Attachment 2 - Statement of Work.pdf
PDF 1 MB Posted
- Solicitation number
- 1240LT26Q0037
- Issued by
-
Department of Agriculture Forest Service
About this file
This is a Statement of Work (SOW) from the U.S. Department of Agriculture (USDA) Forest Service for the Hill City Shop Door Replacement project located at the Hill City Equipment Depot in Hill City, South Dakota. The project involves the removal and replacement of three door and window assemblies at a 10,604 gross square foot timber-framed building constructed in 1937. Specifically, the contractor must replace two steel personnel doors on the south and east sides of the building and one door-window assembly on the west (front) side, including all associated frames, thresholds, hardware, and accessories. The contractor is responsible for supplying all labor, materials, equipment, miscellaneous items, freight, and delivery. The building is occupied year-round and located at an elevation of approximately 5,015 feet above mean sea level at 24030 Highway 385, Hill City, SD 57745.
The contractor must demonstrate expertise in steel door installation, carpentry, and general contracting with strong communication and project management skills. Key deliverables include an Accident Prevention Plan due 10 days prior to on-site work; Product Data and Shop Drawings due 10 days before incorporation into work; Requests for Information submitted as needed; a Construction Schedule due 10 days before on-site work begins with monthly updates; Quality Control submittals as specified; and Operation and Maintenance data in digital format due within 30 days following receipt of review comments. The contractor must provide a company executive contact and maintain an on-site superintendent at all times. Security requirements include installing protective barriers to protect the public, employees, facilities, and surrounding areas, with site gate lockout procedures established if applicable. Travel expenses are the contractor's responsibility with no reimbursement from the U.S. Forest Service. Contract Specifications and Construction Plans are provided as attachments to the solicitation.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
US Department of Agriculture (USDA)
Statement of Work Project Title: Hill City Shop Door Replacement, Black Hills National Forest, South Dakota
Date: December 4, 2025
Contents Project General Information
1.0 Scope of Work
2.0 Background
Contractor Requirements
3.0 Technical Requirements / Tasks
4.0 Government Furnished
5.0 Deliverables / Schedule
6.0 Travel
7.0 Contractor’s Key Personnel
8.0 Security Requirements
9.0 Data Rights
10.0 Section 508 – Electronic and Information Technology Standards
Attachments
Project Hill City Shop Door Replacement, Black Hills National Forest, South Dakota
General Information
1.0 Scope of Work
Work for this project requires the contractor to be responsible for supplying all labor, materials, equipment, miscellaneous items, freight and delivery for the removal and replacement of two steel personnel doors and associated frames, thresholds, hardware and accessories. The removal of wood door and window assembly and replacement with new steel door and window assembly including but not limited to frames, thresholds, hardware and accessories.
The doors to be replaced are personnel doors on the south and east side of the building, and a door-window assembly on the west (front) side of the building. A second door/window assembly on the west side is not included in this project.
2.0 Background
This project is located at the Hill City Equipment Depot, commonly called the Hill City Shop, in Hill City, Pennington County, South Dakota. The 10,604 gross square foot timber-framed building was constructed in 1937. The doors and windows were replaced in the early 1960s. The building is an occupied Government building that is used all year. The project site is open year around.
The address of the Hill City Shop is 24030 Highway 385, Hill City, SD 57745 The elevation of the site is approximately 5,015 feet above mean sea level.
Contractor Requirements
3.0 Technical Requirements / Tasks
Contractors should demonstrate a thorough understanding of the project requirements and attention to detail is crucial for quality construction. Strong communication skills are essential for coordinating with clients, subcontractors and other stakeholders. Past experience in steel door installation, carpentry, and general contracting is beneficial.
Contractors should have the capacity to handle the specific project requirements and deliver within the specified timeline.
A full copy of the Contract Specifications can be found with this solicitation.
A full copy of the Contract Construction Plans can be found with this solicitation.
4.0 Government Furnished
There are no Government Furnished Materials associated with this project.
5.0 Deliverables / Schedule
Key Deliverables
Item No.
Deliverable / Item Title Description Frequency Reference
Delivery Format Due By
Accident Prevention Plan
Design the plan to address Federal, State, and Local Occupational Safety and Health requirements that apply to this project
Once Specifications General Requirements 2.2.A
Via email to
COR
10 days prior to on-site work beginning
Item No.
Deliverable / Item Title Description Frequency Reference
Delivery Format Due By
Product Data Collect information into a single submittal for each element of construction and type of product or equipment
Once per element
Specifications General Requirements 3.3.B
Via email to
COR
10 Days prior to incorporating into the work
Shop Drawings
Prepare Project-specific information, drawn accurately to scale in electronic format. Do not base Shop Drawings on reproductions of the Contract Documents or standard printed data.
Once per element Specifications General Requirements 3.3.C
Via email to
COR
10 Days prior to
Requests for Information Submittals
Prepare and submit Informational Submittals required by other Specification Sections.
Prepare and submit RFI as needed
Specifications General Requirements 3.4
Via email to
COR
Immediately on discovery of need
Contractor's Construction Schedule
Provide a construction schedule that incorporates the full contract period.
Once Specifications General Requirements 3.5.
Via email to
COR
10 days prior to on-site work beginning.
Monthly interval
Contractor Quality Control
Provide electronic Quality Control submittals, including design data, certifications, manufacturer's instructions, manufacturer's field reports, and other quality-control submittals as required under other Sections of the Specifications.
As required by induvial specifications
Specifications General Requirements 3.4.D
Via email to
COR
10 Days prior to
Operation and Maintenance Data furnish two complete sets of operation and maintenance (O&M) data
Before scheduling a final inspection
Specifications General Requirements 6.2
Digital file Via email to COR
Within 30 days following receipt of review comments
6.0 Travel
Travel is the responsibility of the contractor; the U.S. Forest Service will not reimburse contractor’s travel expenses.
7.0 Contractor’s Key Personnel
The Contractor is to provide name, position title and contact information of company executive responsible for the project. Contractor is to provide an onsite superintendent at all times.
8.0 Security Requirements
The Contractor is to install and maintain suitable barriers to ensure the protection of the public, employees, and facilities. Protect persons, motor vehicles, surrounding buildings, plants, and surrounding surfaces or buildings from harm resulting from Contractor’s work. Confine constructions operations to immediate area of work. Do not disturb portions of Project site beyond areas in which the Work is indicated.
Site gate lockout procedures will be established if applicable.
9.0 Data Rights
Data will not be produced with this construction contract.
10.0 Section 508 – Electronic and Information Technology Standards Information technology will not be acquired with this construction contract.
Attachments:
Hill City Shop Doors Replacement Drawings Hill City Shop Doors Replacement Specifications