This document is a technical specification file for the HVAC and Direct Digital Control (DDC) system component of a VA Central Iowa Health Care System renovation project located in Des Moines, IA. The specifications detail requirements for a comprehensive building automation control system focusing on the Building 1 Level 1 Clinics Renovation, with specific emphasis on digital control systems, sensors, controllers, and communication protocols.
The project involves installing a BACnet-compliant control system with multiple components, including one air handling unit, one energy recovery ventilator, four variable frequency drives, two exhaust fans, thirty-two variable air volume terminal units with hot water reheat coils, two tertiary loop hot water pumps, two steam-to-hot water heat exchangers, two hot water radiant heaters, and nine electric radiant heaters. The system will integrate with the existing Metasys Building Automation System by Johnson Controls, utilizing native BACnet devices with Ethernet communication. Key technical requirements include precise temperature and humidity sensing, electronic controllers with advanced programming capabilities, comprehensive network architecture, and stringent performance standards for response times, graphic displays, and system reliability.
View the file
Other files
Show all 36
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Anderson Engineering of Minnesota, LLC
13605 1st Avenue North
Plymouth, MN 55441
Phone: 763-412-4000 Fax: 763-412-4090
Prepared in association with the following:
IMEG Corp.
2882 106th Street | Des Moines, IA 50322
Building 1 Level 1 Clinics Renovation
VA PROJECT NUMBER: 636A6-21-109
13600 30th Street
Des Moines, IA 50310
TECHNICAL SPECIFICATIONS
Volume 2: DIVISIONS 21 - 32
ANDERSON ENGINEERING OF MN, LLC
Project Number: 16270
Issue for
CONSTRUCTION DOCUMENTS
FEBURARY 21, 2025
VA Central Iowa Health Care System VA Project 636A6-21-109
Building 1 Level 1 Clinics Renovation 02-21-2025
13600 30th Street CONSTRUCTION DOCUMENTS
Des Moines, IA 50310 VERSION 01-01-23
00 01 10-1
DEPARTMENT OF VETERANS AFFAIRS
VHA MASTER SPECIFICATIONS
TABLE OF CONTENTS
Section 00 01 10
SECTION NO. DIVISION AND SECTION TITLES DATE
DIVISION 00 - SPECIAL SECTIONS
00 01 15 List of Drawing Sheets 05-20
DIVISION 01 - GENERAL REQUIREMENTS
01 00 00 General Requirements 11-24
01 32 16.15 Project Schedules (Small Projects – Design/Bid/Build 01-24
01 33 23 Shop Drawings, Product Data, and Samples 11-23
01 35 26 Safety Requirements 12-23
01 42 19 Reference Standards 11-20
01 45 00 Quality Control 02-21
01 45 29 Testing Laboratory Services 11-18
01 45 35 Special Inspections 06-21
01 57 19 Temporary Environmental Controls 01-21
01 58 16 Temporary Interior Signage 07-15
01 74 19 Construction Waste Management 04-22
01 81 13 Sustainable Construction Requirements 10-17
01 91 00 General Commissioning Requirements 04-22
DIVISION 02 – EXISTING CONDITIONS
02 21 13 Site Surveys 12-23
02 41 00 Demolition 08-17
02 82 11 Traditional Asbestos Abatement 01-21
02 82 13.13 Glovebag Asbestos Abatement 01-21
02 82 13.19 Asbestos Floor Tile and Mastic Abatement 01-21
02 82 13.31 Asbestos Transite Abatement 01-21
02 83 33.13 Lead-Based Paint Removal and Disposal 01-21
DIVISION 03 – CONCRETE
03 30 00 Cast-in-Place Concrete 01-21
DIVISION 04 – MASONRY
04 01 00 Maintenance of Masonry 01-21
04 05 13 Masonry Mortaring 10-17
04 05 16 Masonry Grouting 01-21
04 20 00 Unit Masonry 08-17
04 72 00 Cast Stone Masonry 01-21
13600 30th Street CONSTRUCTION DOCUMENTS
Des Moines, IA 50310 VERSION 01-01-23
00 01 10-2
SECTION NO. DIVISION AND SECTION TITLES DATE
DIVISION 05 – METALS
05 12 00 Structural Steel Framing 11-18
05 31 00 Steel Decking 01-21
05 36 00 Composite Metal Decking 01-21
05 40 00 Cold-Formed Metal Framing 01-21
05 50 00 Metal Fabrications 08-18
05 51 00 Metal Stairs 01-21
DIVISION 06 – WOOD, PLASTICS AND COMPOSITES
06 10 00 Rough Carpentry 10-17
06 20 00 Finish Carpentry 01-21
DIVISION 07 - THERMAL AND MOISTURE PROTECTION
07 01 50.19 Preparation for Re-Roofing 01-21
07 21 13 Thermal Insulation 01-21
07 22 00 Roof and Deck Insulation 01-21
07 27 26 Fluid-Applied Membrane Air Barrier, Vapor Permeable 01-21
07 53 23 EPDM Roofing 01-21
07 54 23 Thermoplastic Polyolefin (TPO) Roofing 01-21
07 60 00 Flashing and Sheet Metal 01-21
07 71 00 Roof Specialties 01-21
07 81 00 Applied Fireproofing 07-23
07 84 00 Firestopping 01-21
07 92 00 Joint Sealants 04-22
07 95 13 Expansion Joint Cover Assemblies 01-21
DIVISION 08 - OPENINGS
08 11 13 Hollow Metal Doors and Frames 01-21
08 14 00 Interior Wood Doors 01-21
08 14 73.20 Wood Sliding Door Assemblies
08 17 00 Integrated Door Opening Assemblies
08 31 13 Access Doors and Frames 04-22
08 34 00 Special Function Doors 01-23
08 56 53 Extreme High Impact Resistant Windows 01-21
08 71 00 Door Hardware 03-24
08 71 13 Automatic Door Operators 01-21
08 80 00 Glazing 01-21
08 90 00 Louvers and Vents 01-21
DIVISION 09 – FINISHES
09 05 16 Subsurface Preparation for Floor Finishes 01-21
09 22 16 Non-Structural Metal Framing 06-18
09 29 00 Gypsum Board 04-20
09 30 00 Specialty Moldings and Trims
09 30 13 Ceramic/Porcelain Tiling 01-21
13600 30th Street CONSTRUCTION DOCUMENTS
Des Moines, IA 50310 VERSION 01-01-23
00 01 10-3
SECTION NO. DIVISION AND SECTION TITLES DATE
09 51 00 Acoustical Ceilings 12-18
09 62 63 Stainless Steel Wall Base
09 65 13 Resilient Base and Accessories 01-21
09 65 16 Resilient Sheet Flooring 06-22
09 65 19 Resilient Tile Flooring 05-18
09 68 00 Carpeting 01-21
09 91 00 Painting 01-21
09 96 00 High Performance Resinous Wall Coatings 06-22
DIVISION 10 – SPECIALTIES
10 14 00 Signage 01-21
10 21 23 Cubicle Curtain Tracks 01-21
10 26 00 Wall and Door Protection 01-21
10 26 23.11 Decorative Protection Panels
10 28 00 Toilet, Bath, and Laundry Accessories 01-21
10 44 13 Fire Extinguisher Cabinets 08-18
10 51 13 Metal Lockers 10-23
DIVISION 12 – FURNISHINGS
12 24 00 Window Shades 08-17
12 32 00 Manufactured Wood Casework 01-21
12 36 00 Countertops 11-23
DIVISION 21- FIRE SUPPRESSION
21 13 13 Wet-Pipe Sprinkler Systems 06-15
DIVISION 22 – PLUMBING
22 05 11 Common Work Results for Plumbing 01-23
22 05 19 Meters and Gages for Plumbing Piping 09-20
22 05 23 General-Duty Valves for Plumbing Piping 09-20
22 05 33 Heat Tracing for Plumbing Piping 09-20
22 07 11 Plumbing Insulation 09-19
22 08 00 Commissioning of Plumbing Systems 11-16
22 11 00 Facility Water Distribution 05-21
22 13 00 Facility Sanitary and Vent Piping 09-20
22 14 00 Facility Storm Drainage 09-15
22 40 00 Plumbing Fixtures 12-22
DIVISION 23 – HEATING, VENTILATING, AND AIR
CONDITIONING (HVAC)
23 05 11 Common Work Results for HVAC 03-23
23 05 12 General Motor Requirements for HVAC and Steam
Generation Equipment
03-23
13600 30th Street CONSTRUCTION DOCUMENTS
Des Moines, IA 50310 VERSION 01-01-23
00 01 10-4
SECTION NO. DIVISION AND SECTION TITLES DATE
23 05 41 Noise and Vibration Control for HVAC Piping and
Equipment
03-23
23 05 93 Testing, Adjusting, and Balancing for HVAC 03-23
23 07 11 HVAC and Boiler Plant Insulation 02-20
23 08 00 Commissioning of HVAC Systems 03-23
23 09 23 Direct-Digital Control System for HVAC 03-23
23 21 13 Hydronic Piping 03-23 23 21 23 Hydronic Pumps 03-23 23 22 13 Steam and Condensate Heating Piping 08-23 23 22 23 Steam Condensate Pumps 04-20 23 25 00 HVAC Water Treatment 03-23
23 31 00 HVAC Ducts and Casings 03-23
23 34 00 HVAC Fans 03-23
23 36 00 Air Terminal Units 03-23
23 37 00 Air Outlets and Inlets 03-23
23 40 00 HVAC Air Cleaning Devices 03-23
23 73 00 Indoor Central-Station Air-Handling Units 03-23
23 82 00 Convection Heating and Cooling Units 03-23
23 82 16 Air Coils 03-23
DIVISION 26 – ELECTRICAL
26 05 11 Requirements for Electrical Installations 11-22
26 05 19 Low-Voltage Electrical Power Conductors and Cables 11-22
26 05 26 Grounding and Bonding for Electrical Systems 11-22
26 05 33 Raceway and Boxes for Electrical Systems 11-22
26 05 73 Overcurrent Protective Device Coordination Study 11-22
26 08 00 Commissioning of Electrical Systems 11-22
26 09 23 Lighting Controls 11-22
26 24 16 Panelboards 11-22
26 27 26 Wiring Devices 11-22
26 29 11 Motor Controllers 11-22
26 29 21 Enclosed Switches and Circuit Breakers 11-22
26 43 13 Surge Protective Devices 11-22
26 51 00 Interior Lighting 11-22
DIVISION 27 – COMMUNICATIONS
27 05 11 Requirements for Communications Installations 09-19
27 05 26 Grounding and Bonding for Communications Systems 06-15
27 05 33 Raceways and Boxes for Communications Systems 10-18
27 10 00 Control, Communication and Signal Wiring 06-15
27 15 00 Communications Structured Cabling 01-16
27 51 16 Public Address and Mass Notification Systems 01-23
27 51 23 Intercommunications and Program Systems 06-15
27 52 23 Nurse Call and Code Blue Systems 12-20
DIVISION 28 – ELECTRONIC SAFETY AND SECURITY
28 05 00 Common Work Results for Electronic Safety and Security 04-18
13600 30th Street CONSTRUCTION DOCUMENTS
Des Moines, IA 50310 VERSION 01-01-23
00 01 10-5
SECTION NO. DIVISION AND SECTION TITLES DATE
28 05 13 Conductors and Cables for Electronic Safety and
Security
10-18
28 05 26 Grounding and Bonding for Electronic Safety and
Security
01-23
28 05 28.33 Conduits and Backboxes for Electronic Safety and
Security
01-23
28 13 00 Physical Access Control System 01-23
28 23 00 Video Surveillance 04-18
28 31 00 Fire Detection and Alarm 10-22
DIVISION 31 – EARTHWORK
31 20 00 Earthwork 08-23
DIVISION 32 – EXTERIOR IMPROVEMENTS
32 05 23 Cement and Concrete for Exterior Improvements 08-16
32 12 16 Asphalt Paving 09-15
32 17 23 Pavement Markings 08-16
13600 30th Street CONSTRUCTION DOCUMENTS Des Moines, IA 50310 VERSION 06-01-15
WET-PIPE SPRINKLER SYSTEMS
21 13 13 - 1
SECTION 21 13 13
WET-PIPE SPRINKLER SYSTEMS
PART 1 - GENERAL
1.1 DESCRIPTION
A. Design, installation and testing shall be in accordance with
NFPA 13.
B. The design and installation of a hydraulically calculated automatic wet-pipe system complete and ready for operation, for all portions of
Building 1 as shown on the drawings.
C. Modification of the existing sprinkler system as indicated on the drawings and as further required by these specifications.
1.2 RELATED WORK
A. Section 01 33 23, SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES.
B. Section 33 10 00, WATER UTILITIES.
C. Section 07 84 00, FIRESTOPPING.
D. Section 09 91 00, PAINTING.
E. Section 22 05 23, GENERAL-DUTY VALVES FOR PLUMBING PIPING.
F. Section 28 31 00, FIRE DETECTION AND ALARM.
1.3 DESIGN CRITERIA
A. Design Basis Information: Provide design, materials, equipment, installation, inspection, and testing of the automatic sprinkler system in accordance with the requirements of NFPA 13.
1. Perform hydraulic calculations in accordance with NFPA 13 utilizing the Area/Density method. Do not restrict design area reductions permitted for using quick response sprinklers throughout by the required use of standard response sprinklers in the areas identified in this section.
2. Sprinkler Protection: Sprinkler hazard classifications shall be in accordance with NFPA 13. The hazard classification examples of uses and conditions identified in the Annex of NFPA 13 shall be mandatory for areas not listed below. Request clarification from the
Government for any hazard classification not identified. To determining spacing and sizing, apply the following coverage classifications:
a. Light Hazard Occupancies: Patient care, treatment, and customary access areas.
21 13 13 - 2
b. Ordinary Hazard Group 1 Occupancies: Laboratories, Mechanical
Equipment Rooms, Transformer Rooms, Electrical Switchgear Rooms, Electric Closets, and Repair Shops.
c. Ordinary Hazard Group 2 Occupancies: Storage rooms, trash rooms, clean and soiled linen rooms, pharmacy and associated storage, laundry, kitchens, kitchen storage areas, retail stores, retail store storage rooms, storage areas, building management storage, boiler plants, energy centers, warehouse spaces, file storage areas for the entire area of the space up to 140 square meters
(1500 square feet) and Supply Processing and Distribution (SPD).
3. Hydraulic Calculations: Calculated demand including hose stream requirements shall fall no less than 10 percent below the available water supply curve.
4. Water Supply: Base water supply on a flow test data listed on the
Fire Protection Coversheet in the drawings.
5. Zoning:
a. For each sprinkler zone provide a control valve, flow switch, and a test and drain assembly with pressure gauge. For buildings greater than two stories, provide a check valve at each control valve.
b. Sprinkler zones shall conform to the smoke barrier zones shown on the drawings.
1.4 SUBMITTALS
A. Submit as one package in accordance with Section 01 33 23, SHOP
DRAWINGS, PRODUCT DATA, AND SAMPLES. Prepare detailed working drawings that are signed by a NICET Level III or Level IV Sprinkler Technician or stamped by a Registered Professional Engineer licensed in the field of Fire Protection Engineering. As the Government review is for technical adequacy only, the installer remains responsible for correcting any conflicts with other trades and building construction that arise during installation. Partial submittals will not be accepted. Material submittals shall be approved prior to the purchase or delivery to the job site. Suitably bind submittals in notebooks or binders and provide an index referencing the appropriate specification section. In addition to the hard copies, provide submittal items in
Paragraphs 1.4(A)1 through 1.4(A)5 electronically in pdf format on a
21 13 13 - 3 compact disc or as directed by the COR. Submittals shall include, but not be limited to, the following:
1. Qualifications:
a. Provide a copy of the installing contractors state contractor’s license.
b. Provide a copy of the NICET certification for the NICET Level III or Level IV Sprinkler Technician who prepared and signed the detailed working drawings unless the drawings are stamped by a
Registered Professional Engineer licensed in the field of Fire
Protection Engineering.
c. Provide documentation showing that the installer has been actively and successfully engaged in the installation of commercial automatic sprinkler systems for the past ten years.
2. Drawings: Submit detailed 1:100 (1/8 inch) scale (minimum) working drawings conforming to the Plans and Calculations chapter of NFPA
13. Drawings shall include graphical scales that allow the user to determine lengths when the drawings are reduced in size. Include a plan showing the piping to the water supply test location.
3. Manufacturer’s Data Sheets: Provide data sheets for all materials and equipment proposed for use on the system. Include listing information and installation instructions in data sheets. Where data sheets describe items in addition to those proposed to be used for the system, clearly identify the proposed items on the sheet.
4. Calculation Sheets:
a. Submit hydraulic calculation sheets in tabular form conforming to the requirements and recommendations of the Plans and
Calculations chapter of NFPA 13.
5. Valve Charts: Provide a valve chart that identifies the location of each control valve. Coordinate nomenclature and identification of control valves with COR. Where existing nomenclature does not exist, the chart shall include no less than the following: Tag ID
No., Valve Size, Service (control valve, main drain, aux. drain, inspectors test valve, etc.), and Location.
6. Final Document Submittals: Provide as-built drawings, testing and maintenance instructions in accordance with the requirements in
Section 01 33 23, SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES. In
21 13 13 - 4 addition, submittals shall include, but not be limited to, the following:
a. A complete set of as-built drawings showing the installed system with the specific interconnections between the system switches and the fire alarm equipment. Provide a complete set in the formats as follows. Submit items 2 and 3 below on a compact disc or as directed by the COR.
1) One full size (or size as directed by the COR) printed copy.
2) One complete set in electronic pdf format.
3) One complete set in AutoCAD format or a format as directed by the COR.
b. Material and Testing Certificate: Upon completion of the sprinkler system installation or any partial section of the system, including testing and flushing, provide a copy of a completed Material and Testing Certificate as indicated in NFPA
13. Certificates shall be provided to document all parts of the installation.
c. Operations and Maintenance Manuals that include step-by-step procedures required for system startup, operation, shutdown, and routine maintenance and testing. The manuals shall include the manufacturer's name, model number, parts list, and tools that should be kept in stock by the owner for routine maintenance, including the name of a local supplier, simplified wiring and controls diagrams, troubleshooting guide, and recommended service organization, including address and telephone number, for each item of equipment.
d. One paper copy of the Material and Testing Certificates and the
Operations and Maintenance Manuals above shall be provided in a binder. In addition, these materials shall be provided in pdf format on a compact disc or as directed by the COR.
e. Provide one additional copy of the Operations and Maintenance
Manual covering the system in a flexible protective cover and mount in an accessible location adjacent to the riser or as directed by the COR.
1.5 QUALITY ASSURANCE
A. Installer Reliability: The installer shall possess a valid State of
Iowa contractor's license. The installer shall have been actively and
21 13 13 - 5 successfully engaged in the installation of commercial automatic sprinkler systems for the past ten years.
B. Materials and Equipment: All equipment and devices shall be of a make and type listed by UL or approved by FM, or other nationally recognized testing laboratory for the specific purpose for which it is used. All materials, devices, and equipment shall be approved by the VA. All materials and equipment shall be free from defect. All materials and equipment shall be new unless specifically indicated otherwise on the contract drawings.
1.6 APPLICABLE PUBLICATIONS
A. The publications listed below form a part of this specification to the extent referenced. The publications are referenced in the text by the basic designation only.
B. National Fire Protection Association (NFPA):
13-19...................Installation of Sprinkler Systems
25-20...................Inspection, Testing, and Maintenance of Water-
Based Fire Protection Systems
101-18..................Life Safety Code
170-18..................Fire Safety Symbols
C. Underwriters Laboratories, Inc. (UL):
Fire Protection Equipment Directory (2011)
D. Factory Mutual Engineering Corporation (FM):
Approval Guide
PART 2 - PRODUCTS
2.1 PIPING & FITTINGS
A. Piping and fittings for private underground water mains shall be in accordance with NFPA 13.
1. Pipe and fittings from inside face of building 300 mm (12 in.) above finished floor to a distance of approximately 1500 mm (5 ft.)
outside building: Ductile Iron, flanged fittings and 316 stainless steel bolting.
B. Piping and fittings for sprinkler systems shall be in accordance with
NFPA 13.
1. Plain-end pipe fittings with locking lugs or shear bolts are not permitted.
21 13 13 - 6
2. Piping sizes 50 mm (2 inches) and smaller shall be black steel
Schedule 40 with threaded end connections.
3. Piping sizes 65 mm (2 ½ inches) and larger shall be black steel
Schedule 10 with grooved connections. Grooves in Schedule 10 piping shall be rolled grooved only.
4. Plastic piping shall not be permitted except for drain piping.
5. Flexible sprinkler hose shall be FM Approved and limited to hose with threaded end fittings with a minimum inside diameter or 1-inch and a maximum length of 6-feet.
2.2 VALVES
A. General:
1. Valves shall be in accordance with NFPA 13.
2. Do not use quarter turn ball valves for 50 mm (2 inch) or larger drain valves.
B. Control Valve: The control valves shall be a listed indicating type.
Control valves shall be UL Listed or FM Approved for fire protection installations. System control valve shall be rated for normal system pressure but in no case less than 175 PSI.
C. Check Valve: Shall be of the swing type with a flanged cast iron body and flanged inspection plate.
D. Automatic Ball Drips: Cast brass 20 mm (3/4 inch) in-line automatic ball drip with both ends threaded with iron pipe threads.
2.3 FIRE DEPARTMENT SIAMESE CONNECTION
A. Brass, flush wall type, exterior fire department connection with brass escutcheon plate, and a minimum of two 65 mm (2-1/2 inch) connections threaded to match those on the local fire protection service, with polished brass caps and chains. Provide escutcheon with integral raised letters "Automatic Sprinkler". Install an automatic ball drip between fire department connection and check valve with drain piping routed to the exterior of the building or a floor drain. //
2.4 SPRINKLERS
A. All sprinklers shall be FM approved quick response except
“institutional” type sprinklers shall be permitted to be UL Listed quick response. Provide FM approved quick response sprinklers in all areas, except that standard response sprinklers shall be provided in freezers, refrigerators, elevator hoistways, elevator machine rooms, and generator rooms.
21 13 13 - 7
B. Temperature Ratings: In accordance with NFPA 13 except that sprinklers in elevator shafts and elevator machine rooms shall be no less than intermediate temperature rated and sprinklers in generator rooms shall be no less than high temperature rated.
C. Provide sprinkler guards in accordance with NFPA 13 and when the elevation of the sprinkler head is less than 7 feet 6 inches above finished floor. The sprinkler guard shall be UL listed or FM approved for use with the corresponding sprinkler.
2.5 SPRINKLER CABINET
A. Provide sprinkler cabinet with the required number of sprinkler heads of all ratings and types installed, and a sprinkler wrench for each type of sprinkler in accordance with NFPA 13. Locate adjacent to the riser.
B. Provide a list of sprinklers installed in the property in the cabinet.
The list shall include the following:
1. Manufacturer, model, orifice, deflector type, thermal sensitivity, and pressure for each type of sprinkler in the cabinet.
2. General description of where each sprinkler is used.
3. Quantity of each type present in the cabinet.
4. Issue or revision date of list.
2.6 SPRINKLER SYSTEM SIGNAGE
A. Rigid plastic, steel or aluminum signs with white lettering on a red background with holes for easy attachment. Sprinkler system signage shall be attached to the valve or piping with chain.
2.7 SWITCHES:
A. OS&Y Valve Supervisory Switches shall be in a weatherproof die cast/red baked enamel, oil resistant, aluminum housing with tamper resistant screws, 13 mm (1/2 inch) conduit entrance and necessary facilities for attachment to the valves. Provide two SPDT switches rated at 2.5 amps at 24 VDC.
B. Water flow Alarm Switches: Mechanical, non-coded, non-accumulative retard and adjustable from 0 to 60 seconds minimum. Set flow switches at an initial setting between 20 and 30 seconds.
C. Valve Supervisory Switches for Ball and Butterfly Valves: May be integral with the valve.
21 13 13 - 8
2.8 GAUGES
A. Provide gauges as required by NFPA 13. Provide gauges where the normal pressure of the system is at the midrange of the gauge.
2.9 PIPE HANGERS, SUPPORTS AND RESTRAINT OF SYSTEM PIPING
A. Pipe hangers, supports, and restraint of system piping shall be in accordance with NFPA 13.
2.10 WALL, FLOOR AND CEILING PLATES
A. Provide chrome plated steel escutcheon plates.
2.11 VALVE TAGS
A. Engraved black filled numbers and letters not less than 15 mm (1/2 inch) high for number designation, and not less than 8 mm (1/4 inch) for service designation on 19 gage, 40 mm (1-1/2 inches) round brass disc, attached with brass "S" hook, brass chain, or nylon twist tie.
PART 3 - EXECUTION
3.1 INSTALLATION
A. Installation shall be accomplished by the licensed contractor. Provide a qualified technician, experienced in the installation and operation of the type of system being installed, to supervise the installation and testing of the system.
B. Installation of Piping: Accurately cut pipe to measurements established by the installer and work into place without springing or forcing. In any situation where bending of the pipe is required, use a standard pipe-bending template. Concealed piping in spaces that have finished ceilings. Where ceiling mounted equipment exists, such as in operating and radiology rooms, install sprinklers so as not to obstruct the movement or operation of the equipment. Sidewall heads may need to be utilized. In stairways, locate piping as near to the ceiling as possible to prevent tampering by unauthorized personnel and to provide a minimum headroom clearance of 2250 mm (seven feet six inches). Piping shall not obstruct the minimum means of egress clearances required by
NFPA 101. Pipe hangers, supports, and restraint of system piping, shall be installed accordance with NFPA 13.
C. Welding: Conform to the requirements and recommendations of NFPA 13.
D. Drains: Provide drips and drains, including low point drains, in accordance with NFPA 13. Pipe drains to discharge at safe points outside of the building or to sight cones attached to drains of adequate size to readily carry the full flow from each drain under
21 13 13 - 9 maximum pressure. Do not provide a direct drain connection to sewer system or discharge into sinks. Install drips and drains where necessary and required by NFPA 13. The drain piping shall not be restricted or reduced and shall be of the same diameter as the drain collector.
E. Supervisory Switches: Provide supervisory switches for sprinkler control valves.
F. Waterflow Alarm Switches: Install waterflow alarm switches and valves in stairwells or other easily accessible locations.
G. Inspector's Test Connection: Install and supply in accordance with NFPA
13, locate in a secured area, and discharge to the exterior of the building.
H. Affix cutout disks, which are created by cutting holes in the walls of pipe for flow switches and non-threaded pipe connections to the respective waterflow switch or pipe connection near to the pipe from where they were cut.
I. Provide escutcheon plates for exposed piping passing through walls, floors or ceilings.
J. Clearances: For systems requiring seismic protection, piping that passes through floors or walls shall have penetrations sized 50 mm (2 inches) nominally larger than the penetrating pipe for pipe sizes 25 mm
(1 inch) to 90 mm (3 ½ inches) and 100 mm (4 inches) nominally larger for penetrating pipe sizes 100 mm (4 inches) and larger.
K. Sleeves: Provide for pipes passing through masonry or concrete. Provide space between the pipe and the sleeve in accordance with NFPA 13. Seal this space with a UL Listed through penetration fire stop material in accordance with Section 07 84 00, FIRESTOPPING. Where core drilling is used in lieu of sleeves, also seal space. Seal penetrations of walls, floors and ceilings of other types of construction, in accordance with
Section 07 84 00, FIRESTOPPING.
L. Provide pressure gauges at each water flow alarm switch location and at each main drain connection.
M. For each fire department connection, provide the symbolic sign given in
NFPA 170 and locate 2400 to 3000 mm (8 to 10 feet) above each connection location. Size the sign to 450 by 450 mm (18 by 18 inches) with the symbol being at least 350 by 350 mm (14 by 14 inches).
21 13 13 - 10
N. Firestopping shall be provided for all penetrations of fire resistance rated construction. Firestopping shall comply with Section 07 84 00, FIRESTOPPING.
O. Painting of Pipe: In finished areas where walls and ceilings have been painted, paint primed surfaces with two coats of paint to match adjacent surfaces, except paint valves and operating accessories with two coats of gloss red enamel. Exercise care to avoid painting sprinklers. Painting of sprinkler systems above suspended ceilings and in crawl spaces is not required. Painting shall comply with Section 09
91 00, PAINTING. Any painted sprinkler shall be replaced with a new sprinkler.
P. Sprinkler System Signage: Provide rigid sprinkler system signage in accordance with NFPA 13 and NFPA 25. Sprinkler system signage shall include, but not limited to, the following:
1. Identification Signs:
a. Provide signage for each control valve, drain valve, sprinkler cabinet, and inspector’s test.
b. Provide valve tags for each operable valve. Coordinate nomenclature and identification of operable valves with COR.
Where existing nomenclature does not exist, the Tag
Identification shall include no less than the following: (FP-B-
F/SZ-#) Fire Protection, Building Number, Floor Number/Smoke Zone
(if applicable), and Valve Number. (E.g., FP-500-1E-001) Fire
Protection, Building 500, First Floor East, Number 001.)
2. Instruction/Information Signs:
a. Provide signage for each control valve to indicate valve function and to indicate what system is being controlled.
b. Provide signage indicating the number and location of low point drains.
3. Hydraulic Placards:
a. Provide signage indicating hydraulic design information. The placard shall include location of the design area, discharge densities, required flow and residual pressure at the base of riser, occupancy classification, hose stream allowance, flow test information, and installing contractor. Locate hydraulic placard information signs at each alarm check valve.
21 13 13 - 11
Q. Repairs: Repair damage to the building or equipment resulting from the installation of the sprinkler system by the installer at no additional expense to the Government.
R. Interruption of Service: There shall be no interruption of the existing sprinkler protection, water, electric, or fire alarm services without prior permission of the Contracting Officer. Contractor shall develop an interim fire protection program where interruptions involve occupied spaces. Request in writing at least one week prior to the planned interruption.
3.2 INSPECTION AND TEST
A. Preliminary Testing: Flush newly installed systems prior to performing hydrostatic tests in order to remove any debris which may have been left as well as ensuring piping is unobstructed. Hydrostatically test system, including the fire department connections, as specified in NFPA
13, in the presence of the Contracting Officers Representative (COR) or his designated representative. Test and flush underground water line prior to performing these hydrostatic tests.
B. Final Inspection and Testing: Subject system to tests in accordance with NFPA 13, and when all necessary corrections have been accomplished, advise COR to schedule a final inspection and test.
Connection to the fire alarm system shall have been in service for at least ten days prior to the final inspection, with adjustments made to prevent false alarms. Furnish all instruments, labor and materials required for the tests and provide the services of the installation foreman or other competent representative of the installer to perform the tests. Correct deficiencies and retest system as necessary, prior to the final acceptance. Include the operation of all features of the systems under normal operations in test
3.3 INSTRUCTIONS
A. Furnish the services of a competent instructor for not less than two hours for instructing personnel in the operation and maintenance of the system, on the dates requested by the COR.
- - - E N D - - -
21 13 13 - 12
THIS PAGE INTENTIONALLY LEFT BLANK
Des Moines, IA 50310 VERSION 01-01-23
COMMON WORK RESULTS FOR PLUMBING
22 05 11 - 1
SECTION 22 05 11
PART 1 - GENERAL
1.1 DESCRIPTION
A. The requirements of this Section will apply to all sections of Division
22.
B. Definitions:
1. Exposed: Piping and equipment exposed to view in finished rooms.
2. Exterior: Piping and equipment exposed to weather be it temperature, humidity, precipitation, wind or solar radiation.
C. Abbreviations/Acronyms:
1. ABS: Acrylonitrile Butadiene Styrene
2. AC: Alternating Current
3. ACR: Air Conditioning and Refrigeration
4. A/E: Architect/Engineer
5. AFF: Above Finish Floor
6. AFG: Above Finish Grade
7. AISI: American Iron and Steel Institute
8. ASHRAE: American Society of Heating Refrigeration, Air Conditioning
Engineers
9. ASJ: All Service Jacket
10. ASME: American Society of Mechanical Engineers
11. ASPE: American Society of Plumbing Engineers
12. AWG: American Wire Gauge
13. BACnet: Building Automation and Control Network
14. BAg: Silver-Copper-Zinc Brazing Alloy
15. BAS: Building Automation System
16. BCuP: Silver-Copper-Phosphorus Brazing Alloy
17. bhp: Brake Horsepower
18. Btu: British Thermal Unit
19. Btu/h: British Thermal Unit per Hour
20. C: Celsius
21. CD: Compact Disk
22. CDA: Copper Development Association
23. CI: Cast Iron
24. CLR: Color
25. CO: Contracting Officer
22 05 11 - 2
26. COR: Contracting Officer’s Representative
27. CRS: Corrosion Resistant Steel
28. CWP: Cold Working Pressure
29. CxA: Commissioning Agent
30. dB: Decibels
31. db(A): Decibels (A weighted)
32. DCW: Domestic Cold Water
33. DDC: Direct Digital Control
34. DFU: Drainage Fixture Units
35. DHW: Domestic Hot Water
36. DHWR: Domestic Hot Water Return
37. DHWS: Domestic How Water Supply
38. DI: Digital Input
39. DISS: Diameter Index Safety System
40. DN: Diameter Nominal
41. DOE: Department of Energy
42. DVD: Digital Video Disc
43. DWG: Drawing
44. DWH: Domestic Water Heater
45. DWS: Domestic Water Supply
46. DWV: Drainage, Waste and Vent
47. EL: Elevation
48. EPA: Environmental Protection Agency
49. EPACT: Energy Policy Act
50. EPDM: Ethylene Propylene Diene Monomer
51. EPT: Ethylene Propylene Terpolymer
52. ETO: Ethylene Oxide
53. F: Fahrenheit
54. FAR: Federal Acquisition Regulations
55. FD: Floor Drain
56. FED: Federal
57. FG: Fiberglass
58. FNPT: Female National Pipe Thread
59. FPM: Fluoroelastomer Polymer
60. FSK: Foil-Scrim-Kraft Facing
61. FSS: VA Construction & Facilities Management, Facility Standards
Service
22 05 11 - 3
62. FU: Fixture Units
63. GAL: Gallon
64. GPD: Gallons per Day
65. GPH: Gallons per Hour
66. GPM: Gallons per Minute
67. HEFP: Healthcare Environment and Facilities Program (replacement for
OCAMES)
68. Hg: Mercury
69. HOA: Hands-Off-Automatic
70. HP: Horsepower
71. Hz: Hertz
72. ID: Inside Diameter
73. IE: Invert Elevation
74. INV: Invert
75. IPC: International Plumbing Code
76. IPS: Iron Pipe Size
77. Kg: Kilogram
78. kPa: Kilopascal
79. KW: Kilowatt
80. KWH: Kilowatt Hour
81. lb: Pound
82. lbs/hr: Pounds per Hour
83. L/min: Liters per Minute
84. L/s: Liters per Second
85. m: Meter
86. MAWP: Maximum Allowable Working Pressure
87. MAX: Maximum
88. MBH: 1000 Btu per Hour
89. MED: Medical
90. MER: Mechanical Equipment Room
91. MFG: Manufacturer
92. mg: Milligram
93. mg/L: Milligrams per Liter
94. ml: Milliliter
95. mm: Millimeter
96. MIN: Minimum
97. NC: Normally Closed
22 05 11 - 4
98. NIC: Not in Contract
99. NO: Normally Open
100. NOM: Nominal
101. NPTF: National Pipe Thread Female
102. NPS: Nominal Pipe Size
103. NPT: Nominal Pipe Thread
104. NTS: Not to Scale
105. OC: On Center
106. OD: Outside Diameter
107. PA: Pascal
108. PD: Pressure Drop or Difference
109. PDI: Plumbing and Drainage Institute
110. PH: Power of Hydrogen
111. ppb: Parts per Billion
112. ppm: Parts per Million
113. PSI: Pounds per Square Inch
114. PSIA: Pounds per Square Inch Atmosphere
115. PSIG: Pounds per Square Inch Gauge
116. PTFE: Polytetrafluoroethylene
117. RPM: Revolutions Per Minute
118. RTD: Resistance Temperature Detectors
119. SAN: Sanitary Sewer
120. SCFM: Standard Cubic Feet per Minute
121. SMACNA: Sheet Metal and Air Conditioning Contractors National
Association
122. SPEC: Specification
123. SQFT/SF: Square Feet
124. SS: Stainless Steel
125. STD: Standard
126. TEMP: Temperature
127. TFE: Tetrafluoroethylene
128. THERM: 100,000 Btu
129. THHN: Thermoplastic High-Heat Resistant Nylon Coated Wire
130. THWN: Thermoplastic Heat & Water Resistant Nylon Coated Wire
131. TIL: Technical Information Library http//www.cfm.va.gov/til/indes.asp
132. T/P: Temperature and Pressure
22 05 11 - 5
133. TYP: Typical
134. V: Vent
135. V: Volt
136. VA: Veterans Administration
137. VA CFM: VA Construction & Facilities Management
138. VA CFM CSS: VA Construction & Facilities Management, Consulting
Support Service
139. VAC: Voltage in Alternating Current
140. VAMC: Veterans Administration Medical Center
141. VHA OCAMES: This has been replaced by HEFP.
142. VTR: Vent through Roof
143. W: Waste
144. WC: Water Closet
145. WG: Water Gauge
146. WOG: Water, Oil, Gas
147. WPD: Water Pressure Drop
148. WSFU: Water Supply Fixture Units
1.2 RELATED WORK
A. Section 01 00 00, GENERAL REQUIREMENTS.
B. Section 01 33 23, SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES.
C. Section 01 74 19, CONSTRUCTION WASTE MANAGEMENT.
D. Section 01 81 13, SUSTAINABLE CONSTRUCTION REQUIREMENTS.
E. Section 07 60 00, FLASHING AND SHEET METAL: Flashing for Wall and Roof
Penetrations.
F. Section 07 84 00, FIRESTOPPING.
G. Section 07 92 00, JOINT SEALANTS.
H. Section 09 91 00, PAINTING.
I. Section 22 05 12, GENERAL MOTOR REQUIREMENTS FOR PLUMBING EQUIPMENT.
J. Section 22 07 11, PLUMBING INSULATION.
K. Section 22 08 00, COMMISSIONING OF PLUMBING SYSTEMS.
L. Section 26 05 11, REQUIREMENTS FOR ELECTRICAL INSTALLATIONS.
M. Section 26 05 19, LOW-VOLTAGE ELECTRICAL POWER CONDUCTORS AND CABLES.
1.3 APPLICABLE PUBLICATIONS
A. The publications listed below will form a part of this specification to the extent referenced. The publications are referenced in the text by
22 05 11 - 6 the basic designation only. Where conflicts occur these specifications and the VHA standard will govern.
B. American Society of Mechanical Engineers (ASME):
B31.1-2013..............Power Piping
ASME Boiler and Pressure Vessel Code -
BPVC Section IX-2019.... Welding, Brazing, and Fusing Qualifications
C. American Society for Testing and Materials (ASTM):
A36/A36M-2019...........Standard Specification for Carbon Structural
Steel
A575-96(2013)e1.........Standard Specification for Steel Bars, Carbon, Merchant Quality, M-Grades
E84-2013a...............Standard Test Method for Surface Burning
Characteristics of Building Materials
E119-2012a..............Standard Test Methods for Fire Tests of
Building Construction and Materials
D. International Code Council, (ICC):
IBC-2018................International Building Code
IPC-2018................International Plumbing Code
E. Manufacturers Standardization Society (MSS) of the Valve and Fittings
Industry, Inc:
SP-58-2018..............Pipe Hangers and Supports - Materials, Design, Manufacture, Selection, Application and
Installation
F. Military Specifications (MIL):
P-21035B................Paint High Zinc Dust Content, Galvanizing
Repair (Metric)
G. National Electrical Manufacturers Association (NEMA):
MG 1-2016...............Motors and Generators
H. National Fire Protection Association (NFPA):
51B-2019................Standard for Fire Prevention During Welding, Cutting and Other Hot Work
54-2018.................National Fuel Gas Code
70-2020.................National Electrical Code (NEC)
99-2018.................Healthcare Facilities Code
I. NSF International (NSF):
5-2019..................Water Heaters, Hot Water Supply Boilers, and
Heat Recovery Equipment
22 05 11 - 7
14-2019.................Plastic Piping System Components and Related
Materials
61-2019.................Drinking Water System Components – Health
Effects
372-2016................Drinking Water System Components – Lead Content
J. Department of Veterans Affairs (VA):
PG-18-102014(R18).......Plumbing Design Manual
PG-18-13-2017(R18)......Barrier Free Design Guide
1.4 SUBMITTALS
A. Submittals, including number of required copies, will be submitted in accordance with Section 01 33 23, SHOP DRAWINGS, PRODUCT DATA, and
SAMPLES.
B. Information and material submitted under this section will be marked
"SUBMITTED UNDER SECTION 22 05 11, COMMON WORK RESULTS FOR PLUMBING",
with applicable paragraph identification.
C. If the project is phased, contractors will submit complete phasing plan/schedule with manpower levels prior to commencing work. The phasing plan will be detailed enough to provide milestones in the process that can be verified.
D. Contractor will make all necessary field measurements and investigations to assure that the equipment and assemblies will meet contract requirements, and all equipment that requires regular maintenance, calibration, etc are accessable from the floor or permanent work platform. It is the Contractor’s responsibility to ensure all submittals meet the VA specifications and requirements and it is assumed by the VA that all submittals do meet the VA specifications unless the Contractor has requested a variance in writing and approved by COR prior to the submittal. If at any time during the project it is found that any item does not meet the VA specifications and there was no variance approval the Contractor will correct at no additional cost or time to the Government even if a submittal was approved.
E. If equipment is submitted which differs in arrangement from that shown, provide documentation proving equivalent performance, design standards and drawings that show the rearrangement of all associated systems.
Additionally, any impacts on ancillary equipment or services such as foundations, piping, and electrical will be the Contractor’s
22 05 11 - 8 responsibility to design, supply, and install at no additional cost or time to the Government. VA approval will be given only if all features of the equipment and associated systems, including accessibility, are equivalent to that required by the contract.
F. Prior to submitting shop drawings for approval, Contractor will certify in writing that manufacturers of all major items of equipment have each reviewed drawings and specifications, and have jointly coordinated and properly integrated their equipment and controls to provide a complete and efficient installation.
G. Submittals and shop drawings for interdependent items, containing applicable descriptive information, will be furnished together and complete in a group. Coordinate and properly integrate materials and equipment in each group to provide a completely compatible and efficient installation. Final review and approvals will be made only by groups.
H. Manufacturer's Literature and Data including: Manufacturer’s literature will be submitted under the pertinent section rather than under this section.
1. Electric motor data and variable speed drive data will be submitted with the driven equipment.
2. Equipment and materials identification.
3. Firestopping materials.
4. Hangers, inserts, supports and bracing. Provide load calculations for variable spring and constant support hangers.
5. Wall, floor, and ceiling plates.
I. Coordination/Shop Drawings:
1. Submit complete consolidated and coordinated shop drawings for all new systems, and for existing systems that are in the same areas.
2. The coordination/shop drawings will include plan views, elevations and sections of all systems and will be on a scale of not less than
1:32 (3/8-inch equal to 1 foot). Clearly identify and dimension the proposed locations of the principal items of equipment. The drawings will clearly show locations and adequate clearance for all equipment, piping, valves, control panels and other items. Show the access means for all items requiring access for operations and maintenance. Provide detailed coordination/shop drawings of all piping and duct systems. The drawings should include all
22 05 11 - 9 lockout/tagout points for all energy/hazard sources for each piece of equipment. Coordinate lockout/tagout procedures and practices with local VA requirements.
3. Do not install equipment foundations, equipment or piping until coordination/shop drawings have been approved.
4. In addition, for plumbing systems, provide details of the following:
a. Mechanical equipment rooms.
b. Hangers, inserts, supports, and bracing.
c. Pipe sleeves.
d. Duct or equipment penetrations of floors, walls, ceilings, or roofs.
J. Rigging Plan: Provide documentation of the capacity and weight of the rigging and equipment intended to be used. The plan will include the path of travel of the load, the staging area and intended access, and qualifications of the operator and signal person.
K. Plumbing Maintenance Data and Operating Instructions:
1. Maintenance and operating manuals in accordance with Section 01 00
00, GENERAL REQUIREMENTS, Article, INSTRUCTIONS, for systems and equipment.
2. Complete operating and maintenance manuals including wiring diagrams, technical data sheets, information for ordering replacement parts, and troubleshooting guide:
a. Include complete list indicating all components of the systems.
b. Include complete diagrams of the internal wiring for each item of equipment.
c. Diagrams will have their terminals identified to facilitate installation, operation and maintenance.
3. Provide a listing of recommended replacement parts for keeping in stock supply, including sources of supply, for equipment. Include in the listing belts for equipment: Belt manufacturer, model number, size and style, and distinguished whether of multiple belt sets.
L. Provide copies of approved plumbing equipment submittals to the TAB and
Commissioning Subcontractor.
M. Completed System Readiness Checklist provided by the CxA and completed by the Contractor, signed by a qualified technician and dated on the date of completion, in accordance with the requirements of Section 22
08 00 COMMISSIONING OF PLUMBING SYSTEMS.
22 05 11 - 10
N. Submit training plans, trainer qualifications and instructor qualifications in accordance with the requirements of Section 22 08 00
COMMISSIONING OF PLUMBING SYSTEMS.
1.5 QUALITY ASSURANCE
A. Mechanical, electrical, and associated systems will be safe, reliable, efficient, durable, easily and safely operable and maintainable, easily and safely accessible, and in compliance with applicable codes as specified. The systems will be comprised of high quality institutional-class and industrial-class products of manufacturers that are experienced specialists in the required product lines. All construction firms and personnel will be experienced and qualified specialists in industrial and institutional plumbing.
B. Products Criteria:
1. Standard Products: Material and equipment will be the standard products of a manufacturer regularly engaged in the manufacture, supply and servicing of the specified products for at least 5 years.
However, digital electronics devices, software and systems such as controls, instruments, computer work station, will be the current generation of technology and basic design that has a proven satisfactory service record of at least 5 years.
2. Equipment Service: There will be permanent service organizations, authorized and trained by manufacturers of the equipment supplied, located within 160 km (100 miles) of the project. These organizations will come to the site and provide acceptable service to restore operations within 4 hours of receipt of notification by phone, e-mail or fax in event of an emergency, such as the shut-down of equipment; or within 24 hours in a non-emergency. Names, mail and e-mail addresses and phone numbers of service organizations providing service under these conditions for (as applicable to the project): pumps, compressors, water heaters, critical instrumentation, computer workstation and programming will be submitted for project record and inserted into the operations and maintenance manual.
3. All items furnished will be free from defects that would adversely affect the performance, maintainability and appearance of individual components and overall assembly.
22 05 11 - 11
4. The products and execution of work specified in Division 22 will conform to the referenced codes and standards as required by the specifications. Local codes and amendments enforced by the local code official will be enforced, if required by local authorities such as the natural gas supplier. If the local codes are more stringent, then the local code will apply. Any conflicts will be brought to the attention of the Contracting Officers Representative
(COR).
5. Multiple Units: When two or more units of materials or equipment of the same type or class are required, these units will be of the same manufacturer and model number, or if different models are required they will be of the same manufacturer and identical to the greatest extent possible (i.e., same model series).
6. Assembled Units: Performance and warranty of all components that make up an assembled unit will be the responsibility of the manufacturer of the completed assembly.
7. Nameplates: Nameplate bearing manufacturer's name or identifiable trademark will be securely affixed in a conspicuous place on equipment, or name or trademark cast integrally with equipment, stamped or otherwise permanently marked on each item of equipment.
8. Asbestos products or equipment or materials containing asbestos is prohibited.
9. Bio-Based Materials: For products designated by the USDA’s bio-based
Bio-Preferred Program, provide products that meet or exceed USDA recommendations for bio-based content, so long as products meet all performance requirements in this specifications section. For more information regarding the product categories covered by the
Bio-Preferred Program, visit http://www.biopreferred.gov.
C. Welding: Before any welding is performed, Contractor will submit a certificate certifying that welders comply with the following requirements:
1. Qualify welding processes and operators for piping according to ASME
BPVC, Section IX, "Welding and Brazing Qualifications". Provide proof of current certification to CO.
2. Comply with provisions of ASME B31 series "Code for Pressure
Piping".
22 05 11 - 12
3. Certify that each welder and welding operator has passed American
Welding Society (AWS) qualification tests for the welding processes involved, and that certification is current.
4. All welds will be stamped according to the provisions of the AWS or
ASME as required herein and by the association code.
D. Manufacturer's Recommendations: Where installation procedures or any part thereof are required to be in accordance with the recommendations of the manufacturer of the material being installed, printed copies of these recommendations will be furnished to the COR prior to installation. Installation of the item will not be allowed to proceed until the recommendations are received. Failure to furnish these recommendations can be cause for rejection of the material.
E. Execution (Installation, Construction) Quality:
1. All items will be applied and installed in accordance with manufacturer's written instructions. Conflicts between the manufacturer's instructions and the contract documents will be referred to the COR for resolution. Printed copies or electronic files of manufacturer’s installation instructions will be provided to the COR at least 10 working days prior to commencing installation of any item.
2. All items that require access, such as for operating, cleaning, servicing, maintenance, and calibration, will be easily and safely accessible by persons standing at floor level, or standing on permanent platforms, without the use of portable ladders. Examples of these items include but are not limited to: all types of valves, filters and strainers, transmitters, and control devices. Prior to commencing installation work, refer conflicts between this requirement and contract documents to COR for resolution. Failure of the Contractor to resolve or call attention to any discrepancies or deficiencies to the COR will result in the Contractor correcting at no additional cost or time to the Government.
3. Complete layout drawings will be required by Paragraph, SUBMITTALS.
Construction work will not start on any system until the layout drawings have been approved by VA.
4. Installer…