Attachment 3 Statement of Work.pdf
PDF 310 KB Posted
- Attached to
- GAOA Grizzly Bear Campground
- Solicitation number
- 127EAX27Q0004
About this file
This is a Statement of Work (SOW) for the Grizzly Bear Campground Reconstruction project under the United States Department of Agriculture Forest Service at Black Hills National Forest in South Dakota.
The project involves comprehensive reconstruction of Grizzly Bear Campground, a seasonal facility (mid-May to mid-September) located approximately 1.5 miles southwest of Keystone, South Dakota. This Congressionally directed Great American Outdoors Act project requires design, construction, and resurfacing of campground roads while preserving historically significant CCC-built structures from 1936, including a stone picnic pavilion, stone toilet building, stone drainage structures, and stone steps. The contractor must redesign the campground to meet ABA and ADA accessibility requirements, improve road alignment and subbase, replace and reroute the water system (well, pumphouse, service and distribution lines, and point-of-use hydrants), relocate and replace the information board, equip host and volunteer sites with sewage vaults and utilities, redesign campsites for modern recreational vehicles with improved layout and functionality, and construct new stick-built toilet and pumphouse facilities. The water system is classified as a Transient Non-Community Public water system and is in poor condition requiring complete modernization and code compliance.
Contractor requirements include demonstrated expertise in campground construction, general contracting, and road construction with strong communication skills and capacity to meet specified timelines. Key personnel must include an onsite superintendent at all times, and the water system installer must meet South Dakota licensing requirements. Any electrician must hold a South Dakota Electrical License with state inspection and approval required for all electrical work. The contractor is responsible for all travel costs, accident prevention planning, and site security, including protective barriers and site gate lockout procedures. Deliverables include accident prevention plans (due 10 days prior to work start), construction schedules and monthly progress reports, daily construction reports, permits and licenses, testing and inspection reports, operation and maintenance manuals (due within 30 days of review), and project record documents at closeout, all submitted via email to the Contracting Officer's Representative.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 127EAX27Q0004 GAOA Grizzly Bear Campground.pdf | ||
| Attachment 5 Drawings.pdf | ||
| Attachment 2 Schedule of items.xlsx | XLSX spreadsheet | |
| Attachment 4 Specifications.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
US Department of Agriculture (USDA)
United States Department of Agriculture
Forest Service
Black Hills National Forest
Black Hills Campground Reconstruction
Grizzly Bear Campground Statement of Work
Contents Project General Information
1.0 Scope of Work
2.0 Background
Contractor Requirements
3.0 Technical Requirements / Tasks
4.0 Government Furnished
5.0 Deliverables / Schedule
6.0 Travel
7.0 Contractor’s Key Personnel
8.0 Security Requirements
9.0 Data Rights ...................................................................................................... Error! Bookmark not defined.
10.0 Section 508 – Electronic and Information Technology Standards ......................... Error! Bookmark not defined.
Project Grizzly Bear Campground Reconstruction
General Information
1.0 Scope of Work
Grizzly Bear Campground is in the NE1/4 of Section 18, T2S, R6E, BHM, Pennington County, South Dakota.
It is located on US Highway 16A, approximately 1.5 miles southwest of Keystone, South Dakota.
The Civilian Conservation Corps (CCC) built the campground in 1936 and many elements of this campground have historical value and will remain and must be protected during construction activities.
Historical elements include the stone picnic pavilion, stone toilet building, stone drainage structures, stone steps, and drainage ditch. The design and layout of features within the campground do not meet ABA and ADA requirements for accessibility – particularly running slope, cross slope, clear spaces, and firm- and-stable surfaces. The proposed redesign will update the campground including: Road alignment will be adjusted to accommodate expected traffic, subbase will be enhanced. The water system well will remain;
the pumphouse, service and distribution lines, and point-of-use hydrants will be replaced and rerouted to better serve campers. The information board will be replaced and relocated. Host and Volunteer Sites will each to be equipped with sewage vault, water, and electric services. Campsites will be redesigned for accessibility and improved layout, parking and functionality. A new stick-built double toilet and stick-built pump house are part of the project.
2.0 Background
This is a Congressionally directed Great American Outdoors Act project that will make improvements to the road - to include design, construction and resurfacing. Grizzly Bear Campground will be reconstructed to current capacity, improve the water system, and improve host sites with repaired sewage vaults. Camp sites will be designed for modern recreational vehicles using modern design and furnished with modern amenities.
The Grizzly Bear Campground is a seasonal campground operated from approximately mid-May to mid-September annually.
The water system at Grizzly Bear Campground consists of a well with a submersible pump, steel below ground water storage tank, and distribution system with 5 points of use. This system is classified as a Transient Non-Community Public water system. The water system is in poor condition. The well needs pump controls, treatment system, and pump house are not functioning properly, are not compliant with codes and require replacement. The distribution system has numerous leaks, is in poor condition and requires replacement. The existing hydrants are not accessible and require upgrades. The stick-built pumphouse building is in poor condition and has inadequate lighting and inadequate ventilation.
Contractor Requirements
3.0 Technical Requirements / Tasks
Contractors should demonstrate a thorough understanding of the project requirements and attention to detail is crucial for quality construction. Strong communication skills are essential for coordinating with clients, subcontractors and other stakeholders. Experience in campground construction, general contracting, and road construction is beneficial.
Contractors should have the capacity to handle the specific project requirements and deliver within the specified timeline.
A full copy of the Contract Specifications can be found with this solicitation.
A full copy of the Contract Construction Plans can be found with this solicitation.
4.0 Government Furnished
There are no Government Furnished Materials associated with this project.
5.0 Deliverables / Schedule
Key Deliverables Item No.
Deliverable / Item Title Description Frequency Reference
Delivery Format Due By
Accident Prevention Plan
Design the plan to address Federal, State, and Local Occupational Safety and Health requirements that apply to this project
Once Specifications General Requirements 2.2.A
Via email to
COR
10 days prior to on-site work beginning
Action Submittals
Written and graphic information that requires Contracting Officer’s(CO's) responsive action.
Prepare and submit Action Submittals required by individual Specification Sections.
Specifications General Requirements 3.4
Submit four copies of each submittal, unless otherwise indicated.
Before beginning work on individual item
Informational Submittals
Prepare and submit Informational Submittals required by other Specification Sections.
Prepare and submit Action Submittals required by individual Specification Sections.
Specifications General Requirements 3.5.A
Submit two copies of each submittal, unless otherwise indicated.
Before beginning work on individual item
Contractor's Construction Schedule
Provide a construction schedule that incorporates the full contract period.
Once Specifications General Requirements 3.5.B
Via email to
COR
10 days prior to on-site work beginning.
Monthly interval
Upcoming Work Summary
Prepare summary report indicating activities scheduled to occur or commence prior to submittal of next schedule update.
Monthly Specifications General Requirements 3.5.C
Via email to
COR
10 days prior to on-site work beginning.
Monthly interval
Construction Schedule Updating Report
At monthly intervals, update schedule to reflect actual construction progress and activities.
Submit with Applications for Payment
Specifications General Requirements 3.5.D
Via email to
COR
Monthly
Daily Construction Reports
Prepare a daily construction report recording information concerning events at Project site
Monthly Specifications General Requirements 3.5.E
Via email to
COR
Monthly
Item No.
Deliverable / Item Title Description Frequency Reference
Delivery Format Due By
Site Condition Reports
Report of differing site conditions
Submit at time of discovery of differing conditions.
Specifications General Requirements 3.5.F
Via email to
COR
Before continuation of work on individual item
Cost Breakdown Provide a cost breakdown schedule listing main types of work
Following Award Specifications General Requirements 3.5.G
Via email to
COR
Following Award
Project Record Documents
Record Drawings; Record Specifications; Record Product Data
Project Closeout Specifications General Requirements 5.5, 5.6, 5.7
Digital file Via email to COR
Project Closeout
Operation and Maintenance Manual furnish two complete sets of operation and maintenance (O&M) data
Before scheduling a final inspection
Specifications General Requirements 5.8
Digital file Via email to COR
Within 30 days following receipt of review comments
Testing Agency Qualifications proof of qualifications in the form of a recent report on the inspection of the testing agency by a recognized authority.
Once Specifications Quality Requirements 1.4.A
Digital file Via email to COR
Before beginning work on individual item
Permits, Licenses, and Certificates submit copies of permits, licenses, certifications, inspection reports, releases, jurisdictional settlements, notices, receipts for fee payments, judgments, correspondence, records, and similar documents established for compliance with standards and regulations bearing on performance of the Work.
Once Specifications Quality Requirements 1.4.B
Digital file Via email to COR
Before beginning work on individual item
Test and Inspection Reports
Prepare and submit certified written reports specified in other Sections
Prepare and submit test and inspection reports as required by individual Specification Sections.
Specifications Quality Requirements 1.5.A
Digital file Via email to COR
Submit test and inspection reports as required by individual Specification Sections.
Item No.
Deliverable / Item Title
Description Frequency Reference Delivery Format
Due By
Manufacturer's Technical Representative's Field Reports
Prepare written information documenting manufacturer's technical representative's tests and inspections specified in other Sections
Prepare written information documenting manufacturer's technical representative's tests and inspections specified in other Sections
Specifications Quality Requirements 1.5.B
Digital file Via email to COR
Prepare written information documenting manufacturer's technical representative's tests and inspections specified in other Sections
Factory- Authorized Service Representative's Reports
Prepare written information documenting manufacturer's factory-authorized service representative's tests and inspections specified in other Sections.
Prepare written information documenting manufacturer's factory-authorized service representative's tests and inspections specified in other Sections.
Specifications Quality Requirements 1.5.C
Digital file Via email to COR
Prepare written information documenting manufacturer's factory-authorized service representative's tests and inspections specified in other Sections.
6.0 Travel
Travel is the responsibility of the contractor.
7.0 Contractor’s Key Personnel
The Contractor is to provide name, position title and contact information of company executive responsible for the project. Contractor is to provide an onsite superintendent at all times.
Water system installer must meet all State of South Dakota licensing requirements.
Electrician performing electrical installation must have a South Dakota Electrical License. State Electrical Inspection and approval is required on all electrical work.
8.0 Security Requirements
The Contractor is to install and maintain suitable barriers to ensure the protection of the public, employees, and facilities. Protect persons, motor vehicles, surrounding buildings, plants, and surrounding surfaces or buildings from harm resulting from Contractor’s work.
Site gate lockout procedures will be established if applicable.
| Project |
| General Information |
| 1.0 Scope of Work |
| 2.0 Background |
| Contractor Requirements |
| 3.0 Technical Requirements / Tasks |
| 4.0 Government Furnished |
| 5.0 Deliverables / Schedule |
| 6.0 Travel |
| 7.0 Contractor’s Key Personnel |
| 8.0 Security Requirements |