This document is a Past Performance Survey for a federal contract opportunity to provide construction services for a door replacement project at the Federal Aviation Administration's (FAA) Air Route Traffic Control Center (ARTCC) located in Longmont, Colorado.
The survey is requesting ratings on the contractor's past performance in areas such as managing project cost, maintaining schedule, following customer requirements, coordination and scheduling, safety compliance, communication, problem-solving, and overall customer satisfaction. The contract opportunity has a solicitation number of 697DCK-24-R-00450, a contract value estimated between $750,000 and $1,000,000, and is set aside for small businesses under NAICS code 236220 - Commercial and Institutional Building Construction. The site visit is scheduled for July 29, 2024, questions are due by August 15, 2024, and offers are due by August 29, 2024. The contracting agency is the Department of Transportation Federal Aviation Administration Northwest Mountain Region.
View the file
Other files
Show all 11
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PAST PERFORMANCE SURVEY INSTRUCTIONS
SOLICITATION NO. 697DCK-24-R-00450
FEDERAL AVIATION ADMINISTRATION ACQUISITION ACTIVITY
Des Moines, WA The Federal Aviation Administration (FAA) is considering a contractor to provide construction services for a door replacement project at FAA’s Air Route Traffic Control Center (ARTCC) located in Longmont, Colorado. As part of the solicitation process, we are collecting past performance information on contractors and their key personnel. This information will be used to assist the FAA in the selection of a contractor to complete the project. You have been listed as a past performance reference.
Please rate each of the criteria according to the following scale:
| 1 |
| 0 – 25% of the time |
| Strongly Disagree |
| PLEASE RETURN COMPLETED RESPONSE TO: |
Federal Aviation Administration
ATTN: Cindi Tjelde E-MAIL: cindi.tjelde@faa.gov
| 2 |
| 26 – 40% of the time |
| Disagree |
| 3 |
| 41 – 55% of the time |
| Somewhat Disagree |
| 4 |
| 56 – 70% of the time |
| Somewhat Agree |
| 5 |
| 71 – 85% of the time |
| Agree |
| 6 |
| 86 – 100% of the time |
| Strongly Agree |
NA
No Knowledge of This Element
FOR OFFICIAL USE ONLY - SOURCE SELECTION SENSITIVE WHEN COMPLETED
PAST PERFORMANCE SURVEY
RATER’S Name & Title
RATER’S Organization / agency
RATER’S TEL NO.
RATER’S E-MAIL ADDRESS:
CONTRACTOR’S NAME & ADDRESS
PROJECT TITLE OR DESCRIPTION OF REQUIREMENT:
CONTRACT NUMBER:
CONTRACT VALUE (INCLUDING OPTIONS):
CONTRACT TYPE:
FORMCHECKBOX
FIXED PRICE
FORMCHECKBOX
COST + FEE
FORMCHECKBOX
COMPETITIVE
FORMCHECKBOX
NON-COMPETITIVE
FORMCHECKBOX
SET-ASIDE
FORMCHECKBOX
SEALED BID
FORMCHECKBOX
NEGOTIATED
FORMCHECKBOX
SEALED BID
FORMCHECKBOX
NEGOTIATED
CONTRACT AWARD & COMPLETION DATE:
| PAST PERFORMANCE ELEMENT |
| RATING |
| 1 |
| 2 |
| 3 |
| 4 |
| 5 |
| 6 |
| N/A |
1.
Contractor was able to manage project cost (i.e., minimize change orders).
FORMCHECKBOX
FORMCHECKBOX
FORMCHECKBOX
FORMCHECKBOX
FORMCHECKBOX
FORMCHECKBOX
FORMCHECKBOX
2.
Contractor was able to maintain project schedule (completed on time or early).
FORMCHECKBOX
FORMCHECKBOX
FORMCHECKBOX
FORMCHECKBOX
FORMCHECKBOX
FORMCHECKBOX
FORMCHECKBOX
3.
Contractor followed customer’s rules and regulations (i.e., contract requirements, building codes, specific policy, etc.)
FORMCHECKBOX
FORMCHECKBOX
FORMCHECKBOX
FORMCHECKBOX
FORMCHECKBOX
FORMCHECKBOX
FORMCHECKBOX
4.
Contractor was efficient in project coordination and scheduling of different trades.
FORMCHECKBOX
FORMCHECKBOX
FORMCHECKBOX
FORMCHECKBOX
FORMCHECKBOX
FORMCHECKBOX
FORMCHECKBOX
5.
Contractor complied with all safety standards and/or requirements.
FORMCHECKBOX
FORMCHECKBOX
FORMCHECKBOX
FORMCHECKBOX
FORMCHECKBOX
FORMCHECKBOX
FORMCHECKBOX
6.
Contractor communicated effectively with you (the customer) throughout the entire project.
FORMCHECKBOX
FORMCHECKBOX
FORMCHECKBOX
FORMCHECKBOX
FORMCHECKBOX
FORMCHECKBOX
FORMCHECKBOX
7.
Contractor utilized problem-solving skills effectively when problems arose during the project work.
FORMCHECKBOX
FORMCHECKBOX
FORMCHECKBOX
FORMCHECKBOX
FORMCHECKBOX
FORMCHECKBOX
FORMCHECKBOX
8.
Closeout process was smooth and contractor submitted all closeout documents (as-builts, warranties, O&Ms, promptly).
FORMCHECKBOX
FORMCHECKBOX
FORMCHECKBOX
FORMCHECKBOX
FORMCHECKBOX
FORMCHECKBOX
FORMCHECKBOX
| 9. Overall customer satisfaction. |
| FORMCHECKBOX |
FORMCHECKBOX
FORMCHECKBOX
FORMCHECKBOX
FORMCHECKBOX
FORMCHECKBOX
FORMCHECKBOX
Comments or additional information:
FOR OFFICIAL USE ONLY - SOURCE SELECTION SENSITIVE WHEN COMPLETED
File details come from the government source that posted it. Updated .