This document is Forest Service Supplemental Specifications (FSSS) that modifies the FP-24 standard specifications for construction of National Forest System Roads.

The FSSS establishes definitions, terms, and procedures specific to Forest Service road construction contracts, incorporating both public works and timber sale contract frameworks. Key modifications include: deletion of Transportation Acquisition Regulations (TAR) references in favor of Agriculture Acquisition Regulations (AGAR); addition of Forest Service-specific acronyms and abbreviations (FSSS, MSHA, NESC, WCLIB, MFBM); and redefined contract terms such as "Contractor" (also called "Purchaser" in timber contracts), "Notice to Proceed" (replaced with "Contract Award" for timber contracts), and new definitions for "Pioneer Road," "Protected Streamcourse," "Road Order," and "Utilization Standards." The specifications modify excavation and embankment requirements to include rock cuts, earth cuts, and drainage features with specific compaction standards. Clearing and grubbing procedures require merchantable timber to be cut to maximum stump heights and bucked at specified lengths, with all merchantable timber becoming Government property. Measurement and payment terms specify decimal accuracy levels for various pay items ranging from 0.01 to 1 unit precision, with contract quantity adjustments permitted only when errors exceed 15 percent. Section 552 (Structural Concrete) removes the requirement to deliver verification cylinders to the Contracting Officer, and Section 703 (Aggregate) specifies maximum Los Angeles abrasion of 30 percent for chip seal aggregate per AASHTO T 96.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Contents

PREFACE

Section 101. – TERMS, FORMAT, AND DEFINITIONS Section 101. – TERMS, FORMAT, AND DEFINITIONS Section 101. – TERMS, FORMAT, AND DEFINITIONS Section 102. - BID, AWARD, AND EXECUTION OF CONTRACT Section 103. – SCOPE OF WORK Section 104. – CONTROL OF WORK Section 104. – CONTROL OF WORK Section 105. – CONTROL OF MATERIAL Section 106. – ACCEPTANCE OF WORK Section 108. - PROSECUTION AND PROGRESS Section 109. - MEASUREMENT AND PAYMENT Section 109. - MEASUREMENT AND PAYMENT Section 109. - MEASUREMENT AND PAYMENT Section 201. - CLEARING AND GRUBBING Section 201. - CLEARING AND GRUBBING Section 204. – EXCAVATION AND EMBANKMENT Section 204. – EXCAVATION AND EMBANKMENT Section 552. – STRUCTURAL CONCRETE Section 703. - AGGREGATE

PREFACE

Delete all but the first paragraph and add the following:

The Forest Service, US Department of Agriculture has adopted FP-24 for construction of National Forest System Roads. The Forest Service Supplemental Specifications (FSSS) shall be incorporated in the FP-24. The applicable specifications for the project will be the FP-24 as modified by the FSSS.

Section 101. – TERMS, FORMAT, AND DEFINITIONS

Add the following paragraph to Subsection 101.01 Meaning of Terms:

Delete all references to the TAR (Transportation Acquisition Regulations) in the specifications.

Add the following to Subsection 101.03 Abbreviations:

(a) Acronyms.

AGAR — Agriculture Acquisition Regulations

AFPA — American Forest and Paper Association

FSSS – Forest Service Supplemental Specifications

MSHA — Mine Safety and Health Administration

NESC — National Electrical Safety Code

WCLIB — West Coast Lumber Inspection Bureau

(d) Miscellaneous unit abbreviations.

MP - milepost location ppm - parts per million volume

STA – station location

MFBM - thousand feet board measure volume

Make the following changes to Subsection 101.04 Definitions:

Delete these definitions and replace with the following:

Bid Schedule — The Schedule of Items.

Bridge — A structure, including supports, erected over a depression or an obstruction such as water along a road, a trail, or a railway and having a deck for carrying traffic or other loads.

Contractor — The individual or legal entity contracting with the Government for performance of prescribed work. In a timber sale contract, the contractor is the “Purchaser”.

Culvert — Any structure with a bottom, regardless of fill depth, depth of invert burial, or presence of horizontal driving surface, or any bottomless (natural channel) structure with footings that will not have wheel loads in direct contact with the top of the structure.

Drawings —Design sheets or fabrication, erection, or construction details submitted to the CO by the Contractor.

Neat Line — A line defining the proposed or specified limits of an excavation or structure.

Notice to Proceed — (Public Works Contracts) Written notice to the Contractor to begin the contract work. (Timber Contracts) does not apply, replace NTP with Contract Award.

Right-of-Way — A general term denoting (1) the privilege to pass over land in some particular line (including easement, lease, permit, or license to occupy, use, or traverse public or private lands), or (2) Real property necessary for the project, including roadway, buffer areas, access, and drainage areas.

Add the following definitions:

Adjustment in Contract Price — “Equitable adjustment,” as used in the Federal Acquisition Regulations, or “construction cost adjustment,” as used in the Timber Sale Contract, as applicable.

Change — “Change” means “change order” as used in the Federal Acquisition Regulations, or “design change” as used in the Timber Sale Contract.

Forest Service — The United States of America, acting through the Forest Service, U.S.

Department of Agriculture.

Forest Service Supplemental Specifications – The Forest Service uses supplemental specifications to modify the FP-24 to meet the agency needs and intents. FSSS revise the FP-24 by adding, deleting, replacing, revising, replacing part of entire sections or subsections or adding new sections to the FP..

Pioneer Road — Temporary construction access built along the route of the project.

Purchaser — The individual, partnership, joint venture, or corporation contracting with the Government under the terms of a Timber Sale Contract and acting independently or through agents, employees, or subcontractors.

Protected Streamcourse — A drainage shown on the plans or timber sale area map that requires designated mitigation measures.

Road Order — An order affecting and controlling traffic on roads under Forest Service jurisdiction. Road Orders are issued by a designated Forest Officer under the authorities of 36 CFR, part 260.

Utilization Standards — The minimum size and percent soundness of trees described in Public Works contract specifications or Timber Sale and stewardship contract provisions to determine merchantable timber.

Add Figure 101-1—Illustration of road structure terms:

Figure 101-1—Illustration of road structure terms

Section 102. - BID, AWARD, AND EXECUTION OF CONTRACT

Delete Section 102 Bid, Award, and Execution of Contract in its entirety.

Section 103. – SCOPE OF WORK

Delete all of Section 103 Scope of Work except Subsection 103.01 Intent of Contract.

Section 104. – CONTROL OF WORK

Delete Subsection 104.07 Coordination of Contract Documents.

Section 104. – CONTROL OF WORK

Add the following Subsection 104.12 Use of Roads by Contractor:

The Contractor is authorized to use roads under the jurisdiction of the Forest Service for all activities necessary to complete this contract, subject to the limitations and authorizations designated in the Road Order(s) or described in the contract, when such use will not damage the roads or national forest resources, and when traffic can be accommodated safely.

Section 105. – CONTROL OF MATERIAL

Delete second paragraph and subparagraphs (a) and (b) in Subsection 105.05 Use of Material Found in the Work and replace it with the following:

The right to use and process material found in the work excludes the use and processing of material for nongovernment contract work, except for the disposal of waste material. Materials produced or processed from Government lands in excess of the quantities required for performance of this contract are the property of the Government. Place excess material at government-approved agreed to location(s), at no additional cost to government.

Section 106. – ACCEPTANCE OF WORK

Delete the 3rd and 4th paragraphs in Subsection 106.01 Conformity with Contract Requirements.

Section 108. - PROSECUTION AND PROGRESS

Delete Section 108 Prosecution and Progress in its entirety.

Section 109. - MEASUREMENT AND PAYMENT

Delete Subsections 109.06 Pricing and Adjustments, 109.07 Estimated Work, 109.08 Progress Payments, and 109.09 Final Payment.

Delete Table 109-1 of Subsection 109.01 Measurement of Work and replace with the following:

Table 109-1

Decimal Accuracy of Quantities for Payment

Pay Item Level of Precision Acre 0.01 Cubic Foot 1 Cubic Yard 1 Cubic Yard Exception - Structure Excavation;

Sheathing; Materials; Bedding, Bed Course, and Backfill, Materials; Gabions;

0.1

Cubic Yard Exception – Concrete; Masonry 0.01 Day 1 Each 1 Gallon 1 Hour 0.1 Linear Foot 1 Linear Foot Exception - Timber, Steel, and Concrete Piles

0.1

M-Gallon 0.1 Mile 0.01 Month 0.1 Pound 1 Square Foot 0.1 Square Yard 0.1 Station 0.1 Thousand Board Feet Measure 0.01 Ton 0.1 Ton Exception - Calcium Chloride; Sodium Chloride;

Hydrated Lime; Bituminous Materials; Pavements; Bed Course Materials

0.01

Week 0.1

Delete Subsection 109.02(c) Measurement Terms and Definitions, Contract quantity and replace with:

(c) Contract quantity. The quantity to be paid is the quantity listed in the bid schedule. The contract quantity will be adjusted for authorized changes that affect the quantity or for errors made in computing this quantity when that error exceeds 15% or more. If there is evidence that a quantity specific as a contract quantity is incorrect by 15% or more, submit calculations, drawings, or other evidence indicating why the quantity is in error and request in writing that the quantity be adjusted.

Section 201. - CLEARING AND GRUBBING

Delete paragraph (c) in Subsection 201.04(c) Clearing and replace with the following:

(c) In areas outside the excavation, embankment, and slope rounding limits, cut stumps to maximum stump height shown in table below.

Fall and buck the merchantable material at lengths longer than the minimum lengths listed, or in multiples thereof (i.e. 8 ft, 16 ft, 24 ft, 32 ft), not to exceed 8 feet in length to allow for transportation of the material. Merchantable timber shall be decked at designated location(s).

Forest Products Utilization Standards:

Species Product Max. Stump Height

Minimum Specifications

Piece Required to be Removed

Length (feet)

Diameter Inside Bark at Small End (inches)

1/

No merchantable timber NA 3”

1/ Enter Merchantability Factor (Merch. Factor) or Net Scale in % of Gross Scale, whichever is appropriate.

Section 201. - CLEARING AND GRUBBING

Delete Subsection 201.06 Disposal and replace with the following:

201.06 Disposal. Merchantable timber is Government property. Dispose of clearing and grubbing debris according to Subsection 203.07.

Section 204. – EXCAVATION AND EMBANKMENT

Delete Subsection 204.06 Roadway Excavation and replace with the following:

204.06 Roadway Excavation. Excavate as follows:

(a) Rock cuts. Verify the top portion of the rock cuts during pioneer access or initial excavation. Construct the final soil cut before starting drilling for rock blasting or other rock excavation methods unless approved. Blast rock according to Forest Service Supplemental Specification Section 205 if approved by the CO. Excavate rock cuts to 6 inches below subgrade within the roadbed limits. Backfill to subgrade with select borrow. Compact the material according to Subsection 204.11.

(b) Earth cuts. Scarify earth cuts to 6 inches below subgrade within the roadbed limits.

Compact the scarified material according to Subsection 204.11.

(c) Drainage Feature. Drainage feature includes construction of all ditches, minor channel changes, drainage dips, catch basins, surface water deflectors, and other minor drainage structures. Compact the material according to Subsection 204.11. Excavate on a uniform grade between control points.

Remove snow or ice in advance of the work and deposit beyond the roadway limits in a manner to prevent resource damage.

Conserve 6-inch minus material from the roadway excavation to use for finishing the roadbed.

Dispose of unsuitable or excess excavation material according to Subsection 204.14. Replace shortage of suitable material caused by premature disposal of roadway excavation.

At the end of each day’s operations, shape to drain and compact the work area to a uniform cross-section.

Section 204. – EXCAVATION AND EMBANKMENT

Delete 204.16(a)(1)(a) Measurement, Roadway Excavation and replace with the following:

(a) Roadway prism excavation;

Add the following to Subsection 204.16(g) Measurement:

(g) Drainage features. Measurement includes all excavation, embankment, shaping, and grading necessary for a completed drainage feature.

Section 552. – STRUCTURAL CONCRETE

Delete from Table 552-10 Remarks column “Deliver verification cylinders to the CO or designated laboratory for scheduled testing” in Section 552 Structural Concrete.

Section 703. - AGGREGATE

Delete Subsection 703.09(e) Chip Seal Aggregate and Replace with the following:

(e) Los Angeles abrasion, AASHTO T 96 30 percent maximum.

PREFACE
Section 101. – TERMS, FORMAT, AND DEFINITIONS
Section 101. – TERMS, FORMAT, AND DEFINITIONS
Section 101. – TERMS, FORMAT, AND DEFINITIONS
Section 102. - BID, AWARD, AND EXECUTION OF CONTRACT
Section 103. – SCOPE OF WORK
Section 104. – CONTROL OF WORK
Section 104. – CONTROL OF WORK
Section 105. – CONTROL OF MATERIAL
Section 106. – ACCEPTANCE OF WORK
Section 108. - PROSECUTION AND PROGRESS
Section 109. - MEASUREMENT AND PAYMENT
Section 109. - MEASUREMENT AND PAYMENT
Section 109. - MEASUREMENT AND PAYMENT
Section 201. - CLEARING AND GRUBBING
Section 201. - CLEARING AND GRUBBING
Section 204. – EXCAVATION AND EMBANKMENT
Section 204. – EXCAVATION AND EMBANKMENT
Section 552. – STRUCTURAL CONCRETE
Section 703. - AGGREGATE

File details come from the government source that posted it. Updated .