This Statement of Work (SOW) details the installation of MPU5 antennas for the 548th Combat Training Squadron (CTS) at Fort Johnson, Louisiana. The project involves installing 10 S-Band Integrated Sector Antennas (12dBi Gain 120° Sector Antennas by Persistent Systems) across four permanent tower sites: Site 34/Mill Creek (3 antennas), Site 15/Cemetery (3 antennas), Site 32/Peason West (2 antennas), and Site 1/Peason East (2 antennas). The contractor will install antennas at approximately 250 feet above tower bases, oriented toward a central point, with 548th CTS personnel providing CAT 6 cable and installation brackets. The project has a 14-working-day performance period, requires engineering structural analysis of tower CAD drawings, and mandates daily site clean-up and compliance with safety regulations. The contractor must provide a one-year warranty on workmanship and each antenna has a unit acquisition cost of $7,944.05.
View the file
Other files
Show all 12
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATEMENT OF WORK
MPU5 ANTENNA INSTALLATION AND TOWER CLIMB
548TH CTS FORT JOHNSON, LA
10 FEB 2025
PART I – GENERAL
1. PURPOSE
This Statement of Work (SOW) defines the scope of work to accomplish the installation of
MPU5 antennas on 4 permanent towers in the Fort Johnson training area. The contractor shall provide all labor, material, equipment, management, supervision, coordination, and transportation required to accomplish this work; the antennas will be provided (see Appendix A).
After new equipment is installed by Contractor, areas will be cleaned up to maintain a litter-free environment and present a neat and professional appearance. The work shall be performed in accordance with this SOW, accepted proposal, and all Federal, State, and local laws and regulations, codes and industry standards that may apply. Specific requirements are identified below:
1.2. WORK SCHEDULE
The Contractor shall complete the work outside of scheduled Joint Readiness Training Center exercises, contractor shall contact the 548th CTS to schedule the work. The Contractor shall work with the 548th CTS to ensure access to the towers 2 weeks prior to commencing work.
1.3. CLEAN-UP
All debris and rubbish not specified to become Government property resulting from the installation of antennas. Disposal will be in compliance with all applicable Federal, State, and local hauling and disposal regulations. Site clean-up shall occur daily.
1.4. SAFETY REQUIREMENTS
Safety requirement shall be the applicable sections of EM 385- 1-1, Oct 1992 and Occupational
Safety and Health Administration (OSHA) Regulations. The contractor shall ensure that any lifting devices or ladders meet any and all applicable safety standards.
1.5. PERIOD OF PERFORMANCE
Period of performance for installation/service work mentioned above shall not exceed 14 working days. Work shall begin at an agreed upon date by both parties after the contract has been awarded, at which point, the schedule and completion date will be determined.
1.6. WARRANTY
The contractor shall provide the Government with a one-year warranty on workmanship. The contractor shall provide any manufacturer’s warranty to the Government.
PART II – TECHNICAL
2. Fort Johnson Permanent Towers
2.1. TOWER AND ANTENNA LOCATIONS
The antennas shall be installed on towers in the Fort Johnson training area with the following specifications:
Site 34/Mill Creek (31.08371285, -93.1409003); 3 antennas Site 15/Cemetery (31.09604115, -92.97745216); 3 antennas Site 32/Peason West (31.35177588, -93.32792486); 2 antennas Site 1/Peason East (31.35044917, -93.17181034); 2 antennas
2.2. TOWER INSTALLATION SPECIFICATIONS AND DELINEATION OF DUTIES
Contractor shall install antennas at approximately 250 ft above the base of towers oriented toward a central point, under the direction of 548th personnel. 548th will provide CAT 6 cable along with all necessary installation brackets. Contractor shall provide cable-ties or appropriate equipment to secure the CAT6 cable to the tower. The CAT6 cable will be routed into the structure below the tower, 548th personnel will connect the cables to a central power supply.
2.3 ENGINEERING STRUCUTRAL ANALYSIS
Contractor shall revise CAD drawings and produce a new engineering analysis to certify the towers. The 548th CTS will provide current CAD renderings for revision. Contractor is not required to update the engineering analysis of the structure at the base of the tower.
APPENDIX A: GOVERNMENT FURNISHED PROPERTY
1. The name, part number and description, manufacturer, and model number:
S-Band Integrated Sector Antenna, WR-INT-ANT-01 12dBi Gain 120° Sector
Antenna, Persistent Systems, WR-INT-ANT-SYS-01
2. Quantity/unit of measure:
10 Each
3. Unit acquisition cost:
$7,944.05 Each
4. Unique-item identifier or equivalent:
N/A
5. The antennas will be furnished in an “as-is” condition and members from the 548th CTS will be onsite to inspect the property with the contractor.