Attachment 3 - SOW Chilao CG Water System.pdf
PDF 312 KB Posted
- Solicitation number
- 1240LT26Q0066
- Issued by
-
Department of Agriculture Forest Service
About this file
This is a Statement of Work for the GAOA Chilao Campground Complex Water System Rehabilitation project issued by the US Department of Agriculture Forest Service.
The contractor will perform water utility and road work at the Chilao Campground Complex in the Angeles National Forest near Los Angeles, California. Water utility work includes installing and rerouting pipe to run within roadbeds, replacing infrastructure in valve boxes and fire boxes, constructing a new valve box, rehabilitizing three existing tanks, and replacing appurtenances at four well locations. Road work entails pulverization and paving of existing roads. The contractor must maintain water service to the Visitor Center and Fire Station while connecting to existing campground loops. The project location spans from the Chilao Visitor Center and Fire Station area to four wells located approximately two miles north near the 6000 ft PCT Trailhead. The water system, originally developed in the 1930s, requires rehabilitation to serve a fire station, recreation campsites, visitor center, and partner facilities. The estimated start date is Summer 2026 with a 180-day performance period from Notice to Proceed, accounting for winter weather conditions and potential time extensions. The Forest Service intends a complete closure of the Chilao Complex during construction, requiring the contractor to submit closure duration and dates to the Contracting Officer and Contracting Officer's Representative. Work hours are restricted to non-holiday weekdays Monday through Friday from 0700 to 1900, with fire plan restrictions potentially requiring work cessation at 1:00 pm on high fire activity days. The contractor must obtain a valid California contractor's license as a General Engineering Contractor, General Building Contractor, or relevant Specialty Contractor, and a C-57 license is required to perform work at the four wells. Key deliverables include project schedule, plan of operations, traffic control plan, equipment mobilization notification, quality control plan, monthly status reports, and as-built drawings, with the project schedule due 14 days prior to the pre-work meeting.
View the file
Other files
Show all 13
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
US Department of Agriculture (USDA)
Statement of Work
GAOA Chilao Campground Complex – Water System Rehabilitation
Contents Project General Information
1.0 Scope of Work
2.0 Background
3.0 Location
4.0 Estimated Start Date / Period of Performance
5.0 Drawings and Specifications
6.0 Restrictions on Work
7.0 Camping and Housing
8.0 Required Submittals
Contractor Requirements
9.0 Technical Requirements / Tasks
10.0 Government Furnished
11.0 Deliverables / Schedule
12.0 Travel
13.0 Contractor’s Key Personnel
14.0 Security Requirements
15.0 Data Rights
16.0 Section 508 – Electronic and Information Technology Standards Attachments
Project Chilao Campground Complex – Water System Rehabilitation
General Information
1.0 Scope of Work
The Contractor will be performing water utility and road work in the Chilao area. Water utility work will include installing pipe following the existing alignment and rerouting at particular areas to run within the roadbed. Supporting work to include replacement of infrastructure in existing valve boxes, fire boxes, and stand pipes, construction of a new valve box, rehabilitation of three existing tanks, and replacing appurtenances at four well locations. Road work will include pulverization and paving of existing roads. The Contractor will be responsible to maintain water service to buildings at the Visitor Center and Chilao fire station areas and tie into existing campground loops.
2.0 Background
The Chilao Campground Complex water system was developed by the Forest Service in the 1930s, see attachment ChilaoSystemHistoricalDrawing. This aged infrastructure is in need of repair to continue serving a fire station, recreation campsites, visitor’s center, and partners in the immediate area. Repair to the pipeline, valves, tanks, and sources will ensure delivery of potable water at Chilao. The most recent diagram of the system is shown in attachment ChilaoSchematic1999.
3.0 Location
The main portion of the work will take place around the Chilao Campground complex which includes the Chilao Visitor Center (34.32673611, -118.00565556), Chilao Fire Station (34.333400, -118.025400), picnic area, and various campground loops (Manzanita, Coulter, Little Pines, and Meadow). The four wells are located about two miles north up State Route 2 Angeles Forest Highway near the 6000 ft PCT Trailhead (34.34963400, -117.96283056) along a trail.
4.0 Estimated Start Date / Period of Performance
The Chilao Campground Complex area is at a high elevation which can have snow and ice during winter months. The desired start date is Summer 2026 in hopes a majority of the work is completed before winter conditions impact access, which is not always the case, and to avoid work during the summer as the water system serves a fire station which is important for fire response. A period of performance of 180 days will be given for the contract from the issuance of the Notice to Proceed and weather will be taken into account for time extensions. The Forest Service intends to have a complete closure of the Chilao CG Complex during construction activities to limit disruptions. Contractor will need to submit a request for the duration and dates of closure to the CO and COR as indicated in section 6.0 Restrictions on Work.
5.0 Drawings and Specifications
Drawings are included with this solicitation for the work, see attachment GAOAChilao_DesignDrawings. Specifications are included as attachments. One set of specifications is for the utility work, see attachment GAOAChilao_Specifications and the other is for the road work, see attachment GAOAChilao_FSSS.
6.0 Restrictions on Work
• Work hours are limited to non-holiday weekdays, Monday – Friday, 0700 – 1900. Work site much be clear by noon the Friday before a Monday holiday.
• In accordance with the fire plan, see attachment GAOAChilao_FirePlan. The Fire Plan restrictions may require work to cease at 1:00 pm or not be initiated at all on a high fire activity day.
• Contractor is responsible for reviewing the mitigation measures and in accordance with them, see attachment GAOAChilao_MinimizationMeasures.
• When the Contracting Officer (or designated representative) determines that adverse weather has made access too dangerous or that continued vehicular travel would cause unacceptable road damage.
• For sites requiring archaeology monitoring, Contractor must notify COR at least 24 hours prior to any ground disturbing activities and no ground disturbing activities may occur without a Forest Service archaeologist on site.
• When the Contracting Officer or designated representative determines that work must stop due to the presence of archaeological artifacts.
• The Contractor is responsible for the security of their tools and equipment at all times.
• Contractor is responsible for removal and disposal of all excavated dirt and shall not leave excavated dirt scattered over the site, unless approved by the COR.
• All trash and loose materials shall be secured by the contractor daily.
• The Contractor is responsible for installing sediment control devices, such as straw wattles, to prevent sediment runoff to nearby areas. Excavation work shall not commence until sediment control devices have been installed and approved by the
COR.
• The Contractor shall not use Government trash facilities without the COR’S approval.
• All construction debris remains the property of the Contractor and shall be properly disposed of off National Forest Land.
• The Contractor will be able to utilize the Forest Service Roads; however, the Contractor will be responsible for any damage to the roads due to construction activities. The Contractor shall be responsible for obtaining permission to use all other roads and staging areas.
• The Contractor shall submit a request to the CO and COR for closure of the Chilao complex. The Contractor should identify when a closure starts and ends within their schedule so it can be communicated to emergency personnel on the forest.
• The Contractor may use the areas within the Chilao Picnic Day Use Area (34.326399, -118.007481) for layout or staging during the construction. Additional space should be submitted to the CO and COR for approval.
7.0 Camping and Housing
Contractor may request to camp on Forest Service land during the project. Camping on Forest Service land is not a right, permission may be revoked for failure to comply with the terms of the permit.
8.0 Required Submittals
From GAOAChilao_Specifications Section 02318 Excavation and Backfill for Utilities
• Certifications, results, permits, compaction, and construction plans Section 02511 Water Distribution
• Components and plumbing schematic layouts Section 05500 Metal Fabrication
• Shop drawings Section 09960 High-Performance Coatings
• Samples of coatings
From GAOAChilao_FSSS 153 – Contractor Quality Control
• Quality Control Plan 156 – Public Traffic
• Traffic Control Plan 157 – Soil Erosion and Sediment Control
• Erosion Control Measures Plan
Contractor Requirements
9.0 Technical Requirements / Tasks
• The Contractor shall furnish the necessary personnel, material, equipment, services, and facilities to perform the Statement of Work/Specifications.
• The Contractor shall repair all associated damage on established roads or infrastructure caused by their operations or equipment prior to partial or final payment.
• The Contractor shall dispose of all project related trash, debris and excess as it accumulates on site.
• The Contractor is responsible for traffic control and equipment requirements in work areas when working on
National Forest System Lands. The Contractor can request the Forest Service to close areas to the public during portions of the work.
• The Contractor shall coordinate with the Forest Service as the owner to submit required information to the Stormwater Multiple Application and Reporting Tracking System (SMARTS) to properly address a SWPPP.
• The Contractor shall perform work according to items outlined in attachment GAOAChialo_MinimizationMeasures.
• The Contractor shall coordinate with the Forest Service when water service will not be available to facilities or work will impact the ability of the fire station to respond to incidents. The Contractor should notify the Forest Service three weeks prior to impacts so the fire station can stage equipment accordingly or relocate for a period of time.
• The Contractor is responsible for returning the system to operation upon the completion of the work and should not all option items be exercised, appropriately stub water pipes or tie back into existing connections.
• The Contractor must obtain a valid contractors license in the State of California upon award under FAR 52.236-7 Permits and Responsibilities. Contractor must be licensed as a (A) General Engineering Contractor, (B) General Building Contractor, or (C) Specially Contractor with relevant specialization.
• The Contractor or subcontractor must have a C-57 license to perform work at the fours well.
10.0 Government Furnished
There will be no government furnished property, supplies, or materials. The Contractor may be able to use water from the Chilao water system during construction to support work by pulling from the system or tanks while connected or from a location further north during the construction.
11.0 Deliverables / Schedule
Contractor is responsible for the following deliverables:
Key Deliverables
Item No. Deliverable Objective Due 1 Project Schedule Define the timeline, milestones of contract items, and identify critical path. Update of schedule submitted in bid acceptable.
14 days prior to prework meeting
2 Plan of Operations FSSS 314.04 14 days prior to prework meeting 3 Traffic Control Plan FP-14 156 – Public Traffic 14 days prior to prework meeting 4 Equipment
Mobilization Notification
FP-14 151 – Mobilization 14 days prior to mobilizing equipment onto the Angeles National Forest
5 Contractor Quality Control Plan
FP-14 153.02 – Contractor Quality Control Plan Before beginning work
6 Monthly Status Report Cover work completed during the month, state work to be accomplished the following month, and identify any problems that arose via email to COR.
Monthly, by 1700 local time on the last day of the month until contract expires
7 As Built Drawings The Contractor will be provided with project files to update based on work completed and document any changes.
Before final invoice is approved
Expected projected start date will be in Summer 2026. Construction activities will occur in the areas defined in the drawings.
Fire or other forest restrictions such as high PAL levels and area closure shall apply. See attachment GAOAChilao_FirePlan for further information and fire plan requirement.
12.0 Travel
No additional payment will be made to the contractor for any travel incurred while being on the site for the duration of the project. This includes any pre-bid, pre-construction, or field observation meetings.
13.0 Contractor’s Key Personnel
The Contractor shall have key personnel that meet the following:
1. Capability in the same or similar key personnel positions on successful relevant projects of similar scope and magnitude to this solicitation;
2. Strong technical knowledge and skill required for this solicitation;
3. Effective problem solving, communication, coordination, and organization that present lower levels of risk and will be more favorably rated; and
4. Capacity for key personnel to focus on the project. Those not demonstrating these attributes present higher levels of risk and will be less favorably rated.
5. Personnel may serve multiple roles provided the individual possesses the requisite qualifications and competencies for each position, i.e. one person acting as the superintendent and QC Manager.
14.0 Security Requirements
There are no special security requirements that are required for this project.
15.0 Data Rights
N/A
16.0 Section 508 – Electronic and Information Technology Standards All deliverables for this project shall meet Section 508 compliance requirements.
Attachments
• ChilaoSchematics1999
• ChilaoSystemHistoricalDrawing
• GAOAChilao_DesignDrawings
• GAOAChilao_FirePlan
• GAOAChilao_FP-24 FSSS
• GAOAChilao_MinimizationMeasures
• GAOAChilao_Photos
• GAOAChilao_Scheduleof Items
• GAOAChilao_CSI Specifications
| GAOA Chilao Campground Complex – Water System Rehabilitation |
| Project |
| General Information |
| Contractor Requirements |
File details come from the government source that posted it. Updated .