Construction Specification Summary: Fort Randall Chalk Rock Link Trail Construction
This is a Construction Specification document for a natural surface trail link construction project within the Lisa M. Durham Memorial Trail system at Fort Randall, a U.S. Army Corps of Engineers (USACE) facility in South Dakota. The contractor must construct approximately 2,250 linear feet of sustainable trail following Professional Trail Builders Association (PTBA) standards, including clearing a minimum 72-inch-wide and 80-inch-high corridor; bench excavation and tread shaping with a finished width of 36-48 inches; installation of a 4-inch mechanically compacted crushed gravel top layer; switchbacks with 10-foot minimum turning radii; and grade reversals and drainage features. The trail must achieve a 6-8% sustained grade average with maximum 10-15% grades for no more than 30-foot intervals. A 4-foot by 8-foot gravel pad will be constructed at the halfway point for future bench placement. USACE will furnish approximately 245 tons of state-specification crushed gravel to the staging area.
The overall contract period runs from award through December 31, 2026, with all physical construction completion required by November 27, 2026, and a post-construction administrative window through December 31, 2026. Payment is made at a unit price per linear foot following inspection and acceptance. Bidders must demonstrate three years of comparable sustainable trail construction experience with minimum 150-foot elevation change and 50-60% side slope terrain, along with active PTBA Certified Trail Builder status. Pre-construction submittals include Activity Hazard Analysis, Accident Prevention Plan, E-Verify certificates, insurance proof, trail design layout, schedule, and operator qualifications. Work hours are 0700-1700 Monday through Friday, excluding four specified federal holidays. The contractor is responsible for all waste disposal, personnel transportation, equipment operations, and remedial vegetation measures for ground disturbance outside clearing limits. Government inspection includes random spot checks of trail width (±6 inches), gravel thickness (+1.5 inches/-0.25 inches), and alignment verification.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Construction Specification Fort Randall Chalk Rock Link Trail Construction
1.0 Scope of Work. The Fort Randall project is constructing a natural surface trail link within the Lisa M. Durham Memorial Trail system. The trail link is required to follow standard sustainable trail building practices as defined by the Professional Trail Builders Association (PTBA) including rolling contour alignment, grade reversals, outsloped tread, and armored drainage crossings using natural/locally sourced stone that the contractor sources within the trail site location. Contractor will be required to clear and grub a trail corridor that is a minimum of 72-inches wide and 80-inches high within the designated path alignment. This work consists of clearing, grubbing, trimming, removing, and treating trees, logs, limbs, branches, brush, plants, and other vegetation within the clearing limits. Clearing practices must include removal down to ground level of any cedar tree that will be trimmed 25% or more.
Furthermore, the contractor shall work to avoid any damage to existing, native Burr Oak trees. Cleared vegetation must be removed and piled near the staging area adjacent to the asphalt road for future USACE removal. The trail link will be approximately 2,250 linear feet of bench excavation and tread shaping to establish a stable tread base which follows the alignment in attached Drawing 1, which will be staked by USACE prior to mobilization. The finished trail tread width will range between 36 – 48-inches depending on location and terrain and will be topped with a 4-inch lift of crushed gravel, as measured after completion of mechanical compaction. The crushed gravel will be placed, graded, and mechanically compacted. Mechanical compaction shall be via vibratory plate packer, vibratory roller, or another form of vibratory mechanical compaction achieved via specialized equipment attachment(s). Due to the terrain, the final path at minimum will consist of switchbacks with turning platforms that have a minimum of a 10-foot turning radius to ensure a proper turn radii for both foot and bicycle traffic. The required grade average for the trail tread is 6-8% sustained with a max of 10-15% for no more than 30-foot intervals.
Grade reversals and drainage features are required to be installed as preventative measures to promote long-term sustainability. At the halfway point of the trail link, a 4-foot by 8-foot gravel pad with a 4-inch mechanically compacted lift will be constructed adjacent to the trail path for future USACE placement of a cedar log bench.
Ground disturbance outside of the clearing limits must be prevented. Significant ground disturbance outside of these limits will result in the contractor’s need to perform remedial vegetation measures, as directed by USACE.
1.1 Period of Performance & Work Completion
1.1.1 Contract Period of Performance: The overall Period of Performance for this contract shall be from the date of award through December 31, 2026. This timeframe encompasses all physical construction, final inspections, punch-list resolution, submission of final closeout documentation (including as-built drawings), and final invoice processing.
1.1.2 Physical Construction Completion Date: All on-site physical construction activities must commence following the pre-construction meetings and be fully completed no later than November 27, 2026.
1.1.3 Post-Construction Administrative Window: The period from November 28, 2026, through December 31, 2026, is strictly reserved for Government inspections, corrective action/punch-list completion, final submittal processing, and administrative closeout. No new physical construction or trail clearing may be initiated during this window without prior written approval from the Contracting Officer (KO).
2.0 General
2.1 Standards and Regulations. The Contractor shall perform to the standards in the contract and comply with all Local, State, and Federal Regulations during the services performed. The Contractor is responsible for ascertaining the extent to which these regulations affect the operations resulting from this contract. The Contractor shall comply will all applicable regulations. Applicable regulations include, but are not limited to the following:
a. Engineering Manual (EM) 385-1-1 (USACE – Safety and Health Requirements Manual), dated March 2024;
https://www.publications.usace.army.mil/Portals/76/EM%20385-1- 1%20_EFFECTIVE%2015March2024.pdf
b. Occupational Safety and Health Standards (29 CFR 1910);
https://www.publications.usace.army.mil/Portals/76/EM%20385-1-1%20_EFFECTIVE%2015March2024.pdf https://www.publications.usace.army.mil/Portals/76/EM%20385-1-1%20_EFFECTIVE%2015March2024.pdf
2.1.1 Activity Hazard Analysis (AHA). The contractor shall prepare an AHA in accordance with Paragraph 1-6 of the EM 385-1-1 for each Definable Feature of Work. Definable Features of Work shall include Trail Clearing (Equipment Operation), Tree/Vegetation Clearing, and Gravel Placement & Compaction. Submit the AHA electronically for review at least ten (10) calendar days prior to mobilization. The analysis should be used during daily inspections to ensure the implementation and effectiveness of the activity's safety and health controls. An electronic copy of the AHA form may be provided upon request.
2.1.2 Abbreviated Accident Prevention Plan (APP). EM 385-1-1 in its entirety may be too complex for the type of work performed under these contracts; contractors shall utilize ENG Form 6293, for an abbreviated Accident Prevention Plan (APP). The contractor shall only need to submit items in ENG Form 6293 that are pertinent to the contract. The contractor shall use a qualified person to prepare the site-specific abbreviated Accident Prevention Plan (APP). The contractor shall prepare the APP in accordance with the format and requirements of the EM 385-1-1 and supplemented herein. The contractor shall sign and submit the APP for approval prior to the start of work onsite.
2.2 Measurement and Payment.
2.2.1 The Government will make payment after services have been inspected and accepted, and the contractor’s invoice has been reviewed, approved, and processed. The contractor shall submit the invoice to the COR.
The contractor is required to include the contract number on the invoice, make sure that the address matches SAM and the associated CLIN (Contract Line-Item Number) is listed to each line applicable so that receipt and payment for the item or service may be expeditiously processed.
2.2.2 The contractor must provide the contractor’s name, address, contract number, period of services completed (i.e., for the period of performance as listed in part 1.1), CLIN number and specific quantities of work performed (i.e., 1 Month, 40 days, 100 acres, etc.), and total requested, for an invoice to be considered proper. The contractor shall submit the invoice upon completion of all services, in accordance with the period of performance stated in the
CLIN.
2.2.3 Method of Measurement: Trail construction (CLINs 0002 and 0003) will be measured for payment in Linear Feet (LF) along the centerline of the completed, accepted trail tread surface. Measurement will follow the actual slope distance of the trail. No separate measurement or payment will be made for clearing widths, turning platforms/switchbacks, or drainage armoring; these activities are considered incidental to and included within the linear foot unit prices.
2.2.4 Basis of Payment: Payment for trail construction will be made at the contract unit price per Linear Foot (LF) for the quantities measured under Section 2.2.3. This payment shall constitute full compensation for all labor, materials (excluding government-furnished gravel), equipment, and incidentals necessary to complete the work.
2.2.5 Variation in Quantity: In accordance with FAR 52.211-18 (Variation in Estimated Quantity), the quantities listed in the Bid Schedule for CLINs 0002 and 0003 are estimates. If the final measured quantity of either CLIN varies by more than 15% above or below the estimated 2,250 LF, an equitable adjustment in the contract unit price may be demanded by either the Government or the Contractor to reflect actual costs.
2.3 Location. The Lisa M. Durham Memorial Trial is located within the Pickstown Wildlife Management area owned in fee title by USACE. The location of the Chalk Rock Link will be located between the Yucca Loop and Cedar Loop. The terrain in this area has a side slope up to 60% and is inundated primarily by Eastern Red Cedar.
This trail will incur an elevation change of approximately 200 ft between the designated start and end points. See Map 1.
2.4 Staging Area. The government will provide two options for the contractor to stage equipment and material. See Map 2 for location details.
2.5 Delivery, Storage, and Handling. Contractor is responsible for all deliveries to the site. USACE will not assist or receive any deliveries for the contractor. Contract must receive, unload, and take delivery to the designated staging area. No deliveries will be made outside the permitted working hours or days.
2.6 Work Hours and Work Limits. The contractor is responsible for conducting business between the hours of 0700 and 1700 Monday through Friday except Federal holidays or when the Government facility is closed due to local or national emergencies, administrative closings, or similar Government directed facility closings. Contractor may request additional hours Monday through Friday. However, approval is not guaranteed and will be subject to safe practices preventing someone from working alone. Federal holidays within the performance period will include:
Labor Day – Monday September 7th, 2026 Indigenous Peoples’ Day– Monday October 12th, 2026 Veteran’s Day – Wednesday November 11th, 2026 Thanksgiving – Thursday November 26th, 2026
USACE maintenance personnel will be responsible for stockpiling crushed gravel in the staging area adjacent to the asphalt road. Contractor shall coordinate needs prior to mobilization. The Contractor must maintain an adequate workforce for the uninterrupted performance of all tasks defined within this SOW when the Government facility is not closed for the above reasons. When hiring personnel, the Contractor shall keep in mind that the stability and continuity of the workforce are essential.
2.7 Facilities
2.7.1 Portable Toilets. A public vault toilet is available within the Spillway Lakeside Use Area. At the contractor’s option, a portable toilet may be staged and used within the approved staging area, at the contractor’s expense.
2.7.2 Power Availability. There is no power available to the worksite. Contractor will be required to supply their own power source as approved by the project office.
2.8 Environmental Conditions. Contractor is responsible for disposal of all waste materials as a result of this contract. This includes but is not limited to arranging transportation of solid waste and any costs associated with disposal in compliance with Federal, State, and local requirements for solid waste disposal. Demolished vegetation shall be handled as specified in part 1.0. Burning of solid waste or demolished vegetation will not be allowed.
2.9 Antiterrorism/Operation Security Requirements
2.9.1 Pre-screen candidates using E-Verify Program. The Contractor must pre‐screen candidates using the E‐ verify Program (http://www.dhs.gov/E‐Verify) website to meet the established employment eligibility requirements.
The vendor must ensure that the candidate has two valid forms of government issued identification to ensure the correct information is entered into the E-verify system. An initial list of verified/eligible candidates must be provided to Kelsey Kniffen at Kelsey.m.kniffen@usace.army.mil no later than three (3) business days after the initial contract award.
3.0 Submittals. Prior to mobilization, the Contractor shall submit the following submittals to the Government via email to Kelsey Kniffen at Kelsey.m.kniffen@usace.army.mil for review. Each submittal must consist of a single PDF document, with a completed Form 4025 (included in bid package) included as the cover sheet. Submittals below accompanied by a ‘G’ designator must be submitted for Government approval and will receive an (A-code) upon approval. Submittals below that are not accompanied with a ‘G’ designator must be submitted for acknowledgement-of-receipt and will receive an (F-code) upon successful acknowledgment. All Pre-construction submittals must be approved or acknowledged prior to the start of work.
3.0.1 SD-01 Preconstruction Submittals
3.0.1.1 Activity Hazard Analysis (AHA); (10 days prior to start of work); G
3.0.1.2 Abbreviated Accident Prevention Plan: G
3.0.1.3 E-Verify Certificates for On-Site Personnel: G
3.0.1.4 Proof of Insurance for contractor: G
3.0.1.5 Trail Path Design and Field Layout: G
3.0.1.6 Schedule; G
3.0.1.7 Contractor & Operator Qualifications:
3.0.1.7.1 Company Experience: Bidders must submit evidence of having successfully completed at least three
(3) sustainable, natural-surface trail construction projects within the last five (5) years of similar scope, elevation change (minimum 150 ft), and side slope terrain (up to 50–60%). Active certification from the PTBA (e.g., Certified Trail Builder status) or equivalent trail construction training program is required.
3.0.1.7.2 Technical Standards Compliance: Bidders must demonstrate a thorough working knowledge of sustainable trail building guidelines. The contractor’s past project documentation must show adherence to standard sustainable trail building practices as defined by the Professional Trail Builders Association (PTBA) or equivalent municipal/federal trail construction standards.
3.0.1.7.3 Operator Resumes: Bidders must submit a detailed resume for each proposed equipment operator.
Resumes must show alignment of operator proficiencies with the proposed heavy equipment (e.g., mini-excavators, trail dozers) and a documented history of operating such equipment on at least three (3) similar trail projects within the last five (5) years.
3.0.1.8 Quality Control Designation Letter
Prior to mobilization, the Contractor shall submit all items listed above. Each submittal shall include a completed and signed Form 4025 for each submission. In addition to the listed submittals, the Contracting Officer may request submittals for items in the specifications or items shown on the drawings when deemed necessary to adequately describe the work covered in the specifications and drawings. The Contractor shall be responsible for certifying that all submittals comply with the contract requirements. The Contractor shall allow the Government 15 calendar days, beginning from date of receipt by the Government, to review all submittals. The contractor shall consider the review period when providing submittals and possible resubmittals to allow for sufficient time for review and approval by the Government prior to mobilization.
Contractor shall submit a Trail Path Design and Field Layout for Government review. This document shall:
• Provide a PDF drawing of the proposed trail route, including location of drainage crossings and any other non-typical trail features
• State the contractor’s acknowledgement of full intent to follow the Government-staked alignment including all legs and switchbacks shown on Drawing 1 or propose variations which are then clearly indicated on the attached PDF drawing and provided with corresponding justification.
• Define each step in the process and the heavy equipment proposed (Make & Model) for use in the clearing/grubbing process
• Define each step in the process and the heavy equipment proposed (Make & Model) for use in gravel placement and compaction
This submittal will be used by both the Government and the contractor to identify and remedy sources of disagreement before the contractor mobilizes on site. This submittal may require the contractor to perform a site visit prior to mobilization and is therefore critical to submit well in advance of the planned mobilization date.
4.0 Materials. USACE shall furnish and deliver state-spec crushed gravel to the staging area (see Map 2) to be used as final trail tread at an estimated quantity of 245 tons. Gravel will be delivered prior to the start of construction activities. In the event the gravel quantity is insufficient, the contractor is responsible for contacting the Government a minimum of 5 days before additional material will be needed in order to coordinate delivery of said materials.
Excess gravel left at the staging area will be removed by the Government following contract completion. Gravel placed in excess of a 4-inch lift that results in the contractor’s need for gravel quantities beyond this estimate will not constitute a need for additional payment due to the increased volume of gravel requiring placement to finish construction of the trail.
5.0 Miscellaneous Execution Requirements
5.1. Participate in an on-site post-award meeting with U.S. Army Corps of Engineers (USACE) key personnel to review the entire Task Description, schedule, deliverables, submittal dates, and expectations for the final deliverable.
It is expected that the contractor may use this meeting to view existing conditions, obtain measurements, and review start and end points for trail link, as this will assist with developing the ‘Trail Path Design and Field Layout’ submittal. This meeting must be completed at least 15 days prior to mobilization.
5.2. Upon mobilization and prior to commencing any activities, the contractor’s on-site personnel shall arrange a Pre-work Meeting with the COR and natural resource representative. The Meeting shall discuss the work requirements, scheduling, and other expectations of the contract.
6.0 Inspection and Tests. The government will inspect all work in accordance with FAR 52.213-4 – Terms and Conditions – Simplified Acquisitions (Other Than Commercial Items). This will include:
• random spot checks to ensure trail width is maintained within +/- 6” of the specified width
• random pot-hole checks to ensure the thickness of compacted gravel is within +1.5”/-0.25” of the specified, compacted layer thickness.
• Routine checks to ensure the agreed-upon alignment is being followed
A quality assurance representative and representative from the Ft. Randall natural resource section must be present during the final assessment of trail construction. Any deficiencies will be communicated to the contractor, and remedial work will be required.
6.1 Quality Control
6.1.1 The contractor shall designate, in writing, a member of the work crew who shall serve as the contact for matters involving quality and performance or nonperformance of the required work assigned to that crew. The employee(s) shall be qualified and fully competent with full authority to act for, and on behalf of, the contractor as necessary to ensure that the required work is performed in accordance with the specifications and standards contained herein. The contractor shall furnish the above written designation to the Contracting Officer’s Representative (COR) no later than one week prior to the first day of work. The contractor shall include the name(s), address(s), and telephone number(s) of the responsible individual(s). The named individual(s) will be required to have a physical presence on site during the performance of any and all work.
6.1.2 The Contracting Officer reserves the right to disapprove any individual whom he considers incompetent to perform the work required. The Contracting Officer will provide a written notice of any disapproval to the contractor.
6.1.3 The Government has the right to inspect all services called for by the contract, to the extent practicable at all times and places during the term of the contract. The Government shall perform inspections in a manner that will not delay the work.
6.1.4 If any of the services do not conform to contract requirements, the Government may require the contractor to perform the services in conformity with contract requirements and at no increase in cost. If the contract requirements are not met after a second attempt the Government may (1) require the contractor to take necessary action to ensure that future performance conforms to contract requirements and (2) reduce the contract price to reflect the reduced value of the services performed (3) terminate the contract in whole or in part.
6.1.5 The Government may take action, if the contractor fails to perform the services again or to take the necessary action to ensure future performance is in conformity with the contract requirements. The Government may (1) by contract, or otherwise, perform the services and charge to the contractor any cost incurred by the Government that related to the performance of such service or (2) terminate the contract in whole or in part.
6.1.6 The contractor is responsible to replace/repair any damage to Government property due to negligence, at his or her own cost. The Government may take action, if the contractor fails to replace/repair any damage to Government property. The Government may by contract, or otherwise, replace/repair damaged Government property and charge to the contractor any cost incurred by the Government to replace/repair any damage.
7.0 Point of Contact. USACE POC is Kelsey Kniffen, Kelsey.M.Kniffen@usace.army.mil
8.0 Reference Drawings and Photos. Drawings provided for reference only. Drawings may not reflect actual site conditions or show all equipment installed and the government does not guarantee the accuracy of the reference drawings and information provided within this document. Therefore, field verification by the Contractor is highly recommended to determine actual site-specific conditions.
10. Attachments
Form 4025 Price Schedule Drawing 1 Map 1 Map 2