they shall be repaired immediately upon discovery.
2. Temporary protection against damage for portions of existing structures and grounds where work is to be done, materials handled and equipment moved and/or relocated.
Portland, OR VA Medical Center 03 30 00 - 10 of 27
Portland VA Healthcare CAST-IN-PLACE CONCRETE
Project No. 648-20-113
01 00 00 - 10 of 27
GENERAL REQUIREMENTS
3. Protection of interior of existing structures at all times, from damage, dust and weather inclemency. Wherever work is performed, floor surfaces that are to remain in place shall be adequately protected prior to starting work, and this protection shall be maintained intact until all work in the area is completed.
1.8 DISPOSAL AND RETENTION
A. Materials and equipment accruing from work removed and from demolition of buildings or structures, or parts thereof, shall be disposed of as follows:
1. Reserved items which are to remain property of the
Government are identified by attached tags or noted on drawings or in specifications as items to be stored. Items that remain property of the Government shall be removed or dislodged from present locations in such a manner as to prevent damage which would be detrimental to re-installation and reuse. Store such items where directed the COR.
2. Items not reserved shall become property of the Contractor and be removed by Contractor from Medical Center.
3. Items of portable equipment and furnishings located in rooms and spaces in which work is to be done under this contract shall remain the property of the Government. When rooms and spaces are vacated by the Department of Veterans Affairs during the alteration period, such items which are NOT required by drawings and specifications to be either relocated or reused will be removed by the Government in advance of work to avoid interfering with Contractor's operation.
1.9 PROTECTION OF EXISTING VEGETATION, STRUCTURES, EQUIPMENT,
UTILITIES, AND IMPROVEMENTS
A. The Contractor shall preserve and protect all structures, equipment, and vegetation (such as trees, shrubs, and grass) on or adjacent to the work site, which are not to be removed and which do not unreasonably interfere with the work required under this contract. The Contractor shall only remove trees when specifically authorized to do so, and shall avoid damaging vegetation that will remain in place. If any limbs or branches of trees are broken during contract performance, or by the careless operation of equipment, or by workers, the Contractor shall trim those limbs or branches with a clean cut and paint the cut with a tree-pruning compound as directed by the COR.
B. The Contractor shall protect from damage all existing improvements and utilities at or near the work site and on adjacent property of a third party, the locations of which are made known to or should be known by the Contractor. The
Portland, OR VA Medical Center 03 30 00 - 11 of 27
Portland VA Healthcare CAST-IN-PLACE CONCRETE
Project No. 648-20-113
01 00 00 - 11 of 27
GENERAL REQUIREMENTS
Contractor shall repair any damage to those facilities, including those that are the property of a third party, resulting from failure to comply with the requirements of this contract or failure to exercise reasonable care in performing the work. If the Contractor fails or refuses to repair the damage promptly, the COR may have the necessary work performed and charge the cost to the Contractor.
C. Refer to Articles, "Alterations", "Restoration", and "Operations and Storage Areas" for additional instructions concerning repair of damage to structures and site improvements.
D. A National Pollutant Discharge Elimination System (NPDES) permit is required for this project. The Contractor is considered an "operator" under the permit and has extensive responsibility for compliance with permit requirements. VA will make the permit application available upon request. The apparent low bidder, contractor and affected subcontractors shall furnish all information and certifications that are required to comply with the permit process and permit requirements. Many of the permit requirements will be satisfied by completing construction as shown and specified. Some requirements involve the Contractor's method of operations and operations planning and the Contractor is responsible for employing best management practices. The affected activities often include, but are not limited to the following:
1. Designating areas for equipment maintenance and repair;
2. Providing waste receptacles at convenient locations and provide regular collection of wastes;
3. Locating equipment wash down areas on site, and provide appropriate control of wash-waters;
4. Providing protected storage areas for chemicals, paints, solvents, fertilizers, and other potentially toxic materials;
and
5. Providing adequately maintained sanitary facilities.
1.10 RESTORATION
A. Remove, cut, alter, replace, patch and repair existing work as necessary to install new work. Except as otherwise shown or specified, do not cut, alter or remove any structural work, and do not disturb any ducts, plumbing, steam, gas, or electric work
Portland, OR VA Medical Center 03 30 00 - 12 of 27
Portland VA Healthcare CAST-IN-PLACE CONCRETE
Project No. 648-20-113
01 00 00 - 12 of 27
GENERAL REQUIREMENTS
without approval of the COR. Existing work to be altered or extended and that is found to be defective in any way, shall be reported to the COR before it is disturbed. Materials and workmanship used in restoring work, shall conform in type and quality to that of original existing construction, except as otherwise shown or specified.
B. Upon completion of contract, deliver work complete and undamaged. Existing work (walls, ceilings, partitions, floors, mechanical and electrical work, lawns, paving, roads, walks, etc.) disturbed or removed as a result of performing required new work, shall be patched, repaired, reinstalled, or replaced with new work, and refinished and left in as good condition as existed before commencing work.
C. At Contractor's own expense, Contractor shall immediately restore to service and repair any damage caused by Contractor's workers to existing piping and conduits, wires, cables, etc., of utility services or of fire protection systems and communications systems (including telephone) which are not scheduled for discontinuance or abandonment.
1.11 PROFESSIONAL SURVEYING SERVICES
A. A registered professional land surveyor or registered civil engineer whose services are retained and paid for by the
Contractor shall perform services specified herein and in other specification sections. The Contractor shall certify that the land surveyor or civil engineer is not one who is a regular employee of the Contractor, and that the land surveyor or civil engineer has no financial interest in this contract.
1.12 LAYOUT OF WORK
A. The Contractor shall lay out the work from Government established base lines and bench marks, indicated on the drawings, and shall be responsible for all measurements in connection with the layout. The Contractor shall furnish, at
Contractor's own expense, all stakes, templates, platforms, equipment, tools, materials, and labor required to lay out any part of the work.
1. The Contractor shall be responsible for executing the work to the lines and grades that may be established or indicated by the COR.
Portland, OR VA Medical Center 03 30 00 - 13 of 27
Portland VA Healthcare CAST-IN-PLACE CONCRETE
Project No. 648-20-113
01 00 00 - 13 of 27
GENERAL REQUIREMENTS
2. The Contractor shall also be responsible for maintaining and preserving all lines, stakes, and other marks established by the COR until authorized to remove them.
3. If such marks are destroyed by the Contractor or through
Contractor's negligence before their removal is authorized, the COR may replace them and deduct the expense of the replacement from any amounts due or to become due to the
Contractor.
B. Establish and plainly mark such other lines and grades that are reasonably necessary to properly assure that location, orientation, and elevations established for utilities are in accordance with lines and elevations shown on contract drawings.
C. The Contractor shall keep on the work site a copy of the Drawings and Specifications and shall at all times give access to the COR. Anything mentioned in the Specification and not shown on the Drawings, or shown on the Drawings and not mentioned in the Specifications, shall be of like effect as if shown or mentioned in both. In case of difference between Drawings and Specifications, the Contractor shall issue a Request for Information (RFI) requesting confirmation as to which shall govern. In case of discrepancy in the figures, in the Drawings, or in the Specifications, the matter shall be promptly submitted to the COR, who shall promptly make a determination in writing. Any adjustment by the Contractor without such a determination shall be at the Contractor’s own risk and expense. The COR shall furnish from time to time such detailed drawings and other information as considered necessary unless otherwise provided.
D. Wherever in the Specifications or upon the Drawings the words “directed”, “required”, “ordered”, “designated”, “prescribed”, or words of like import are used, it shall be understood that the “direction”, “requirement”, “order”, “designation”, or “prescription” of the COR is intended and similarly the words “approved”, “acceptable”, “satisfactory”, or words of the like import shall mean “approved by”, or “acceptable to”, or “satisfactory to” the Contracting Officer, unless otherwise expressly stated.
E. Where “as shown”, “as indicated”, “as detailed” or words of similar import are used, it shall be understood that the reference is made to the Drawings accompanying this Contract unless stated otherwise. The word “provided” as used herein
Portland, OR VA Medical Center 03 30 00 - 14 of 27
Portland VA Healthcare CAST-IN-PLACE CONCRETE
Project No. 648-20-113
01 00 00 - 14 of 27
GENERAL REQUIREMENTS
shall be understood to mean “provide complete in place”, that is
“furnished and installed”.
H. Upon completing the work under this Contract, the Contractor shall furnish a complete set of all shop drawings as finally approved. These drawings shall show all changes and revisions made up to the time the equipment is completed and accepted.
I. The COR’s interpretation of the Drawings and Specification will be final, as per FAR 52.233-1 Disputes.
J. Large scale drawings supersede small scale drawings.
K. Dimensions govern in all cases. Scaling of Drawings may be done only for general location and general size of items.
L. Dimensions shown of existing work and all dimensions required for work that is to connect with existing work, shall be verified by the Contractor by actual measurement of the existing work. Any work at variance with that specified or shown in the
Drawings shall not be performed by the Contractor until approved in writing by the COR.
1.13 AS-BUILT DRAWINGS
A. The contractor shall maintain two full size sets of as-built drawings which will be kept current during construction of the project, to include all contract changes, modifications and clarifications.
B. All variations shall be shown in the same general detail as used in the contract drawings. To ensure compliance, as-built drawings shall be made available for the COR's review, as often as requested.
C. Contractor shall deliver two approved completed sets of as-built drawings in the electronic version (scanned PDF) to the COR within 15 calendar days after each completed phase and after the acceptance of the project by the COR.
D. Paragraphs A, B, & C shall also apply to all shop drawings.
E. Failure to keep as-built drawings up-to-date shall be cause for withholding payments.
F. Contractor is to provide an updated sequence of operation in digital format indicating all changes made to the original sequence of operation.
1.14 WARRANTY MANAGEMENT
A. Performance Bond: The Performance Bond must remain effective throughout the construction period and warranty period.
Portland, OR VA Medical Center 03 30 00 - 15 of 27
Portland VA Healthcare CAST-IN-PLACE CONCRETE
Project No. 648-20-113
01 00 00 - 15 of 27
GENERAL REQUIREMENTS
1. In the event the Contractor fails to commence and diligently pursue any construction warranty work required, the COR will have the work performed by others, and after completion of the work, will charge the remaining construction warranty funds of expenses incurred by the Government while performing the work, including, but not limited to administrative expenses.
2. In the event sufficient funds are not available to cover the construction warranty work performed by the Government at the contractor’s expenses, the COR will have the right to recoup expenses from the bonding company.
3. Following oral or written notification of required construction warranty repair work, the Contractor shall respond in a timely manner. Written verification will follow oral instructions. Failure to respond will be cause for the
COR to proceed against the Contractor.
B. Pre-Warranty Conference: Prior to contract completion, and at a time designated by the COR, the Contractor shall meet with the
COR to develop a mutual understanding with respect to the requirements of this section. Communication procedures for
Contractor notification of construction warranty defects, priorities with respect to the type of defect, reasonable time required for Contractor response, and other details deemed necessary by the Contracting Officer for the execution of the construction warranty will be established/ reviewed at this meeting. In connection with these requirements and at the time of the Contractor’s quality control completion inspection, furnish the name, telephone number and address of a licensed and bonded company which is authorized to initiate and pursue construction warranty work action on behalf of the Contractor.
This point of contract will be located within the local service area of the warranted construction, be continuously available and be responsive to Government inquiry on warranty work action and status. This requirement does not relieve the Contractor of any of its responsibilities in conjunction with other portions of this provision.
C. Contractor’s Response to Construction Warranty Service
Requirements:
1. Following oral or written notification by the Contracting
Officer, the Contractor shall respond to construction warranty service requirements in accordance with the
“Construction Warranty Service Priority List” and the three categories of priorities listed below. Submit a report on any warranty item that has been repaired during the warranty period. Include within the report the cause of the problem, date reported, corrective action taken, and when the repair was completed. If the Contractor does not perform the
Portland, OR VA Medical Center 03 30 00 - 16 of 27
Portland VA Healthcare CAST-IN-PLACE CONCRETE
Project No. 648-20-113
01 00 00 - 16 of 27
GENERAL REQUIREMENTS
construction warranty within the timeframe specified, the
Government will perform the work and back charge the construction warranty payment item established.
a. First Priority Code 1. Perform onsite inspection to evaluate situation, and determine course of action within
4 hours, initiate work within 6 hours and work continuously to completion or relief.
b. Second Priority Code 2. Perform onsite inspection to evaluate situation, and determine course of action within
8 hours, initiate work within 24 hours and work continuously to completion or relief.
c. Third Priority Code 3. All other work to be initiated within 3 work days and work continuously to completion or relief.
d. The “Construction Warranty Service Priority List” is as follows:
1) Code 1-Life Safety Systems
(a) Fire suppression systems.
(b) Fire alarm system(s).
2) Code 1-Air Conditioning Systems
(a) Air conditioning leak in part of the building, if causing damage.
(b) Air conditioning system not cooling properly.
3) Code 1 Doors
(a) Overhead doors not operational, causing a security, fire or safety problem.
(b) Interior, exterior personnel doors or hardware, not functioning properly, causing security, fire or safety problem.
4) Code 3-Doors
(a) Overhead doors not operational.
(b) Interior/exterior personnel doors or hardware not functioning properly.
5) Code 1-Electrical
(a) Power failure (entire area or any building operational after 1600 hours).
(b) Security lights.
Portland, OR VA Medical Center 03 30 00 - 17 of 27
Portland VA Healthcare CAST-IN-PLACE CONCRETE
Project No. 648-20-113
01 00 00 - 17 of 27
GENERAL REQUIREMENTS
(c) Smoke detectors.
6) Code 2-Electrical
(a) Power failure (no power to a room or part of building).
(b) Receptacles and lights not operational (in a room or part of building).
7) Code 3-Electrical
(a) Exterior lights not operational.
8) Code 1-Gas
(a) Leaks and pipeline breaks.
9) Code 1-Heat
(a) Power failure affecting heat.
10) Code 1-Plumbing
(a) Hot water heater failure.
(b) Leaking water supply pipes.
11) Code 2-Plumbing
(a) Flush valves not operating properly
(b) Fixture drain, supply line or any water pipe leaking.
(c) Toilet leaking at base.
12) Code 3- Plumbing
(a) Leaky faucets.
13) Code 3-Interior
(a) Floors damaged.
(b) Paint chipping or peeling.
(c) Casework damaged.
14) Code 1-Roof Leaks
(a) Damage to property is occurring.
15) Code 2-Water (Exterior)
(a) No water to facility.
16) Code 2-Water (Hot)
Portland, OR VA Medical Center 03 30 00 - 18 of 27
Portland VA Healthcare CAST-IN-PLACE CONCRETE
Project No. 648-20-113
01 00 00 - 18 of 27
GENERAL REQUIREMENTS
(a) No hot water in portion of building listed.
17) Code 3
(a) All work not listed above.
1.15 USE OF ROADWAYS
A. For hauling, use only established public roads and roads on
Medical Center property and, when authorized by the COR, such temporary roads which are necessary in the performance of contract work. Temporary roads shall be constructed and restoration performed by the Contractor at Contractor's expense.
When necessary to cross curbing, sidewalks, or similar construction, they must be protected by well-constructed bridges.
1.16 TEMPORARY USE OF MECHANICAL AND ELECTRICAL EQUIPMENT
A. Use of new installed mechanical and electrical equipment to provide heat, ventilation, plumbing, light and power will be permitted subject to written approval and compliance with the following provisions:
1. Permission to use each unit or system must be given by the
COR in writing. If the equipment is not installed and maintained in accordance with the written agreement and following provisions, the COR will withdraw permission for use of the equipment.
2. Electrical installations used by the equipment shall be completed in accordance with the drawings and specifications to prevent damage to the equipment and the electrical systems, i.e. transformers, relays, circuit breakers, fuses, conductors, motor controllers and their overload elements shall be properly sized, coordinated and adjusted.
Installation of temporary electrical equipment or devices shall be in accordance with NFPA 70, National Electrical
Code, (2017 Edition), Article 590, Temporary Installations.
Voltage supplied to each item of equipment shall be verified to be correct and it shall be determined that motors are not overloaded. The electrical equipment shall be thoroughly cleaned before using it and again immediately before final inspection including vacuum cleaning and wiping clean interior and exterior surfaces.
3. Units shall be properly lubricated, balanced, and aligned.
Vibrations must be eliminated.
4. Automatic temperature control systems for preheat coils shall function properly and all safety controls shall function to prevent coil freeze-up damage.
Portland, OR VA Medical Center 03 30 00 - 19 of 27
Portland VA Healthcare CAST-IN-PLACE CONCRETE
Project No. 648-20-113
01 00 00 - 19 of 27
GENERAL REQUIREMENTS
5. The air filtering system utilized shall be that which is designed for the system when complete, and all filter elements shall be replaced at completion of construction and prior to testing and balancing of system.
6. All components of HVAC systems and equipment and other auxiliary facilities used in temporary service shall be cleaned prior to use; maintained to prevent corrosion internally and externally during use; and cleaned, maintained and inspected prior to acceptance by the
Government.
B. Prior to final inspection, the equipment or parts used which show wear and tear beyond normal, shall be replaced with identical replacements, at no additional cost to the Government.
C. This paragraph shall not reduce the requirements of the mechanical and electrical specifications sections.
D. Any damage to the equipment or excessive wear due to prolonged use will be repaired replaced by the contractor at the contractor’s expense.
1.17 TEMPORARY USE OF EXISTING ELEVATORS
A. Use of existing elevator(s) for handling building materials and
Contractor's personnel will be permitted subject to following provisions:
1. Contractor makes all arrangements with the COR for use of elevators. The COR will ascertain that elevators are in proper condition.
2. Contractor covers and provides maximum protection of following elevator components:
a. Entrance jambs, heads soffits and threshold plates.
b. Entrance columns, canopy, return panels and inside surfaces of car enclosure walls.
c. Finish flooring.
3. Government will accept hoisting ropes of elevator and rope of each speed governor if they are worn under normal operation. However, if these ropes are damaged by action of foreign matter such as sand, lime, grit, stones, etc., during temporary use, they shall be removed and replaced by new hoisting ropes at the contractor's expense.
4. If brake lining of elevators are excessively worn or damaged during temporary use, they shall be removed and replaced by new brake lining at the contractors expense.
Portland, OR VA Medical Center 03 30 00 - 20 of 27
Portland VA Healthcare CAST-IN-PLACE CONCRETE
Project No. 648-20-113
01 00 00 - 20 of 27
GENERAL REQUIREMENTS
5. All parts of main controller, starter, relay panel, selector, etc., worn or damaged during temporary use shall be removed and replaced with new parts at the contractors expense, if recommended by elevator inspector after elevator is released by Contractor.
6. Place elevator in condition equal, less normal wear, to that existing at time it was placed in service of Contractor as approved by COR.
1.18 TEMPORARY TOILETS
A. Contractor may have for use of Contractor's workers, such toilet accommodations as may be assigned to Contractor by Medical
Center. Contractor shall keep such places clean and be responsible for any damage done thereto by Contractor's workers.
Failure to maintain satisfactory condition in toilets will deprive Contractor of the privilege to use such toilets.
1.19 AVAILABILITY AND USE OF UTILITY SERVICES
A. Heat: Furnish temporary heat necessary to prevent injury to work and materials through dampness and cold. Use of open salamanders or any temporary heating devices which may be fire hazards or may smoke and damage finished work, will not be permitted.
Maintain minimum temperatures as specified for various materials.
B. Electricity (for Construction and Testing): Furnish all temporary electric services.
1. Obtain electricity by connecting to the Medical Center electrical distribution system. The Contractor shall meter and pay for electricity required for electric cranes and hoisting devices, electrical welding devices and any electrical heating devices providing temporary heat.
Electricity for all other uses is available at no cost to the Contractor.
C. Water (for Construction and Testing): Furnish temporary water service.
1. Obtain water by connecting to the Medical Center water distribution system. Provide reduced pressure backflow preventer at each connection as per code. Water is available at no cost to the Contractor.
2. Maintain connections, pipe, fittings and fixtures and conserve water-use so none is wasted. Failure to stop leakage or other wastes will be cause for revocation (at the COR's discretion) of use of water from Medical Center's system.
Portland, OR VA Medical Center 03 30 00 - 21 of 27
Portland VA Healthcare CAST-IN-PLACE CONCRETE
Project No. 648-20-113
01 00 00 - 21 of 27
GENERAL REQUIREMENTS
1.20 TESTS
A. As per specification Section 01 91 00, GENERAL COMMISSIONING
REQUIREMENTS, Section 21 08 00, COMMISSIONING OF FIRE
SUPPORESSION SYSTEMS, Section 22 08 00, COMMISSIONING OF
PLUMBING SYSTEMS, Section 23 08 00, COMMISSIONING OF HVAC
SYSTEMS, Section 23 05 93, TESTING, ADJUSTING, AND BALANCING FOR
HVAC, Section 26 08 00, COMMISSIONING OF ELECTRICAL SYSTEMS, and
Section 27 08 00, COMMISSIONING OF TELECOMMUNICATIONS SYSTEMS, the contractor shall provide a written testing and commissioning plan complete with component level, equipment level, sub-system level and system level breakdowns. The plan will provide a schedule and a written sequence of what will be tested, how and what the expected outcome will be. This document will be submitted for approval prior to commencing work. The contractor shall document the results of the approved plan and submit for approval with the as built documentation.
B. Pre-test mechanical and electrical equipment and systems and make corrections required for proper operation of such systems before requesting final tests. Final test will not be conducted unless pre-tested.
C. Conduct final tests required in various sections of specifications in presence of an authorized representative of the Contracting Officer. Contractor shall furnish all labor, materials, equipment, instruments, and forms, to conduct and record such tests.
D. Mechanical and electrical systems shall be balanced, controlled and coordinated. A system is defined as the entire system which must be coordinated to work together during normal operation to produce results for which the system is designed.
1. For example, air conditioning supply air is only one part of entire system which provides comfort conditions for a building. Other related subsystems and components may include return air, exhaust air, makeup air, outside air, refrigerant, controls, and electrical power, etc.
E. All related components as defined above shall be functioning when any system component is tested. Tests shall be completed within a reasonably period of time during which operating and environmental conditions remain reasonably constant and are typical of the design conditions.
F. Individual test result of any component, where required, will only be accepted when submitted with the test results of related components and of the entire system.
Portland, OR VA Medical Center 03 30 00 - 22 of 27
Portland VA Healthcare CAST-IN-PLACE CONCRETE
Project No. 648-20-113
01 00 00 - 22 of 27
GENERAL REQUIREMENTS
1.21 INSTRUCTIONS
A. Contractor shall furnish Maintenance and Operating manuals (hard copies and electronic) and verbal instructions when required by the various sections of the specifications and as hereinafter specified but no later than 2 weeks prior to final inspection.
B. Manuals: Maintenance and operating manuals and one compact disc
(four hard copies and one electronic copy each) for each separate piece of equipment shall be delivered to the COR coincidental with the delivery of the equipment to the job site.
Manuals shall be complete, detailed guides for the maintenance and operation of equipment. They shall include complete information necessary for starting, adjusting, maintaining in continuous operation for long periods of time and dismantling and reassembling of the complete units and sub-assembly components. Manuals shall include an index covering all component parts clearly cross-referenced to diagrams and illustrations. Illustrations shall include "exploded" views showing and identifying each separate item. Emphasis shall be placed on the use of special tools and instruments. The function of each piece of equipment, component, accessory and control shall be clearly and thoroughly explained. All necessary precautions for the operation of the equipment and the reason for each precaution shall be clearly set forth. Manuals must reference the exact model, style and size of the piece of equipment and system being furnished. Manuals referencing equipment similar to but of a different model, style, and size than that furnished will not be accepted.
C. Instructions: Contractor shall provide qualified, factory-trained manufacturers' representatives to give…