This is a Statement of Objectives (SOO) for the accreditation of six Armag Corporation Armored Rapid-deployment Compartmented Vaults (ARMAGs) to become Sensitive Compartmented Information Facilities (SCIFs) at Kadena Air Base, Okinawa, Japan. The contractor must ensure installation, integration, and testing of Intrusion Detection System (IDS), Intrusion Detection Equipment (IDE), and Access Control System (ACS) in all six ARMAGs to meet specifications outlined in Intelligence Community Directive 705 (ICD 705) Version 1.5.1, Air Force Life Cycle Management Center (AFLCMC) Non-Nuclear Configuration Management Database (CMD) Equipment Approval, Air Force Materiel Command (AFMC) Electronic Systems Center (ESC) Electronic Security Equipment (ESE) Master Installation Acceptance Test and Turnover Plan (ESE-TP-0023), Unified Facilities Criteria (UFC 4-021-02), and Committee on National Security Systems Advisory Memorandum (CNSSAM) TEMPEST/01-13. The contractor's point of responsibility ends at ARMAG IDS connectivity to Kadena Air Base Alarm System and internal components of the six ARMAGs, excluding base infrastructure.

The contractor must conduct a site survey to identify missing IDS components, physically install all security components including the Security Archive Workstation (SAW), IDE, and ACS, provide training on operation of Access Control System, Premise Control Units (PCUs), and SAW to 353 SOW personnel, and integrate IDS into Kadena AB Alarm System by coordinating with 353 SOW Special Security Office and 18th Civil Engineering Squadron. The contractor must install and test the Honeywell Vindicator IDS package with specific firmware versions (Vindicator Command and Control Platform Version 10, V3 Network Security Firmware 4.3.2 SP VR22, and AES-1500 Network Field Device Firmware 4.3.2 SP VR22), complete IDS acceptance testing with 18th Security Forces Squadron, and comply with Construction Security Plan requirements. The contractor must have Vindicator certifications and bring all necessary tools and equipment. The delivery of equipment (1-1/4" x 200' Liquid-Tight Non-Metallic Conduit) is expected on or about August 10, 2026. The Government Furnished Equipment List details specific equipment for all six ARMAGs, including workstations, network devices, UPS units, and power cords.

View the file

Other files

File Type Posted
QandA.xlsx XLSX spreadsheet
combined synopsis_07172026.docx DOCX document
combined synopsis_FA527026QB015.pdf PDF
Attachment 1_Provisions and Clauses_FA527026QB015.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Revised July 4, 2026

CUI

STATEMENT OF OBJECTIVES (SOO)

(ARMAG IDS)

I. Purpose: Accredit six Armag Corporation Armored Rapid-deployment Compartmented Vaults (A.R.C. Vaults) to become Sensitive Compartmented Information Facilities (SCIFs) [herein, the term “ARMAG(s)” will be used to refer to the Armag Corporation A.R.C. Vault(s)].

II. Scope or Mission:

1. Ensure Intrusion Detection System (IDS), Intrusion Detection Equipment (IDE), Access Control System (ACS), and all associated security hardware/software components are installed in all six ARMAGs and functioning to meet specification requirements as outlined in the following publications:

a. Intelligence Community Directive 705 (ICD 705) Version 1.5.1, IC Tech

Spec – for ICS/ICD 705 Technical Specifications for Construction and Management of Sensitive Compartmented Information Facilities (SCIFs), 26 July 2021

b. Air Force Life Cycle Management Center (AFLCMC), Non-Nuclear

Configuration Management Database (CMD) Equipment Approval, 29 April 2024

c. Air Force Materiel Command (AFMC) Electronic Systems Center (ESC), Electronic Security Equipment (ESE) Master Installation Acceptance Test and Turnover Plan (ESE-TP-0023), 22 June 2021

d. Unified Facilities Criteria (UFC 4-021-02), Electronic Security Systems, 28 July 2025

e. Committee on National Security Systems Advisory Memorandum

(CNSSAM) TEMPEST/01-13, RED/BLACK Installation Guidance, 17 January 2014

2. Ensure IDS meets all testing requirements and is programmed and integrated into the Kadena Air Base Alarm System.

3. Report to place of performance with all tools and equipment necessary for install and integration of all components. See Government Furnished Equipment (GFE) list for complete list of all equipment that will be provided by the government.

III. Period and Place of Performance: Kadena Air Base, Okinawa, Japan. Contractor should propose a start date and project length that will ensure all installation, integration, and testing of IDS, IDE and ACS and the installation and end user training of the badging station and Security Archive Workstation (SAW) is complete. There is a different construction project happening simultaneously that requires items being stored to be moved to the ARMAGS. For the construction project to continue timely, the Government requires the completion of the ARMAGs to ensure the stored items can be moved into the ARMAGs.

IV. Point of Responsibility: Contractor’s point of responsibility ends at ARMAG IDS connectivity to Kadena Air Base Alarm System and internal components of the six ARMAGs.

Responsibility does not include base infrastructure.

V. Background: Six ARMAGs were prefabricated in the USA and delivered to the 353d Special Operations Wing (353 SOW) on 08 July 2025. The Honeywell Vindicator IDS package was pre-installed but is incomplete due to several factors, including non-installation of several systems, missing pieces of network equipment, and lack of required mounting hardware.

VI. Performance Objectives: The objectives are as follows:

1. Conduct site survey. Survey is required to identify any missing components of the IDS (to be procured prior to work start) . Vender will identify all necessary tools and hardware to conduct labor and complete IDS installation.

2. Report to location of performance with all tools and equipment necessary for install and integration and supplementary tools to include but not limited to ladders, cleaning tools, etc. See government furnished equipment (GFE) list for complete list of all equipment that will be provided by the government.

3. Confirm pre-installation of IDS and associated components is correct and functional. Make modifications as necessary.

4. Physically install all other components of IDS, to include the Security Archive

Workstation (SAW), IDE, and ACS.

5. Provide training on operation of ACS, Premise Control Units (PCUs), and SAW to designated 353 SOW personnel.

6. Integrate IDS into Kadena AB Alarm System by coordinating with 353 SOW

Special Security Office (SSO) and 18th Civil Engineering Squadron (18 CES) alarms section.

IDS should be physically integrated and software must be fully integrated in BDOC.

7. Integrate ACS into IDS and ensure ACS is fully functioning.

Necessary firmware to integrate the IDS is the following:

• Vindicator Command and Control Platform Version 10

• V3 Network Security (IDS & ACS) Firmware 4.3.2 SP VR22

• AES–1500 Network Field Device Firmware 4.3.2 SP VR22

8. Confirm installation of badging station and its associated components are functional and provide end user training on badging system.

9. Complete the IDS acceptance test by coordinating with 18th Security Forces

Squadron (18 SFS) and providing successful test documentation to 353 SOW SSO.

10. Follow all security requirements outlined in the Construction Security Plan (CSP).

Any deviations or mitigations must be approved by the 353 SOW SSO.

11. Vendor must have Vindicator certifications to operate on Vindicator systems.

12. Install, connect, and test IDS Uninterrupted Power Supply (UPS).

VI. Operating Constraints: Not all ARMAGs have working air conditioning, resulting in average indoor temperature of 86°F (current as of 22 April). Doors will be propped open and a fan will be provided to allow airflow. Risk of damage/injury to equipment/personnel inside the ARMAGs due to lack of lightning protection systems in the event of a thunderstorm. 353 SOW is currently awaiting delivery of the following equipment: 1-1/4" x 200' Liquid-Tight Non- Metallic Conduit, which shipped on June 10, 2026. While we cannot provide a definitive arrival date, standard transit is estimated at two months from the shipping date, placing the projected delivery on or about August 10, 2026.

VII. End User Requirements: The 353 SOW will provide cleared escorts. Coordination with 18 WG Security Forces will be done by the 353 SOW prior to work start.

VIII. GFE List: See Attachment 1

GFE List (CAO 20260505)

ARMAG #1

Model: Vin Site Commander Part No: 548-52000-11 Serial No: VSC-SA24C00400

Model: AE VBM 3 Client Workstation Part No: 548-53000-11 Serial No: P0002N

Model: AE SAW 2 Client Workstation Part No: 548-51400-11 Serial No: P0002T

AE V3 IDS - AES

Part No: 548-54200-01 HW/SW Rev: 3.3 Rel 8 SP3 Serial No: 9c2e

V3 ACS AES, RJ45

Part No: 548-54300-01 HW/SW Rev: 3.3 Rel 8 SP3 Serial No: 9d7c

Cisco IE 3300-8T2S-E Serial No: FVH2943L2P0

ARMAG #2

Model: Vin Site Commander Part No: 548-52000-11 Serial No: SA24803962

AE V3 IDS - AES

Part No: 548-54200-01 HW/SW Rev: 3.3 Rel 8 SP3 Serial No: 9c2a

V3 ACS AES, RJ45

Part No: 548-54300-01 HW/SW Rev: 3.3 Rel 8 SP3 Serial No: 9d78

Serial No: FVH2943L2NP

ARMAG #3

Part No: 548-52000-11 Serial No: VSC-SA24C00399

AE V3 IDS - AES

Part No: 548-54200-01 HW/SW Rev: 3.3 Rel 8 SP3 Serial No: 9ae0

V3 ACS AES, RJ45

Part No: 548-54300-01 HW/SW Rev: 3.3 Rel 8 SP3 Serial No: 9d8a

Serial No: FVH2943L2P5

ARMAG #4

Part No: 548-52000-11 Serial No: VSC-SA24C00398

AE V3 IDS - AES

Part No: 548-54200-01 HW/SW Rev: 3.3 Rel 8 SP3 Serial No: 9c2c

V3 ACS AES, RJ45

Part No: 548-54300-01 HW/SW Rev: 3.3 Rel 8 SP3 Serial No: 9d7e

Serial No: FVH2943L2KW

ARMAG #5

Model: Vin Site Commander Part No: 548-52000-11 Serial No: VSC-SA24B00515

AE V3 IDS - AES

Part No: 548-54200-01 HW/SW Rev: 3.3 Rel 8 SP3 Serial No: 9ea8

V3 ACS AES, RJ45

Part No: 548-54300-01 HW/SW Rev: 3.3 Rel 8 SP3 Serial No: 9d80

Serial No: FVH2942L6NT

ARMAG #6

Part No: 548-52000-11 Serial No: VSC-SA24C00436

AE V3 IDS - AES

Part No: 548-54200-01 HW/SW Rev: 3.3 Rel 8 SP3 Serial No: 9ed6

V3 ACS AES, RJ45

Part No: 548-54300-01 HW/SW Rev: 3.3 Rel 8 SP3 Serial No: 9d8e

Serial No: FVH2943L2M0

Additional Equipment

9x UPS 17x Multi-mode SFP

6x CAB-AC= AC POWER CORD (NORTH AMERICA), C13, NEMA 5-15P, 2.1M 1x Security Archive Workstation 1x AE VBM 3 Badge Manager Client Workstation 1x AE SAW 2 Client Workstation