Attachment 2 - Submittal Register 4DEC2020.xlsx
XLSX spreadsheet 36 KB Posted
- Solicitation number
- FA301621B0002
About this file
This submittal register outlines 267 submittal items required for the repair of storm drainage at the Medical Education and Training Campus dormitories in San Antonio, Texas. Key submittals include a schedule of work, safety data sheets, quality control plans, sustainability notebooks, surveys, as-built drawings, product data sheets for plumbing fixtures and water heaters meeting energy efficiency standards, test reports, material certifications, and operation and maintenance manuals. The opportunity is a set-aside for HUBZone small businesses with a value between $500,000 and $1 million requiring compliance with Davis-Bacon prevailing wage rates. Electronic bids are due by the closing date specified in solicitation FA301621B0002 issued by the Department of the Air Force Air Education and Training Command for repairs at Joint Base San Antonio - Fort Sam Houston.
View the file
Other files
Show all 16
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Navy4288
| TITLE: | Repair Storm Drainage METC Dorms | SUBMITTAL REGISTER | ||||||||||||||||
| JOB NAME: | JBSF160208 | |||||||||||||||||
| LOCATION: | FSH | |||||||||||||||||
| CONTRACT NO: | ||||||||||||||||||
| CONTRACTOR: | ||||||||||||||||||
| CONTRACTOR SCHEDULE DATES | CONTRACTOR ACTION | APPROVING AUTHORITY | ||||||||||||||||
| (a) | (b) | (c) | (d) | (e) | (f) | (g) | (h) | (i) | (j) | (k) | (l) | (m) | (n) | (o) | (p) | (q) | (r) |
| Line | Activity # | Transmittal # | Specification Section | SD # | Submittal Description | Item Submitted | Paragraph # | Classification: GOVT or A/E Reviewer | Submit | Approval Needed By | Material Needed By | Action Code | Date Of Action | Date FWD to APPR / Auth Date RCD From CONTR | Date FWD To Other Revwr | Date RCD From Other Reviewer | Action Code | Date Of Action | Mailed To CONTR/ Date RCD From APPR Authority | Remarks |
| 1 | 01 11 00 | 1 | Preconstruction Submittals | Schedule Of Work; G | ||||||||||||||||
| 2 | 01 11 00 | 1 | Preconstruction Submittals | Existing Conditions | G | |||||||||||||||
| 3 | 01 11 00 | 1 | Preconstruction Submittals | Permits | ||||||||||||||||
| 4 | 01 11 00 | 1 | Preconstruction Submittals | Shop Drawings | G | |||||||||||||||
| 5 | 01 11 00 | 1 | Preconstruction Submittals | Laboratory Testing Results | 2.2 | G | ||||||||||||||
| 6 | 01 11 00 | 3 | Product Data | Safety Data Sheet | 3.1.5 | G | ||||||||||||||
| 7 | 01 11 00 | 6 | Test Reports | Quality Control | G | |||||||||||||||
| 8 | 01 11 00 | 6 | Test Reports | Accident Prevention Plan | G | |||||||||||||||
| 9 | 01 14 00 | 1 | Preconstruction Submittals | list of Contract Personnel | 1.4.1.1 | G | ||||||||||||||
| 10 | 01 14 00 | 1 | Preconstruction Submittals | Installation Access | 1.4.1.2 | |||||||||||||||
| 11 | 01 30 00 | 1 | Preconstruction Submittals | View Location Map | 1.3 | G | ||||||||||||||
| 12 | 01 30 00 | 1 | Preconstruction Submittals | Progress and Completion Pictures | 1.4 | G | ||||||||||||||
| 13 | 01 32 01.00 10 | 1 | Preconstruction Submittals | Project Schedule CPM | G | |||||||||||||||
| 14 | 01 32 16.00 20 | 1 | Preconstruction Submittals | Construction Schedule | 1.2 | G | ||||||||||||||
| 15 | 01 32 16.00 20 | 7 | Certificates | Monthly Updates | 1.4 | |||||||||||||||
| 16 | 01 33 00 | 1 | Preconstruction Submittals | Submittal Register | 1.7 | G | ||||||||||||||
| 17 | 01 33 29 | 1 | Preconstruction Submittals | Preliminary Sustainability Notebook | G | |||||||||||||||
| 18 | 01 33 29 | 1 | Preconstruction Submittals | Preliminary High Performance and Sustainable Building Checklist | ||||||||||||||||
| 19 | 01 33 29 | 7 | Certificates | Third Party Certification (TPC) | 1.4.5 | |||||||||||||||
| 20 | 01 33 29 | 11 | Closeout Submittals | Final Sustainability Notebook | G | |||||||||||||||
| 21 | 01 33 29 | 11 | Closeout Submittals | Final High Performance and Sustainable Building Checklist | G | |||||||||||||||
| 22 | 01 33 29 | 11 | Closeout Submittals | Amended Final Sustainability Notebook | G | |||||||||||||||
| 23 | 01 33 29 | 11 | Closeout Submittals | Third Party Certification Plaque and Certificates | 3.2.1 | G | ||||||||||||||
| 24 | 01 35 13.30 00 | 1 | Preconstruction Submittals | Digital Photos | ||||||||||||||||
| 25 | 01 35 13.30 00 | 2 | Shop Drawings | Surveys | ||||||||||||||||
| 26 | 01 35 13.30 00 | 2 | Shop Drawings | File Geodatabase | ||||||||||||||||
| 27 | 01 35 13.30 00 | 2 | Shop Drawings | Maps | ||||||||||||||||
| 28 | 01 35 26 | 1 | Preconstruction Submittals | Accident Prevention Plan (APP) | 1.6 | G | ||||||||||||||
| 29 | 01 35 26 | 7 | Certificates | Certificate of Compliance | 1.11.3 | |||||||||||||||
| 30 | 01 35 26 | 7 | Certificates | License Certificates | ||||||||||||||||
| 31 | 01 35 29 | 1 | Preconstruction Submittals | Accident Prevention Plan (APP) | 1.5 | |||||||||||||||
| 32 | 01 35 29 | 1 | Preconstruction Submittals | GA | ||||||||||||||||
| 33 | 01 35 29 | 1 | Preconstruction Submittals | Asbestos Hazard Abatement Plan (for description see spec section 13280); GA | ||||||||||||||||
| 34 | 01 35 29 | 1 | Preconstruction Submittals | Lead Hazard Control Plan (for description see spec section 13281); GA. | ||||||||||||||||
| 35 | 01 35 29 | 1 | Preconstruction Submittals | Activity Hazard Analysis (AHA) | 1.6 | G | ||||||||||||||
| 36 | 01 35 29 | 1 | Preconstruction Submittals | Crane Critical Lift Plan | G | |||||||||||||||
| 37 | 01 35 29 | 1 | Preconstruction Submittals | Crane Operators | G | |||||||||||||||
| 38 | 01 35 29 | 6 | Test Reports | Accident Reports | G | |||||||||||||||
| 39 | 01 35 29 | 6 | Test Reports | Crane Reports | ||||||||||||||||
| 40 | 01 35 29 | 6 | Test Reports | GA | ||||||||||||||||
| 41 | 01 35 29 | 6 | Test Reports | Monthly Exposure Reports | ||||||||||||||||
| 42 | 01 35 29 | 6 | Test Reports | Regulatory Citations and Violations | ||||||||||||||||
| 43 | 01 35 29 | 7 | Certificates | Confined Space Entry Permit | ||||||||||||||||
| 44 | 01 35 29 | 7 | Certificates | Hot work permit | ||||||||||||||||
| 45 | 01 35 30 | 8 | Manufacturer’s Instructions | Site Safety and Health Plan | G | |||||||||||||||
| 46 | 01 35 30 | 9 | Manufacturer’s Field Reports | Safety and Health Phase-Out Report | G | |||||||||||||||
| 47 | 01 45 00.00 10 | 1 | Preconstruction Submittals | Contractor Quality Control (CQC) Plan | 3.2 | G | ||||||||||||||
| 48 | 01 45 00.00 20 | 1 | Preconstruction Submittals | Contractor Quality Control (CQC) Plan | G | |||||||||||||||
| 49 | 01 50 00 | 1 | Preconstruction Submittals | Construction Site Plan | 1.3 | G | ||||||||||||||
| 50 | 01 50 00 | 1 | Preconstruction Submittals | Traffic Control Plan | G | |||||||||||||||
| 51 | 01 50 00 | 6 | Test Reports | Backflow Preventer Tests | ||||||||||||||||
| 52 | 01 50 00 | 7 | Certificates | Backflow Tester | ||||||||||||||||
| 53 | 01 50 00 | 7 | Certificates | Backflow Preventers | 1.4 | |||||||||||||||
| 54 | 01 57 20 | 1 | Preconstruction Submittals | ENVIRONMENTAL PROTECTION PLAN | 1.6 | |||||||||||||||
| 55 | 01 57 20 | 1 | Preconstruction Submittals | ENVIRONMENTAL PROTECTION PLAN | 3.16 | |||||||||||||||
| 56 | 01 57 20 | 1 | Preconstruction Submittals | G Fish and Wildlife Protection Measures as applicable; G Environmental Permits as applicable; G | ||||||||||||||||
| 57 | 01 57 20 | 1 | Preconstruction Submittals | Equipment Inventory | 3.7.2 | |||||||||||||||
| 58 | 01 57 20 | 2 | Shop Drawings | Asbestos Work Plans | G | |||||||||||||||
| 59 | 01 57 20 | 2 | Shop Drawings | Asbestos Certifications | G | |||||||||||||||
| 60 | 01 57 20 | 2 | Shop Drawings | Asbestos Transporter License | G | |||||||||||||||
| 61 | 01 57 20 | 2 | Shop Drawings | Asbestos Medical clearances (may be reviewed on site) | G | |||||||||||||||
| 62 | 01 57 20 | 2 | Shop Drawings | Asbestos Training Certificates | G | |||||||||||||||
| 63 | 01 57 20 | 2 | Shop Drawings | Asbestos TDSHS License as applicable | G | |||||||||||||||
| 64 | 01 57 20 | 2 | Shop Drawings | Any Asbestos Inspection reports that have not been provided by the area specific Environmental Office. | G | |||||||||||||||
| 65 | 01 57 20 | 2 | Shop Drawings | Any Asbestos Inspection Reports that were not included in the original assessment or a results to a change in the scope of work. | ||||||||||||||||
| 66 | 01 57 20 | 2 | Shop Drawings | G Unsigned copy of State Renovation, Demolition Notifications 15 days prior; G | ||||||||||||||||
| 67 | 01 57 20 | 2 | Shop Drawings | Lead Work Plans | G | |||||||||||||||
| 68 | 01 57 20 | 2 | Shop Drawings | Lead Occupant Protection Plan. | G | |||||||||||||||
| 69 | 01 57 20 | 2 | Shop Drawings | Texas Department of State Health Services Lead Licenses | G | |||||||||||||||
| 70 | 01 57 20 | 2 | Shop Drawings | Lead Notifications | G | |||||||||||||||
| 71 | 01 57 20 | 2 | Shop Drawings | Lead Training Certificates | G | |||||||||||||||
| 72 | 01 57 20 | 2 | Shop Drawings | Lead Based Paint Reports | G | |||||||||||||||
| 73 | 01 57 20 | 2 | Shop Drawings | Lead Inspection reports | G | |||||||||||||||
| 74 | 01 57 20 | 3 | Product Data | Asbestos Air Monitoring reports | G | |||||||||||||||
| 75 | 01 57 20 | 3 | Product Data | Lead Air Monitoring reports | G | |||||||||||||||
| 76 | 01 57 20 | 4 | Samples | Lead OSHA Negative Exposure Assessment or | G | |||||||||||||||
| 77 | 01 57 20 | 4 | Samples | Lead Work Plan. | G | |||||||||||||||
| 78 | 01 57 20 | 4 | Samples | EPA Lead Training | ||||||||||||||||
| 79 | 01 57 20 | 4 | Samples | Lead Awareness Training certificates | G | |||||||||||||||
| 80 | 01 57 20 | 4 | Samples | OSHA Air Monitoring | G | |||||||||||||||
| 81 | 01 57 20 | 4 | Samples | Lead Training Certificates | G | |||||||||||||||
| 82 | 01 57 20 | 4 | Samples | Waste Disposal Plan, May be included in work plan | G | |||||||||||||||
| 83 | 01 57 20 | 4 | Samples | Lead Inspection reports | G | |||||||||||||||
| 84 | 01 57 20 | 4 | Samples | Lead Based Paint Reports | G | |||||||||||||||
| 85 | 01 57 20 | 6 | Test Reports | Analytical Results | 3.1.4.1 | G | ||||||||||||||
| 86 | 01 78 00 | 1 | Preconstruction Submittals | As-Built Drawings | G | |||||||||||||||
| 87 | 01 78 00 | 2 | Shop Drawings | As-Built Record of Materials | ||||||||||||||||
| 88 | 01 78 00 | 2 | Shop Drawings | FIO | ||||||||||||||||
| 89 | 01 78 00 | 3 | Product Data | Warranty Management Plan | 1.4.1 | G | ||||||||||||||
| 90 | 01 78 00 | 4 | Samples | Warranty Tags | G | |||||||||||||||
| 91 | 02 32 00 | 2 | Shop Drawings | Drilling Log | 3.12 | G | ||||||||||||||
| 92 | 02 32 00 | 3 | Product Data | Permits, Certifications, and Licenses | 1.5 | |||||||||||||||
| 93 | 02 32 00 | 3 | Product Data | Schedule of Drilling, Sampling, and Testing | 1.3.7.1 | G | ||||||||||||||
| 94 | 02 41 00 | 1 | Preconstruction Submittals | Existing Conditions | 1.1 | |||||||||||||||
| 95 | 02 41 00 | 7 | Certificates | Demolition Plan | 1.2.1 | G | ||||||||||||||
| 96 | 02 41 00 | 7 | Certificates | Notification | G | |||||||||||||||
| 97 | 02 41 00 | 11 | Closeout Submittals | Receipts | ||||||||||||||||
| 98 | 02 61 13 | 2 | Shop Drawings | Surveys | 3.1 | |||||||||||||||
| 99 | 02 61 13 | 3 | Product Data | Work Plan | G | |||||||||||||||
| 100 | 02 61 13 | 3 | Product Data | Closure Report | 3.11 | G | ||||||||||||||
| 101 | 02 61 13 | 6 | Test Reports | Backfill | 2.2 | |||||||||||||||
| 102 | 02 61 13 | 6 | Test Reports | Confirmation Sampling and Analysis | 3.5 | |||||||||||||||
| 103 | 02 61 13 | 6 | Test Reports | Sampling of Stored Material | 3.7.1 | |||||||||||||||
| 104 | 02 61 13 | 6 | Test Reports | G] | ||||||||||||||||
| 105 | 02 61 13 | 6 | Test Reports | Sampling Liquid | 3.7.2 | G | ||||||||||||||
| 106 | 02 61 13 | 6 | Test Reports | Compaction | 3.9.2 | |||||||||||||||
| 107 | 02 81 00 | 3 | Product Data | Onsite Hazardous Waste Management | 3.1 | G | ||||||||||||||
| 108 | 02 81 00 | 3 | Product Data | Notices of Non-Compliance and Notices of Violation | 3.2 | |||||||||||||||
| 109 | 02 81 00 | 3 | Product Data | Packaging Notifications | 2.1.1 | |||||||||||||||
| 110 | 02 81 00 | 6 | Test Reports | Recordkeeping | 3.7 | G | ||||||||||||||
| 111 | 02 81 00 | 6 | Test Reports | Spill Response | 3.8 | |||||||||||||||
| 112 | 02 81 00 | 6 | Test Reports | Exception Report | 3.7 | G | ||||||||||||||
| 113 | 02 81 00 | 7 | Certificates | Certification | 1.4.3 | |||||||||||||||
| 114 | 02 81 00 | 7 | Certificates | Security Plan | 3.2.4 | |||||||||||||||
| 115 | 02 81 00 | 7 | Certificates | Transportation and Disposal Coordinator | 1.4.1 | G | ||||||||||||||
| 116 | 02 81 00 | 7 | Certificates | Training | 1.4.2 | G | ||||||||||||||
| 117 | 02 81 00 | 7 | Certificates | EPA Offsite Policy | 3.2.2 | |||||||||||||||
| 118 | 02 81 00 | 7 | Certificates | Certificates of Disposal | 3.2.5 | |||||||||||||||
| 119 | 02 81 00 | 7 | Certificates | Shipping Documents and Packagings Certification | 3.2.3 | G | ||||||||||||||
| 120 | 02 81 00 | 7 | Certificates | Waste Minimization | 3.6 | |||||||||||||||
| 121 | 22 00 00 | 2 | Shop Drawings | Plumbing System | 3.9.1 | G | ||||||||||||||
| 122 | 22 00 00 | 3 | Product Data | Recycled Content for Steel Pipe | S | |||||||||||||||
| 123 | 22 00 00 | 3 | Product Data | Fixtures | 2.4 | |||||||||||||||
| 124 | 22 00 00 | 3 | Product Data | Flush Valve Water Closets | 2.4.2 | |||||||||||||||
| 125 | 22 00 00 | 3 | Product Data | WaterSense Label for Flush Valve Water Closet | 2.4.2 | S | ||||||||||||||
| 126 | 22 00 00 | 3 | Product Data | Flush Valve Urinals | 2.4.3 | |||||||||||||||
| 127 | 22 00 00 | 3 | Product Data | WaterSense Label for Urinal | 2.4.3 | S | ||||||||||||||
| 128 | 22 00 00 | 3 | Product Data | Flush Tank Water Closets | 2.4.5 | |||||||||||||||
| 129 | 22 00 00 | 3 | Product Data | WaterSense Label for Flush Tank Water Closet | 2.4.5 | S | ||||||||||||||
| 130 | 22 00 00 | 3 | Product Data | Wall Hung Lavatories | 2.4.7 | |||||||||||||||
| 131 | 22 00 00 | 3 | Product Data | Countertop Lavatories | 2.4.8 | |||||||||||||||
| 132 | 22 00 00 | 3 | Product Data | WaterSense Label for Lavatory Faucet | S | |||||||||||||||
| 133 | 22 00 00 | 3 | Product Data | Kitchen Sinks | 2.4.9 | |||||||||||||||
| 134 | 22 00 00 | 3 | Product Data | Service Sinks | 2.4.10 | |||||||||||||||
| 135 | 22 00 00 | 3 | Product Data | Drinking-Water Coolers | 2.4.11 | G | ||||||||||||||
| 136 | 22 00 00 | 3 | Product Data | Energy Star Label for Electric Water Cooler | 2.4.11 | S | ||||||||||||||
| 137 | 22 00 00 | 3 | Product Data | Energy Star Label for Wheelchair Electric Water Cooler | 2.4.12 | S | ||||||||||||||
| 138 | 22 00 00 | 3 | Product Data | Plastic Bathtubs | ||||||||||||||||
| 139 | 22 00 00 | 3 | Product Data | Plastic Shower Stalls | ||||||||||||||||
| 140 | 22 00 00 | 3 | Product Data | WaterSense Label for Showerhead | 2.6.2 | S | ||||||||||||||
| 141 | 22 00 00 | 3 | Product Data | Plastic Bathtub Liners | ||||||||||||||||
| 142 | 22 00 00 | 3 | Product Data | Plastic Bathtub Wall Surrounds | ||||||||||||||||
| 143 | 22 00 00 | 3 | Product Data | Water Heaters | 2.1 | G | ||||||||||||||
| 144 | 22 00 00 | 3 | Product Data | Energy Star Label for Gas Storage Water Heater | S | |||||||||||||||
| 145 | 22 00 00 | 3 | Product Data | Energy Star Label for Gas Instantaneous Water Heater | 2.10.2 | S | ||||||||||||||
| 146 | 22 00 00 | 3 | Product Data | Pumps | 2.12 | G | ||||||||||||||
| 147 | 22 00 00 | 3 | Product Data | Backflow Prevention Assemblies | 3.9.1.1 | G | ||||||||||||||
| 148 | 22 00 00 | 3 | Product Data | Vibration-Absorbing Features | 3.4 | G | ||||||||||||||
| 149 | 22 00 00 | 6 | Test Reports | Tests, Flushing and Disinfection | 3.9 | |||||||||||||||
| 150 | 22 00 00 | 6 | Test Reports | Test of Backflow Prevention Assemblies | 3.9.1.1 | G | ||||||||||||||
| 151 | 22 00 00 | 7 | Certificates | Materials and Equipment | 1.3 | |||||||||||||||
| 152 | 22 00 00 | 7 | Certificates | Bolts | 2.1.1 | |||||||||||||||
| 153 | 22 00 00 | 10 | Operation and Maintenance Data | Plumbing System | 3.9.1 | G | ||||||||||||||
| 154 | 31 00 00 | 1 | Preconstruction Submittals | Shoring | G | |||||||||||||||
| 155 | 31 00 00 | 1 | Preconstruction Submittals | Dewatering Work Plan | G | |||||||||||||||
| 156 | 31 00 00 | 3 | Product Data | Utilization of Excavated Materials | 3.6 | G | ||||||||||||||
| 157 | 31 00 00 | 3 | Product Data | Rock Excavation | ||||||||||||||||
| 158 | 31 00 00 | 3 | Product Data | Opening of any Excavation or Borrow Pit | 3.2 | |||||||||||||||
| 159 | 31 00 00 | 3 | Product Data | Shoulder Construction | ||||||||||||||||
| 160 | 31 00 00 | 6 | Test Reports | Testing | 3.11 | |||||||||||||||
| 161 | 31 00 00 | 6 | Test Reports | Borrow Site Testing | 2.1 | |||||||||||||||
| 162 | 31 00 00 | 7 | Certificates | Testing | 3.11 | |||||||||||||||
| 163 | 31 05 21 | 2 | Shop Drawings | Installation | 3.1 | G | ||||||||||||||
| 164 | 31 05 21 | 3 | Product Data | Allowable Strength | 2.1.1.1 | |||||||||||||||
| 165 | 31 05 21 | 3 | Product Data | Manufacturer | 1.4 | |||||||||||||||
| 166 | 31 05 21 | 4 | Samples | Geogrid Reinforcement | 2.1 | |||||||||||||||
| 167 | 31 05 21 | 6 | Test Reports | Geogrid Reinforcement | 2.1 | |||||||||||||||
| 168 | 31 05 21 | 6 | Test Reports | Coefficient of Interaction | 2.1.1 | |||||||||||||||
| 169 | 31 05 21 | 6 | Test Reports | Interface Friction Testing | 2.1.1.2 | |||||||||||||||
| 170 | 31 05 21 | 6 | Test Reports | Splices | 3.1.5 | |||||||||||||||
| 171 | 31 05 21 | 6 | Test Reports | Conformance Testing | 3.4 | |||||||||||||||
| 172 | 31 05 21 | 7 | Certificates | Certificates of Compliance | 2.1 | |||||||||||||||
| 173 | 31 11 00 | 1 | Preconstruction Submittals | Herbicide Application Plan | 3.1.1 | |||||||||||||||
| 174 | 31 11 00 | 3 | Product Data | Tree Wound Paint | 2.1.1 | |||||||||||||||
| 175 | 31 11 00 | 3 | Product Data | Herbicides | 1.3.2 | G | ||||||||||||||
| 176 | 31 11 00 | 7 | Certificates | Qualifications | 1.3.2 | G | ||||||||||||||
| 177 | 31 11 00 | 11 | Closeout Submittals | Pest Management Report | 3.5.1 | |||||||||||||||
| 178 | 31 23 00.00 20 | 1 | Preconstruction Submittals | Shoring and Sheeting Plan | 1.7.1 | |||||||||||||||
| 179 | 31 23 00.00 20 | 1 | Preconstruction Submittals | Dewatering work plan | 1.7.2 | |||||||||||||||
| 180 | 31 23 00.00 20 | 1 | Preconstruction Submittals | Blasting | 1.5 | |||||||||||||||
| 181 | 31 23 00.00 20 | 6 | Test Reports | Borrow Site Testing | 1.6 | G | ||||||||||||||
| 182 | 31 23 00.00 20 | 6 | Test Reports | Fill and backfill | 3.17.2.1 | |||||||||||||||
| 183 | 31 23 00.00 20 | 6 | Test Reports | Select material | 3.17.2.2 | |||||||||||||||
| 184 | 31 23 00.00 20 | 6 | Test Reports | Porous fill | 3.17.2.3 | |||||||||||||||
| 185 | 31 23 00.00 20 | 6 | Test Reports | Density tests | 3.17.2.4 | |||||||||||||||
| 186 | 31 23 00.00 20 | 6 | Test Reports | Moisture Content Tests | 3.17.2.5 | |||||||||||||||
| 187 | 32 11 23 | 3 | Product Data | Plant, Equipment, and Tools | 1.5 | G | ||||||||||||||
| 188 | 32 11 23 | 3 | Product Data | Waybills and Delivery Tickets | 1.1.3 | |||||||||||||||
| 189 | 32 11 23 | 6 | Test Reports | Initial Tests | 2.3.1 | G | ||||||||||||||
| 190 | 32 11 23 | 6 | Test Reports | In-Place Tests | 3.13.1 | G | ||||||||||||||
| 191 | 32 31 13 | 2 | Shop Drawings | Fence Assembly | 2.1 | G | ||||||||||||||
| 192 | 32 31 13 | 2 | Shop Drawings | Location of Gate, Corner, End, and Pull Posts | 3.2.2.1 | G | ||||||||||||||
| 193 | 32 31 13 | 2 | Shop Drawings | Gate Assembly | 2.1 | G | ||||||||||||||
| 194 | 32 31 13 | 2 | Shop Drawings | Gate Hardware and Accessories | 2.2.13 | G | ||||||||||||||
| 195 | 32 31 13 | 2 | Shop Drawings | Erection/Installation Drawings | Part 3 | G | ||||||||||||||
| 196 | 32 31 13 | 3 | Product Data | Fence Assembly | 2.1 | G | ||||||||||||||
| 197 | 32 31 13 | 3 | Product Data | Concrete | 2.3.3 | G | ||||||||||||||
| 198 | 32 31 13 | 7 | Certificates | Certificates of Compliance | 1.3.1 | |||||||||||||||
| 199 | 32 31 13 | 8 | Manufacturer’s Instructions | Fence Assembly | 2.1 | |||||||||||||||
| 200 | 32 31 13 | 8 | Manufacturer’s Instructions | Hardware Assembly | 2.1 | |||||||||||||||
| 201 | 32 31 13 | 8 | Manufacturer’s Instructions | Accessories | 2.1 | |||||||||||||||
| 202 | 32 92 19 | 3 | Product Data | Wood Cellulose Fiber Mulch | 2.5.3 | |||||||||||||||
| 203 | 32 92 19 | 3 | Product Data | Fertilizer | 2.4 | |||||||||||||||
| 204 | 32 92 19 | 6 | Test Reports | Topsoil Composition Tests | 2.2.3 | |||||||||||||||
| 205 | 32 92 19 | 7 | Certificates | Seed | 2.1 | |||||||||||||||
| 206 | 32 92 19 | 8 | Manufacturer’s Instructions | Erosion Control Materials | 2.7 | |||||||||||||||
| 207 | 33 11 00.00 01 | 1 | Preconstruction Submittals | Connections | 3.1.1 | G | ||||||||||||||
| 208 | 33 11 00.00 01 | 3 | Product Data | Pipe, Fittings, Joints and Couplings | 2.1.1 | G | ||||||||||||||
| 209 | 33 11 00.00 01 | 3 | Product Data | Ball And Socket Joint | 2.1.1.6.3.1 | G | ||||||||||||||
| 210 | 33 11 00.00 01 | 3 | Product Data | Valves | 2.1.2 | G | ||||||||||||||
| 211 | 33 11 00.00 01 | 3 | Product Data | Valve Boxes | 2.1.2.8 | G | ||||||||||||||
| 212 | 33 11 00.00 01 | 3 | Product Data | Fire Hydrants | 2.1.4.1 | G | ||||||||||||||
| 213 | 33 11 00.00 01 | 3 | Product Data | Pipe Restraint | 2.2.1 | G | ||||||||||||||
| 214 | 33 11 00.00 01 | 3 | Product Data | Tapping Sleeves | 2.2.3 | G | ||||||||||||||
| 215 | 33 11 00.00 01 | 3 | Product Data | Corporation Stops | 2.2.9.1 | G | ||||||||||||||
| 216 | 33 11 00.00 01 | 3 | Product Data | Backflow Preventer | 1.5.2.1.1 | G | ||||||||||||||
| 217 | 33 11 00.00 01 | 3 | Product Data | Railroad Crossing Casing Pipe | 2.1.1.7 | G | ||||||||||||||
| 218 | 33 11 00.00 01 | 3 | Product Data | Precast Concrete Thrust Blocks | 2.2.1.2 | G | ||||||||||||||
| 219 | 33 11 00.00 01 | 3 | Product Data | Disinfection Procedures | 3.2.5 | G | ||||||||||||||
| 220 | 33 11 00.00 01 | 6 | Test Reports | Backflow Preventer Tests | 3.3.1.4 | G | ||||||||||||||
| 221 | 33 11 00.00 01 | 6 | Test Reports | Bacteriological Samples | 3.3.1.3 | G | ||||||||||||||
| 222 | 33 11 00.00 01 | 6 | Test Reports | Post-Construction Fusion Report | 3.2.1.9.1 | G | ||||||||||||||
| 223 | 33 11 00.00 01 | 6 | Test Reports | Leakage Test | 3.3.1.2 | |||||||||||||||
| 224 | 33 11 00.00 01 | 6 | Test Reports | Hydrostatic Test | 3.3.1.1 | |||||||||||||||
| 225 | 33 11 00.00 01 | 7 | Certificates | Pipe, Fittings, Joints and Couplings | 2.1.1 | |||||||||||||||
| 226 | 33 11 00.00 01 | 7 | Certificates | Lining | ||||||||||||||||
| 227 | 33 11 00.00 01 | 7 | Certificates | Lining for Fittings | 2.1.1.1.1.3 | |||||||||||||||
| 228 | 33 11 00.00 01 | 7 | Certificates | Valves | 2.1.2 | |||||||||||||||
| 229 | 33 11 00.00 01 | 7 | Certificates | Fire Hydrants | 2.1.4.1 | |||||||||||||||
| 230 | 33 11 00.00 01 | 7 | Certificates | Backflow Prevention Training Certificate | 1.5.2.1.1.1 | |||||||||||||||
| 231 | 33 11 00.00 01 | 7 | Certificates | Backflow Tester | ||||||||||||||||
| 232 | 33 11 00.00 01 | 7 | Certificates | Fusion Technician Qualifications | 1.5.2.2 | G | ||||||||||||||
| 233 | 33 11 00.00 01 | 7 | Certificates | Turbine Type Meters | 2.1.5.1 | |||||||||||||||
| 234 | 33 11 00.00 01 | 7 | Certificates | Propeller Type Meters | 2.1.5.2 | |||||||||||||||
| 235 | 33 11 00.00 01 | 7 | Certificates | Displacement Type Meters | 2.1.5.3 | |||||||||||||||
| 236 | 33 11 00.00 01 | 7 | Certificates | Compound Type Meters | 2.1.5.4 | |||||||||||||||
| 237 | 33 11 00.00 01 | 7 | Certificates | Fire Service Type Meters | 2.1.5.5 | |||||||||||||||
| 238 | 33 11 00.00 01 | 7 | Certificates | Backflow Certificate | 2.1.6 | |||||||||||||||
| 239 | 33 11 00.00 01 | 8 | Manufacturer’s Instructions | Ductile Iron Piping | ||||||||||||||||
| 240 | 33 11 00.00 01 | 8 | Manufacturer’s Instructions | PVC Piping | 2.1.1.1.1.1 | |||||||||||||||
| 241 | 33 11 00.00 01 | 8 | Manufacturer’s Instructions | PVCO Piping | 2.1.1.1.1.2 | |||||||||||||||
| 242 | 33 11 00.00 01 | 8 | Manufacturer’s Instructions | Polyethylene (PE) Pipe | 2.1.1.1.3 | |||||||||||||||
| 243 | 33 11 00.00 01 | 8 | Manufacturer’s Instructions | Fiberglass Pipe, Fittings, Joints And Joint Materials | 2.1.1.2 | |||||||||||||||
| 244 | 33 11 00.00 01 | 8 | Manufacturer’s Instructions | Concrete Pressure Pipe | ||||||||||||||||
| 245 | 33 11 00.00 01 | 8 | Manufacturer’s Instructions | Prestressed Concrete Pressure Pipe | ||||||||||||||||
| 246 | 33 11 00.00 01 | 8 | Manufacturer’s Instructions | Reinforced Concrete Cylinder Pipe | ||||||||||||||||
| 247 | 33 11 00.00 01 | 8 | Manufacturer’s Instructions | PVC Piping For Service Lines | 2.1.1.1.2 | |||||||||||||||
| 248 | 33 11 00.00 01 | 8 | Manufacturer’s Instructions | Copper Pipe For Service Lines | 2.1.1.5 | |||||||||||||||
| 249 | 33 30 00 | 1 | Preconstruction Submittals | Contractor's License | 1.3.1 | G | ||||||||||||||
| 250 | 33 30 00 | 2 | Shop Drawings | Installation Drawings | 3.1.1 | G | ||||||||||||||
| 251 | 33 30 00 | 3 | Product Data | Precast Concrete Manholes | 2.2.7 | |||||||||||||||
| 252 | 33 30 00 | 3 | Product Data | Frames, Covers, and Gratings | 2.2.14 | |||||||||||||||
| 253 | 33 30 00 | 3 | Product Data | Gravity Pipe | 2.2.1 | |||||||||||||||
| 254 | 33 30 00 | 3 | Product Data | Pressure Pipe | 2.2.2 | |||||||||||||||
| 255 | 33 30 00 | 3 | Product Data | Precast Concrete Septic Tanks | G | |||||||||||||||
| 256 | 33 30 00 | 6 | Test Reports | Precast Concrete Sewer Manhole Test | G | |||||||||||||||
| 257 | 33 30 00 | 6 | Test Reports | Hydrostatic Sewer Test | G | |||||||||||||||
| 258 | 33 30 00 | 6 | Test Reports | Infiltration Tests And Exfiltration Tests | G | |||||||||||||||
| 259 | 33 30 00 | 6 | Test Reports | Negative Air Pressure Test | G | |||||||||||||||
| 260 | 33 30 00 | 6 | Test Reports | Low-Pressure Air Tests | G | |||||||||||||||
| 261 | 33 30 00 | 6 | Test Reports | Tests For Pressure Lines | G | |||||||||||||||
| 262 | 33 30 00 | 6 | Test Reports | Deflection Testing | ||||||||||||||||
| 263 | 33 30 00 | 6 | Test Reports | Concrete Pipe Test | G | |||||||||||||||
| 264 | 33 30 00 | 7 | Certificates | Portland Cement | 2.2.5 | |||||||||||||||
| 265 | 33 30 00 | 7 | Certificates | Gaskets | 2.2.1.2.2 | |||||||||||||||
| 266 | 33 30 00 | 7 | Certificates | Pre-Installation Inspection Request | G | |||||||||||||||
| 267 | 33 30 00 | 7 | Certificates | Post-Installation Inspection | G | |||||||||||||||
| 11/16/20 10:33 |