This document is a Work Request Unscheduled Repair Authorization Request form used to document and obtain approval for repair services and associated costs. The form is structured into four primary sections: Scope of Work & Repair Description, Contractor Approved Markup on Materials, Labor, and Approval and Authorization. Contractors must provide detailed information about repair needs, including specific parts/materials (both OEM and non-OEM), quantities, costs, and labor hours. The form requires comprehensive documentation, such as proof of cost, fair and reasonable price justification, and specifications for non-OEM parts.

The approval process mandates signatures from multiple parties, including the Contractor, Project Manager (PM), Contracting Officer's Representative (COR), and Contracting Officer (KO). Each party must verify specific elements, such as parts suitability, labor hours, funding availability, and compliance with contract-approved rates. No work can commence until all required approvals are obtained and the form is signed and returned to the Contractor. The form emphasizes transparency in cost breakdown, requiring separate invoicing for parts, labor, and markup, with all rates matching pre-approved contract terms.

View the file

Other files

File Type Posted
Exhibit C Rev 2.xlsx XLSX spreadsheet
Exhibit A Rev 2.xlsx XLSX spreadsheet
Exhibit B Rev 2.xlsx XLSX spreadsheet
N39040400T4815 Combined Synopsis Solicitation Rev 1.pdf PDF
N39040400T4815 Questions and Answers.pdf PDF
Attachment 1 Performance Work Statement Rev 1.pdf PDF
Exhibit C Rev 1.xlsx XLSX spreadsheet
Exhibit A Rev 1.xlsx XLSX spreadsheet
N39040400T4815 Question and Answer.pdf PDF
Exhibit B Rev 1.xlsx XLSX spreadsheet
Attachment 6 Wage Determination 2025-4111 Rev 32.pdf PDF
Exhibit B.xlsx XLSX spreadsheet
N39040400T4815 Combined Synopsis Solicitation.pdf PDF
Attachment 1 Performance Work Statement.pdf PDF
Attachment 4 Quality Assurance Surveillance Plan.pdf PDF
Attachment 5 PNS Operations Security Contract Requirements.pdf PDF
Attachment 6 Wage Determination 2025-4011 Rev 31.pdf PDF
Exhibit C.xlsx XLSX spreadsheet
Attachment 3 DD1423 Data Requirements.pdf PDF
Exhibit A.xlsx XLSX spreadsheet
Show all 20

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

WORK REQUEST UNSCHEDULED REPAIR AUTHORIZATION REQUEST -

Date of Request:

Work Request Number: (e.g. 1, 2) Project Name/Number: Contract Number:

1. Contractor Signature: __________________________ Date: __________________________

SECTION 1: SCOPE OF WORK & REPAIR DESCRIPTION

1.1 Provide a concise description of the repair or service needed, referencing the affected equipment, issue(s) observed, and any relevant background details:

SECTION 1A: OEM Parts/Materials – Complete as applicable or see attached estimate

Item (Part/material) Description QTY Cost to

Contractor Discounts Passed to Government Total Cost to Government

• Supporting Documentation: Contractor must provide “proof of cost” Fair and Reasonable Price Justification (e.g., catalog prices, commercial invoices, online listings) o Parts must be genuine, manufacturer-approved unless expressly waived (fill out section 1B)

Section 1B: Non-OEM Parts/Materials – Complete as applicable or see attached estimate

Item (Part/material) Description QTY Cost to

Contractor (Non-OEM)

Cost of

OEM

Equivalent

Non-OEM Specifications

Total Cost to Government

• Additional Requirements for Non-OEM:

1. Contractor must provide cost comparison (OEM vs. Non-OEM) for fair and reasonable determination.

2. Contractor must provide detailed Non-OEM specifications for PM to verify suitability.

SECTION 2: CONTRACTOR APPROVED MARKUP ON MATERIALS

Total Cost of Parts/Materials (OEM + Non-OEM)

Pre-Approved Markup Rate (%)

Markup Amount

Total Cost with Markup

• Notes: Cost of parts and markup must match contract approved rates and be separated on the contractor’s invoice.

SECTION 3: LABOR

Description of Work Estimated

Hours

Agreed-Upon Labor Rate ($/hr) for each labor category

Total Unburdened Labor Cost ($)

SECTION 4: APPROVAL AND AUTHORIZATION

Statement: Work may commence only upon approval of this Work Request by the Project Manager (PM), Contracting Officer’s Representative (COR) and Contracting Officer (KO).

Contractor will Separate costs on invoice, all labor and markup rates match approved rates, and support material costs with approved supporting documentation. No work will commence until PM/KO signs below and returns to Contractor.

PM approves Section 1A or 1B: Part/Material OEM or waived for Non-OEM are needed for the work being performed.

PM approves Section 3: The level of effort (number of hours) is commensurate with the work being performed.

2. Project Manager (PM): __________________________ Date: __________________________

Title: __________________________

COR approves Section 1A or 1B, 2, and 3: Sufficient funds are available to cover the Part/Materials, markup, and the markup rate matches the agreed-upon rate in the contract. Labor rate matches the contract, and sufficient funds are available to cover the labor cost.

3. Contracting Officer Representative_________________________ Date:_______________________

4. Contracting Officer: __________________________ Date: __________________________

Additional Notes or Special Conditions:

Use.this.space.or.see.attachment.for.any.special.instructions¡.