Attachment 2 Schedule of items.xlsx

XLSX spreadsheet 12 KB Posted

Attached to
GAOA Grizzly Bear Campground
Solicitation number
127EAX27Q0004
Issued by

About this file

This is a Schedule of Items document that provides the pricing template for the Grizzly Bear Campground Reconstruction project located in the Black Hills National Forest. The schedule lists 17 line items organized by project phase, including general requirements and mobilization, demolition work (pumphouse building, water system, campground furnishings), site improvements (campground roads, campsites), new construction (pumphouse building, water storage tank, water system, host and volunteer sites), utility connections (wastewater, electrical), facility construction (new toilet building, improved existing toilet building), gates, and signage. All items are listed with zero pricing, indicating this is a blank pricing template requiring offerors to submit cost proposals for each line item.

Offerors must provide pricing on all 17 items to be considered responsive; partial quotations will not be accepted. The document specifies that payment for bond premiums shall be in accordance with FAR 52.232-5 and may be included under the Mobilization line item rather than added to the contract price. Quantities are provided for reference as in-place quantities without shrinkage or swell factors applied, and contractors are required to verify quantities independently. Offerors must provide their name, phone number, address, email, and UEI SAM number with their price quotation submission.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Sheet1

GRIZZLY BEAR CAMPGROUND RECONSTRUCTION

BLACK HILLS NATIONAL FOREST

PROJECT TITLE: GRIZZLY BEAR CAMPGROUND RECONSTRUCTION

SCHEDULE OF ITEMS

ITEM
NUMBERDESCRIPTIONPAY UNITEST QTYUNIT COSTTOTAL
0001General Requirements/MobilizationLS1$0.00
0002Pumphouse Building DemolitionEACH1$0.00
0003Water System DemolitionLS1$0.00
0004General Demolition, Campground Furnishings and AmenitiesLS1$0.00
0005Existing Campground Road ImprovementsLS1$0.00
0006Site Work for Camp SitesLS1$0.00
0007New Pumphouse BuildingLS1$0.00
0008Water Storage TankLS1$0.00
0009Water SystemLS1$0.00
0010Host Site ConstructionEACH1$0.00
0011Volunteer Site ImprovementsEACH1$0.00
0012Host Site Wastewater Connections and TankLS1$0.00
0013ElectricalLS1$0.00
0014New Toilet BuildingEACH1$0.00
0015GatesEACH1$0.00
0016SignageLS1$0.00
0017Improve Existing Toilet BuildingLS1$0.00
TOTAL BASE COST$0.00
NOTES:
1. Offerors must submit pricing on all items to be considered responsive. Must quote on all items.

2. Payment for bond premiums in accordance with FAR 52.232-5. Payments under Fixed-Price Construction Contracts shall not be in addition to the contract price but can be included under Mobilization.

3. Quantities are provided for information only and are in-place quantities. No shrinkage or swell factors have been applied. Contractor shall verify quantities.

Price Quotation Furnished By:

Name: ______________________________

Phone: ______________________________

Address:_____________________________

E-mail:______________________________

UEI SAM#: __________________________

File details come from the government source that posted it. Updated .