This document is a combined synopsis/solicitation for dockside repairs of the USCGC WAESCHE (WMSL 751). The Coast Guard seeks ship repair and support work including inspection and testing of relief valves, cleaning and inspection of grey water tanks, and renewal of anchor windlass and glide slop indicator hoses. The total small business set-aside contract will be fixed-price with an estimated performance period from November 2020 to February 2021. Offerors must submit pricing using Attachment 2 by October 16, 2020. Proposals will be evaluated on price, technical capability, and past performance. The Coast Guard will award one contract to the responsible and responsive offeror providing the best value.
View the file
Other files
Show all 23
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ATTACHMENT 3-Continuation of Combined Synopsis Solicitation
SOLICITATION No. 70Z08521RP4502900
Dockside Repairs of USCG WAESCHE (WMSL 751)
CONTINUATION OF COMBINED SYNOPSIS/SOLICITATION
70Z08521RP4502900
USCGC WAESCHE (WMSL 751)
DOCKSIDE REPAIRS FQ1 FY21
TABLE OF CONTENTS FOR ATTACHMENT 3
DESCRIPTION PAGE NUMBER
Contract Clauses FAR 52.212-4 Contract Terms and Conditions Addendum 3 - 16
Method of Payment and Invoicing Instructions 12
FAR 52.212-5 Contract Terms and Conditions Required to Implement
Statutes and Executive Orders
HSAR 3052.212-70 Contract Terms and Conditions Applicable to DHS
Acquisition of Commercial Items
Solicitation Provisions
FAR 52.212-1 Instructions to Offerors Addendum 24
Inspection of Cutter Prior to Submission of Proposals 25
FAR 52.212-2 Evaluation-Commercial Items 31
FAR 52.209-5 Certification Regarding Responsibility Matters 35
FAR 52.209-7 Information Regarding Responsibility Matters 37
FAR 52.212-3 Representations and Certifications-Commercial Items 39
NOTICE FOR FILING AGENCY PROTESTS
United States Coast Guard Ombudsman Program
It is the policy of the United States Coast Guard (USCG) to issue solicitations and make contract awards in a fair and timely manner. The Ombudsman Program for Agency Protests (OPAP) was established to investigate agency protest issues and resolve them without expensive and time- consuming litigation.
OPAP is an independent reviewing authority that is empowered to grant a prevailing protester essentially the same relief as the Government Accountability Office (GAO).
Interested parties are encouraged to seek resolution of their concerns within the USCG as an Alternative
Dispute Resolution (ADR) forum rather than filing a protest with the GAO or some external forum.
Interested parties may seek resolution of their concerns informally or opt to file a formal agency protest with the Contracting Officer or Ombudsman.
Informal Forum with the Ombudsman. Interested parties who believe a specific USCG procurement is unfair or otherwise defective should first direct their concerns to the applicable Contracting Officer. If the
Contracting Officer is unable to satisfy their concerns, interested parties are encouraged to contact the U.S.
Coast Guard Ombudsman for Agency Protests. Under this informal process the agency is not required to suspend contract award performance. Use of an informal forum does not suspend any time requirement for filing a protest with the agency or other forum. In order to ensure a timely response, interested parties should provide the following information to the Ombudsman: solicitation/contract number, contracting office, Contracting Officer, and solicitation closing date (if applicable).
Formal Agency Protest with the Ombudsman. Prior to submitting a formal agency protest, protesters must first use their best efforts to resolve their concerns with the Contracting Officer through open and frank discussions. If the protester’s concerns are unresolved, an Independent Review is available by the
Ombudsman. The protester may file a formal agency protest to either the Contracting Officer or as an alternative to that, the Ombudsman under the OPAP program. Contract award or performance will be suspended during the protest period unless contract award or performance is justified, in writing, for urgent and compelling reasons or is determined in writing to be in the best interest of the Government. The agency’s goal is to resolve protests in less than 35 calendar days from the date of filing. Protests shall include the information set forth in FAR 33.103(d) (2). If the protester fails to submit the required information, resolution of the protest may be delayed or the protest may be dismissed. To be timely protests must be filed within the period specified in FAR 33.103(e). Formal protests filed under the OPAP program should be submitted electronically to OPAP@uscg.mil and the Contracting Officer or by hand delivery to the Contracting Officer.
Election of Forum. After an interested party protests a Coast Guard procurement to the Contracting
Officer or the Ombudsman, and while the protest is pending, the protester agrees not to file a protest with the GAO or other external forum. If the protest is filed with an external forum, the agency protest will be dismissed.
The Ombudsman Hotline telephone number is 202.372.3695.
This Request for Proposal incorporates provisions’ and clauses in effect through Federal Acquisition
Circular 2020-07. The NAIC code applicable is 336611.
FAR 52.212-4 CONTRACT TERMS AND CONDITIONS – COMMERCIAL ITEMS (OCT 2018)
ADDENDUM
(1) FAR 52.204-1 APPROVAL OF CONTRACT (DEC 1989)
This contract is subject to the written approval of the Contracting Officer and shall not be binding until so approved.
(2) FAR 52.252-2 CLAUSES INCORPORATED BY REFERENCE (FEB 1998)
This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this address:
http://www.dhs.gov/publication/hsar www.acquisiton.gov/far/
Clause No. Clause Title Date
FAR 52.203-12 Limitation on Payments to Influence Certain Federal
Transaction
JUN 2020
FAR 52.203-17 Contractor Employee Whistleblower Rights JUN 2020
FAR 52.204-4 Printed or Copied Double-Sided on Postconsumer Fiber
Content Paper
MAY 2011
FAR 52.215-21 Requirements for Certified Cost or Pricing Data and Data
Other Than Certified Cost or Pricing Data- Modification
JUN 2020
FAR 52.223-3 Hazardous Material Identification and Material Safety Data JAN 1997
FAR 52.228-5 Insurance – Work on a Government Installation JAN 1997
FAR 52.229-3 Federal, State, and Local Taxes FEB 2013
FAR 52.232-18 Availability of Funds APRIL 1984
FAR 52.232-40 Providing Accelerated Payment To Small Business
Subcontractors
DEC 2013
FAR 52.233-2 Service of Protest SEP 2006
FAR 52.233-1 Disputes Clause MAY 2014
FAR 52.242-2 Production Progress Reports APR 1991
FAR 52.242-15 Stop – Work Order AUG 1989
FAR 52.242-17 Government Delay in Work APR 1984
FAR 52.245-1 Government Property (JAN 2017) Alternate 1 APR 2012 FAR 52.245-9 Use and Charges APR 2012 FAR 52-246-2 Inspection of Supplies – Fixed Price AUG 1996 FAR 52.246-4 Inspection of Services – Fixed-Price AUG 1996 FAR 52.246-16 Responsibility for Supplies APR 1984
FAR 52.247-55 F.O.B. Point for Delivery of Government Furnished Property JUN 2003
HSAR 3052.204-71 Contractor Employee Access SEP 2012
HSAR 3052.211-70 Index of Specification DEC 2003
HSAR 3052.222-70 Strikes or Picketing Affecting Timely Completion of the
Contract Work
DEC 2003
HSAR 3052.222-71 Strikes or Picketing Affecting Access to a DHS Facility DEC 2003 http://www.acquisiton.gov/far/
HSAR 3052.222-90 Local Hire JUN 2006
HSAR 3052.223-90 Accident and Fire Reporting DEC 2003
(3) Optional Items
Optional items listed in Attachment 2 under CLIN 0003 of the Schedule of Items may be awarded if inspection reports reveal the necessity for activation, or if funds are made available, at the price proposed in the Contractor’s proposal and without any other consideration whatsoever. However, after midnight on 22 DEC 2020 or three days after the corresponding Critical Inspection Report is accepted, whichever is later, the Contractor shall have the right to refuse to accept the award of such Optional Items.
Such award refusals shall bar neither the Government nor the Contractor from subsequently negotiating with each other for performance of the work embodied in the refused Optional Items.
Optional items shall be awarded by written notice to the Contractor through issuance of a contract modification (SF-30). Evaluation of the Optional items will not obligate the Government.
(4) 52.217-7 Option for Increased Quantity—Separately Priced Line Item. (MAR 1989)
The Government may require the delivery of the numbered line item, identified in the Schedule as an option item, in the quantity and at the price stated in the Schedule. The Contracting Officer may exercise the option by written notice to the Contractor within 24 hours via email. Delivery of added items shall continue at the same rate that like items are called for under the contract, unless the parties otherwise agree.
(5) HSAR 3052.223-70 REMOVAL OR DISPOSAL OF HAZARDOUS SUBSTANCES –
APPLICABLE LICENSES AND PERMITS (JUN 2006)
The Contractor shall have all licenses and permits required by Federal, state, and local laws to perform hazardous substance(s) removal or disposal services. If the Contractor does not currently possess these documents, it shall obtain all requisite licenses and permits within [10] days after date of award. The
Contractor shall provide evidence of said documents to the Contracting Officer or designated
Government representative prior to commencement of work under the contract.
(End of clause)
(6) HAZARDOUS WASTE
Contractors performing dockside ship repair work at Government facilities are required to comply with
FAR 52.223-3, Hazardous Material Identification and Material Safety Data (JAN 1997) Alt I, the U.S.
Coast Guard shipboard hazardous waste policy, as prescribed in COMDINST M16478.1B, and MLCA standard specifications. Disposal of all hazardous wastes shall be performed by the Contractor and the
Contractor shall meet all federal and state requirements. The Contractor is also required to submit an acceptable hazardous waste management plan to the Port Engineer at the Arrival Conference. The plan will be reviewed by the facility hazardous waste manager. An acceptable plan must address, at a minimum, the following requirements:
(a) EPA and local authority hazardous waste generator ID numbers or registration of the
Contractors, his transporters, and disposal facilities (TSDFs);
(b) An inventory of all hazardous chemicals, compounds and other agents brought aboard the facility accompanied by their respective Material Safety Data Sheets;
(c) A list of all anticipated hazardous wastes to be generated and a federal/state/local regulation cross reference list for those wastes;
(d) Waste collection and containment procedures;
(e) A hazardous material spill and cleanup plan including tools and materials that will be on hand and readily available to facility containment and cleanup;
(f) Training certification for the Contractor's hazardous waste manager.
The Contractor shall note the local environmental regulations in Alameda, and for the state of California.
As with all environmental regulations, it is the Contractor's responsibility to research, prepare for, and comply with, the local and state regulations.
All waste generated under the performance of this contract shall be disposed under Coast Guard Base
Alameda's EPA hazardous waste generator ID number. The Contractor shall notify the Contracting
Officer's Representative (COR) 24 hours prior to any waste removals, and ensure that waste removals are conducted during normal business hours (0800-1600) on Monday through Friday (excluding holidays). All hazardous waste manifests shall be reviewed and signed by USCG Base Alameda hazardous waste personnel.
(7) CONTRACTOR COVID-19 PREVENTION AND RESPONSE PLAN
The Contractor shall adhere to CDC, OSHA, state, and local guidance regarding COVID-19 precautions.
In addition, the Contractor shall adhere to the following additional requirements, as necessary:
Requirements specific to District 11 and Base Alameda, CA: mandatory wear of cloth face coverings by all personnel; mandatory temperature scan screenings of all personnel at the access gate by USCG security (personnel with temperature readings in excess of 100.4°F will be denied entry).
Requirements specific to USCGC WAESCHE: mandatory wear of cloth face coverings by all personnel.
Finally, the Contractor shall prepare a COVID-19 Prevention and Response Plan specific to this contract which details the Contractor’s prevention and response plans and procedures. This document shall be submitted after award but no later than the Arrival Conference.
(8) VOLATILE ORGANIC COMPOUNDS (VOC) REGULATIONS
(a) Contractors are required to comply with federal, state and local VOC compliance laws and regulations. Among other requirements, certain Contractors may also be required to operate pursuant to a Title V permit. The need for such a permit will depend on the provisions of the applicable state’s “State Implementation Plan” (SIP) and the type/quantity of the
Contractor’s regulated emissions, including VOCs. Certain SIPs may also mandate certain
Contractors to operate under the terms of a compliance plan intended to reduce VOC emissions.
(b) Contractors, therefore, must submit the following to the designated Port Engineer not later than two weeks after contract award:
1) Copies of any federal, state or local permits required and applicable to the use or application of VOCs at Contractor’s facility or offsite work places;
2) Copies of any compliance plans required and applicable to the use or application of VOCs at Contractor’s facility or offsite work places.
(c) If no federal, state or local permits or compliance plans are required and applicable to the use or application of VOCs at Contractor’s facility or offsite workplaces, then Contractor shall submit to the designated Port Engineer a letter, notarized under oath, that such documents are not required.
(d) Contractors will submit the following to the designated Port Engineer not later than two weeks after contract award: Data Sheets (MSDS) documents, certificates, specifications or any other manufacturing data verifying the VOC ratings of paints to be applied to the Cutter in accordance with MLCA Standard Spec 63000N, Section 5.3.1.
(9) SECURITY REQUIREMENTS:
A. For access to USCG Base Alameda, the contract shall have RAPIDGate credentials. All personnel that need access to the base, such as on-site personnel, subcontractors (including second and third-tier subcontractors) and suppliers will need RAPIDGate credentials. This process must be completed prior to the start of work. Therefore, the Contractor shall begin the RAPIDGate registration process no less than 45 calendar days before on-site work is to commence. For enrollment into the
RAPIDGate program for base access privileges, information can be found at www.rapidgate.com or by calling the RAPIDGate program at 1-877-727-4342. Please note that all costs associated with registration and participation in the RAPIDGate Program is at the sole expense of the contractor.
B. The Contractor shall provide a list of all on-site personnel, sub-contractors (including second and third tier subcontractors), and suppliers, to the contracting officer and Contracting Officer’s
Representative no less than 30 calendar days before on-site work is to commence. The Contractor shall update this list when changes occur and ensure all personnel satisfy base access standards, and have
RAPIDGate credentials.
C. Contractor personnel not listed and without RAPIDGate credentials may be denied access to the
Coast Guard Facility. Contractor personnel will be restricted to designated working areas. Any personnel violating this policy may lose access to the Coast Guard Facility. Contractor personnel shall have photo identification at all times while working on Coast Guard facilities. Special identification requirements may be needed to obtain the RAPIDGate credentials.
D. Contractor and delivery personnel may be required to present personal photo identification to gain access to a Coast Guard installation. Valid forms of identification are current passport or driver’s license that meet Real ID Act requirements. The Real ID Act of 2005 established minimum security standards for license issuance and production and prohibits Federal agencies from accepting, for certain purposes, driver's licenses and identification cards from states not meeting the Act's minimum standards.
Anyone requiring access to a military facility under this contract, to include subcontractors, who holds a driver's license from any state without approved licenses will be required to provide identification other than that driver's license to gain access. Government IDs annotated with "Federal Limits Apply" will not be accepted for access purposes. It is the responsibility of the Contractor to ensure that their personnel have federally acceptable personal photo identification and comply with any other requirements for base access. TWIC and DBIDS identification cards are not sufficient forms of identification for access to
Coast Guard Island, Alameda
E. If identification does not indicate United States citizenship, Coast Guard Security may require proof of the legal right to work in the United States. Contractor and delivery personnel also may be subjected to an immigration status and outstanding criminal warrants check.
F. Contractors shall provide the Contracting Officer’s Representative with 24 hours of advance notice of every delivery to the site (e.g. concrete, lumber, parts, etc) and provide the company name, delivery person. And phone number of the firm(s) making deliveries. All vehicle access to Government property requires vehicle registration and proof of liability insurance. Otherwise access to the Coast
Guard facility may be denied.
Please contact the Port Engineer, LTJG Hannah Eshleman, (510) 437-5872, or by email at
Hannah.M.Eshleman@uscg.mil, for additional information and processes on base access protocols.
(10) INSPECTIONS
Except as specified elsewhere, the U.S. Coast Guard shall rely on the Contractor to accomplish all inspection and testing needed to ensure that the work conforms to contract quality requirements.
Records of all inspection work by the Contractor shall be kept complete and available to the Government during the term of this contract and for such longer period as may be specified elsewhere in this contract.
The name and telephone number of the U.S. Coast Guard Inspector will be provided after the award of a contract resulting from this solicitation.
(11) GROWTH WORK
(a) The Contractor shall not perform growth work without the Contracting Officer's authorization. Growth work is work within the scope of the contract, which has not been previously priced as a pre-priced CLIN. The Contracting Officer reserves the right to contract for growth work on the basis of a negotiated, firm, fixed price, when it is in the best interest of the Government. Scope of services shall include ship repair and associated support work, and may include work that is not currently listed as Definite or Optional Items.
(b) The Contractor shall furnish a price breakdown directly to the Contracting Officer, itemized as required by the Contracting Officer, of any proposal submitted for a contract modification. Unless otherwise directed, the breakdown shall be submitted with the contractor’s proposal, permitting an analysis of all materials, labor, equipment, subcontract, overhead costs, and profit covering all work involved in the change/modification whether such work was deleted, added or changed. Any amount claimed for subcontracts shall be supported by a separate, similar price breakdown. If the proposal includes a request for a time extension, justification shall be furnished with the proposal.
(c) This clause is to be used in conjunction with the clause COMPOSITE LABOR RATE incorporated into this solicitation. The Contractor is required to have and/or furnish all tools and equipment incidental to each bench trade. Supplies such as wiping rags, hacksaw blades, sandpaper, welding wire, helium, etc., are also to be furnished by the Contractor. Other materials are to be charged at regular rates and prices currently in effect and as agreed to by the Contracting Officer. Material shall be best commercial quality available except where a precise specification is indicated in which case the specification shall apply, e.g., MILSPEC, FEDERAL SPEC.
mailto:Hannah.M.Eshleman@uscg.mil
(12) ACCESS TO VESSEL
A reasonable number of officers, employees, and associates of the Government, or other Prime
Contractors with the Government, and their subcontractors, shall, as authorized by the Contracting
Officer, have, at all reasonable times, and access to vessel to perform and fulfill their respective obligations to the Government on a noninterference basis.
The Contractor shall make reasonable arrangements with the Government or Contractors of the
Government, as shall have been identified and authorized by the Contracting Officer, to be given access to the vessel(s) necessary for the performance of their respective responsibilities and reasonable to their performance.
(13) INDEMNIFICATION FOR ACCESS TO VESSELS
Notwithstanding any provision in the "Access to Vessels" clause, or any other clause of the contract, the
Contractor agrees to allow officers, employees, and associates of the Government, or other Prime
Contractors with the Government and their subcontractors, and officers, employees, and associates of quoters on other contemplated work, access to the vessel without any further request for indemnification from any party, which has not been previously included in the contract price.
(14) COMPOSITE LABOR RATE: The composite labor rate offered shall be the sole labor hour rate used to price the Prime Contractor's direct labor hours for contract changes, i.e. growth work. The
Contractor shall not receive any compensation in addition to this rate for the Prime Contractor's direct labor associated with such changes under this contract.
(a) The composite labor hour rate shall represent total compensation for the following:
(1) direct labor wages and salaries;
(2) all employee benefits including, but not limited to, paid leave, supplemental pay, insurance, retirement, savings, and legally required benefits;
(3) other direct costs associated with transit time, delay, disruption, expendable supplies, and equipment;
(4) all indirect costs such as overhead and general and administrative expense;
(5) any port or association fees, rents, or other levies;
(6) profit (fee); and
(7) all direct and indirect costs and profit associated with the following support functions:
Supervision and Management Planning
Material Handling Housekeeping
Engineering Transportation/Drivers
Quality Assurance Contract Administration
Security Testing
Worker Transit Time Guards
Fire Watches Estimating
(b) The composite labor hour rate will be applied to production labor hours only.
Production labor hours include only those hours necessary and reasonable to perform direct production functions and do not include the hours expended on the support functions listed above. This exclusion of support function hours applies whether such support functions are normally charged directly or indirectly by the Contractor's accounting system. These support functions are to be priced into the composite labor rate quoted and shall not be separately compensated.
(c) The Quantity of Composite Labor hours indicated in the Schedule of Supplies/Services, is only an estimate and is an Optional Item pursuant to this solicitation. The Estimated Quantity represents the Government’s best estimate of the total number of additional hours that may be required throughout the contract. The Government may elect to exceed this value at the prices stated in the schedule and its discretion during performance of the contract. The inclusion of this item does not obligate the Government to exercise the item nor entitle the Contractor to compensation if not exercised.
(15) DISCOVERIES AND CHANGES TO CONTRACT
Condition Found Report and Change Requests will be transmitted electronically by using email. The bullets below display the process of how these documents are to be followed for the duration of the contract performance period:
(a) Condition Found Report (CFR)- All readings and inspections are to be taken within 24 hours after the machinery or system is opened. All reports of reading and inspections required by the specifications shall be submitted to the COR in writing using a
“Condition Found Report (CFR)” form, within 24 hours after the readings and/or inspections are made.
Promptness in taking and reporting readings is particularly importance for underbody work items such as shaft bearing or rudder bearing clearances. Often during the progress of a work item, conditions are discovered by the contractor which are considered abnormal for reasons of safety, expected reliability, health, or habitability. These conditions must be brought to the attention of the Coast Guard using a CFR. Details provided by the Contractor in a CFR are important because the CFR may result in a contract change. To spend the contract progress, the
Contractor should include in his/her CFR the following details as a minimum:
(i) A sequential number
(ii) The contract item which the “CFR” relates to.
(iii) A clear statement, definition, and description of the condition found, including but not limited to frame numbers, part numbers, materials and dimensions as appropriate.
(iv) A proposed or recommended repair to correct the defective condition.
(v) Indicate whether the report requires Coast Guard action, or if it is provided “for Info” only. If action is required, indicate the response time require by the Coast Guard and whether or not a contract extension would be needed if the additional work is authorized.
(vi) A space on the form for the Coast Guard to make comments.
(vii) All CFR’s will be dated, submitted, and signed by a representative of the Contractor.
Contracting Officer’s Representative (COR) will respond to the Contractor’s within 24 hours of receiving a Condition Found Report. A copy of ALL condition Found Reports shall be retained in the Cutter’s file.
(b) Change Request (CR) Process will occur in the following order:
1. Condition Found Report – Generated by the Contractor and provided to COR.
2. Condition Report Reply – Generated by the COR and provide to Contractor.
3. Change Request – CR and IGE are generated by the COR and entered in the Contract
Workbook. COR will assign the Change Request number.
4. COR provides copy of Change Request to the Contractor.
5. Contractor’s Proposal – provided to the KO for the identified tasking on CR.
6. Negotiations – if needed, take place to establish pricing.
7. Approved Change Request – forwarded to Contractor and COR by the KO.
8. Modification to Contract – The KS/KO will issue a modification covering all CRs.
Change Request must be submitted by the COR to the Contractor within 24 hours after responding to the CFR. Contractor must submit proposal to the Contracting Officer within 72 hours of receipt of the Change Request.
A modification will be issued to incorporate and implement all changes made by change orders.
(16) CONTRACT DEFICIENCY REPORT
The Contracting Officer or Contracting Officer’s Representative (COR) may issue a Contract Deficiency
Report (CDR), SFLC Form PDM - 29. The Contractor shall respond in writing within 24 hours of receipt, unless otherwise approved by the Contracting Officer, to the COR. The COR will comment on the Contractor's response and will forward the Deficiency Report and comments to the Contracting
Officer, with a copy to the Contractor and Availability Program Manager. The Contracting Officer will render a final determination and provide it to the Contractor and COR in writing.
(17) MAINTAINING, REPORTING, AND DISPOSING OF GOVERNMENT PROPERTY IN
THE PERFORMANCE OF A SHIP REPAIR CONTRACT
1. The Government Property Clause incorporated by reference delineates the Contractor's overall responsibility when taking possession of government property in performance of a contract. In performance of this contract the Contractor will be required to properly identify, track and control property within its possession. This includes, a) property furnished by the government (GFP) to the
Contractor in conjunction with specific CLIN Items. These items and their values are listed in the specification, b) property that is pre-existing in a location that during the course of performance will be replaced or renewed.
2. The items listed in the specification, as government furnished property will be provided in the quantities designated. Government furnished property may be provided in person by an official Coast
Guard employee, shipment via commercial carrier, etc. The Contractor shall sign for all government furnished property using either a DD Form 1149, entitled, “Requisition and Invoice/Shipping
Document” or a DD Form 1348, entitled, “Issue Release/Receipt Document”. A copy of the DD
1149 or DD 1348 must be sent within 48 hours of receipt of property, to the designated
Government Property Administrator. The name of the individual assigned as Property Administrator will be furnished to the Contractor at time of award. The Contractor shall not take receipt of property that is not listed in the specification, has not been previously identified as becoming part of the contract
(via contract modification) or which otherwise cannot be identified. Such irregularities shall be immediately reported to the Property Administrator.
3. The Contractor shall complete the report provided herein, entitled, “Government Property Report”.
This report is intended as a living document whereby relevant fields shall be filled in, maintained and kept current at all times. All property described in paragraph 1 (a and b) above shall be reported on the report. At contract completion the Contractor and the Property Administrator shall ensure that all fields are appropriately completed. A signature block is provided at the end of the report for both parties to attest to the report's accuracy and completeness. The Government Property Report shall clearly delineate the complete track that all Government property took over the course of the contract. This completed report must accompany the Contractor's final invoice. Final payment may be delayed, without penalty of interest, until such time as the report is received. A separate copy of the completed report and any final DD 1149s or DD 1348s executed, as a result of carrying out disposition instructions shall be provided to the Property Administrator.
4. Pursuant to the Government Property Clause the authority to render disposition instructions of
Government property associated with this contract is delegated to the Property Administrator. The
Contractor shall comply with all instructions in the contract for the return of government property to the
Coast Guard. This includes government property taken off the vessel (shafts, propellers, etc.), government property returned to the vessel (special tools, etc.) or surplus government property not used during performance of the contract.
(18) CONTRACTING OFFICER’S AUTHORITY
No oral or written statement of any person other than the Contracting Officer will in any manner or degree modify or otherwise affect the terms of this contract. The Contracting Officer is the only person authorized to approve changes in any of the requirements under this contract, and, notwithstanding any provisions contained elsewhere in this contract, said authority remains solely with the Contracting
Officer. In the event the Contractor effects any such change at the direction of any person other than the
Contracting Officer, the change will be considered to have been made without authority and no adjustment will be made in the contract price to cover any increase in cost incurred as a result thereof.
(19) CONTRACTOR PERFORMANCE EVALUATION
(a) The U.S. Coast Guard Surface Forces Logistic Center (SFLC) will monitor and evaluate the successful offeror’s past performance of this contract and prepare a Contractor Performance Assessment
Report (CPAR) in accordance with FAR Part 42.15. All information contained in this assessment may be used, within the limitations of FAR 42.15, by the government for future source selections and in accordance with FAR 15.304, when past performance is an evaluation factor for award.
(b) NOTIFICATION: Upon completion of the contract, the contractor will be notified of the assessment. The contractor will be allowed 60 days to respond to the SLFC’s assessment of its performance entered into CPARS. The contractor’s response, if any, will be made part of the CPAR system at https://www.cpars.cpars.gov.
(c) INFORMATION: Information included in the CPAR may include, but is not limited to, the contractor’s record of conforming to contract requirements and to standards of good workmanship; the contractor’s record of forecasting and controlling costs; the contractor’s adherence to contract schedules, including the administrative aspects of performance; the contractor’s history of reasonable and cooperative behavior and commitment to customer satisfaction; the contractor’s record of integrity and business ethics, and generally, the contractor’s business-like concern for the interest of the customer.
(d) RELEASE OF DATA: CPARS information is considered business sensitive and will not be released except: (1) to other Federal procurement activities which request it; (2) when SFLC must release pursuant to a Freedom of Information Act (FOIA) request; or (3) when prior written consent is requested and obtained from the contractor.
(20) METHOD OF PAYMENT AND INVOICING INSTRUCTIONS
INVOICE SUBMISSION PROCESS:
(a) A request for payment is proper if it includes the items required by the clause at FAR 52.232-25, Prompt Payment [(a)(3)(i) through (a)(3)(ix)] and those items are accurate. If a request for payment does not include all the items required by the clause at FAR 52.232-25, Prompt Payment, or any information is inaccurate, then the request is not proper and shall be returned to the contractor with a statement of the reason(s) it is not proper.
(b) Each invoice shall at a minimum contain the following information:
(1) Invoice Date
(2) Invoice Number
(3) Contract and Delivery/Task Order Number
(4) Contractor’s Name
(5) Contractor’s Address
(6) Contractor’s DUNS
(7) Contracting Officer’s Name
(8) Contracting Officer’s Representative’s (COR’s) Name
(9) Invoice Routing Code (IRC) assigned by the Coast Guard as follows: SFLC-2
(10) Period of Performance for Work Invoiced
(11) Contract Line Item Number(s) (CLIN(s)) and Description
(12) CLIN units for the period (if applicable), CLIN rate (if applicable), CLIN Total
(13) Invoice Total
(14) For Travel: Components in accordance with FAR 31.205-46
(15) Discount Offerings
(16) Status as a Small Business (if applicable) for accelerated payment
(17) The last invoice submitted for this award shall be clearly labeled with “FINAL
INVOICE.”
(c) The contractor shall submit each invoice in accordance with the information at:
https://www.fincen.uscg.mil/electron.htm https://www.fincen.uscg.mil/electron.htm
(d) The contractor shall email the invoice and supporting documentation to include the invoice receipt generated by FINCEN from step (c) above. Failure to email the invoice and supporting documentation to the following contacts may result in invoice rejection or delay in payment:
Denise.E.Manor@uscg.mil, Wilma.L.Estrada@uscg.mil and the TBD COR.
(e) In accordance with the Prompt Payment Act, for the purposes of determining a payment due date and the date on which interest will begin to accrue if a payment is late, a proper invoice shall be deemed to have been received:
(1) On the later of:
(i) For invoices that are mailed, the date a proper invoice is actually received by the designated billing office and annotates the invoice with date of receipt at the time of receipt.
(ii) For invoices electronically transmitted by the contractor via web based submission, the date a transmission is received by the designated billing office, and receipt confirmation is provided to the designated recipient; or
(ii) The seventh day after the date on which the property is actually delivered or performance of the services is actually completed; unless—
a) The agency has actually accepted the property or services before the seventh day in which case the acceptance date shall substitute for the seventh day after the delivery date; or
b) A longer acceptance period is specified in the contract, in which case the date of actual acceptance or the date on which such longer acceptance period ends shall substitute for the seventh day after the delivery date;
(2) On the date placed on the invoice by the contractor, when the agency fails to annotate the invoice with date of receipt of the invoice at the time of receipt (such invoice must be a proper invoice); or
(3) On the date of delivery, when the contract specifies that the delivery ticket may serve as an invoice.
(4) Web-based submission by the contractor and receipt confirmation does not reflect Government review or acceptance of the invoice.
(5) Payment inquiries and status may be obtained at the following website:
https://www.fincen.uscg.mil/electron.htm.
(f) Failure to follow any of these instructions shall result in invoice rejection
8. A copy of the invoice and any supporting documentation shall also be e-mailed to the following individuals: Wilma.L.Estrada@uscg.mil and Denise.E.Manor@uscg.mil and the COR (will be appointed after award)
Additional work verbally agreed to by the parties that has not yet been incorporated into the contract by modification shall not be included in an invoice. Payments will not be made for any work to which a modification has not been properly executed. Invoices submitted for payment that includes such a request will be reduced by the unmodified amount.
mailto:Denise.E.Manor@uscg.mil mailto:Wilma.L.Estrada@uscg.mil https://www.fincen.uscg.mil/electron.htm mailto:Wilma.L.Estrada@uscg.mil mailto:Denise.E.Manor@uscg.mil
NOTE: 10% OF THE TOTAL CONTRACT PRICE WILL BE WITHHELD UNTIL ALL
DELIVERABLES, REQUIRED BY THE CONTRACT, ARE RECEIVED AND ACCEPTED.
FURTHER CONSIDERATIONS WITH INVOICING:
In accordance with the Prompt Payment Act, for the purposes of determining a payment due date and the date on which interest will begin to accrue if a payment is late, a proper invoice shall be deemed to have been received:
(1) On the later of:
(i) For invoices that are mailed the date a proper invoice is actually received by the designated billing office and annotates the invoice with date of receipt at the time of receipt.
(ii) For invoices electronically transmitted by the contractor via web based submission, the date a transmission is received by the designated billing office, and receipt confirmation is provided to the designated recipient; or
(iii) The seventh day after the date on which the property is actually delivered or performance of the services is actually completed; unless—
a) The agency has actually accepted the property or services before the seventh day in which case the acceptance date shall substitute for the seventh day after the delivery date;
or
b) A longer acceptance period is specified in the contract, in which case the date of actual acceptance or the date on which such longer acceptance period ends shall substitute for the seventh day after the delivery date;
(2) On the date placed on the invoice by the contractor, when the agency fails to annotate the invoice with date of receipt of the invoice at the time of receipt (such invoice must be a proper invoice); or
(3) On the date of delivery, when the contract specifies that the delivery ticket may serve as an invoice.
(4) Web based submission by the contractor and receipt confirmation does not reflect
Government review or acceptance of the invoice.
(5) For inquiries and payment status please visit https://fincen.uscg.mil/secure/payment.htm
All payments for partial performance rendered by the Government under this contract are based on the assumption that the Contractor will, in good faith, execute and honor all payment terms entered into between it, the Prime Contractor, and any subcontractor thereof in the performance of this contract. The
Contractor hereby acknowledges the Government’s right to reduce or suspend progress payments based on non-payment in accordance with any payment terms of the subcontract agreement.
Any amount deemed not payable will be deducted from the Contractor’s invoice. Deducted amounts may be resubmitted on the next invoice for reconsideration.
https://fincen.uscg.mil/secure/payment.htm
(21) PROGRESS PAYMENTS:
A. The Contractor may invoice requesting progress payments without discount, other than any prompt payment discount offered, not more frequently than every two weeks.
B. The invoice amount should reflect the percentage and dollar amount of completion established by the cutter’s appropriate weekly progress report. Payments shall be derived from the accomplished percentage of completion as determined by the Contracting Officer.
C. All material and work paid for by progress payments shall thereby become the sole property of the Government, but this provision shall not relieve the contractor from the obligation to complete the requirements of the contract.
D. The Contractor shall be paid the remaining amount due upon completion and acceptance of all work under this contract.
(End of Clause)
(22) Associate Contractor Agreement
After award, the Contractor shall enter into an Associate Contractor Agreement, if applicable, with one or more other prime contractors with the Government who will be present and performing work on the vessel during the dry dock availability.
ASSOCIATE CONTRACTOR CLAUSE
(1) This clause is intended to ensure that there will be appropriate integration of work by the CGC
WAESCHE associate contractors to maximize coordination and prevent delay or additional costs.
(2) The Firm Fixed-Price (FFP) for each Work Item in ATTACHMENT 2, Price Schedule shall include all costs associated with the Prime Contractor executing each requirement stipulated in the Associate
Contractor Agreement (“ACA”) as required by this clause, in support of this contract.
(3) For purposes of this clause, the Associate Contractor, known at this time, is defined as:
(a) [Prime Contractor under 70Z08521CP4502900.]
(4) The Associate Contractors shall work and maintain close liaison with each other. In order to assure accomplishment of this objective, the Associate Contractors shall enter into a written ACA with each other.
(5) The ACA shall provide for a complete and unbiased exchange of scheduling information to include work locations. The following shall be included in the ACA:
(a) Identification of the information to be furnished between the Associate Contractors.
This shall, at a minimum, include the schedule and locations of work to be performed.
(b) Services to be provided by one Associate Contractor to another [if applicable]
(c) The materials to be provided between the Associate Contractors during performance.
[if applicable]
(d) In accordance with Specification General Requirements, the Prime Contractor shall hold a weekly progress meeting, and also daily production meetings.
(i) At the daily production meetings, Associate Contractors shall attend and participate to resolve any potential conflicts in the work schedule for that day, so as to minimize delay, disruption or overlapping work.
(ii) At the weekly progress meetings, the Associate Contractors shall provide an integrated and de-conflicted master planning document for review by the USCG COR. Associate Contractors shall meet together prior to the weekly progress meeting to develop this master planning document.
(iii) The Associate Contractors are responsible to resolve all planning conflicts. However, the USCG
COR reserves the right to serve as final decision authority when needed to ensure timely schedule completion and/or that Operational Commander’s priorities are met.
(e) The ACA may also address treatment of any proprietary or confidential information.[if applicable]
(6) Following execution by both Associate Contractors, the ACA may be made an attachment to this contract. The ACA is for information purposes only and shall not be subject to or governed by this contract. In the event of a conflict between the terms of this contract and terms of the ACA, the terms of this contract shall control.
(7) Where the Associate Contractors fail to agree upon action to be taken in connection with their respective responsibilities, each of them shall promptly notify the COR responsible for their respective contract and furnish their recommendations for a solution. The Associate Contractors shall not be relieved of its obligations to make timely deliveries or be entitled to any other adjustment because of their failure to: (a) resolve ACAs disputes; (b) promptly refer matters to the COR assigned to their respective contract; or (c) to implement any direction given by the COR assigned to their respective contract.
(End of FAR 52.212-4 Addendum)
(23) 52.212-5 CONTRACT TERMS AND CONDITIONS REQUIRED TO IMPLEMENT
STATUTES OR EXECUTIVE ORDERS—COMMERCIAL ITEMS. (AUG 2020)
(a) The Contractor shall comply with the following Federal Acquisition Regulation (FAR) clauses, which are incorporated in this contract by reference, to implement provisions of law or Executive orders applicable to acquisitions of commercial items:
(1) 52.203-19, Prohibition on Requiring Certain Internal Confidentiality Agreements or
Statements (Jan 2017) (section 743 of Division E, Title VII, of the Consolidated and Further
Continuing Appropriations Act, 2015 (Pub. L. 113-235) and its successor provisions in subsequent appropriations acts (and as extended in continuing resolutions)).
(2) 52.204-23, Prohibition on Contracting for Hardware, Software, and Services Developed or
Provided by Kaspersky Lab and Other Covered Entities (Jul 2018) (Section 1634 of Pub. L. 115-
91).
(3) 52.204-25, Prohibition on Contracting for Certain Telecommunications and Video
Surveillance Services or Equipment. (Aug 2020) (Section 889(a)(1)(A) of Pub. L. 115-232).
(4) 52.209-10, Prohibition on Contracting with Inverted Domestic Corporations (Nov 2015).
(5) 52.233-3, Protest After Award (Aug 1996) (31 U.S.C. 3553).
(6) 52.233-4, Applicable Law for Breach of Contract Claim (Oct 2004) (Public Laws 108-77 and
108-78 ( 19 U.S.C. 3805 note)).
(b) The Contractor shall comply with the FAR clauses in this paragraph (b) that the Contracting Officer has indicated as being incorporated in this contract by reference to implement provisions of law or
Executive orders applicable to acquisitions of commercial items:
_X__ (1) 52.203-6, Restrictions on Subcontractor Sales to the Government (June 2020), with
Alternate I (Oct 1995) (41 U.S.C. 4704 and 10 U.S.C. 2402).
__ (2) 52.203-13, Contractor Code of Business Ethics and Conduct (Jun 2020) (41 U.S.C. 3509)).
__ (3) 52.203-15, Whistleblower Protections under the American Recovery and Reinvestment
Act of 2009 (Jun 2010) (Section 1553 of Pub. L. 111-5). (Applies to contracts funded by the American
Recovery and Reinvestment Act of 2009.)
_X__ (4) 52.204-10, Reporting Executive Compensation and First-Tier Subcontract Awards (Jun
2020) (Pub. L. 109-282) ( 31 U.S.C. 6101 note).
__ (5) [Reserved].
_X__ (6) 52.204-14, Service Contract Reporting Requirements (Oct 2016) (Pub. L. 111-117, section
743 of Div. C).
__ (7) 52.204-15, Service Contract Reporting Requirements for Indefinite-Delivery Contracts
(Oct 2016) (Pub. L. 111-117, section 743 of Div. C).
_X__ (8) 52.209-6, Protecting the Government’s Interest When Subcontracting with Contractors
Debarred, Suspended, or Proposed for Debarment. (Jun 2020) (31 U.S.C. 6101 note).
_X__ (9) 52.209-9, Updates of Publicly Available Information Regarding Responsibility Matters
(Oct 2018) (41 U.S.C. 2313).
__ (10) [Reserved].
__ (11) (i) 52.219-3, Notice of HUBZone Set-Aside or Sole-Source Award (Mar 2020) (15 U.S.C.
657a).
__ (ii) Alternate I (Mar 2020) of 52.219-3.
__ (12) (i) 52.219-4, Notice of Price Evaluation Preference for HUBZone Small Business
Concerns (Mar 2020) (if the offeror elects to waive the preference, it shall so indicate in its offer) (15
U.S.C. 657a).
__ (ii) Alternate I (Mar 2020) of 52.219-4.
__ (13) [Reserved]
_X__ (14) (i) 52.219-6, Notice of Total Small Business Set-Aside (Mar 2020) (15 U.S.C. 644).
__ (ii) Alternate I (Mar 2020) of 52.219-6.
__ (15) (i) 52.219-7, Notice of Partial Small Business Set-Aside (Mar 2020) (15 U.S.C. 644).
__ (ii) Alternate I (Mar 2020) of 52.219-7.
_X__ (16) 52.219-8, Utilization of Small Business Concerns (Oct 2018) (15 U.S.C. 637(d)(2) and
(3)).
__ (17) (i) 52.219-9, Small Business Subcontracting Plan (Jun 2020) (15 U.S.C. 637(d)(4)).
__ (ii) Alternate I (Nov 2016) of 52.219-9.
__ (iii) Alternate II (Nov 2016) of 52.219-9.
__ (iv) Alternate III (Jun 2020) of 52.219-9.
__ (v) Alternate IV (Jun 2020) of 52.219-9
__ (18) (i) 52.219-13, Notice of Set-Aside of Orders (Mar 2020) (15 U.S.C. 644(r)).
(ii) Alternate I (Mar 2020) of 52.219-13.
_X__ (19) 52.219-14, Limitations on Subcontracting (Mar 2020) (15 U.S.C. 637(a)(14)).
__ (20) 52.219-16, Liquidated Damages-Subcontracting Plan (Jan 1999) (15 U.S.C.
637(d)(4)(F)(i)).
__ (21) 52.219-27, Notice of Service-Disabled Veteran-Owned Small Business Set-Aside (Mar
2020) (15 U.S.C. 657f).
_X__ (22) (i) 52.219-28, Post Award Small Business Program Re-representation (May 2020) (15
U.S.C. 632(a)(2)).
(ii) Alternate I (MAR 2020) of 52.219-28.
__ (23) 52.219-29, Notice of Set-Aside for, or Sole Source Award to, Economically
Disadvantaged Women-Owned Small Business Concerns (Mar 2020) (15 U.S.C. 637(m)).
__ (24) 52.219-30, Notice of Set-Aside for, or Sole Source Award to, Women-Owned Small
Business Concerns Eligible Under the Women-Owned Small Business Program (Mar2020) (15 U.S.C.
637(m)).
__ (25) 52.219-32, Orders Issued Directly Under Small Business Reserves (Mar 2020) (15
U.S.C. 644(r)).
__ (26) 52.219-33, Non-manufacturer Rule (Mar 2020) (15U.S.C. 637(a)(17)).
_X__ (27) 52.222-3, Convict Labor (Jun 2003) (E.O.11755).
_X__ (28) 52.222-19, Child Labor-Cooperation with Authorities and Remedies (Jan2020)
(E.O.13126).
_X__ (29) 52.222-21, Prohibition of Segregated Facilities (Apr 2015).
_X__ (30) (i) 52.222-26, Equal Opportunity (Sep 2016) (E.O.11246).
__ (ii) Alternate I (Feb 1999) of 52.222-26.
_X__ (31) (i) 52.222-35, Equal Opportunity for Veterans (Jun 2020) (38 U.S.C. 4212).
__ (ii) Alternate I (Jul 2014) of 52.222-35.
_X__ (32) (i) 52.222-36, Equal Opportunity for Workers with Disabilities (Jun 2020) (29 U.S.C.
793…