SECTION 01 11 10 Page 1
SECTION 01 11 10
SPECIAL CONDITIONS
REVISED 6APRIL 2021
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
SECTION 01 12 00 Environmental Special Conditions Langley Air Force Base (AFB), Joint Base Langley-
Eustis (JBLE)
U.S. ARMY CORPS OF ENGINEERS (USACE) EM 385-1-1
(2003 or most current version) Safety and Health Requirements
LANGLEY AFB, JBLE TELECOMMUNICATIONS BUILDING CABLING SYSTEMS STANDARDS
(Langley AFB, JBLE Specification 27 10 10 dated 02 June 2008 or most current version)
1.2 SUBMITTALS
The following items specified herein shall be submitted in accordance with SUBMITTAL PROCEDURES:
SD-03 Product Data
Material Safety Data Sheet (MSDS) for each item
State and EPA Region 3 Notifications
Trip Tickets
Affirmative Procurement Report
Exemption Form, Annex B to LAFB Affirmative Procurement Plan
32-7080
All Employee Names and Social Security Numbers
Work Clearance Requests (Air Force Form 103)
Quality Control (QC) Report
SD-11 Closeout Submittals
Survey Report
Metadata
Deliverables and Final As-builts
One As-Built (Redline) Drawings
Warranty of Construction
Equipment Warranty Certificate
Equipment Warranty/Guarantee Record
SECTION 01 11 10 Page 2
DD Form 1354 Acceptance and Transfer of Real Property Facilities
1.2.1 SUBMITTAL PROCEDURES
1.2.1.1 Schedule of Material Submittals (Air Force Form 66)
Information, shop drawings, certificates, test data, etc., listed on the attached AF Form 66, Schedule of Material
Submittals, shall be submitted for approval by the Contracting Officer, or his/her designated representative in ac-cordance with the General Provisions. Whenever in this contract materials or drawings are required to be submitted by the Contractor to the Contracting Officer for approval and the material or drawings submitted are at variance with the specifications or Government drawings, but are, nevertheless, approved by the Contracting Officer, inad-vertently and without consciousness of the variance, and regardless that a closer review could have revealed the variance, then such approval shall not be final unless the Contractor expressly noted in a memorandum to the
Contracting Officer, on the material submittal or drawing that “this material or drawing varies from specifications in the following aspects –” or uses other works of similar clear meaning. In the event of such an inadvertent, erroneous approval, the Contracting Officer, upon discovering the variance at any stage, have the right to require the Contractor to do such rework and/or material replacement as is necessary to obtain compliance with the speci-fications, and the expense of such rework and material replacement shall be borne solely by the Contractor.
1.3 SCOPE OF WORK
The work under this project consists of demolition of Facilities 732 and 735 to include the removal of foundation and associated concrete pads, roadway, parking area, sidewalks, fence and storage units.
1.3.1 Work Hours
Normal duty hours for Langley AFB, JBLE are 0730 through 1630, Monday through Friday. Work on weekends, recognized Federal holidays, or other than normal duty hours must be coordinated with the Contracting Officer
(CO) or his/her designated representative.
1.3.2 General Working Conditions
a. Work shall be performed in such a manner as to cause minimum disruption to the users in the area.
b. The Contractor shall notify the Contracting Officer or his/her designated representative when he intends to work so Government inspection can be provided while work is in progress.
SECTION 01 11 10 Page 3
1.4 ORDER OF WORK
The Contractor shall coordinate all work with the Contracting Officer, or his/her designated representative, and the
Base Civil Engineer. Before starting work at the job site, provide five days notice to the Contracting Officer or his/her designated representative and the Chief of Contract Management at 764-3268.
1.5 APPLICABLE CODES AND REGULATIONS
The latest edition of the following Building Codes shall be used for all construction under this contract:
A. International Building Code
B. International Mechanical Code
C. International Fire Code
D. International Code Council (ICC) International Plumbing Code
E. National Electrical Code (NEC)
F. ANSI C-2, National Electrical Safety Code (QIESC)
G. Life Safety Code, NFPA 101
H. Americans with Disabilities Act (ADA)
I. National Fire Protection Association (NFPA)
J. MIL Handbook 1190
K. Unified Facilities Criteria (UFC) 3-600-01
L. Applicable Unified Facilities Guide Specifications
M. Supervisory Control and Data Acquisition (SCADA)
N. American National Standards Institute (ANSI)
O. American Standards for Testing Materials (ASTM)
P. Institute of Electrical and Electronics Engineers (IEEE)
Q. International Society of Automation (ISA)
R. National Electrical Manufacturers Association (NEMA)
S. Underwriters Laboratories, Inc. (UL)
T. Leadership in Energy and Environmental Design (LEED®) for New Construction and Major
Renovation v2.2 Reference Guide
U. National Fire Protection Association Codes (NFPA) – latest edition
V. Langley AFB, JBLE Electrical, Fire, and Communications Design Standards -- latest edition
W. Air Force Engineering Technical Letter ETL 01-1, Reliability and Maintainability (R&M)
Design Checklist
NOTE: If there is a conflict between these codes or regulations and these contract specifications, the most stringent requirements shall apply at all times.
1.6 SALVAGE
Title to all materials and equipment to be demolished, excepting items indicated as Government salvage, shall be vested to the Contractor upon removal from the base except as noted below. The Government will not be respon-sible for the condition, loss or damage to such property after notice to proceed. All unsalvageable material will be disposed of legally off base.
1.6.1 Items Salvaged for the Government
The Contractor shall salvage the following existing materials to the Government as indicated below. Salvaged materials shall be cleaned, sorted, identified, bundled, boxed, etc. and delivered to the collection location identified below.
ITEM DELIVERY LOCATION
SECTION 01 11 10 Page 4
None
1.7 CONSTRUCTION STANDARDS
1.7.1 General
The Contractor is reminded that the construction site must be operated and maintained according to these specifi-cations and is subject to inspection and enforcement according to all federal, state and local codes/regulations.
1.7.2 Office Trailers and Storage Units
1.7.2.1 Office Trailers
If a trailer is required for work and at the discretion of the Government, an office trailer may be located at the project site. The Contractor shall request Contracting Officer approval for the trailer location. The Contractor shall make the request in writing at least fourteen calendar days prior to placement of trailer at site. All office trailers shall be located in areas as directed by the Contracting Officer or his/her designated representative. Any office trailer shall be not more than 10’ x 32’ in size, provided with a skirt on all sides, in like new condition, and painted either Langley Brown (Federal Standard 595a, 20100), Langley Beige, or white. Office trailers in need of painting and / or repairs or that are in an unsightly condition will not be al-lowed at the project site. Displayed on the exterior of all trailers shall be a nameplate which has the name of the Contractor’s company, name for Contractor’s point(s) of contact (POC) and telephone number where he or she can be reached, contract number, project number, title and date trailer was placed on site where located.
1.7.2.2 Storage Units
The Contractor shall request Contracting Officer approval for the siting, size and color of Storage Units, CONEX boxes and dumpsters. The Contractor shall not bring any such items to the job site without the Contracting Officer’s approval. All storage units shall be painted Langley Brown (Federal Standard 595a, 20100), Langley Beige or white. Displayed on the exterior of all storage units shall be a nameplate which has the name of the Contractor’s company, name for Contractor’s point(s) of contact (POC) and telephone number where he or she can be reached, contract number, project number, title and date unit was placed on site where located.
1.7.3 On-Site Storage Units
Availability and size of material lay down area shall be restricted as noted on the contract documents or as discussed during the preconstruction conference. The Contractor shall consolidate all bulk or large quantities of materials at the construction site in area(s) approved by the CO. All such items shall be stored neatly grouped together. Bulky or unsightly construction materials, heavy or light equipment or tanks shall not be delivered to or stored on the construction site for any period longer than seven calendar days prior to use, installation in the project or start of construction. The Contractor shall store all supplies and equipment on project site to preclude theft or damage.
Protection and security for materials and equipment on site is the sole responsibility of the Contractor. The Con-tractor shall not use any area(s) for material or equipment storage that has not been approved by the CO or his/her designated representative.
1.7.4 Fencing and Screening
Contractor shall enclose the lay down area with a chain link fence that has been erected to a minimum height of six feet. Contractor’s lay down area shall also be screened from view. Screening shall be fabricated of 100% Poly-propylene, woven, 92% blockage fabric that has been mechanically attached to the fence for the full height of the fence. The edges of each section of screening fabric shall be finished with a reinforced hem. Attachment points shall be reinforced fabric built into the hem or metal grommets built into the hem. All fabric used for screening of the construction lay down area shall be UV rated and dark brown or dark bronze in color. Fence screening fabric shall be inspected weekly to insure all sections remain properly in-stalled and taut at all times.
SECTION 01 11 10 Page 5
1.7.5 Locksets
Not Applicable (N/A)
1.7.6 Communications
Not Applicable (N/A)
1.7.7 Electrical Panels
Any electrical panel altered by the Contractor shall have every circuit and circuit modification legibly identified as to its clear, evident and specific purpose and use. The identification shall include sufficient detail to allow each circuit to be distinguished from all others. Spare positions that contain unused overcurrent devices or switches shall be described accordingly. The identification shall be included in a circuit directory that shall be located on the face or inside of the panel door in the case of a panelboard and located at each switch in a switchboard. No circuit shall be described in a manner that depends on transient conditions of occupancy. This is in accordance with §408.4 of the 2008 version of the National Electric Code (NEC).
1.8 CONTRACTOR OPERATIONS
1.8.1 Grassy Areas
Grass and weed growth in excavated materials that are stockpiled on site shall be controlled or cut weekly. Weeds and grass within the construction site shall also be controlled or cut weekly and any bushes or shrubs shall be trimmed monthly. Areas disturbed by construction or those areas required by the plans to be “re-seeded” shall be re-established by hydroseeding only. Straw shall not be used as a cover for freshly seeded areas.
1.8.2 Privately Owned Vehicles (POVs)
POVs used by Contractor personnel to commute to work are required to park in existing parking lots. Contractor or Contractor’s employees, including subcontractors, shall not park any personally owned vehicle (POV) or com-pany or delivery vehicle on grassy areas near or in the construction site without prior approval from the Contracting
Officer, or his/her designated representative. When allowed, parking on grassy areas will only be for short-term delivery purposes (to include heavy tools, equipment, construction materials, etc.). Use designated hard surfaces or existing parking lots near or within the project site for parking of POVs or company or delivery vehicles. Tire and track impressions (ruts) created on wet or soft soil by vehicles or equipment used in the Contractor’s operations
SECTION 01 11 10 Page 6 shall not be left for more than one day after removal of such vehicle or equipment that cased the rutting. The
Contractor shall restore the affected area(s) of the site to its original condition within that one-day period.
1.8.3 Site Cleanup
During construction, the Contractor shall maintain all areas in a neat and orderly manner. Contractor shall keep the construction site cleaned daily of all construction trash, trash generated by employees, debris or demolished building materials. If the work areas are not kept neat and orderly, the Contractor must return to the area to correct the unacceptable condition. During the laying of asphalt roads, streets or parking surfaces, areas soiled by residual asphalt shall be cleaned daily. The Contractor shall treat with lime entrances and exits to asphalt work site at his/her own expense.
1.8.4 Access Routes
Access routes to this project shall be limited along Sweeney Blvd and Perimeter Road as shown on the plans.
1.8.5 Removal of Formwork
Not Applicable (N/A)
1.8.6 Noise Control
The Contractor shall comply with all applicable state, local and installation laws, ordinances and regulations rela-tive to noise control, to include applicable quiet hours exclusive to Langley AFB, JBLE. Work site is in a residential area of Langley AFB, JBLE. There shall be absolutely no construction activities in or around the construction site prior to or after the hours designated in “Work Hours” paragraph above without an approval from the Contracting
Officer, or his/her designated representative. This restriction also applies to holidays also.
1.8.7 Excavations
All trenches/excavations shall be back filled and compacted to 95% of maximum Proctor density. Trenches will be top dressed with no less than three inches of shifted topsoil and then compacted. The finished area will be free of all debris, rocks and then graded to conform to the surrounding area. The area will be hydroseeded in accordance with SECTION 32 92 19 SEEDING of the specifications.
1.8.8 In-Ground Obstructions
Any type of raised obstructions shall have the surrounding soil backfilled, compacted to 95% of maximum Proctor density, and graded. The area will be top dressed as above to within three inches of the top of obstruction. Ground level obstructions will have the area dressed to the level of the obstruction. The area will be hydroseeded in ac-cordance with SECTION 32 92 19 SEEDING of the specifications.
1.8.9 Architectural Compatibility
Due to Langley AFB, JBLE’s distinct historic architecture and the high visitor traffic it receives, several special actions are required during construction:
a. The Contractor is solely responsible for spillage from his/her vehicles and such spillage shall be cleaned up immediately. For the duration of this contract and on a daily basis, the Contractor shall remove from all base roads and streets asphalt, mud, soil, rocks, trash and debris that result from his/her construction operation on base. All roads or streets affected shall be cleaned before close of business on the particular day affected.
In the case of asphalt, roads will be cleaned and/or treated with lime immediately upon detection.
b. Newly placed concrete curbing and sidewalks shall match existing, adjacent concrete in color and tex-ture.
SECTION 01 11 10 Page 7
c. Unprimed or factory-finished equipment installed on the exterior of facilities shall be painted with two coats of brown paint to match existing equipment.
1.8.10 Patching
All holes in walls or other parts of the structure where material or equipment is removed or replaced shall be sealed, painted, caulked or plugged neatly with original type of materials to match the existing part of the structure so involved. All above work and materials shall be approved by the Contracting Officer or his/her designated repre-sentative.
1.8.11 Repairs
Replace or restore all pavement, curb and gutter, and sidewalk disturbed by operations under this contract to the original condition, except where shown or specified otherwise. Compact backfill in pavement repairs with me-chanical tampers to affect a density equal to adjacent subgrade. Replace pavement with equal materials and equal thicknesses to that removed, unless indicated otherwise. Each pavement area shall be replaced immediately after the work operation for that area is completed. At the Contractor’s option, a temporary repair with a surface of bituminous concrete may be made immediately and removed and the permanent repair made before completion of the contract.
1.8.12 Marking
Contractor shall not mark any curb or pavement with paint.
1.8.13 Protection Requirements
The Contractor shall at all times protect and preserve the property of the Government which is within the work area and could be affected by the accomplishment of the work specified and indicated, and all parties and individuals within or near the work areas who could be endangered by the installation of the work.
1.8.14 Accidental Spills
In the event of fuel spillage during the performance of this contract, the Contractor shall be responsible for its containment, clean-up and related disposal costs. The operator shall have sufficient spill supplies readily available on the pumping vehicle or at the site to contain any spillage. In the Event of a Contractor related release, the
Contractor shall immediately notify the Environmental Management Office and take appropriate actions to correct its cause and prevent future occurrences. If the federal, state, or local authorities assess any monetary fine, penalty or assessment related to the release of any substance by the Contractor, his/her employees, or agents during the performance of this contract, the Contractor shall be solely liable for its payment, authorizes the United States Air
Force to withhold such form of payment and otherwise indemnify and hold the United States Air Force harmless.
1.9 ENVIRONMENTAL PROTECTION. PLEASE REFER TO LANGLEY AFB, JBLE SECTION 01 12 00, ENVIRONMENTAL SPECIAL CONDITIONS.
1.9.2 NOTIFICATION OF ASBESTOS CONTAINING MATERIALS (ACM)
1.9.2.1 Asbestos Notification
There are no records indicating the presence of Asbestos Containing Materials (ACM) in the areas affected by this work. However if ACM is discovered the Contractor is reminded that all asbestos removal work is subject to OSHA, EPA and Commonwealth of Virginia compliance and inspection for asbestos abatement. Contractor must perform asbestos removal work in accordance with these specifications and EPA National Emissions Standards for
Hazardous Air Pollutants (NESHAPs) for asbestos and any subsequent updates thereto. This includes State and EPA
Region 3 Notifications that shall be accomplished at least twenty days prior to starting any asbestos abatement or removal. A copy of the notifications shall be submitted to the Contracting Officer. All hazardous waste manifests shall be signed by 633 CES/CEAN (37 Sweeney Boulevard) prior
SECTION 01 11 10 Page 8 to removal of such waste from the base. Only CEV is authorized to sign these manifests. The Asbestos Program
Manager can be contacted at (757) 764-1126. Please contact him if you have any questions.
1.10 PROTECTION OF GOVERNMENT PROPERTY
1.10.1 General
The Contractor shall at all times protect and preserve the property of the Government which is within the work area and could be affected by the accomplishment of the work specified and indicated, and all parities and individuals within or near the work areas who could be endangered by the installation of the work. Protection requirements include protecting the interior of the facility from inclement weather. Any actions necessary for adequate protection are solely the Contractor’s responsibility. Any temporary boarding of windows or doors must be painted Langley
Brown or Langley Beige to match the exterior.
1.10.2 Protection of Equipment
Contractor is required to cover equipment that is to remain in place within the area of contract operations and protect it against damage or loss and store equipment that is removed in performance of work where directed or use in work as required by drawings and specifications. Equipment temporarily removed shall be protected and returned equal to its condition prior to starting work at no additional expense to the Government. Security for equipment or material that is to be reused and is removed for temporary storage shall be the sole responsibility of the Contractor.
1.10.3 Protection of Grounds
Contractor shall provide protective barriers for all grass, trees, shrubs, sidewalks, curbs and gutters within the con-struction boundary. Furthermore, such items, including grass, outside the construction boundary shall also be pro-tected during delivery of materials or moving of equipment. Damages caused by the Contractor to existing grounds, plants, pavements, utilities, work by others, fixtures, or furnishings shall be repaired by the Contractor. Such repairs shall be of as good condition as exited before the damaging, unless such existing work is scheduled for removal or replacement by the work requirements of the contract. This requirement also pertains to grading of site to remove all clods and grade irregularities prior to final inspection and acceptance. The Contractor may be required to install temporary fencing to protect the site, at no cost to the Government.
1.11 SAFETY
1.11.1 Safety Barriers and Signs
Contractor shall provide barricades, traffic control signs and construction safety signs that meet industry standards.
Actual location, size and final arrangement of these items shall be discussed and approved by the Contracting
Officer prior to installation. Such approved items shall be of uniform size, design and color. All cones, barricades, warning lights, temporary signs and protective devices shall conform to the current requirements of the Federal
Highway Administration’s Manual of Uniform Traffic Control Devices for Streets and Highways (MUTCD) and the US Army Corps of Engineers Safety and Health Requirements Manual EM 385-1-1.
http://mutcd.fhwa.dot.gov/pdfs/2003r1r2/pdf_index.htm
1.11.2 Employee Health and Safety
1.11.2.1 Compliance
In order to provide safety controls for protection to the life and health of employees and other persons; for preven-tion of damage to property, materials, supplies, and equipment; and for avoidance of work interruptions in the performance of this contract, the Contractor shall comply with all pertinent provisions of the Corps of Engineers
Manual, EM 385-1-1 (2003), entitled “Safety and Health Requirements Manual”, as amended. The Contractor will http://mutcd.fhwa.dot.gov/pdfs/2003r1r2/pdf_index.htm
SECTION 01 11 10 Page 9 also take or cause to be taken such additional measures as the Contracting Officer or his/her designated representa-tive may determine to be reasonably necessary for the purpose. A copy of the manual is available for review in the
Civil Engineering Contract Management Section office (Building 328) or copies can be obtained from the Govern-ment Printing Office, Washington DC 20402.
1.11.2.2 Subcontractor’s Compliance
Compliance with the provisions of this clause by subcontractors will be the responsibility of the Contractor.
1.11.2.3 Safety Records
The Contractor will maintain an accurate record of, and will report to the Contracting Officer or his/her designated representative in the manner and on the forms prescribed by the Contracting Officer or his/her designated repre-sentative, exposure data and all accidents resulting in death, traumatic injury, occupational disease, and damage to property, materials, supplies and equipment incident to work performed under this contract.
1.11.2.4 Notification of Non-Compliance and Corrective Action
The Contracting Officer or his/her designated representative will notify the Contractor of any noncompliance with the foregoing provisions and the action to be taken. After receipt of such notice, the Contractor shall take immediate corrective action. Such notice, when delivered to the Contractor or his/her representative at the site of the work, shall be deemed sufficient for the purpose. If the Contractor fails or refuses to comply promptly, the Contracting
Officer or his/her designated representative may issue an order stopping all or part of the work until satisfactory corrective action has been taken. No part of the time lost due to any such stop orders shall be made the subject of claim for extension of time or for excess costs or damages by the Contractor.
1.11.3 Applicable Publications
The publications listed below form a part of this specification to the extent referenced. The publications are referred to in the text by basic designation only.
a. Code of Federal Regulations (CFR):
(1) OSHA General Industry Safety and Health Standards (29 CFR 1910); Publication V2206; OSHA
Construction Industry Standards (29 CFR 1926). One source of these regulations is OSHA Publication
2207, which includes a combination of both Parts 1910 and 1926 as they relate to construction safety and health. They are for sale by the Superintendent of Documents, U.S. Government Printing Office, Washington, DC 20402.
b. National Emission Standards for Hazardous Air Pollutants (40 CFR, Part 61).
c. Federal Standard (Fed. Std.):
(1) 313A Material Safety Data Sheets, Preparation and the Submission to the BioEnvironmental Office on Langley AFB, JBLE. Safety and Health Requirements Manual, EM 385-1-1
(2) Use of Asbestos Containing Material or any Class 1 ozone depleting chemical compounds is pro-hibited at Langley AFB, JBLE, DA Circular 40-83-4
(3) Work covered by this section: This section is applicable to all work covered by this contract.
(4) Definition of Hazardous Materials: Refer to hazardous and toxic materials/substances included in
Subparts H and Z of 29 CFR 1910 and to others as additionally defined in Fed. Std. 313. Those most commonly encountered include asbestos, lead paint, polychlorinated biphenyl’s (PCBs), explosives and radioactive material, but may include others. The most likely products to contain asbestos are sprayed-on fireproofing, insulation, boiler lagging and pipe covering.
SECTION 01 11 10 Page 10
1.11.4 Precautions Against Hazards
1.11.4.1 Welding, Cutting and Burning
All welding and cutting operations shall be done in accordance with nationally recognized good practice. The current publications of the American Welding Society, 2501 NW 7th Street, Miami FL 33125, and the National Fire
Protection Association, 470 Atlantic Avenue, Boston MA 02110, shall be used as a minimum standard of nationally recognized safety procedures in welding and cutting.
The Contractor shall provide the necessary methods of fire extinguishment and fire prevention, and before opera-tions begin, clear all welding and cutting operations with the representative of the Contracting Officer or his/her designated representative. The Contractor shall request and receive an AF Form 592, USAF Welding and Brazing
Permit, before preparing for such operations.
The Contractor shall discontinue all burning, welding or cutting operations one hour prior to the end of the normal workday. The Contractor shall provide a workman to remain at the site for thirty minutes after discontinuing the above operations. This workman shall make a thorough inspection of the area for possible sources of latent com-bustion. Any unsafe conditions shall be reported to the Fire Department for their investigation – EMERGENCY
PHONE NO 911.
1.11.4.2 Open Flames
The use of open-flame heating devices will not be allowed except by special permission of the Contracting Officer or his/her designated representative. Such permission will not be granted unless the Contractor has taken all venting precautions. Burning trash, brush or trees on the job site will not be allowed unless specific approval is granted for each incident by the Contracting Officer or his/her designated representative. Approval for the use of open fires and open-flame heating devices will in no way relieve the Contractor from the responsibility of any damage in-curred because of fires
1.11.4.3 Flammable Liquid Storage
Flammable liquids shall be stored and handled in accordance with the Flammable Liquids Code (No. 30) of the
National Fire Protection Association. Flammable liquids shall not be stored in the Contractors storage trailers.
1.11.4.4 Technical Services
The Langley Fire Department, Technical Services Section, (757) 764-4275, is available for assistance concerning fire hazard questions.
1.12 SECURITY
1.12.1 General Base Requirements
Access to Langley AFB, JBLE is restricted to those Contractor and subcontractor employees required for the per-formance of this contract and only for the performance period of this contract. Contractor passes are issued by the
Pass and Registration Section, Building 15 (Room 103), after a signed letter from the Contractor listing all em-ployee names and social security numbers has been delivered to and approved by the Contracting Officer or his/her designated representative. Procedures for requesting Base Passes for employees and Contractor vehicles will be further explained during the preconstruction conference.
1.12.2 Emergency Security Situations
If a security violation is detected from any cause, it may result in the cessation of all work and evacuation of the area by all Contractor personnel to a point to be determined by the Security Forces Supervisor at the scene. The
SECTION 01 11 10 Page 11 control of construction personnel under these conditions is a Security Forces Officer and their orders shall be fol-lowed in detail. Construction will be permitted to resume as quickly as possible. The individual causing the vio-lation may be apprehended, and if so, will be processed and released to a responsible supervisor; such person might be away from his/her work site as long as 1 to 1½ hours. If a hostile situation is detected because of the construction activity, the entire crew may be removed from the area and detained until competent authority approved their re-lease. All Security Forces exercises will be scheduled not to interfere with construction personnel or with their work.
1.12.3 Work In Special Security Areas
1.12.3.1 Escorts
Not Applicable (N/A)
1.12.3.2 Applicable Security Criteria
AFI 31-101, The Air Force Installation Security Program shall apply to construction projects at Langley AFB, JBLE.
1.12.4 Controlled Areas
Most work will be accomplished on LAFB at the Flight Line perimeter in Hampton, VA
1.12.4.13 Safety
Flame and spark producing equipment (i.e., matches, lighters, vehicle cigarette lighters) shall be surrendered at the
Entry Control Point prior to entry to the area. Smoking within the area is prohibited except in Contractor provided approved smoking areas. The use of flame and spark producing equipment within the area is discouraged; however, in the event that it is necessary to use electric welders, oxygen-acetylene torches or other spark producing devices, the Contractor shall notify the Contracting Officer or his/her designated representative. Should a hazardous con-dition arise during the use of such devices, contact the Fire Department (Main Base: 911; Bethel Manor Housing:
865-1042). All Contractor personnel are subject to base safety and traffic regulations and may be barred from motor vehicle operation for cause.
1.13 HISTORIC DISTRICT/ARCHITECTURAL COMPATIBILITY
Due to the distinct historic architecture and the high visitor traffic LAFB receives, several special actions are re-quired during construction and are listed herein. Coordinate the following with the Contracting Officer since the
Project is remote from the Base.
1.13.1 Newly Placed Concrete
When placing concrete adjacent to existing concrete, all newly placed concrete curbs, gutters and sidewalks shall match existing adjacent concrete in color and texture. Miami Buff is the predominate color used on LAFB. All concrete that is newly placed by the Contractor shall be Miami Buff in color unless specifically noted otherwise in the contract documents or instructed otherwise by the Contracting Officer or his/her designated representative.
1.13.2 Unprimed or Factory Finished Equipment
Unprimed or factory-finished equipment installed on the exterior of facilities shall be painted with two coats of brown paint to match existing equipment.
SECTION 01 11 10 Page 12
1.13.3 Patching
All holes in walls or other parts of the structure where material or equipment is removed or replaced shall be sealed, painted, caulked or plugged neatly with original type of materials to match the existing part of the structure so involved. The Contracting Officer or his/her designated representative shall approve all above work and materials.
1.13.4 Pavement Repairs
Replace or restore all pavement, curb and gutter, and sidewalk disturbed by operations under this contract to the original condition, including any markings or striping, except where shown or specified otherwise. Compact Back-fill in pavement repairs with mechanical tampers to affect a density that is equal to adjacent subgrade. Replace pavement with equal materials and equal thickness to that removed, unless indicated otherwise. Each pavement area shall be replaced immediately after the work operation for that area is completed. At the Contractor’s option, a temporary repair with a surface of bituminous concrete may be made immediately and removed and the permanent repair made before completion of the contract.
1.13.5 Marking Restrictions
Contractor shall not mark any curb or pavement with paint unless directed by the Contracting Officer or his/her designated representative.
1.14 RECORDING AND PRESERVING HISTORICAL AND ARCHAEOLOGICAL FINDS
1.14.1 Preservation
All items having any apparent historical or archeological interest, which are discovered in the course of any con-struction activities shall be carefully preserved. The Contractor shall leave the archeological find undisturbed and shall immediately report the find to the Contracting Officer or his/her designated representative so that the proper authorities may be notified.
1.14.2 Rehabilitation
All repair, maintenance, and construction must be completed in a manner that is consistent with the Secretary of the Interior’s “Standards for Historic Preservation Projects” and the Secretary’s “Illustrated Guidelines for Reha-bilitating Historic Buildings”.
1.15 EXCAVATION REQUIREMENTS
The Government will furnish the Contractor with an approved AF Form 103, BCE Work Clearance Request, indi-cating any special precautions or areas that will be marked (for utilities). The contract drawings, AF Form 103 and marking will indicate all information the Government has knowledge of, but will not indicate all conditions that may occur in the field. The Contractor shall not begin (work) excavation until the Clearance Request is issued.
The Contractor shall be responsible for removing all markings made for his benefit as soon as the need for an individual mark is passed. The Government will mark utilities one time only. Maintaining these marks or addi-tional marking is the responsibility of the Contractor.
1.15.1 Acquiring a Work Clearance Request (Air Force Form 103)
A coordinated and approved Work Clearance Request is required prior to any excavation activities. The Contractor shall submit a request to the Project Inspector 14 days prior to the start of excavation work. All requests must be initiated no later than Thursday of any week to be inserted into the Work Clearance approval process for the fol-lowing week. The Contractor will be notified to attend a Work Clearance scheduling meeting. At the Work Clear-ance meeting, the Contractor will receive an AF Form 103, instructions for completing the form, and a date and time for utilities to be marked. The Contractor shall not commence excavation prior to obtaining an approved
AF Form 103. After all respective utilities have been marked and verified by the Project Inspector, the Contractor
SECTION 01 11 10 Page 13 shall return the original AF Form 103 to his/her respective Project Inspector for coordination and signature by the
Chief of Engineering. No digging or excavation shall begin before the Chief of Engineering signs the AF Form
103. After the Chief of Engineering signs the AF Form 103, the Project Inspector will return it to the Contractor.
Then, and only then, shall the Contractor commence excavation. The Contractor shall maintain all utility markings for the duration of the contract. Contractor shall maintain original version of the AF Form 103 for the duration of excavation work at the particular site. Ensure all applicable parties have coordinated on the form prior to excava-tion. For Miss Utility, use the Ticket Information Exchange (TIE) number or actual technician signature as evi-dence of coordination. The AF Form 103 clearance shall not be allowed to expire. The Contractor shall revali-date/resubmit the AF Form 103 within seven days prior to the expiration date if it is anticipated or known that the duration of excavation will exceed the 30-day limitation.
1.15.2 Miss Utility
Contractor shall contact Miss Utility (1-800-552-7001) at least 48 hours prior to excavation to identify non-Air
Force-owned underground utilities (cable TV, Bell Atlantic and Virginia Power, etc.). Notices to Miss Utility are good for 15 working days; after that period, Contractor shall renew the notice. Indicate renewals on the AF Form
103 as applicable. Miss Utility is open 24 hours, seven days a week. Calls after 1700, before 0700, on weekends and on holidays are accepted for emergencies only. Holidays include New Year’s Day, Martin Luther King Day, President’s Day, Memorial Day, Independence Day, Labor Day, Veteran’s Day, Thanksgiving Day, Day after
Thanksgiving and Christmas Day. After 48 hours, Contractor should contact Miss Utility to confirm that clear-ance/marking operations have been completed. The Contractor must wait an additional 24 hours if any operators or contract locators have not responded to the Ticket Information Exchange (TIE) system request within the first
48 hours.
1.15.3 Markings
1.15.3.1 General Requirements for Marking Utilities
a. Prior to commencing any excavation, the Contractor must inspect the site for clear evidence of unmarked facilities. If evidence of such facilities is present, the excavator must notify the notification center and wait an additional three hours for the facilities to be marked.
b. The Contractor may choose to wait 72 hours and begin work after that time if there is no evidence that any underground facilities remain unmarked. However, it is recommended that Contractors contact the TIE system and confirm the status of underground facilities before they commence work.
c. After the markings have been made, Contractors are required to maintain a minimum clearance of two feet between a marked, underground utility line and the cutting edge of any power-operated excavating equip-ment. If excavation is required within two feet of any marking, it shall be performed very carefully with hand tools in accordance with Virginia Code Section 56-265.24.
d. If, during the course of excavation, a utility line has been exposed, before backfilling, the Contractor must inspect these facilities to ascertain if the facilities have been damaged. If damage of any kind is dis-covered or suspected, it is the Contractor’s responsibility to immediately notify the utility owner directly.
The Contractor must NOT attempt to repair damaged facilities.
e. Maintain any paint marks or stakes indicating underground utilities/lines as required during the duration of work or thirty calendar days from date of approved AF Form 103 (whichever is earlier). Note that Miss
Utility clearance expires after fifteen working days.
1.16 OCCUPANCY AND SERVICES TO EXISTING FACILITIES
a. The Government will not occupy the existing building during construction. The Contractor shall not interrupt utilities serving these areas without coordinating with the Contracting Officer or his/her designated representative.
SECTION 01 11 10 Page 14
1.17 UTILITIES
All reasonable amounts of water and electricity required for this work will be made available to the Contractor if such utilities exist at the project site. Temporary lines, connections, installation, maintenance and removal shall be the Contractor’s responsibility. The Contracting Officer, or the Contracting Officer’s designated representative, shall approve any temporary lines and connections. All services are subject to discontinuance without notice to the
Contractor in an emergency. Three-phase power may not be available. The Contractor shall provide his/her own necessary utilities when such utilities are not available at the project site.
1.18 UTILITY OUTAGES AND TRAFFIC
Contractor shall request utility/power outages or changes to normal traffic flow pattern at least 14 calendar days in advance of disruption or change to either. For medical facilities, a notice of at least 30 calendar days is required.
1.19 CONVENIENCE FACILITIES
Existing restroom facilities may not be used by construction personnel. The Contractor shall maintain, in a neat and sanitary condition, such accommodations for the use of his employees. Temporary restroom facilities shall be white in color.
1.20 SUPERVISION
1.20.2 Superintendent
The Contractor shall employ a construction superintendent to oversee all work under this contract. The superin-tendent shall remain at the project site at all times when work is in progress except for such incidental errands required by his/her duties. The superintendent is responsible for the proper coordination and timeliness of the work, and for proper workmanship of all trades; therefore, his/her absence from the project site without a suitable substi-tute representative of the Contractor shall be considered as damaging to the Government. The ability of the super-intendent, based on his/her knowledge and experience, are essential to the proper execution of the work, as is his/her ability to communicate and direct the efforts of those performing the work.
1.22 RECORD DRAWINGS
1.22.1 Record of Work Progress
During the progress of the work, the Contractor shall keep a careful record at the job site of all changes, corrections and deviations from the layouts and details shown on the drawings to include all contract modifications. The
Contractor shall enter such changes on project drawings promptly, but not later than on a weekly basis. Such revised drawings shall be considered “redline” as-built drawings.
1.22.2 Record of Underground Utilities
Where underground utilities are installed, note the elevation of the utility installed every fifty feet. Where new utilities cross existing utilities, note the elevation of the new and existing utility and the vertical or horizontal separation. Where new utilities run parallel to new and existing utilities, note the elevation at which installed and the horizontal and vertical separation between utilities.
1.23 DELIVERABLES AND FINAL AS-BUILTS
1.23.1 Geodetic Control Surveys
The Contractor shall provide horizontal and vertical control surveys for the precise location of primary survey points for planning, engineering, construction, real estate projects, GIS applications or facility manage-ment.
SECTION 01 11 10 Page 15
1.23.2 Deliverable Requirements
All locational base map (point, line and polygon feature(s)) data collected shall be delivered in ESRI ArcGIS 9.x digital format along with the original source files. The geospatial files shall have an external spatial reference
(.prj) file attached specifying the parameters of the coordinate system used (as provided by the government). All topologically correct geospatial data shall overlay on the installations latest orthorectified imagery provided by the government, using the same coordinate and projection system of the imagery (WGS84). All accuracy errors shall be reported to the contract program manager.
1. All Architectural/Engineering data (building components, plans, designs, etc.) shall be in a digital (electronic information) format AutoCAD 2005 or higher. Drawings will be delivered in the AutoCAD “.DWG” file format. The Contractor shall use the A-E/C CADD Standard 4.0 (or latest version) when creating or revising any CADD data deliverables.
2. All graphic and non-graphic data will be collected in the format defined by the Spatial Data Standards Facil-ities, Infrastructure, and Environmental (SDSFIE) release 2.60 (or the most current version available), except where modified by the Government. This standard can be found at https://www.sdsfie.org.
3. The contractor shall provide a quality control (QC) report that must state whether all inconsistencies in the data generated were corrected, or it must detail the remaining errors by case. The contractor shall utilize a topology build and clean routine to assure that there are no overshoots or undershoots in the line work, slivers or dangles in polygons, and that there is complete closure of polygons with a maximum fuzzy tolerance value of 10-9. The quality report must identify the software (name and version) and satisfy these conditions:
a. The edges of all digitized vector data or raster imagery must exactly match digitally with those of all adjacent maps.
b. The digital representation of the common boundaries for all graphic features must be exactly the same, regardless of feature layer. Each feature within a layer must be represented by a single graphic element
(e.g. polygon, line or line string).
c. Lines and line strings which represent the same graphic element must be continuous (i.e., not broken or segmented), unless that segmentation reflects a specific visual line type. Lines or line strings represent-ing the same type of data must not cross except at intersections.
d. Polygons must be closed (i.e. the first x- and y-coordinates must exactly match the last x- and y-coordi-nates). Each polygon must have a single unique centroid to which attributes (i.e. an attribute table) can be attached. Polygons of the same coverage must not overlap and must cover the area of interest com-pletely (i.e. have no gaps in coverage).
e. All graphic elements that connect must exactly connect digitally, without overlaps or gaps.
f. Straight lines must be represented by only the beginning and ending x- and y-coordinate points. Line strings must not cross back on themselves or be of zero length.
4. Feature Attributes: The contractor shall identify the classification, type, size, location, ID number and any other necessary attributes (specified by the Government) for all surveyed, mapped, designed or proposed features.
5. All symbol libraries, font libraries, text size, text format and text placement shall be prepared in accordance with and conform to the Spatial Data Standards (SDS).
6. The contractor shall not develop new libraries without prior written approval from the Government.
7. The contractor shall provide metadata files for all locational data produced under this contract. The metadata file shall conform to the Federal Geographic Data Committee’s “Content Standard for Digital Geospatial
Metadata, Version 2.0” (or latest version) found at:
http://www.fgdc.gov/standards/standards_publications/index_html. The output from the ESRI ArcCatalog metadata generator software (or compatible software) shall be the standard format for all metadata files created under this contract. In addition, the metadata data shall be provided in ASCII text format. The digital metadata files shall be provided to the Government along with each final product deliverable, unless otherwise approved in writing by the Government.
https://www.sdsfie.org/ http://www.fgdc.gov/standards/standards_publications/index_html
SECTION 01 11 10 Page 16
1.23.3 Survey Data
1. The contractor shall use conventional surveying and other methods, such as a total station or Global Posi-tioning Systems (GPS) for field data collection at an accuracy level in accordance with “Geospatial Position-ing Accuracy Standards, Part 3: National Standard for Spatial Data Accuracy,” published by the Federal
Geographic Data Committee (FGDC), dated July 1998. This standards document can be found at http://www.fgdc.gov/standards/standards_publications/index_html.
2. All Survey data collected shall be provided to the Government in a digital format with an attached Survey
Report identifying survey method, equipment list, calibration documentation, survey layout, description of control points, control diagrams and field survey data.
3. Data on the location of utility lines shall be captured at a minimum every 50 feet and each turn or bend in a utility line must be captured.
4. A Survey Control Database (consisting of a survey marker database and a survey traverse database) will be produced for all survey control points established under this contract, and delivered in a .dbf or ASCII comma-delimited format.
5. If GPS is used, the contractor shall use survey grade GPS, at an accuracy level of ± 2 cm. when appropriate, to collect data to be overlaid onto the installation’s orthophotograph and/or base map.
1.23.4 Delivery Format
Note: No deviations from the Government’s established standards will be permitted unless prior written approval of such deviation has been issued by the Government. All linkages of non-graphical data with graphic elements, relationships between data objects and attributes, and report formats shall be maintained.
These deliverables include, but are not limited to:
1) Site plans
2) As-built drawings
3) Engineering designs, plans or surveys
4) Topographic surveys or studies
5) Boundary or Cadastral surveys
6) Master Plan drawings
7) Utility (water, sewer, power, storm, etc.) designs, plans, surveys and studies
8) Pavement, Grading, or Excavation plans
9) Soil/Geology studies or surveys
10) Environmental assessments, surveys, studies or plans
11)…