This is a Price Schedule for the Chalk Rock Link Trail Construction project at Fort Randall Project in Pickstown, South Dakota, dated July 2026.

The contract encompasses three base line items (CLINs) totaling 2,250 linear feet of trail construction. CLIN 0001 covers Mobilization/Demobilization and Field Layout as a one-time occurrence priced per job. CLIN 0002 addresses Trail Clearing at 2,250 linear feet, including excavation, bench construction, switchback construction, drainage features, and final shaping of the trail corridor. CLIN 0003 covers Trail Surfacing at 2,250 linear feet, consisting of placement, grading, and compaction of aggregate surfacing layer and gravel pad for future bench construction. All unit prices are indicated as "XXX" and require bidders to enter actual pricing for each line item and calculate corresponding CLIN totals.

The instructions specify that prices must be submitted for all schedule items, with total amounts lacking unit prices subject to rejection. In cases of discrepancy, unit prices take precedence over CLIN totals, and CLIN totals take precedence over cumulative totals. Bidders must complete all pricing fields to have their proposal considered compliant.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Chalk Rock Link Trail Construction Fort Randall Project, Pickstown South Dakota

Price SCHEDULE

July-26

BASE ITEMS

CLIN

Description

Estimated Quantity Unit of Measure

Unit Price

CLIN Total

Mobilization / Demobilization & Field Layout

1 (Occurrence Each)

JOB

XXX

Trail Clearing (Excavation, bench construction, switchback construction, drainage features, and final shaping of trail corridor)

2,250

LF

Trail Surfacing (Placement, grading, and compaction of aggregate surfacing layer and gravel pad for future bench)

2,250

LF

Total Base (Items 0001 - 0003):

Notes:

1. Prices must be entered for all items of the price schedule. Total amounts submitted without prices being entered on unit prices or CLIN totals will be rejected. In the case of variation between the unit prices and the CLIN total, the unit prices shall be considered the quote. In the case of variation between the CLIN totals and the cumulative total(s), the CLIN prices shall be considered the quote.