About this file
This document is a Section C Description and Specifications for a federal contract to replace interior lighting fixtures and controls at the Lewis and Clark Interpretive Center in Great Falls, Montana. The project requires a contractor to update all existing lighting systems, with work to be completed within 60 consecutive calendar days between January 1, 2027, and March 31, 2027, with potential flexibility to shift the construction window if the concurrent LCIC Exhibit Updates contract is completed earlier.
The contractor will be responsible for all labor, materials, and tools necessary to complete the work, ensuring coordination with the Owner's representative for scheduling disruptions to access and utilities. All waste and excess materials must be disposed of off Forest Service lands in compliance with federal, state, and local laws. No pre-bid tour is scheduled, and prospective bidders are expected to visit the site at 4201 Giant Springs Road in Great Falls, Montana, prior to bidding. The project requires careful planning to minimize disruption to the facility, which will remain occupied during construction.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| 1240LU25R0026 LCIC Lighting Upgrade.pdf | ||
| Attachment 4 LCIC Lighting Drawings.pdf | ||
| Attachment 1 Schedule of Items.docx | DOCX document | |
| Attachment 3 LCIC Lighting Specifications.pdf | ||
| Attacment 5 Wage Determination.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SECTION C – DESCRIPTION AND SPECIFICATIONS
C.1 PROJECT SCOPE
a. Description:
This project is for replacement of interior lighting fixtures and controls serving the Lewis and Clark Interpretive Center in Great Falls Montana. All existing lighting systems are out of date.
The Owner will continue to occupy the site during construction. The Contractor is responsible for all coordination with the Owner's representative in scheduling all disruptions of access and utilities. Bid pricing must take into account the required project sequencing.
Contractor is responsible for all labor, materials, tools, etc. necessary to complete the work. All waste and excess materials generated from construction shall be disposed of off Forest Service lands and in compliance with governing federal, state, and local laws.
b. Location: (See attached Map)
Lewis and Clark Interpretive Center 4201 Giant Springs Road Great Falls, MT 59405
c. Period of Performance: Contractor allowed 60 consecutive calendar days to complete the work between the months of January 1, 2027, to March 31, 2027.
NOTE: Work to be performed after LCIC Exhibit Updates contract is complete. If exhibit work is completed earlier, the 60-day construction window may be shifted between the months of October 1-March 31.
d. Pre-Bid Tour: No Pre-Bid Tour is scheduled for this project. Prospective bidders are responsible for visiting the site prior to bidding.