Attachment 2 - UPS MASTER LIST Price Sheet.xlsx
XLSX spreadsheet 3 MB Posted
- Solicitation number
- W25G1V22R0018
About this file
This document contains an attachment listing equipment for a UPS-Generator maintenance and repair contract opportunity. The list includes over 80 UPS units and generators across multiple buildings along with manufacturer, model, installation date and preventative maintenance schedules. It also includes related static switches, DC plants, and distribution panels.
The opportunity is a solicitation from the Army Contracting Command Aberdeen Proving Ground seeking proposals for a hybrid contract consisting of firm fixed price for regularly scheduled preventative maintenance visits twice yearly along with time and materials pricing for remedial repairs. Proposals are due on March 21, 2022. The contractor must provide all labor, equipment, transportation and other resources to perform maintenance and repairs as defined in the Performance Work Statement except for government furnished property. The point of contact for the solicitation is Jacqueline Ramsey.
View the file
Other files
Show all 12
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sheet1
| ATTACHMENT 2 - UPS LIST BY UNIT NUMBER & PRICING SHEET | ||||||||||||||||||||||
| Equipment # | Location | Type | Manufacturer | Model # | Serial # | kVA | Installed | Next PM | Load % | Battery Install Date | Battery EOSL | AC Capacitor Date Code | AC Capacitor EOSL | DC Capacitor Date Code | DC Capacitor EOSL | Fan Date Code | Fan EOSL | Notes | Proposed Price Base Year Semi Annual PM (Price per 6mth) | Proposed Price OPTION YR1 Semi Annual PM (Price per 6mth) | Proposed Price OPTION YR2 Semi Annual PM (Price per 6mth) | DO NOT COMPLETE Option to Extend Service per FAR 52.217-8 For Evaluation - price will be 1/2 Option Yr 2 price |
| 1263 | Bldg 11 | UPS | Eaton | 9395-275 | ED043BAA05 | 225 | 9/1/09 | 12/1/21 | 21.5% | 7/16/20 | 7/16/25 | 7/20/20 | 7/20/27 | 9/1/09 | NA | 7/20/20 | 7/20/27 | Bldg 11 9395-275K UPS#1 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| 1264 | Bldg 11 | UPS | Eaton | 9395-275 | ED043BAA06 | 225 | 9/1/09 | 12/1/21 | 16.5% | 5/3/19 | 5/3/24 | 8/14/20 | 8/14/27 | 9/1/09 | NA | 8/14/20 | 8/14/27 | Bldg 11 9395-275K UPS#2 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| 1806 | Bldg 11 | Static Switch | Cyberex | Super Switch | 47544-01-01 | na | 2/9/10 | 12/1/21 | 41.0% | NA | NA | NA | NA | NA | NA | NA | NA | Bldg 11 Cyberex S/S#1 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| 1824 | Bldg 11 | Static Switch | Cyberex | Super Switch | 47544-01-02 | na | 2/9/10 | 12/1/21 | 28.7% | NA | NA | NA | NA | NA | NA | NA | NA | Bldg 11 Cyberex S/S#2 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| 1265 | Bldg 11 | DC PLANT | Northern Telecom | MPR200 | Multiple | 12/1/21 | ?? | 5/12/11 | 5/12/26 | NA | NA | NA | NA | NA | NA | Bldg 11 9395-275K UPS#1 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | ||
| 1267 | Bldg 1BB3 | UPS | Eaton | 9395-450 | ED043BAA04 | 450 | 1/20/10 | 12/1/21 | 11.9% | 2/11/16 | 2/11/21 | 1/20/10 | 1/20/17 | 1/20/10 | 1/20/17 | 1/20/10 | 1/20/17 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |
| 1268 | Bldg 1BB1 | UPS | Eaton | 9395-275 | EF251BAA02 | 225 | 1/1/13 | 12/1/21 | 9.1% | 5/25/17 | 5/25/22 | 1/20/13 | 1/20/20 | 1/20/13 | 1/20/20 | 1/20/13 | 1/20/20 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |
| 1269 | Bldg 1CB1 | UPS | Eaton | 9395-275 | EF251BAA04 | 225 | 1/1/13 | 12/1/21 | 8.3% | 5/3/17 | 5/3/22 | 1/20/13 | 1/20/20 | 1/20/13 | 1/20/20 | 1/20/13 | 1/20/20 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |
| 8016 | Bldg 20 | UPS | Eaton | 9PXM-12kVA | BF12L43101 | 12 | 10/15/21 | 12/1/21 | 28.0% | 10/15/21 | 10/15/24 | NA | NA | NA | NA | 7/13/05 | 2028 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |
| 1273 | Bldg 72 | UPS | Eaton | 9395-450 | ED064BAA08 | 450 | 2/20/10 | 12/1/21 | 11.4% | Str 1 & 3 11/5/2020 Str 2 & 4 5/5/2019 | Str 1 & 3 11/5/2025 Str 2 & 4 5/5/2024 | 11/5/20 | 11/5/27 | 2/20/10 | NA | 11/5/20 | 11/5/27 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |
| 1274 | Bldg 72 | UPS | Liebert | Series 610 | D08L5A0023 | 150 | 12/12/08 | 12/1/21 | 18.2% | 5/7/19 | 5/7/24 | ?? | ?? | 3/27/14 | 3/27/21 | 12/3/18 | 12/3/25 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |
| 2261 | Bldg 72C | UPS | Eaton | 9395-275 | EP031BBA01 | 225 | 2/25/20 | 12/1/21 | * | 2/25/20 | 2/25/25 | 2/25/20 | 2/25/27 | 2/25/20 | NA | 2/25/20 | 2/25/27 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |
| 8075 | Bldg 1C Mezz ASRS | UPS | Eaton | 9PXM-12kVA | BF12M18112 | 12 | 11/5/21 | 12/1/21 | 8.0% | 11/5/21 | 11/5/24 | NA | NA | NA | NA | 2021 | 2028 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |
| 1283 | Bldg 63 | DC PLANT | Mesa Technical | MSR 125 1BC 50F | 7034 | na | 10/1/11 | 12/1/21 | NA | 10/1/11 | 10/1/26 | NA | NA | NA | NA | NA | NA | Bldg 63 Rectifier #1 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| 1284 | Bldg 63 | DC PLANT | Mesa Technical | MSR 125 1BC 50F | 7030 | na | 10/1/11 | 12/1/21 | NA | 10/1/11 | 10/1/26 | NA | NA | NA | NA | NA | NA | Bldg 63 Rectifier #2 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| 1396 | Bldg 12 | UPS | Eaton | 9355-20 | BF145KXX08 | 20 | 12/1/11 | 12/1/21 | 23.9% | 6/16/20 | 6/16/23 | 12/1/11 | 12/1/18 | 12/1/11 | NA | 12/1/11 | 12/1/18 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |
| 1436 | Bldg 50 | UPS | Best Power | Ferrups | EA152FM020 | 12.5 | 1/1/07 | 12/1/21 | 24.8% | 11/5/20 | 11/5/25 | 1/1/07 | 1/1/14 | 1/1/07 | 1/1/14 | 8/1/14 | 8/1/21 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |
| 1535 | Bldg 17 | UPS | Eaton | 9170+M3-B4-9 | BH241T0004 | 6 | 9/12/14 | 12/1/21 | 8.0% | 5/1/19 | 5/1/22 | NA | NA | NA | NA | NA | NA | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |
| 1666 | Bldg 16 | UPS | Eaton | 9355-20 | BF362KXX19 | 20 | 4/1/16 | 12/1/21 | 0.0% | 4/1/16 | 4/1/19 | 4/1/16 | 4/1/23 | 4/1/16 | NA | 4/1/16 | 4/1/23 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |
| 1825 | Bldg 1BB3 | Static Switch | Cyberex | Super Switch | 47544-02-01 | na | 1/20/10 | 12/1/21 | 5.5% | NA | NA | NA | NA | NA | NA | NA | NA | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |
| 1938 | Bldg 5 | UPS | Eaton | 93PM-100 | EK461UXX02 | 100 | 11/22/17 | 12/1/21 | 8.2% | 7/22/16 | 7/22/21 | 7/22/16 | 7/22/23 | 7/22/16 | NA | 7/22/16 | 7/22/23 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |
| 1939 | Bldg 5 | UPS | Eaton | 93PM-100 | EK461UXXO3 | 100 | 11/22/17 | 12/1/21 | 9.3% | 7/22/16 | 7/22/21 | 7/22/16 | 7/22/23 | 7/22/16 | NA | 7/22/16 | 7/22/23 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |
| 1940 | Bldg 5 | Static Switch | Cyberex | Super Switch | E0021016-01 | na | 11/22/17 | 12/1/21 | 14.8% | NA | NA | NA | NA | NA | NA | NA | NA | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |
| 1941 | Bldg 5 | Static Switch | Cyberex | Super Switch | E0021016-02 | na | 11/22/17 | 12/1/21 | 14.3% | NA | NA | NA | NA | NA | NA | NA | NA | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |
| 2168 | Bldg 5 Bay 1 | UPS | Eaton | 93PM-250 | EN311UXX03 | 250 | 11/18/19 | 12/1/21 | 11/18/19 | 11/18/24 | 11/18/19 | 11/18/26 | 11/18/19 | NA | 11/18/19 | 11/18/26 | Bldg 5 Bay 1 UPS A | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |
| 2169 | Bldg 5 Bay 1 | UPS | Eaton | 93PM-250 | EN312UXX01 | 250 | 11/18/19 | 12/1/21 | 11/18/19 | 11/18/24 | 11/18/19 | 11/18/26 | 11/18/19 | NA | 11/18/19 | 11/18/26 | Bldg 5 Bay 1 UPS B | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |
| 2184 | Bldg 5 Bay 1 | Static Switch | PDI | STS-SBR | 442-0217-1B | na | 11/18/19 | 12/1/21 | NA | NA | NA | NA | NA | NA | NA | NA | Bldg 5 Bay 1 S/S A | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |
| 2185 | Bldg 5 Bay 1 | Static Switch | PDI | STS-SBR | 442-0217-2B | na | 11/18/19 | 12/1/21 | NA | NA | NA | NA | NA | NA | NA | NA | Bldg 5 Bay 1 S/S B | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |
| 2175 | Bldg 5 Bay 1 | Distribution Panell | PDI | RPP | na | 11/18/19 | 12/1/21 | NA | NA | NA | NA | NA | NA | NA | NA | Bldg 5 Bay RPP A | Bldg 5 Bay RPP A | Bldg 5 Bay RPP A | Bldg 5 Bay RPP A | ERROR:#VALUE! | ||
| 2176 | Bldg 5 Bay 1 | Distribution Panell | PDI | RPP | na | 11/18/19 | 12/1/21 | NA | NA | NA | NA | NA | NA | NA | NA | Bldg 5 Bay RPP B | Bldg 5 Bay RPP B | Bldg 5 Bay RPP B | Bldg 5 Bay RPP B | ERROR:#VALUE! | ||
| 2177 | Bldg 5 Bay 1 | Distribution Panell | PDI | RPP | na | 11/18/19 | 12/1/21 | NA | NA | NA | NA | NA | NA | NA | NA | Bldg 5 Bay RPP C | Bldg 5 Bay RPP C | Bldg 5 Bay RPP C | Bldg 5 Bay RPP C | ERROR:#VALUE! | ||
| 2178 | Bldg 5 Bay 1 | Distribution Panell | PDI | RPP | na | 11/18/19 | 12/1/21 | NA | NA | NA | NA | NA | NA | NA | NA | Bldg 5 Bay RPP D | Bldg 5 Bay RPP D | Bldg 5 Bay RPP D | Bldg 5 Bay RPP D | ERROR:#VALUE! | ||
| 2179 | Bldg 5 Bay 1 | Distribution Panell | PDI | RPP | na | 11/18/19 | 12/1/21 | NA | NA | NA | NA | NA | NA | NA | NA | Bldg 5 Bay RPP E | Bldg 5 Bay RPP E | Bldg 5 Bay RPP E | Bldg 5 Bay RPP E | ERROR:#VALUE! | ||
| 2180 | Bldg 5 Bay 1 | Distribution Panell | PDI | RPP | na | 11/18/19 | 12/1/21 | NA | NA | NA | NA | NA | NA | NA | NA | Bldg 5 Bay RPP F | Bldg 5 Bay RPP F | Bldg 5 Bay RPP F | Bldg 5 Bay RPP F | ERROR:#VALUE! | ||
| 2181 | Bldg 5 Bay 1 | Distribution Panell | PDI | RPP | na | 11/18/19 | 12/1/21 | NA | NA | NA | NA | NA | NA | NA | NA | Bldg 5 Bay RPP G | Bldg 5 Bay RPP G | Bldg 5 Bay RPP G | Bldg 5 Bay RPP G | ERROR:#VALUE! | ||
| 2182 | Bldg 5 Bay 1 | Distribution Panell | PDI | RPP | na | 11/18/19 | 12/1/21 | NA | NA | NA | NA | NA | NA | NA | NA | Bldg 5 Bay RPP H | Bldg 5 Bay RPP H | Bldg 5 Bay RPP H | Bldg 5 Bay RPP H | ERROR:#VALUE! | ||
| 2183 | Bldg 5 Bay 1 | Distribution Panell | PDI | RPP | na | 11/18/19 | 12/1/21 | NA | NA | NA | NA | NA | NA | NA | NA | Bldg 5 Bay RPP I | Bldg 5 Bay RPP I | Bldg 5 Bay RPP I | Bldg 5 Bay RPP I | ERROR:#VALUE! | ||
| 2322 | DISA-FLT3 | UPS | Eaton | 93E-60/40 | E0021016-02 | 40 | 10/1/16 | 12/1/21 | 10/1/16 | 10/1/19 | 10/1/16 | 10/1/23 | 10/1/16 | * | 10/1/16 | 10/1/23 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | ||
| TOTAL EVALUATED PROPOSED PRICE | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
File details come from the government source that posted it. Updated .