Attachment 2 - William Tate - Specification Rev 1.doc

DOC document 3 MB Posted

Attached to
Dockside (DS): USCGC William Tate FY20 Repair
Solicitation number
70Z085-20-Q-P4595400
Issued by

About this file

This solicitation seeks proposals for dockside repair services for the USCGC William Tate. The contractor shall provide all necessary labor, materials, equipment and supplies to perform repairs in accordance with the attached specification. Repairs include cleaning and inspecting voids, servicing the cargo hatch, cleaning main diesel engine exhaust piping, cleaning generator exhaust systems, cleaning ventilation ducts in various spaces, inspecting and testing potable water tanks, inspecting and testing air receivers and valves, inspecting hydraulic chain stoppers, crossdeck winches and other deck machinery, and preserving structures. The Coast Guard will provide replacement parts as needed. The contractor must have the capabilities and facilities to perform the work at its own shipyard.

View the file

Other files

Show all 15

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

USCGC WILLIAM TATE (WLM 560)

SPECIFICATION FOR DOCKSIDE REPAIRS

FY2020

Developed By: Alessandra K Twomey (Rev-1, 27 February 2020)

TABLE OF CONTENTS

iiiRevisions Record ivConsolidated List of References ixConsolidated List of Government-furnished Property xiiConsolidated List of Critical Inspection Items xiiiPrincipal Characteristics - TENDER

1General Requirements

13WORK ITEM 1: Voids (Accessible), Clean and Inspect

16WORK ITEM 2: Hydraulically Operated Cargo Hatch, Inspect and Service

20WORK ITEM 3: Main Diesel Engine (MDE) Exhaust Piping, Commercial Clean

23WORK ITEM 4: Ship Service Diesel Generator (SSDG) Exhaust Piping, Commercial Clean

27WORK ITEM 5: Vent Ducts (Engine And Motor Room All), Commercial Cleaning

30WORK ITEM 6: Vent Ducts (Galley and Pantry Room All), Commercial Cleaning

33WORK ITEM 7: Vent Ducts (Laundry Exhaust), Commercial Cleaning

36WORK ITEM 8: Vent Ducts (All Other), Commercial Cleaning

39WORK ITEM 9: Potable Water Pneumatic Tank(s), Clean and Inspect

42WORK ITEM 10: Compressed Air Receivers and System Valves (All), Clean, Inspect, Hydro and Lift

48WORK ITEM 11: Hydraulic Chain Stoppers, Inspect and Service

52WORK ITEM 12: Hydraulic Crossdeck Winches, Inspect And Service

57WORK ITEM 13: Hydraulic Inhaul Winch, Inspect And Service

66WORK ITEM 14: Mechanical Chain Stoppers, Inspect and Service

69WORK ITEM 15: Warping Capstan (Aft), Inspect and Service

73WORK ITEM 16: Single Point Davit, Disassemble and Inspect

76WORK ITEM 17: Buoy Crane, Inspect And Service

86WORK ITEM 18: Sewage Holding Tank(s), Clean and Inspect

90WORK ITEM 19: Sewage Piping, Clean And Flush

93WORK ITEM 20: Crane Winch DCV, Replace

99WORK ITEM 21: Oily Water Separator, Replace

106WORK ITEM 22: Thruster Quick Disconnects (QDs), Install

113WORK ITEM 23: Sea Trial Performance, Support, Provide

117WORK ITEM 24: Ceiling Tiles, Renew

119WORK ITEM 25: Auxiliary AC Motor, Overhaul

122WORK ITEM 26: Power Circuit Breakers, Inspect, Maintain & Test

133WORK ITEM 27: Hawse Pipe Covers , Renew

135WORK ITEM 28: Vent Spaces, Deck, Preserve

137WORK ITEM 29: Pump Room, Deck, Preserve

139WORK ITEM 30: Gooseneck Vent and Cofferdam, Renew

142WORK ITEM 31: Gooseneck Vents and Cofferdams, Preserve

144WORK ITEM 32: Stanchions, Renew

147WORK ITEM 33: Main Diesel Engine, Check Alignment

158WORK ITEM 34: Tanks (Sewage Holding), Preserve “100%”

161WORK ITEM 35: Tanks (Sewage Holding), Preserve “Partial”

164WORK ITEM 36: Vents, Preserve and Renew Covers

Revisions Record This page is used to record specification revisions, which may have occurred subsequent to a Revision 0 (Rev-0) package. Information listed is intended to provide contractors and field unit personnel a means to ensure all the current specification revision pages are present when reviewing or utilizing this specification package.

DATE
REV#
WORK ITEM#
CHANGES MADE
04/21/2020
#1
32
Updated Table #1

NOTE : All work item and paragraph numbers listed above for a given revision correspond to same numbers in the previous revision. This revised specification is self-contained with all of the above listed changes incorporated.

Consolidated List of References The below-listed documents form a part of this specification to the extent specified herein. Approval/publication dates or revision dates/numbers are also identified, to ensure that same document versions are used at the time of specification writing and during contract execution.

All Coast guard drawings, technical publications, and standard specifications will be provided to contractors by the Coast Guard at an appropriate time, or upon request, free of charge. Other Government documents may be accessed – free of charge – from links located on the SFLC website. Commercial sites provide access to their respective documents.

COAST GUARD DRAWINGS

Coast Guard Drawing (DWG) 175-WLM-201-002, Rev D, Machinery Removal Routes Coast Guard Drawing (DWG) 175-WLM-320-002, Rev G, Pwr Sys Dk Plan Fr24-Fwd Hull Blk 910 & 901 Coast Guard Drawing (DWG) 175-WLM-437-007, Rev P, Buoy Dk Control Sys Block, ISO & Elem Wrg Diag Coast Guard Drawing 175 WLM 130-001, Rev -, Mods to Buoy Deck Incidental to Hawser Pipe Cover Coast Guard Drawing 175 WLM 185-001, Rev -, Foundation Incidental to Boss 2.2 GPM OWS Installation Coast Guard Drawing 175 WLM 201-001, Rev C, Machinery Spaces Arrangement Coast Guard Drawing 175 WLM 202-002, Rev G, MPCMS Wiring Data (COED) Coast Guard Drawing 175 WLM 243-2, Rev E, Propulsion Shaft Arrangement Coast Guard Drawing 175 WLM 256-001, Rev J, Seawater Cooling System Diagram Coast Guard Drawing 175 WLM 259-001, Rev A, Combustion Exhaust Diagram Coast Guard Drawing 175 WLM 259-005, Rev C, Combustion Exhaust A&D, Hull Block 970 Coast Guard Drawing 175 WLM 262-001, Rev J, Lube Oil System Diagram Coast Guard Drawing 175 WLM 262-002, Rev H, Waste Oil System Diagram Coast Guard Drawing 175 WLM 262-005, Rev G, Lube Oil System A/D – Hull Blocks 910, 930, 940, & 970 Coast Guard Drawing 175 WLM 320-001, Rev AL, Electrical One-Line Diagram Coast Guard Drawing 175 WLM 320-004, Rev G, Power System Deck Plan ER and Pump Rm Hull Block 920 Coast Guard Drawing 175 WLM 320-012, Rev -, Power System Mods Incidental to OWS Removal/Installation One-Line Diagram Coast Guard Drawing 175 WLM 506-001, Rev G, Overflows, Air Escapes & Sounding Tubes Diagram Coast Guard Drawing 175 WLM 506-007, Rev D, Vents & Sndg Tubes Main Deck & Above A/D Hull Block 970 Coast Guard Drawing 175 WLM 506-008, Rev C, Oil Containment Coamings Coast Guard Drawing 175 WLM 512-001, Rev E, HVAC Diagram Coast Guard Drawing 175 WLM 512-005, Rev A, HVAC A & D FR 6-FWD Hull Block 901 Coast Guard Drawing 175 WLM 512-006, Rev D, HVAC A & D FR 24-6 Hull Block 910 Coast Guard Drawing 175 WLM 512-011, Rev E, HVAC A & D FR 70-50 Main Deck & Above Hull Block 960 Coast Guard Drawing 175 WLM 512-012, Rev D, HVAC A & D FR 70-88 Main Deck & Above Hull Block 970 Coast Guard Drawing 175 WLM 512-013, Rev C, HVAC Standard Details and General Instructions Coast Guard Drawing 175 WLM 533-001, Rev G, Potable Water System Diagram Coast Guard Drawing 175 WLM 549-001, Rev E, Onboard Lubrication Requirements Coast Guard Drawing 175 WLM 549-1, Rev E, Onboard Lubrication Requirements Coast Guard Drawing 175 WLM 551-001, Rev J, Compressed Air System Diagram Coast Guard Drawing 175 WLM 568-2, Rev M, Bow Thruster Assembly (Model 125 Fixed Pitch) Coast Guard Drawing 175 WLM 573-001, Rev T, Buoy Deck Arrangement Coast Guard Drawing 175 WLM 573-001, Rev T; Buoy Deck Arrangement Coast Guard Drawing 175 WLM 573-050, Rev A, Hydraulic Piping Installation for Chain Stopper Coast Guard Drawing 175 WLM 573-051, Rev B, Chain Stopper Structural Modifications for Hydraulic Roller Assembly Coast Guard Drawing 175 WLM 593-001, Rev G, Sewage & Waste Water System Diagram Coast Guard Drawing 175 WLM 593-001, Rev G, Sewage and Waste Water System Diagram Coast Guard Drawing 175 WLM 593-002, Rev H, Oily Bilge System Diagram Coast Guard Drawing 175 WLM 593-009, Rev E, Independent Tanks, Sewage Holding Tank Coast Guard Drawing 175 WLM 593-013, Rev C, Oily Water Separator A&D Coast Guard Drawing 175 WLM 593-014, Rev A, OWS System Operating Instructions BOSS 2.2T-107-YM Coast Guard Drawing 175 WLM 601-001, Rev R; General Arrangement Inboard and Outboard Profiles Coast Guard Drawing 175 WLM 601-001, Rev T, General Arrangement Inboard & Outboard Profiles Coast Guard Drawing 175 WLM 601-003, Rev F, Booklet of General Drawings (552-564) Coast Guard Drawing 175 WLM 633-001, Rev D, Cathodic Protection Coast Guard Drawing 175 WLM 801-015, Rev C, Scantlings, Decks & Platforms Coast Guard Drawing 175 WLM 920-001, Rev K, Hull Block 920 Panels Coast Guard Drawing 175 WLM-528-001, Rev E, Plumbing and Interior Deck Drains Diagram Coast Guard Drawing 175-WLM 320-1, Rev AL, Electrical One-Line Diagram Coast Guard Drawing 175-WLM 516-004, Rev A, HVAC Refrigeration System Piping Arrangement & Details Coast Guard Drawing 175-WLM 549-001, Rev E, Onboard Lubrication Requirements Coast Guard Drawing 175-WLM 549-1, Rev C, Onboard Lubrication Requirements Coast Guard Drawing 175-WLM 556-1, Rev J, Hydraulic System Diagram Coast Guard Drawing 175-WLM 573-001, Rev R, Buoy Deck Arrangement Coast Guard Drawing 175-WLM 601-001, Rev T, General Arrangement Inboard and Outboard Profiles Coast Guard Drawing 175-WLM-612-001, Rev G, Lifelines/Rails & Stanchions Coast Guard Drawing 175-WLM-637-001 Rev H., Joiner, Sheathing & Ceilings Arrangement & Details Coast Guard Drawing FL 2605-031, Rev D, Mechanical Chain Stopper, 1-7/8" Buoy Chain Coast Guard Drawing FL 2605-034, Rev D, Mechanical Chain Stopper Repair Kit: 1-7/8", 1-5/8" & 1-1/4" Coast Guard Drawing FL 7101-573, Rev L, Buoy Chain Winch Assy Model CW1 Coast Guard Fleet Drawing FL-2605-029, Rev L, Chain Stopper System – Rising Sheave Assembly

COAST GUARD PUBLICATIONS

Coast Guard Commandant Instruction(COMDTINS) M10360.3 (series), Coatings and Color Manual Coast Guard Technical Publication (TP) 3498, Section A, Jul 2015, Buoy Chain Winch Coast Guard Technical Publication (TP) 3605A, Nov 2007, MPCMS Operating Manual (Volume 1) Coast Guard Technical Publication (TP) 3610, Section 167-A, Nov 2005, Hydraulic Cargo Hatch - Model No. D-WK-787 Coast Guard Technical Publication (TP) 3613, Oct 1997; Flexible Coupling Coast Guard Technical Publication (TP) 3619, Mar 2001 Switchboard, Ship Service & Emergency Coast Guard Technical Publication (TP) 3626, Manufacturers Instruction Book-SWBS Group(s) 516-533, SWBS 516, Section B, Pump, AC Heat Coast Guard Technical Publication (TP) 3627, Section A, SWBS 556, Feb 2007, HPU Deck Machinery - Model 7D3-05575 Coast Guard Technical Publication (TP) 3628, SWBS 568, Section A, March 2017, Bow Thruster – (Bird-Johnson Company) Coast Guard Technical Publication (TP) 3630, 07-JAN-97, Manufacturers Instruction Book-SWBS Group(s) 573 Coast Guard Technical Publication (TP) 3630, SWBS 573, Section A (573A), Jun 2015, Manufacturer's Instruction Book-SWBS Group 573, Buoy Crane Coast Guard Technical Publication (TP) 3631, Mar 2007, Manufacturer’s Instruction Book-SWBS Group(s) 573-581, Section B, Cross Deck Winch – Appleton Marine Model BMD-463 Coast Guard Technical Publication (TP) 3632, March 2014, Chapter 583, Section C, Technical Manual for Slewing Arm Davit Model D6000CT Coast Guard Technical Publication (TP) 3632, Section 582-A, March 2014, Manufacturer's Instruction Book-SWBS Groups 582-583, Aft Capstan Coast Guard Technical Publication (TP) 3749, 26-APR-05, 1-7/8 Inch ATON Mechanical Chain Stopper Coast Guard Technical Publication (TP) 3939, SWBS 573-A, Apr 2007, Rising Sheave Chain Stopper Surface Forces Logistics Center Standard Specification (SFLC Std Spec) 0000, 2018, General Requirements Surface Forces Logistics Center Standard Specification (SFLC Std Spec) 3020, 2012, Overhaul AC Electrical Motors Surface Forces Logistics Center Standard Specification (SFLC Std Spec) 3042, 2018, Shipboard Electrical Cable Removal, Relocation, Splice, Repair, and Installation Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2018, General Requirements Surface Forces Logistics Center Standard Specification 0740 (SFLC Std Spec 0740), 2018, Requirements for Welding and Allied Processes Surface Forces Logistics Center Standard Specification 0740 (SFLC Std Spec 0740), 2018, Welding and Allied Processes Surface Forces Logistics Center Standard Specification 3020 (SFLC Std Spec 3020), 2018, Overhaul AC Electrical Motors Surface Forces Logistics Center Standard Specification 3041 (SFLC Std Spec 3041), 2018, Shipboard Electrical Cable Test Surface Forces Logistics Center Standard Specification 3042 (SFLC Std Spec 3042), 2018, Shipboard Electrical Cable Removal, Relocation, Splice, Repair, and Installation Surface Forces Logistics Center Standard Specification 3042 (SFLC Std Spec 3042), 2018, Shipboard Electrical Cable Removal, Relocation, Splice, Repair, And Installation Surface Forces Logistics Center Standard Specification 5000 (SFLC Std Spec 5000), 2018, Auxiliary Machine Systems Surface Forces Logistics Center Standard Specification 5100 (SFLC Std Spec 5100), 2018, Clean Shipboard Ventilation Systems Surface Forces Logistics Center Standard Specification 6310 (SFLC Std Spec 6310), 2018, Requirements for Preservation of Ship Structures Surface Forces Logistics Center Standard Specification 8636 (SFLC Std Spec 8636), 2018, Temporary Hull Accesses

OTHER REFERENCES

American National Standards Institute/American Water Works Association (ANSI/AWWA) C652, 2011, Disinfection of Water-Storage Facilities American National Standards Institute/National Electrical Manufacturers Association (ANSI/NEMA) AB 4, Mar 2011, Guidelines for Inspection and Preventive Maintenance of Molded Case Circuit Breakers Used in Commercial and Industrial Applications American Society for Testing and Materials (ASTM) International F1508, 2016, Standard Specification for Angle Style, Pressure Relief Valves for Steam, Gas, and Liquid Services American Society of Mechanical Engineers (ASME) B16.34, 2013, Valves-Flanged, Threaded, and Welding End American Welding Society (AWS) D1.1/D1.1M, 2010, Structural Welding Code - Steel Appleton Marine Control Valve Retrofit Manual 20793 ASTM International (ASTM) A106, 2015, Standard Specification for Seamless Carbon Steel Pipe, for High-Temperature Service ASTM International (ASTM) D1330, 2004, Standard Specification for Rubber Sheet Gaskets ASTM International (ASTM) D1330, 2010, Standard Specification for Rubber Sheet Gaskets ASTM International (ASTM) D1330, 2015, Standard Specification for Rubber Sheet Gaskets ASTM International (ASTM) D5363, 2008, Standard Specification for Anaerobic Single Component Adhesives (AN) ASTM International (ASTM) F992, 2017, Standard Specification for Valve Label Plates Code of Federal Regulations (CFR) Title 29, Part 1915, 2014, Occupational Safety and Health Standards for Shipyard Employment Manufacturers Standardization Society of the Valve and Fittings Industry (MSS) SP-61, 2013 Edition, Pressure Testing Of Valves Manufacturers Standardization Society of the Valve and Fittings Industry (MSS) SP-67, 2011 Edition, Butterfly Valves Manufacturers Standardization Society of the Valve and Fittings Industry (MSS) SP-72, 2010 Edition, Ball Valves with Flanged or Butt-Welding Ends for General Service Manufacturers' Standardization Society of the Valve and Fittings Industry (MSS) SP-80, 2013 Edition, Bronze Gate, Globe, Angle and Check Valves Manufacturers Standardization Society of the Valve and Fittings Industry (MSS), SP-58, 2009, Pipe Hangers and Supports – Materials, Design, Manufacture, Selection, Application and Installation MIL-PRF-24176 , Oct 2004, Cement, Epoxy, Metal Repair And Hull Smoothing (Metric) MIL-S-45180, 1998; Sealing Compound, Gasket, Hydrocarbon Fluid and Water Resistant Recovered Energy, Inc, BOSS 107 Separator System Operation & Maintenance Manual – YM Model The Society for Protective Coatings (SSPC) Surface Preparation Specification No.11 (SSPC-SP 11), 2004, Power Tool Cleaning to Bare Metal The Society for Protective Coatings (SSPC)/NACE International (NACE) Joint Surface Preparation Standard SSPC-SP 10/NACE No.2, 2007, Near-White Blast Cleaning Underwriters Laboratories Inc. (UL) 1066, Low-Voltage AC and DC Power Circuit Breakers Used in Enclosures, Apr 2012 Consolidated List of Government-furnished Property The following is a list of property, which the Government will furnish. This list supersedes any other material obligations indicated or implied by referenced drawings.

WORK ITEM
MTI
ITEM DESCRIPTION
NSN/PN
QTY
ESTIMATED COST

($/Unit)

11
N
Repair Kit Assembly
NSN: 2040-01-496-9418
2 ea.
1,968.67
11
N
Rod Seal Repair Kit (FL-2605-29 PC#37)
NSN: 2040-01-496-9422
2 ea.
3,030.07
11
N
Repair Kit, Cable Chain (Includes Pads) (FL-2605-29 PC#36)
NSN: 3020-01-538-0684
16 ea.
257.99
11
N
Cylinder Assembly Actuating, Linear
NSN: 3040-01-496-9424
4 ea.
1,969.24
12
Y
Hydraulic Brake Assembly
NSN: 2530-01-550-7474
4 ea.
399.00
12
N
Winch Gear Box Assembly
NSN: 3010-01-F16-4570 PN: SK9052AZ-SAEB-31.4-H1 (Nord Gear Corp) or YMD-7914 (Appleton Marine Inc)
4 ea.
1,000.00
12
Y
Hydraulic Motor
NSN: 4320-01-470-8467
4 ea.
900.00
12
N
Wire Rope
NSN: 4010-01-620-9604
4 ea.
577.95
12
N
Counter Balance Valve
NSN: 4820-01-324-4269
8 ea.
107.50
12
N
Shuttle Valve
NSN: 4820-01-317-2748
8 ea.
34.78
12
N
Needle Valve
NSN: 4820-01-329-0051
4 ea.
38.00
12
Y
**Directional Control Valve
NSN: 4810-01-543-3252
4 ea.
3,465.17
12
N
Electrical Connector, Hirshmann
NSN: 5935-01-640-6747
8 ea.
32.00
13
N
Roller bearing Unit
NSN: 3130-01-504-4363
2 ea.
4,012.00
13
N
Grease seal
NSN: 5330-01-462-5544
4 ea.
79.25
13
N
Level wind pivot bushing
NSN: 3120-01-621-2293
1 ea.
1,139.00
13
N
Level wind thrust bearing
NSN: 3120-01-621-2300
2 ea.
483.30
13
N
Rexroth DCV
NSN: 4810-01-507-0037
1 ea.
208.29
13
N
Rexroth Sandwich Flow Control
NSN: 4810-01-505-9289
1 ea.
250.00
13
N
Sun Sandwich Relief Valves
NSN: 4820-01-439-2451
2 ea.
900.00
13
Y
Level Wind Hydraulic Cylinder
NSN: 3040-01-441-3721
1 ea.
7,423.00
13
N
3:1 Pilot Ratio, Vented Counterbalance Valve Assembly
NSN: 4820-01-563-5841
1 ea
98.70
13
N
Fully Adjustable Needle Valve
NSN: 4820-01-416-0579
1 ea
48.75
13
N
Wire Rope Assembly
NSN: 4010-01-646-6972
1 ea.
500.00
13
Y
**Hydraulic Motor
NSN: 4320-01-445-2248
1 ea
23,998
13
N
**Pump, Hydraulic Ram, Hand Driven
NSN: 4320-01-286-4065
1 ea.
419.77
13
N
**Cylinder Pin
NSN: 5315-01-515-9847
1 ea
500.00
13
N
**Cylinder Pin
NSN: 5315-01-515-9912
1 ea
520.00
14
N
Hardware Kit, Pins
NSN: 2030-01-485-7209
2 ea.
528.47
14
N
Hardware Kit, Mechanical
NSN: 2030-01-485-7215
2 ea.
538.91
16
N
Swing Brake Seal Kit
NSN: 2030-01-351-2820
2 ea
138.80
16
N
Swing Brake Disc & Bearing Kit
NSN: 2030-01-349-9486
2 ea
937.70
16
N
Wire Rope Assembly, Single Leg
NSN: 4010-01-602-8365
1 ea.
234.00
16
Y
**Winch Assembly
NSN: 2030-01-505-1581
1 ea.
17,454.50
17
N
Wire Rope, Crane Aux Fall
NSN: 3950-01-617-1692
1 ea
522.54
17
N
Wire Rope, Crane Main Fall
NSN: 3950-01-617-1700
1 ea
1,275.49
17
N
Luff Cylinder Seal kit
NSN: 5330-01-433-6307
1 ea
357.99
17
N
Holding Valve
NSN: 4810-01-353-0586
2 ea
67.33
17
N
Shuttle Valve
NSN: 4820-01-317-2748
2 ea
24.32
17
N
Needle Valve
NSN: 4820-01-329-0051
1 ea
38.11
17
Y
Valve Assembly, Manifold
NSN: 4810-01-506-7738
1 ea.
19,892.60
17
N
Bushing, Heel
NSN: 5365-01-F12-2920
4 ea
67.00
17
N
Hydraulic swivel seal kit
NSN: 4730-01-566-2864
1 ea
1,298.00
17
N
**Pin, Heel
NSN: 5315-01-500-6931
2 ea
2,463.45
17
N
**Hand pump w/ Stainless Steel Option, P18
NSN: 4320-01-517-1444
1 ea
1,724.57
17
N
**Plate, Backing, Brake (Item 231 and 234)
NSN: 3040-00-119-9848
2 ea
1,500.40
17
N
**Plate, Brake (Item 232)
NSN: 3040-01-068-7647
1 ea.
377.00
17
N
**Driver Plate (Item 233)
NSN: 3040-01-F14-3994
1 ea.
138.34
17
N
**Packing Assortment, Preformed
NSN: 5330-01-191-2622
1 ea.
10.94
17
N
**Disc-Friction, Brake
NSN: 3040-01-051-3606
1 ea.
15.74
17
N
**Spring, Helical, Comp
NSN: 5360-01-268-0044
12 ea
12.12
17
N
**PD12C Seal kit
NSN: 2590-01-398-5741
1 ea
147.76
17
N
**Disc, Steel
NSN: 2530-01-066-9585
1 ea
38.38
17
N
**Master brake rebuild kit
NSN: 5330-01-F16-4572 PN: 98-015-3001 (Eskridge Inc)
3 ea
556.39
17
N
**Aux Hoist Hook (Overhaul Ball)
NSN: 4030-01-572-3945
1 ea
2,800.00
17
Y
**Block, Tackle
NSN: 3940-01-566-2929
1 ea
3,806.87
17
N
**Relief Valve Cartridge
NSN: 4820-01-481-7116 PN: RPIC-LAN (Sun Hydraulics Inc)
1 ea
117.35
17
N
**Control Stand Selector Valve Assembly
NSN: 4730-01-507-3516
1 ea
1,247.94
17
N
**Bushing, Luff Cylinder
NSN: 3120-01-363-7629
4 ea
89.53
17
N
**Pin, Luff Cylinder
NSN: 5315-01-F12-2922 PN: MMD-2232
2 ea
2,432.30
17
Y
**Valve Assembly, Directional Control
NSN: 4810-01-F17-5027
1 ea.
14,806.50
20
N
HDRAULIC CONTROL VALVE ASSEMBLY PARTS KIT
PN: AMD-2633 ACN 4810-01-F18-5588
1
15,061.00
21
N
Boss 2.2 GPM OWS
NSN: 4330-01-F13-3461 PN: BOSS 2.2T-107 YM
1 ea.
14,300.00

*Government-loaned property, which shall be returned to the vessel upon completion of the availability.

**New or refurbished equipment that the Government may provide for installation in place of existing equipment.

***Government-furnished property, which is to be supplied by either the vessel or the C4IT ServiceCenter

Consolidated List of Critical Inspection Items The following is a list of work items, which contain Critical Inspection reports, which the Contractor must complete within the first 25% of the availability contract period (see SFLC Std Spec 0000, paragraph 3.2.6.5 (Inspection report particulars)):

Work Item
Title
2
Hydraulically Operated Cargo Hatch, Inspect and Service
11
Hydraulic Chain Stoppers, Inspect and Service
12
Hydraulic Crossdeck Winches, Inspect And Service
13
Hydraulic Inhaul Winch, Inspect And Service
14
Mechanical Chain Stoppers, Inspect and Service
15
Warping Capstan (Aft), Inspect and Service
16
Single Point Davit, Disassemble and Inspect
17
Buoy Crane, Inspect And Service
20
Crane Winch DCV, Replace
26
Power Circuit Breakers, Inspect, Maintain & Test
28
Vent Spaces, Deck, Preserve
29
Pump Room, Deck, Preserve

Principal Characteristics - TENDER

175' WLM, BUOY TENDER

Physical

Length overall
174' 8"
Length between perpendiculars
155' 1"
Depth
14' 8"
Maximum beam
36' 0"
Designed draft
8' 0"
Mast height (above 8' waterline)
58' 8"
Frame spacing
20"
Full load displacement
855.15 Long Tons SW
Light load displacement
719.78 Long Tons SW
Minimum op condition displ
852.19 Long Tons SW

HULL

Hull material
Steel

Machinery

Main propulsion
Two Caterpillar 3508 DITA V-8 diesel; 999 BHP ea @ 1500 RPM

Two Ulstein 360 degree steerable Z-Drives, 403 SRPM @ 1600 ERPM

Reduction gears
Two Z-Drive units, Cardan shafting; 3.973:1 gear ratio
Shaft seal
John Crane Type ND
Shaft bearings
Five pedestal mounted, Cooper split roller bearings
Number of propellers
2
Number of blades
4
Diameter
57.1"
Rudders
None; Z-drive
Ship's service generators
Three Caterpillar Model 3406 DITA Turbocharged; 285KW, 450V, 60 Hz, 1800 RPM
Emergency diesel generator
One Caterpillar Model 3406 DIT 210 KW, 24V, 60 Hz, 1800 RPM

Tank Capacities

Diesel oil capacity (100%)
16,385 gal
Fresh water capacity (100%)
7,339 gal
Lubricating oil (100%)
86 gal

00000_0618_FLT

REC_00000_FLT_Commercial Project @ CG Facility (1212) General Requirements

1. SCOPE

1.1 Intent. This standard specification invokes general requirements for conducting vessel repairs performed by commercial contractors at a Coast Guard facility for Coast Guard vessels.

1.2 Term interchangeability. The terms 'Contractor', 'CG Yard', 'NAVSTA EVERETT', 'shipyard', 'Base', and 'Coast Guard Industrial' are used interchangeably in this specification. Where the primary service provider is Coast Guard personnel, references to contractor and other noted descriptors within this specification or within drawings, publications, SFLC Standard Specifications or other commercial and military references are deemed the same as prime service provider.

2. REFERENCES

Coast Guard Drawings None Coast Guard Publications Coast Guard Commandant Instruction(COMDTINS) M10360.3 (series), Coatings and Color Manual Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2018, General Requirements Surface Forces Logistics Center Standard Specification 0740 (SFLC Std Spec 0740), 2018, Welding and Allied Processes Surface Forces Logistics Center Standard Specification 6310 (SFLC Std Spec 6310), 2018, Requirements for Preservation of Ship Structures Other References None

3. REQUIREMENTS

3.1 General. The Contractor shall conform to all requirements specified in SFLC Std Spec 0000 and in this item, as applicable, during the performance of this availability.

NOTE

The requirements of paragraph 3.1 (General) applies to all work under the scope of this contract, whether explicitly stated in work items or not, and to all other work subsequently authorized by changes, modifications, or extensions to the contract.

3.2 Fire watch requirements. The Contractor shall refer to 3.3.1.3 (Fire watch requirements) of SFLC Std Spec 0000, in accomplishing the following task:

· Provide portable fire extinguishers for Coast Guard fire watch personnel. Coast Guard fire watch is in lieu of contractor personnel during the hours of 0800-1600, Monday through Friday, and limited to two Coast Guard fire watch personnel.

· Provide fire watch personnel and fire extinguishers for the duration of the availability period, during and beyond noted Coast Guard fire watch support.

3.3 Preservation requirements. The Contractor shall accomplish all preservation tasks, including touch-ups, in accordance with SFLC Std Spec 6310.

3.3.1 Brand name approval. Ensure that all contractor-furnished coatings are in accordance with SFLC Std Spec 6310, Appendix C (Authorized Coatings for Use on Cutters and Boats).

3.3.2 Coating colors and system color schemes. Ensure that all colors and color coat/paint schemes are in accordance with COMDTINST M10360.3, Chapter 6 (Cutter and Boat Colors Exterior and Interior).

NOTE

Unless a waiver has been granted (in writing) by the KO, deviations from authorized coatings (listed in Appendix C of SFLC Std Spec 6310) and colors and color schemes (provided in Chapter 6 of COMDTINST M10360.3) are strictly prohibited.

3.4 Welding and brazing requirements. The Contractor shall perform all welding and allied processes, and NDE in accordance with SFLC Std Spec 0740.

3.5 Environmental protection requirements. The Contractor shall adhere to the following environmental protection requirements in accordance with the SFLC Stand Spec 0000:

3.5.1 USCG facilities. The Contractor shall provide and maintain environmental protection as defined in SFLC Std Spec 0000 Appendix B, Requirements for Environmental Protection at USCG Facilities, during the performance of this availability. Contractor shall plan for and provide environmental protective measures to control pollution that develops during normal practice, as well as plan for and provide environmental protective measures required to correct conditions that develop during the project. Contractor shall comply with applicable Federal, state, and local laws, codes, ordinances, and regulations in their entirety. Any reference to a specific portion of a Federal, state, or local law, code, ordinance, or regulation in this or any other item shall not be construed to mean that relief is provided from any other sections of the law, code, ordinance, or regulation.

3.5.1.1 USCG Generator status. The activity Generator Status for the Coast Guard Facility is “Large Quantity” Generator.

3.5.1.2 Plans and permits. The CG Facility has unit specific permits including the following:

· Spill Prevention Control and Countermeasures (SPCC) Plan: Unit has a SPCC Plan which requires certain unit-specific procedures be followed for the storage, inspection, and transfer of petroleum products in containers 55 gallons or greater.

· National Pollutant Discharge Elimination System (NPDES) Storm Water (SW) Permit: Unit has an NPDES SW permit which requires unit-specific procedures be followed for the storage and inspection of equipment and materials which may contribute contaminants to storm water discharges.

· Air Emission Permit: Unit has a Air Emission Permit which requires unit-specific procedures be followed for the emissions of VOCs and hazardous air pollutants.

3.5.2 Test and procedures. The Contractor shall be required to promptly conduct tests and procedures for the purpose of assessing whether operations are in compliance with applicable Environmental Laws. Analytical work shall be done by qualified laboratories; and where required by law, the laboratories shall be certified.

3.5.3 Regulatory notifications. The Contractor shall be responsible for all regulatory notification requirements in accordance with Federal, State and local regulations. In cases where the Coast Guard must also provide public notification, such as storm water permitting, the Contractor must coordinate with the Contracting Officer or COR, and if work is being performed at a USCG Facility, the local Facility Engineer or Engineering Officer. The Contractor shall submit copies of all regulatory notifications to the Contracting Officer and the local Facility Engineer or Engineering Officer prior to commencement of work activities. Regulatory notifications shall be provided for including but not limited to demolition, renovation, National Pollutant Discharge Elimination System (NPDES) defined site work, and remediation of controlled substances such as asbestos, hazardous waste, and lead paint.

3.5.4 Environmental manager. The Contractor shall appoint in writing an Environmental Manager for the project, and shall be responsible for coordinating Contractor compliance with Federal, State, local, and station environmental requirements. The Environmental Manager shall ensure compliance with Hazardous Waste Program requirements, including hazardous waste handling, storage, manifesting, and disposal; implement the Contractors’ Environmental Management Plan; ensure that all environmental permits are obtained, maintained, and closed out; ensure compliance with Storm Water Program Management requirements; ensure compliance with Hazardous Materials including storage, handling, and reporting requirements; as well as coordinate any remediation of regulated substances such as lead, asbestos, and polychlorinated biphenyl (PCB). This may be a collateral position; however the individual must be trained to accomplish the following duties; ensure waste segregation and storage compatibility requirements are met; inspect and manage Satellite Accumulation areas; ensure only authorized personnel add wastes to containers; ensure all Contractor personnel are trained in 40 CFR requirements and individual position requirements; coordinate removal of waste containers; and maintain the Environmental Records binder and required documentation, including environmental permits compliance and close-out.

3.5.5 HW disposal. Contractor shall comply with SFLC Std Spec 0000 Appendix B, Requirements For Environmental Protection At USCG Facilities for HW disposal, and ensure that waste removals are conducted during normal business hours (0800-1600) on Monday through Friday (excluding holidays).

3.5.6 Additional Requirements. The Contractor shall be aware of the following:

3.5.6.1 No Contractor or Subcontractor shall have the authority to sign a Hazardous Waste Manifest using the Coast Guard facility’s EPA Generator ID Number or remove contract generated hazardous waste from the Coast Guard facility without COR or KO-approval.

3.5.6.2 Local environmental regulations at the Government facilities may be more stringent. As with all environmental regulations, the Contractor shall prepare for and comply with local and state regulations.

3.5.6.3 Coast Guard facilities do not maintain Facilities Response Plans (FRPs) per 33 CFR 154. Contractor shall furnish the FRP when required for over-the-water liquids transfers to and from vessels, and is required for oil/fuel transfers to/from vessels for 250 barrels (10,500 gallons) or more.

3.6 Local Policy. None.

3.7 SFLC standard specification approved changes. The Contractor shall be aware that the following are approved changes to published SFLC 2014 Edition Standard Specifications and supersede published content:

3.7.1 Change to SFLC Std Spec 0000, paragraph 1.3. ‘Acronyms and term definitions’, page 5, “PCL (Paint Containing Lead)” definition replaced by, “Any paint or coating containing lead in excess of 0.009 percent by weight (1.0 mg/cm2 or 90 ppm). Lead Based Paint (LBP) is an interchangeable term with PCL.”

3.7.1.1 Change Std Spec 0000 paragraph 3.2.4.2.3(QP 1 inspector or tech rep duties) bullet, “Determine when applied coats have sufficiently cured for overcoating or for system service resumption (see paragraph 3.1.19 of SFLC Std Spec 6310 (Critical drying time requirements)).” to “Determine when applied coats have sufficiently cured for overcoating or for system service resumption (see paragraph 3.1.17 of SFLC Std Spec 6310 (Critical drying time requirements)).”

3.7.2 Change to Std Spec 5000, paragraph D2.2.1.1 bullet, "For running rigging, furnish class 6x37, uncoated, independent wire rope core (IWRC), right regular lay (RRL) wire rope or Dyform-18, rotation resistant wire rope," to "For running rigging, furnish class 6x36, uncoated, independent wire rope core (IWRC), right regular lay (RRL) wire rope or Dyform-18, rotation resistant wire rope."

3.7.2.1 Change to Std Spec 5000, page D-2, Table D-1 title from "DYFORM-18, 6X19 AND 6X37 IWRC RRL," to " DYFORM-18, 6X19 AND 6X36 IWRC RRL"

4. NOTES

4.1 QA inspection forms. QA inspection forms (QA-1 thru QA-5), required in SFLC Std Spec 6310 to be completed and submitted during preservation of “critical-coated surfaces”, are provided at the end of this document.

QA-1 - QUALITY ASSURANCE INSPECTION FORM

(PRESERVATION CHECKLIST)

Vessel Name
Hull #
Work Item #
Work Item Title
Location of Work (incl. frame #’s)
Area (sqft)

CHECKPOINT 1 – COATING SYSTEM COMPLIANCE

Ensure all coatings are in compliance with SFLC Std Spec 6310, Appendix C.

CHECKPOINT 2 - PAINT STORAGE

Ensure all coatings are kept at a temperature of 65 to 85°F at all times, unless otherwise specified by the coating mfgr.

CHECKPOINT 3 - AMBIENT CONDITIONS

Ensure surface and surrounding temperatures are each between 50 and 90°F for water-containing coatings, and 35 and 95°F for other coatings, unless otherwise specified by the coating manufacturer(s).

Ensure maximum relative humidity (RH) is as follows, from surface preparations through final curing of topcoat: 50% for tanks, voids, and vent plenum; and 85% for all other areas, unless otherwise specified by manufacturer(s).

Ensure surface temperature is at least 5°F above the dew point, unless otherwise specified by the coating mfgr.

CHECKPOINT 4 - PRE-SURFACE PREPARATION

Remove surface contaminants (soluble salts, loose rust, mud, and marine growth) with low pressure fresh water wash down (maximum 5,000 psi). If oil and grease are present, perform solvent cleaning, as per SSPC SP-1.

Verify equipment setup, blast media, and surface preparation methods match designated test coupon.

CHECKPOINT 5 - SURFACE PREPARATION

Verify environmental conditions (see CHECKPOINT 3).

Ensure cleanliness of prepared surface is as per specification (i.e.: SSPC SP-11, SP-10, SP WJ-2…).

Verify surface anchor profile using ASTM D4417-Methods B or C against SFLC Std Spec 6310. Conduct profile readings at a minimum of 5 locations for the first 1000-sqft area, and 2 locations for each succeeding 1000-sqft area.

Measure soluble salt conductivity in accordance with SSPC-Guide 15. Conduct 5 measurements per each 1000-sqft area (max. threshold: 70 microsiemens/cm for non-submerged surfaces, 30 microsiemens/cm for submerged surfaces).

CHECKPOINT 6 - PRIMER COAT APPLICATION

Verify environmental conditions (see CHECKPOINT 3).

Verify proper mixing and stand-in (induction) times.

Ensure no paint is applied when the temperature is expected to drop to freezing before the paint has dried.

Ensure surfaces are completely dry, unless otherwise allowed by the coating manufacturer(s).

Verify wet film thickness (WFT) at random, to prevent under or over application. Verify final DFT.

Brush out all runs, sags, drips, and puddles.

Perform visual inspection for holidays and other defects.

CHECKPOINT 7 – STRIPE COAT APPLICATION

Verify environmental conditions (see CHECKPOINT 3).

Ensure overcoating window is as per manufacturer’s instructions.

After primer coat (mist coat after inorganic zinc), brush-apply un-thinned coat of same primer paint over edges, weld seams, cut-outs, and areas of complex geometries @ 3-4 mils wet film thickness (WFT).

CHECKPOINT 8 – TOP COAT APPLICATION

Verify environmental conditions (see CHECKPOINT 3).

Ensure overcoating window is as per manufacturer’s instructions.

Verify proper mixing and stand-in (induction) times, as applicable.

Verify wet film thickness at random, to prevent under or over application.

Brush out all runs, sags, drips, and puddles.

CHECKPOINT 9 – FINAL INSPECTION

Verify final system dry film thickness. Conduct 5 sets of 3 readings for each of the first 3 100-sqft areas, followed by 5 sets of 3 readings for each succeeding 1000-sqft area.

Ensure that system cure is in accordance with manufacturer's recommendation for intended service.

Ensure potable water tank exhaust ventilation is maintained continuously from and during coating application through final system cure, to exhaust all solvent to the atmosphere and to prevent solvent entrapment.

For immersion coatings (including tank U/W body), record date and time of the following events:

Final coat application: _____/_____; Return to service or removal from environment controls: _____/_____

CHECKPOINT 10 – RECORD KEEPING

Complete, sign, and submit all provided QA Inspection Forms.

Name of QP-1/NACE Inspector
Signature
Cert. #
Date / Time

QA-2 - QUALITY ASSURANCE INSPECTION FORM

(ENVIRONMENTAL READINGS)

Vessel Name
Hull #
Work Item #
Work Item Title

Use one sheet for each activity. Record conditions every four hours from before surface preparation to application of final coating system coat.

DATE & TIME
ACTIVITY (Surface preparation, primer coat, barrier coat, top coat, etc…)
LOCATION (Frame & Deck, relation to equipment, etc.)
TEMPERATURE
% REL. HUMID-ITY
DEW PT.
SURFACE
AMBIENT
ΔT

| DP - Surface |

Name of QP-1/NACE Inspector
Signature
Cert. #
Date / Time

QA-3a - QUALITY ASSURANCE INSPECTION FORM

(SURFACE PROFILE LOG FOR PROFILE MEASUREMENTS IAW ASTM D4417-METHOD-C)

Vessel Name
Hull #
Work Item #
Work Item Title
Location of Work (incl. frame #’s)
Area (sqft)
SURFACE PREPARATION METHOD
PROFILE ACHIEVED (mils)
Min
Max
Mean
SSPC-SP-10/NACE No. 2
(
SSPC-SP WJ-1/NACE WJ-1
(
SSPC-SP WJ-2/NACE WJ-2
(
SSPC-SP WJ-3/NACE WJ-3
(
SSPC-SP WJ-4/NACE WJ-4
(
SSPC-SP-3
(
SSPC-SP-11
(
SSPC-SP-11 (inaccessible area)
(
Brush-blasting (non-metallic substrate)
(

Abrasive Manufacturer:

Abrasive Sieve Size:

Place surface profile replica tapes in the spaces provided below, to serve as permanent QA record. Maintain a separate log for each location. When an area is divided into separate sections, maintain a separate log for each section.

Place Surface Profile Replica Tape Here Place Surface Profile Replica Tape Here Place Surface Profile Replica Tape Here

Reading (mils):

Reading (mils):

Reading (mils):

Place Surface Profile Replica Tape Here Place Surface Profile Replica Tape Here Place Surface Profile Replica Tape Here

Reading (mils):

Reading (mils):

Reading (mils):

Place Surface Profile

Place Surface Profile Replica Tape Here Place Surface Profile Replica Tape Here

Reading (mils):

Reading (mils):

Reading (mils):

Place Surface Profile

Place Surface Profile Replica Tape Here Place Surface Profile Replica Tape Here

Reading (mils):

Reading (mils):

Reading (mils):

Place Surface Profile

Place Surface Profile Replica Tape Here Place Surface Profile Replica Tape Here

Reading (mils):

Reading (mils):

Reading (mils):

Mean Mil Reading (IAW ASTM D4417-Method C) for above 15 readings:

Name of QP-1/NACE Inspector
Signature
Cert. #
Date / Time

QA-3b - QUALITY ASSURANCE INSPECTION FORM

(SURFACE PROFILE LOG FOR PROFILE MEASUREMENTS IAW ASTM D4417-METHOD-B)

Vessel Name
Hull #
Work Item #
Work Item Title
Location of Work (incl. frame #’s)
Area (sqft)
SURFACE PREPARATION METHOD
PROFILE ACHIEVED (mils)
Min
Max
Mean
SSPC-SP-10/NACE No. 2
(
SSPC-SP WJ-1/NACE WJ-1
(
SSPC-SP WJ-2/NACE WJ-2
(
SSPC-SP WJ-3/NACE WJ-3
(
SSPC-SP WJ-4/NACE WJ-4
(
SSPC-SP-3
(
SSPC-SP-11
(
SSPC-SP-11 (inaccessible area)
(
Brush-blasting (non-metallic substrate)
(

Abrasive Manufacturer:

Abrasive Sieve Size:

Record measurements taken in the spaces provided below, to serve as permanent QA record. Maintain separate log for each location. When an area is divided into separate sections, maintain a separate log for each section.

Reading (mils):

Reading (mils):

Reading (mils):

Reading (mils):

Reading (mils):

Reading (mils):

Reading (mils):

Reading (mils):

Reading (mils):

Reading (mils):

Mean Reading (mils)

Mean Reading (mils) IAW ASTM DD4417).

Name of QP-1/NACE Inspector
Signature
Cert. #
Date / Time

QA-4 - QUALITY ASSURANCE INSPECTION FORM

(SURFACE SOLUBLE SALT CONDUCTIVITY LOG)

Vessel Name
Hull #
Work Item #
Work Item Title
Location of Work (incl. frame #’s)
Area (sqft)

SOLUBLE SALT CONDUCTIVITY Measurements IAW SSPC-GUIDE 15.

Date
Test Locations
Conductivity (Microsiemens/CM)
Name of QP-1/NACE Inspector
Signature
Cert. #
Date / Time

QA-5 - QUALITY ASSURANCE DATA FORM

(COATING THICKNESS)

(Use one sheet for each sequence)

Vessel Name
Hull #
Work Item #
Work Item Title
Coating Mfg
Product Name
Batch #
Induction Time
Coating System Sequence (Primer/Touchup/3rd Coat, etc.)

Dry Film Thickness (DFT) Measurements IAW SSPC-PA 2.

SPOT
1
2
3
4
5
AVERAGE VALUE

*BASE METAL READING (BMR) Required, If Magnetic Pull-Off (Type I/Banana) Gauge Is Used.

Location (Frame Reference):

SPOT
1
2
3
4
5
Overall Avg. DFT
ADJUSTMENTS
Avg. BMR
Deviation
Before Adjustments
After Adjustments

Avg.

Location (Frame Reference):

SPOT
1
2
3
4
5
Overall Avg. DFT
ADJUSTMENTS
Avg. BMR
Deviation
Before Adjustments
After Adjustments

Avg.

Location (Frame Reference):

SPOT
1
2
3
4
5
Overall Avg. DFT
ADJUSTMENTS
Avg. BMR
Deviation
Before Adjustments
After Adjustments

Avg.

Application Method (Airless, Conventional Spray, Rolled)
Average DFT
Name of QP-1/NACE Inspector
Signature
Cert. #
Date / Time

12316_0617_FLT

REC_12316_FLT175’ WLM (ALL) (0813)

WORK ITEM 1: Voids (Accessible), Clean and Inspect

1. SCOPE

1.1 Intent. This work item describes the requirements for the Contractor to clean and inspect the following void(s):

TABLE 1 - VOIDS

TYPE OF STRUCTURE
LOCATION
CAPACITY - 95%

(gallons)

LOW SUCTION

(gallons)

Void
3-18-0-T
2,000
50
Void
3-52-0-V
5,000
50

1.2 Government-furnished property.

None.

2. REFERENCES

Coast Guard Drawings Coast Guard Drawing 175 WLM 601-003, Rev F, Booklet of General Drawings (552-564) Coast Guard Publications Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2018, General Requirements Other References ASTM International (ASTM) D1330, 2004, Standard Specification for Rubber Sheet Gaskets

3. REQUIREMENTS

3.1 General.

3.1.1 CIR.

None.

3.1.2 Tech Rep.

Not applicable.

3.1.3 Protective measures. The Contractor shall furnish and install all protective coverings to seal off and protect all non-affected vessel’s components, equipment, and spaces near the work area against contamination during the performance of work. Upon completion of work, the Contractor shall remove all installed protective measures, inspect for the presence of contamination, and return all contaminated equipment, components, and spaces to original condition of cleanliness.

3.1.4 Interferences. The Contractor shall handle all interferences in accordance with SFLC Std Spec 0000, paragraph 3.3.5 (Interferences).

note Coast Guard personnel will operate all shipboard machinery and equipment.

3.1.5 Operational test, initial. Prior to commencement of work, the Contractor shall witness Coast Guard personnel perform an initial operational test of the TLI’s for tanks listed in paragraph 1.1 (Intent), to demonstrate existing operational condition. Submit a CFR.

3.2 Cleaning and inspection requirements. The Contractor shall refer to Coast Guard Drawing 175 WLM 601-003 for guidance. to accomplish the following tasks:

3.2.1 Content removal. The Contractor shall remove and dispose of all fluids and/or residues in accordance with all applicable Federal, state, and local regulations.

3.2.2 Cleaning. The Contractor shall remove access cover(s). Clean the designated structure’s interior surfaces free of all foreign materials, such as sediment, sludge and fungal growth. Remove all persistent residues, taking care not to damage the tank coating system. Remove cleaning media and residues continuously from the compartment during the washing process. Remove any residual wash media and wipe up residual moisture with clean lint-free cloths. Collect, contain, and dispose of all wash media, residues, and cleaning materials in accordance with all Federal, state, and local regulations.

3.2.3 Inspection. The Contractor shall visually inspect all interior surfaces, including, but not limited to bulkheads, floor and overhead plating, structural members, manhole cover surfaces, fasteners and gasket seating surfaces. Submit a CFR including the following, as applicable:

· Structural condition.

· Inaccessible areas, if any.

· Condition of coating, including measurements taken, percentage, location, and type of coating failure.

· Tank level indicator (TLI) and/or float switch condition.

· Sounding tube and striker plate condition.

· Suction and discharge piping condition.

· Fastener material and condition.

3.3 Closing. The Contractor shall ensure that the compartment(s) remain open for approximately 24 hours after completion of the tasks specified above. Notify the COR at least 24 hours prior to closing the compartment(s). After satisfactory inspection by the Coast Guard Inspector, and completion of all authorized repairs, close the manhole cover(s) with new gasket material conforming to ASTM D1330 and cotton grommets on the studs (as applicable). The Contractor shall renew up to 10% of missing or damaged nuts and washers.

NOTE

Coast Guard personnel will operate all shipboard machinery and equipment.

3.4 Operational test, post repairs. After completion of work and in the presence of the Coast Guard inspector, the Contractor shall thoroughly test and demonstrate the TLI’s for tanks listed in paragraph 1.1 (Intent), to be in satisfactory operating condition. Submit a CFR.

4. NOTES

This section is not applicable to this work item.

16700_ACC_0318_IBCT

REC_16700_CrgHtchInspctSrvc_IBCT_175 WLM (ALL)(0815) WORK ITEM 2: Hydraulically Operated Cargo Hatch, Inspect and Service

1. SCOPE

1.1 Intent. This work item describes the requirements for the Contractor to perform inspections and service for the hydraulically-operated cargo hatch.

1.2 Government-furnished property.

None.

2. REFERENCES

Coast Guard Drawings Coast Guard Drawing 175 WLM 130-001, Rev -, Mods to Buoy Deck Incidental to Hawser Pipe Cover Coast Guard Drawing 175 WLM 549-001, Rev E, Onboard Lubrication Requirements Coast Guard Drawing 175 WLM 601-001, Rev R; General Arrangement Inboard and Outboard Profiles Coast Guard Drawing 175 WLM 920-001, Rev K, Hull Block 920 Panels Coast Guard Publications Coast Guard Technical Publication (TP) 3610, Section 167-A, Nov 2005, Hydraulic Cargo Hatch - Model No. D-WK-787 Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2018, General Requirements Surface Forces Logistics Center Standard Specification 0740 (SFLC Std Spec 0740), 2018, Welding and Allied Processes Surface Forces Logistics Center Standard Specification 5000 (SFLC Std Spec 5000), 2018, Auxiliary Machine Systems Surface Forces Logistics Center Standard Specification 6310 (SFLC Std Spec 6310), 2018, Requirements for Preservation of Ship Structures Other References None

3. REQUIREMENTS

3.1 General.

3.1.1 CIR. The Contractor shall submit a CIR for the inspections listed in the following paragraph(s):

· 3.2 (Tasks to be accomplished) – Task #1.

3.1.2 Tech Rep.

Not applicable.

3.1.3 Protective measures. The Contractor shall furnish and install all protective coverings to seal off and protect all non-affected vessel's components, equipment, and spaces near the work area against contamination during the performance of work. Upon completion of work, the Contractor shall remove all installed protective measures, inspect for the presence of contamination, and return all contaminated equipment, components, and spaces to original condition of cleanliness.

3.1.4 Interferences. The Contractor shall handle all interferences in accordance with SFLC Std Spec 0000, paragraph 3.3.5 (Interferences). Known interferences include, but are not limited to the below-listed:

· Electrical and hydraulic switches.

· Dogs.

· Toggles.

· Hydraulic cylinders.

· Hydraulic lines.

· Electrical cables.

· Hoses.

· Overhead insulation.

3.2 Tasks to be accomplished. The Contractor shall perform the following tasks:

CAUTION

Do not paint gaskets or any moving parts, including dogs, nuts, wedges, spindles, yokes, packing, connecting rods and hinge pins.

CAUTION

For Task #2, failure to remove hinge interferences during hatch removal/reinstallation may result in damage to coaming and hinges. Protect hinges during hatch removal and reinstallation.

ADDITION REQUIREMENTS

#
TASK TYPE
QTY
COMPONENT OR ASSEMBLY
APPENDIX AND PARA. FROM 5000_STD
OTHER
1
Operate and Inspect
1
Cargo hatch assembly
3.2.1 (Operate and inspect)
1. Check hatch for proper operation of all indicators, switches, dogging un-dogging and overall operation.

2. Check entire coaming and drains for signs or debris or clogging of drains.

3. Conduct a visual inspection of the hatch. Check all linkages.

4. Inspect both inner and outer knife-edges for proper height and evenness of wear.

5. Inspect entire hatch structure, for signs of paint wear and corrosion.

6. Inspect gasket channels for corrosion. 7. Take 10 UT measurements of gasket channel surfaces, in locations designated by the Coast Guard Inspector, in accordance with SFLC Std Spec 0740, Appendix C.

8. Inspect hydraulic hose condition.

9. Check condition of dogs and wedges.

Submit A CIR.

2
Remove and reinstall
1
Cargo hatch assembly
N/A
Remove hatch, to facilitate inspections and service tasks, and reinstall hatch, upon completion of work.

Coaming in way of hatch hinges may be an interference to hatch removal. Inspect hinge clearance prior to commencing unshipping operations and determine if modifications are required. Modify/remove as necessary and return to original configuration at hatch reinstallation.

Failure to remove interferences may result in damage to coaming and hinges. Protect hinges during hatch removal and reinstallation.

3
NDE
1
Cargo hatch assembly
3.2.5 (NDE)
Components designated for NDE: All welds.

Submit a CFR.

4
Service and Inspect
1
Hydraulic hatch lift cylinder
3.2.2 (Service and inspect)
Submit CFR
5
Renew
1
Cargo hatch gasket
N/A
See CG TP-3610.

Conduct gasket compression test, upon installation. Submit CFR.

6
Preserve
1
Cargo hatch assembly
3.2.4 (Preservation)
Use Coating System: “Weather Decks (Weather Deck, Buoy Tender Working Deck)” in accordance with in SFLC Std Spec 6310, Appendix A (Cutter and Boat Exterior Painting Systems).

Submit CFR.

7
Groom And Lubricate
1
Cargo hatch assembly
3.2.6 (Groom and lubricate)
See Coast Guard Drawing 175 WLM 549-001.
8
Boundary Testing
1
Cargo hatch assembly
N/A
Accomplish a chalk test and water hose test, in accordance with SFLC Std Spec 0740, Appendix C. Adjust dogs in accordance with CG TP-3610.

Submit a CFR.

9
Operational Testing – Post Repairs
1
Cargo hatch assembly
N/A

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .