Attachment 3 - SCB Building Elevator Modernization Specification Summary.pdf
PDF 124 KB Posted
- Attached to
- Elevator Maintenance Services
- Solicitation number
- RFP AAGA 2027000019 1
- Issued by
- Denver County, Denver City, Colorado
About this file
This is a specification summary document for the State of Colorado's Office of the State Architect, State Buildings Program, detailing modernization requirements for passenger elevators at the State Capitol Building located at 200 East Colfax Avenue in Denver, Colorado. The project, designated 2025-088M24, involves comprehensive modernization of the building's elevator system while preserving certain existing components. The modernization scope includes replacement of the original Otis gearless DC hoist machines with new permanent magnet AC gearless hoist machines, installation of new MCE iBox two-car group microprocessor control systems, and provision of new ReGen VVVF motor drive units with transformers as required. Additional work encompasses installation of new Hollister-Whitney governors, GAL hoistway door equipment, TLS limit switches, Elsco roller guides, new car door operators, and complete signaling systems including new main car operating panels, digital position indicators, dual hall push button risers with LED illuminated fixtures, and directional hall lanterns with "opposite elevator arriving" notification systems at each floor. The specification calls for retaining existing elements including bronze hoistway door panels, entrances, sills, car safeties and linkages, buffers, and elevator cab interiors. The system will maintain a speed of 500 feet per minute at 2,500 pounds capacity with four stops across floors marked G, 1, 2, and 3, with an approximate total travel distance of 60 feet.
The specification document functions as a technical summary and notes that it is abbreviated in nature; any discrepancies between the summary and the full technical specifications, or items not included in the summary, are to be resolved in favor of the complete technical specifications. The document does not address pricing terms, contract duration, set-asides, incumbent contractors, funding sources, or other financial and administrative details. All work is subject to compliance with current code standards, specifically A17.1 2019 standards for elevator systems. The contractor is responsible for verifying existing conditions and performing realignment work as needed to ensure smooth and quiet elevator operation.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
State of Colorado – State Capitol Building 200 East Colfax Avenue
Passenger Elevator Modernization Specifications Denver, CO 80203
State of Colorado – Office of the State Architect - State Buildings Program February 27, 2025
Project: 2025-088M24 – Modernize Passenger Elevators – State Capitol Building
2.01 PASSENGER ELEVATOR SCHEDULE/EQUIPMENT SUMMARY (1)
State Capitol Building Existing After Modernization
Description:
Speed/Capacity 500 FPM @ 2,500 Lbs. 500 FPM @ 2,500 Lbs.
Stops/Openings Four (4) Four (4) Floor Marking: G, *1, 2, 3
Travel: Approximately 60 feet Contractor to verify
Operation Duplex Operation Microprocessor – Two (2) Car Group
Machine Room:
Gearless Hoist Machine, Bedplate, Deflector
Sheave, and Hoist Cables
Remove the original Otis Gearless DC Hoist Machines, and install new Permanent Mag-net AC Gearless Hoist Machine, Bed Plate, Machine Room mounted 1:1 Double Wrap
Deflector Sheave, w/ Main and Auxiliary Brake Assembly. Install new Hoist Cables. (5 –
½ Hoist Cables)
Controller Install new MCE iBox Two Car Group microprocessor control system.
Power Conversion Provide new "ReGen" VVVF Motor Drive Unit and Transformers, if required.
Governors Install new Hollister-Whitney Governors, Governor Cable and Tension Sheave.
Hoistway:
Hoistway door equipment Install new GAL or approved equal hoistway door tracks, hanger rollers, closers, inter-locks, pickup rollers, retainers, door gibs, and fire stops.
Hoistway Doors, Entrances and Sills
Clean, polish, and retain the existing Bronze Hoistway Door Panels, Entrances, and Sills.
Hoistway limit switches Install new TLS Slowdown, ETS, and Limit Switches.
Car & Cwt Rails Realign as needed for smooth/quiet ride.
Wiring/Duct Install new traveling cables, hoistway wiring, and machine room wiring.
Car & Cwt. Roller Guides Install new Elsco Type “A” Tandem Car Roller Guides. Install new Elsco Type “D”
Counterweight Roller Guides.
Car Safeties Retain the existing Hollister-Whitney Type “B” Safeties & Linkages.
Car:
Car-top-control Provide new
Door Operator Install new GAL – MOVFE Linear or approved equal Car Door Operators.
Car Door Panels Install new #4 satin finish Bronze Car Door Panels, Header, Tracks, Hanger Rollers, and
Gate Switch. Support Car Door Operator from the Car Top, not the Car Sling.
Door Protective Device Provide new Janus 3D or approved equal.
Top of Car Railing Provide per current code
Cab: . new Front Return Panel, Strike Jamb, and Transon. Clean and polish Car Door Sill. Retain the existing elevator cab interiors. Provide new Cab Protective Pads and Pad Hooks.
Pit:
Stop Switch Provide in compliance with code.
Buffers Clean, refurbish and retain the existing Car and Counterweight Buffers.
Signal Fixtures
Car Operating Panel Provide new Main COP. A17.1 2019 compliant. Provide Digital PI’s. Install Dual Car
Lanterns
Hall PB Station
Dual Hall Push Button
Riser (North & South)
Install new A17.1 - 2019 compliant LED illuminated Hall Pushbutton fixtures and Posi-tion Indicator at each floor. At the 1st floor install new three (3) position Firefighters’ key switch, Phase I Operating Instructions, “Communication Failure" indicator light, Buzzer, and Key Switch. Provide an Emergency Power indicator light.
Combo Hall PI & Lanterns
“Opposite Elevator Arriv-ing” notification
Above each entrance, install a new combination Directional Hall Lantern and “Opposite
Elevator Arriving” light and Gong on each Car and at each floor.
Hoistway Access Switch Provide Top and Bottom Hoistway Access per code
(1) Summary is just a brief outline to give general scope of work. If a discrepancy exists between the summary and body of the technical specifications, or if an item is not included in the summary, the body of the technical specifications should take precedence.