Attachment 3 Statement of Work.pdf
PDF 224 KB Posted
- Attached to
- GAOA Barracks Renovation Phase 2 Tahoe NF
- Solicitation number
- 127EAX26Q0088
- Issued by
-
Department of Agriculture Forest Service
About this file
This is a Statement of Work (SOW) for the Forestwide Barracks Maintenance Phase 2 project on the Tahoe National Forest located in Sierra, Yuba, Nevada, and Placer Counties in California.
The project requires comprehensive renovation of barracks buildings including roofing replacement with screwless or hidden fastener high-rib metal roofing; removal and replacement of exterior siding and trim (with Building 1029 in Sierraville retaining asbestos siding with new siding installed on top); installation of commercial-grade vinyl plank flooring; interior painting with Swiss coffee-colored Sherwin Williams SuperPaint; complete bathroom renovation including standing showers with Aquatic 13632P curtain bars, Delta Classic Bath Collection fixtures, Peerless P188620LF-BN faucets, Grover Western Pottery B872WH/T8HPWH toilets, Master Brand Mantra vanities, and low-flow fixtures; replacement of cabinets and countertops with Corian Solid Surface counters and Master Brand Mantra cabinets; and proper removal and disposal of asbestos-containing materials. The contractor must furnish all labor, materials, equipment, and incidentals necessary for completion. All work must be performed by a contractor licensed to install scheduled items in California. Full submittals requiring Forest Service approval prior to purchase and installation are required for roofing systems, siding, flooring, toilets, showers, fixtures, curtain/towel bars, sinks, faucets, vanities, mirrors, cabinets, countertops, and paint.
The project schedule runs from November 1, 2026 through May 1, 2027, with all work to be completed by May 1, 2027. An organized site visit is scheduled for June 24, 2026 at 0800 AM PST led by Assistant Forest Engineer Cesar Villa (530-966-6183). Bidders are strongly urged to conduct site visits prior to bidding. Barracks are generally occupied May through October, and typically only one barracks will be available for work at a time with all work requiring completion within an agreed timeframe to allow occupant return. Bidders must submit a proposed schedule with their bid. Contractors may propose alternative systems or items but must demonstrate cost savings or superior performance and provide manufacturer specifications for alternative structural metal roofing systems.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Attachment 2 Updated Schedule of Items.pdf | ||
| Questions and Answers 2 -9 Sep 26.pdf | ||
| 127EAX26Q0100 Amendment 1.pdf | ||
| Questions and Answers 2 Sep 26.pdf | ||
| Attachment 6 Foresthill Map.jpg | JPG image | |
| Attachment 8 Wage Determination.pdf | ||
| 127EAX26Q0088 GAOA Barracks Renovation Phase 2.pdf | ||
| Attachment 7 Sierraville Map.jpg | JPG image | |
| Attachment 2 Schedule of Items.docx | DOCX document | |
| Attachment 4 Big Bend Map.jpg | JPG image | |
| Attachment 5 Bullards Map.jpg | JPG image |
Show all 11
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
FORESTWIDE BARRACKS MAINTENANCE PHASE 2
Tahoe National Forest
Sierra, Yuba, Nevada and Placer Counties
STATEMENT OF WORK
The purpose of this project is to renovate all barracks located on the Tahoe National Forest due to being outdated. This includes but is not limited to roofing, exterior siding, flooring, interior/exterior painting, replacing doors and locks, bathroom renovation, cabinets, countertops, HAZMAT mitigation.
Furnish all labor, materials, equipment, and other incidentals necessary to complete the following work items as listed in the Schedule of Items:
• Roofing (074113) - Remove and replace all roofing on specified buildings with screwless or hidden fastener high-rib style metal roofing. Complete any structural repairs necessary before installation of new roofing. Installation of roofing shall provide a complete and usable roofing system including but not limited to all surfacing materials, associated venting, penetration sealing, and replacement of any existing gutters. Installation will comply with contract specifications and manufacturer’s installation instructions. All installations must comply with Modoc County Building Codes. Contractor will dispose of all waste, including removed roofing and decking materials. Up to 15% of the roof structural assembly, including sheathing, rafters, fascia, soffit, vent assemblies, and other roof components, if damaged, will be replaced or repaired per the CO with no modification to this contract. Additional needs will be addressed via negotiation and contract modification.
• Siding (074646) - Remove and replace all siding and trim on specified buildings. Building 1029 in Sierraville will keep the asbestos siding and new siding will be installed on top.
Complete any needed repairs or replacement of insulation. Paint siding and trim to match other buildings on complex or other colors as approved.
• Flooring (096516) - Remove and replace all flooring in specified buildings with commercial grade vinyl plank flooring. Complete any structural repairs necessary before installation of new flooring.
• Interior Painting – Paint all interior walls in specified buildings with satin finish, Swiss coffee colored paint, Sherwin Williams SuperPaint Interior Latex Satin or equivalent.
• Bathroom Renovation – Gut (remove tub, shower, toilet, vanity, mirror, cabinets, flooring, towel bars, fixtures, etc.) bathroom and renovate in specified buildings, replacing all items and fixtures in kind (unless otherwise noted) with modern, high-quality, products.
o All tubs/showers shall be replaced with standing showers with high-quality mounted curtain bars, Aquatic 13632P or equivalent. Tub/shower fixtures shall be Delta Classic Bath Collection (T13020, T13120, T13220) or equivalent. All fixtures shall be low flow.
o Vanities shall be free standing Master Brand Mantra or equivalent.
o Faucets shall be single-handle commercial grade faucets. Peerless P188620LF-BN or equivalent.
o Toilets shall be Grover Western Pottery B872WH/T8HPWH or equivalent.
• Cabinets & Countertops – Remove and replace all cabinets and countertops with modern, high quality cabinets/countertops matching current layout and design. Counters shall be Corian Solid Surface or equivalent. Cabinets shall be Master Brand Mantra or equivalent.
• HAZMAT Mitigation – Properly remove and dispose of any asbestos containing materials (noted in Schedule of Items).
Note that removal of any items listed for removal includes appropriate disposal off-forest.
SUBMITTALS
Full submittals including product specifications and details shall be required by the successful bidder for the following. Brands, materials, colors, designs, sizes, and other details as applicable must be approved by a Forest Service representative prior to purchase and installation:
• Roofing systems
• Siding
• Flooring
• Toilets
• Showers and shower fixtures
• Curtain/towel bars
• Sinks/faucets/vanities/mirrors
• Cabinets/countertops
• Paint
PROPOSALS
Contractor’s quotes shall provide for the purchase and installation of the items and types specified in the Schedule of Items and Specifications. Contractors may also provide quotes and technical plans for optional alternative systems or items but must demonstrate cost savings or superior performance of the alternative options. The contractor’s technical proposal should clearly identify the use of either a metal roofing system structurally rated for the existing purlin span, or the addition of sheathing to support the type of metal roofing specified in this contract, which requires a continuous, rigid substrate. If proposing an alternative structural metal system, provide manufacturer’s specifications.
SITE VISITS
An organized site visit has been scheduled for-
See solicitation for date and time
FS personnel leading Site Visit Contact Info
Title: Assistant Forest Engineer
Engineer/COR Name: Cesar Villa
Phone #: 530-966-6183
All bidders are strongly urged to conduct site visits prior to entering bids in order to best assess the nature and condition of the existing buildings. The building exteriors are accessible without prior approval. A tour of several representative facilities will be held starting June 24th , 2026 at 0800 AM PST at which time the interior of the buildings in concern will be open for viewing. Please contact Assistant Forest Engineer, Cesar Villa at (530) 966-6183 cesar.villa@usda.gov for further questions or to schedule site visits you would like to conduct to barracks not shown on the tour.
SCHEDULE
Calander days: November 1st, 2026 through May 1st, 2027
All work shall be completed by May 1, 2027. Barracks are generally occupied between May and October. Unless circumstances allow, only one barracks will be made available for work at a time and all work must be completed within an agreed time frame to allow for occupants to return. All buildings shall be entirely functional while occupied. Bidders shall submit a proposed schedule along with their bid so that the US Forest Service can manage tenants accordingly.
PERSONNEL QUALIFICATIONS
All work shall be performed by a contractor licensed to install scheduled items in the State of California.
mailto:cesar.villa@usda.gov
PROJECT LOCATION
A map of complex locations has been provided in the contracting documents and sites are generally locatable through online mapping applications. Approximate GPS coordinates and addresses have been submitted. Some sites require travel on National Forest roads which can be infeasible in the winter depending on conditions. For further information, or directions, contact Assistant Forest Engineer, Cesar Villa at (530) 966-6183 cesar.villa@usda.gov.
mailto:cesar.villa@usda.gov.
| STATEMENT OF WORK |
| SUBMITTALS |
| PROPOSALS |
| SITE VISITS |
| An organized site visit has been scheduled for- |
| FS personnel leading Site Visit Contact Info |
| SCHEDULE |
| Calander days: November 1st, 2026 through May 1st, 2027 |
| PERSONNEL QUALIFICATIONS |
| PROJECT LOCATION |
File details come from the government source that posted it. Updated .