William Tate - Request for Clarification 3.docx

DOCX document 22 KB Posted

Attached to
Dockside (DS): USCGC William Tate FY20 Repair
Solicitation number
70Z085-20-Q-P4595400
Issued by

About this file

This document contains a request for clarification form and correspondence regarding a solicitation for dockside repair services for the USCGC William Tate. The solicitation number is 70Z085-20-Q-P4595400 and is seeking a contractor to furnish all necessary facilities, labor, materials, services, equipment, and supplies to perform various dockside repairs to the 175-foot USCGC William Tate in accordance with the attached specification. Questions concerning this solicitation must be submitted in writing using the attached request for clarification form by 27 May 2020 at 9:00 am Pacific Time and emailed to Andrew.G.Jacobs@uscg.mil. The correspondence addresses a question regarding allowing the contractor to tie an overboard connection into the same location as the current overboard connection, to which the response indicates the contractor must follow all reference drawings, installation instructions, and obtain CFR, CR, and contracting officer approval for any deviations.

View the file

Other files

Show all 15

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Offeror’s questions will be answered by an Amendment.

1. Offeror’s questions concerning this solicitation shall be submitted in writing, and must be submitted on the attached “Request for Clarification” form. One question should be submitted per form. Each form should indicate the name of the offeror’s firm.

2. Questions should be submitted via email to Andrew.G.Jacobs@uscg.mil.

REQUEST FOR CLARIFICATION

Submit requests not later than 27 May 2020 at 9:00 am Pacific Time

Offeror’s Name:

Date:
27 May 2020

Question No.

Three

FY20 Dockside repairs for CGC WILLIAM TATE

RFQ Number:
70Z085-20-Q-P4595400

SOLICITATION SECTION:

PARA NO.

DEFINITE/OPTIONAL ITEM NO.
Work Item 021
PARA NO.
3.4.5

TITLE:

OWS Overboard

QUESTION: Will the Contractor be allowed to tie the overboard into the same location as the current overboard connection?

RESPONSE: The contractor shall follow all reference, drawings, and installation instructions in the specification.

CFR / CR and Contracting Officer approval is required for any requested deviation.