Attachment 1 - RFP 36C26024R0014 0001 Q_A.pdf
PDF 80 KB Posted
- Solicitation number
- 36C26024R0014
About this file
The document provided is a Questions and Answers (Q&A) attachment related to RFP 36C26024R0014 for the project "CON 648-20-113 Structural Repair Bldg. 102 and 103 Connection". The Q&A addresses several key details:
-
Confirmation that a scheduling/project management software will be required to create and maintain project schedules, though RFIs and submittals can be submitted without use of such software.
-
Approval for the use of temporary chain link fence panels as traffic and pedestrian barriers during the work, as long as they are in good condition without sharp edges.
-
Permission to block off areas of the West and Central Pedestrian Bridges with security fence panels, cones, tape, plastic, and signage during the tile work in those areas.
-
Confirmation that a laydown area can be coordinated with the Contracting Officer's Representative (COR) by reserving nearby parking spaces or another space for construction barriers, tools, and other needs between work shifts.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ATTACHMENT 1 - RFP 36C26024R0014 0001 Q & A
1. Specification section 01 00 00, 1.31 Project Management Software, B. Please confirm a project management software will be required for this project.
a. A scheduling/project management software will be required to create and maintain project schedules; however, RFIs and submittals can be submitted without use of a project management software.
2. Will temporary chain link fence panels be able to be used as the temporary traffic and pedestrian barriers at each location of work? Plastic and other means would still be utilized for dust/debris control during grinding, fireproofing, etc.
a. Yes, chain link fence panels will be fine. Any temporary barrier should be in good condition without sharp edges exposed.
3. The work at the upper portions of the West Pedestrian Bridge and the Central Pedestrian Bridge (areas with tile work) will not be able to be completed in one shift or made safe for pedestrian travel during the regular working hours in between shifts. Will the contractor be able to block these areas off with security fence panels (outside) and cones/tape/plastic/signage (inside) for the duration of the work at these areas?
a. Yes.
4. Is there a laydown area that we can utilize for construction barriers, tools, etc. in between shifts of work?
a. Yes, this can be coordinated with the COR by reserving several parking spaces or reserving another space nearby the area of work.