Attachment 2 SOW-Specs Multi-Site Demolition of Recreational Structures (29 pages).pdf

PDF 1 MB Posted

Attached to
Multi-Site Demolition of Recreational Structures on the Francis Marion, Sumter National Forest, SC
Solicitation number
12467020R0075
Issued by

View the file

Other files

File Type Posted
SF30-Amendment 03.pdf PDF
SF30-Amendment 02 RFP 12467020R0075 Multi-Site Demolition of Recreational Structures on the Francis Marion Sumter National Forest SC.pdf PDF
SF30-Amendment 01 RFP 12467020R0075 Multi-Site Demolition of Recreational Structures on the Francis Marion Sumter National Forest SC.pdf PDF
Attachment 4c Wage Determination for Chester County-13 pages.pdf PDF
Site Visit Pre-Bid Meeting Attendees.pdf PDF
Site Visit Pre-Bid Questions and Answers 25 June 2020.docx DOCX document
Attachment 3d Chattooga Cabin Asbestos Report (30 pages).pdf PDF
Attachment 3a Woods Ferry Asbestos Report (21 pages).pdf PDF
Attachment 4b Wage Determination for Edgefield County (13 pages).pdf PDF
Attachment 3b Parsons Mtn Asbestos Report (29 pages).pdf PDF
Attachment 1 Schedule of Items for Multi-Site Demolition (4 pages).pdf PDF
12467020R0075 SF1449 Multi-Site Demolition of Recreational Structures.pdf PDF
12467020R0075 SF1449 Continuation Pages (23 pages).pdf PDF
Attachment 5b LC Parsons Mt Bath Decom (1 page).jpg JPG image
Attachment 3e Woods Ferry bath house(s) ACM variance request (2 pages).pdf PDF
Attachment 4a Wage Determination for Oconee-Abbeville County (13 pages).pdf PDF
Attachment 5c LC Lick Fork Rec Bath Decom (1 page).jpg JPG image
Attachment 4c Wage Determination for Union County (13 pages).pdf PDF
Attachment 3c Lick Fork Lake Asbestos Report (25 pages).pdf PDF
Attachment 6 Experience Questionnaire (3 pages).pdf PDF
Attachment 5a EN Woods Ferry CG Bathhouse Decom (1 page).jpg JPG image
Show all 21

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Solicitation# 12467020R0075

USDA FOREST SERVICE

Francis Marion and Sumter National Forests

Multi-Site Demolition of Structures at

Woods Ferry Campground

Parsons Mountain Campground and Recreation Site

Lick Fork Lake Recreation Site

US Forest Service

4931 Broad River Road Columbia, SC 29212

DIVISION 1 - GENERAL REQUIREMENTS

01010 - SUMMARY OF WORK

A. In accordance with the contract provisions, the contractor is to provide the complete demolition and site recontouring as indicated in the Schedule of Items for Woods Ferry Campground, Parsons Mountain Campground and Recreation area and Lick Fork Lake Recreation area in accordance with the specifications and other provisions of the contract.

Work shall include but not be limited to the following:

Woods Ferry

1. Demolition and disposal of Woods Ferry campground bathhouses in loop A and B (464 sq ft each) and appurtenances. This includes:

a. Complete off-site disposal of demolition debris in a permitted construction and debris landfill. Certificates of disposal or landfill dump tickets are required for submittal.

b. Generally, removal of any asbestos-containing material required by federal or state regulation for separate removal prior to demolition. See asbestos inspection reports for details. The interior surfaces of the cinderblocks are coated with an asbestos-containing skim coat, which is under layers of paint. We have a SC DHEC variance for abatement as a “demo in place” for this structure.

c. Removal of concrete foundations, sidewalks adjacent to the buildings, plus an additional 40 linear feet of nominal 3-foot wide sidewalk extending from the building.

d. Removal of all buried piping under the buildings. All waterlines will be capped approximately 5 feet from the buildings and cap the buried waterline at an up-line distribution point, as directed or agreed by the COR.

e. Remove buried waterline valves and valve boxes servicing the building and generally within 10 feet of the buildings.

f. Coordinate with local power company to disconnect the electrical power from the nearest transformer. Disconnected powerlines shall be removed, recycled, reused, or disposed off Forest Service land.

g. The cleared ground shall be left smoothed and contoured to match surrounding land. Seed and mulch according to Section 02485 below.

2. Not used (Item 1 above includes item 2 from schedule of items.)

Parsons Mountain

3. Demolition and disposal of Parsons Mountain campground and day-use bathhouses (400 sq ft and 864 sq ft) and appurtenances. This includes:

a. Complete off-site disposal of demolition debris in a permitted construction and debris landfill. Certificates of disposal or landfill dump tickets are required for submittal.

b. Removal of any asbestos-containing material required by federal or state regulation for separate removal prior to demolition. See asbestos inspection reports for details. No asbestos was found in this structure.

c. Removal of concrete foundations, sidewalks adjacent to the buildings, plus an additional 40 linear feet of nominal 3-foot wide sidewalk extending from the building.

d. Removal of all buried piping under the buildings. All waterlines will be capped approximately 5 feet from the buildings and cap the buried waterline at an up-line distribution point, as directed or agreed by the COR.

e. Remove buried waterline valves and valve boxes servicing the building and generally within 10 feet of the buildings.

f. Coordinate with local power company to disconnect the electrical power from the nearest transformer. Disconnected powerlines shall be removed, recycled, reused, or disposed off Forest Service land.

g. The cleared ground shall be left smoothed and contoured to match surrounding land. Seed and mulch according to Section 02485 below.

4. Not used (Item 3 above includes item 4 from schedule of items.)

Lick Fork Lake

5. Demolition and disposal of Lick Fork Lake recreation area bathhouse (864 sq ft) and appurtenances. This includes:

a. Complete off-site disposal of demolition debris in a permitted construction and debris landfill. Certificates of disposal or landfill dump tickets are required for submittal.

b. Removal of any asbestos-containing material required by federal or state regulation for separate removal prior to demolition. See asbestos inspection reports for details. No asbestos was found in this structure.

c. Removal of concrete foundations, sidewalks adjacent to the buildings, plus an additional 40 linear feet of nominal 3-foot wide sidewalk extending from the building.

d. Removal of all buried piping under the buildings. All waterlines will be capped approximately 5 feet from the buildings and cap the buried waterline at an up-line distrtibution point, as directed or agreed by the COR.

e. Remove buried waterline valves and valve boxes servicing the building and generally within 10 feet of the buildings.

f. Crush in-place buried concrete septic tank for building.

g. Coordinate with local power company to disconnect the electrical power from the nearest transformer. Disconnected powerlines shall be removed, recycled, reused, or disposed off Forest Service land.

h. The cleared ground shall be left smoothed and contoured to match surrounding land. Seed and mulch according to Section 02485 below.

OPTION ITEMS:

Woods Ferry

6. Demolition and disposal of Woods Ferry campground pump house (72 sq ft) and attached 10,000 gallon cistern. This includes:

a. Complete off-site disposal of demolition debris in a permitted construction and debris landfill. Certificates of disposal or landfill dump tickets are required for submittal.

b. Removal of any asbestos containing material required by federal or state regulation for separate removal prior to demolition. See asbestos inspection reports for details. Asbestos was detected in the silver coating on the tops of the Pump House/Storage Tank.

c. Concrete foundations/floor may be crushed to 12” minus and left in place and covered by existing site soil at least 12” deep. The surface shall be left smoothed and contoured to match surrounding land. Seed and mulch according to Section 02485 below.

d. The buried waterlines (one coming and one leaving the building) shall be connected to bypass the tank/pumphouse outside the old building footprint. Trench shall be at least 2 feet deep and in accordance to plumbing code. COR must inspect the installed line prior to burial.

e. Coordinate with local power company to disconnect the electrical power from the nearest transformer. Disconnected powerlines shall be removed, recycled, reused, or disposed off Forest Service land.

7. Remove and dispose concrete, metal, and wood debris located at Woods Ferry. This debris has been piled in a campsite awaiting disposal. It is composed of concrete picnic tables, lantern poles, and fire rings. Dispose of debris in a permitted construction and debris landfill.

Certificates of disposal or landfill dump tickets are required for submittal.

Parsons Mountain

8. Demolition and disposal of Parsons Mountain former pump house (120 sq ft).

a. Complete off-site disposal of demolition debris in a permitted construction and debris landfill. Certificates of disposal or landfill dump tickets are required for submittal.

b. No asbestos was found on this structure. See asbestos inspection reports for details.

c. Concrete foundations/floor may be crushed to 12” minus and left in place, and covered by imported soil at least 12” deep. The surface shall be left smoothed and contoured to match surrounding land. Seed and mulch according to Section 02485 below.

d. Coordinate with local power company to disconnect the electrical power from the nearest

9. Demolition and disposal of Parsons Mountain 10,000 gallon in-ground concrete cistern; crushed in-place; cover with 10 cu yds of imported soil.

a. The surface shall be left smoothed and contoured to match surrounding land. Seed and mulch according to Section 02485 below.

b. Disconnect electrical service (power to former pump). The electrical service is reportedly disconnected from the tank, but must be verified prior to demolition.

10. Demolition and disposal of Lick Fork Lake pump house (300 sq ft) and water well (6” dia., 197’ deep)

a. Complete off-site disposal of demolition debris in a permitted construction and debris landfill. Certificates of disposal or landfill dump tickets are required for submittal.

b. No asbestos was found on this structure. See asbestos inspection reports for details.

c. The surface shall be left smoothed and contoured to match surrounding land. Seed and mulch according to Section 02485 below.

d. Well is to be abandoned in accordance SC Department of Health and Environmental Control regulations by a SC licensed well driller. Submit a certificate of well abandonment or equivalent documentation to the COR.

e. All waterlines will be capped approximately 5 feet from the building and cap the buried waterline at an up-line distribution point, as directed or agreed by the COR.

f. Coordinate with local power company to disconnect the electrical power from the nearest

11. Demolition and disposal of Lick Fork Lake 10,000 gallon in-ground concrete cistern; crushed in-place.

a. Crushed in-place to 12” minus. cover with 10 cu yds of imported soil.

b. The surface shall be left smoothed and contoured to match surrounding land. Seed and mulch according to Section 02485 below.

c. The electrical service is reportedly disconnect from the tank and must be verified prior to demolition.

12. Demolition and disposal of the Chattooga River cabin (591 sq ft), ~30’ drinking water well, and appurtenances

a. Complete off-site disposal of demolition debris in a permitted construction and debris landfill. Certificates of disposal or landfill dump tickets are required for submittal.

b.Removal of any asbestos containing material required by federal or state regulation for separate removal prior to demolition. See asbestos inspection reports for details. Asbestos was detected in the white/green vinyl flooring and window glaze.

c. Well is to be abandoned in accordance SC Department of Health and Environmental Control regulations by a SC licensed well driller. Submit a certificate of well abandonment or equivalent documentation to the COR.

d. Coordinate with local power company to disconnect the electrical power from the nearest transformer. Disconnected powerlines shall be removed, recycled, reused, or disposed off Forest Service land.

e. The cleared ground shall be left smoothed and contoured to match surrounding land. Seed and mulch according to Section 02485 below.

13. Remove and dispose of yard hydrants, free-standing drinking fountains, and associated concrete slabs. The cleared ground shall be left smoothed and contoured to match surrounding land. Seed and mulch according to Section 02485 below. Slab size ranges from 5’ x 5’ to no slab.

14. Remove and dispose of concrete picnic tables.

a. Smooth and compact surface to match surrounding ground.

15. Disconnect, remove and dispose of campsite electrical pedestal.

a. Coordinate with local power company to disconnect the electrical power from the nearest transformer.

b. Disconnected powerlines shall be removed, recycled, reused, or disposed off Forest

Service land.

c. Smooth and compact surface to match surrounding ground.

B. Contractor shall contact the power company and telephone company for the location of existing underground electric and telephone lines prior to any excavation or trenching. Phone service is not known to be present at these sites, but contractor should inquire prior to excavation. All utilities, structures, trees and surfaces not planned for demolition shall be protected from damage.

Contractor shall coordinate with the serving electric cooperative for the permanent disconnection of electrical service from all buildings to be demolished.

Woods Ferry area: Fairfield Electric Cooperative, 803-754-0153 Parsons Mountain area: Little River Electric Cooperative, 864-366-2141 or 800-459-2141 Lick Fork Lake area: Aiken Electric Cooperative, 803-649-6245 Chattooga River Cabin: Haywood Electric Member Cooperative (North Carolina), (828)

966-4215 or (800) 951-6088.

C. See Appendix A, Directions to the sites and photos of buildings and items to be demolished.

01060 – REGULATORY REQUIREMENTS

All material to be removed shall be disposed of in accordance with SC State Regulations.

Contractor shall complete and submit the DHEC D-3428 form, Demolition License Application for a demolition permit from SCDHEC for all buildings authorized for demolition. Contractor is responsible for payment of all required fees.

Contractor shall complete and submit the DHEC D-3430 form, Asbestos Abatement Project License Application for a demolition permit from SCDHEC for any buildings that require asbestos removal. Contractor is responsible for payment of all required fees.

Contractor shall complete and submit the DHEC D-3688 form, Waste Shipment Record upon completion of demolishment of all buildings authorized for demolition. Contractor is responsible for payment of all required fees.

Forms are available at: https://www.scdhec.gov/permits-regulations/forms-applications-registration-reporting-etc#asbestos_demolition

The US Forest Service has completed the asbestos building inspections. There have been no changes to the structures since the last inspection, except deterioration from natural processes.

Well abandonment must be completed according to SCDHEC Regulation 61-71, SC Well Standards, https://www.scdhec.gov/sites/default/files/media/document/R.61-71.pdf. The SC DHEC Water Well Record Form 1903 may be required to be submitted to the state by the licensed well driller. Contractor is responsible for payment of all required fees.

01300 – SUBMITTALS

A. Contractor shall submit to the COR, data sheets and/or drawings for all "or equal" substitutions proposed in lieu of the name brands specified prior to commencing any work that relates to a respective submittal. Contractor shall submit 3 copies of all submittals, or electronically if approved by the Contracting Officer. Technical submittals related to the contract may be submitted to the COR electronically.

B. Submittals to the COR for this contract include:

1. Proposed work schedule and any changes to work schedule, in advance.

2. Contractor’s safety plan and spill abatement plan.

3. Copy of all forms submitted to SC DHEC.

01410 - TESTING LABORATORY SERVICES

A. The Contractor shall be responsible for securing the services of a recognized testing and laboratory firm that is approved by the State to perform all tests required. The Contractor shall be responsible for taking, handling and transporting all samples to the laboratory.

01510 - TEMPORARY UTILITIES

A. Electricity – electricity is only available in limited areas of the work sites. Contractor should plan to use a portable generator if power is needed.

B. Water -Potable water (drinking water) may or may not be available at the sites. Each site has a water system, but the system is shut down seasonally and is sometimes determined to be not potable. Contractor shall plan to bring water for crew drinking water needs.

C. Sanitary - Sanitary facilities may or may not be available at the site (vault toilet). One or more sites may use rented portable toilets during seasonal opening.

01635 - PROTECTION OF ADJACENT AREAS

A. The Contractor shall be responsible for protecting from damage all adjacent areas and existing improvements around or near the project site. All damage to areas caused by construction/demolition activities or equipment shall be immediately reported to the COR.

The Contractor shall be responsible for repairing all damaged areas as directed by the CO

01700 - PROJECT CLOSEOUT

A. Instructing Owner in Use of Building

It is the responsibility of the Contractor to see that the proper manufacturer's representatives, subcontractors, contractor's superintendents, etc., are available at completion of the job and before occupancy to provide instructions in the use of all facilities and equipment and to train personnel in the proper use and maintenance of the building, equipment controls, switches, valves, etc.

For this contract, this section covers contractor instructing COR on all valves installed, condition of all pipes terminated, electrical power terminations, and any other utilities changed during the contract.

01732 - SELECTIVE DEMOLITION

PART 1 - GENERAL

1.1 SECTION REQUIREMENTS

A. Unless otherwise indicated, demolished materials become Contractor's property.

Remove from Project site.

B. Items indicated to be removed and salvaged remain Government property. Remove, clean, and deliver to Owner's designated storage area.

C. Comply with EPA regulations and disposal regulations of authorities having jurisdiction.

D. Conduct demolition without disrupting Governments use of sites.

E. Hazardous Materials: Some normal building materials may become hazardous materials during the demolition process and associated hazardous materials waste can be generated.

1. Asbestos inspection reports have been completed on buildings as required by law.

Asbestos is addressed in section 024230.

2. Air conditioners and heat pumps contain freon gases that must be recovered prior to final disposal. These appliances are not known to be present in these buildings.

3. Other building components that may contain hazardous materials include: exit signs, mercury lamps, mercury thermostats and switches, PCB ballasts and capacitors, and smoke detectors. These items may be recycled as universal wastes at licensed landfills or other licensed disposal sites. None of these items have been identified in these buildings.

4. If hazardous materials or materials suspected of containing hazardous materials are encountered that are beyond the normal scope of building demolition, immediately notify the COR or Contracting Officer.

1.2 DEMOLITION

A. Maintain and protect existing utilities to remain in service before proceeding with demolition, providing bypass connections to other parts of the building.

B. Locate, identify, shut off, disconnect, and cap off utility services to be demolished.

C. Conduct demolition operations and remove debris to prevent injury to people and damage to adjacent buildings and site improvements.

D. All asbestos materials shall be removed and disposed prior to demolition of the structure.

E. Contractor shall prevent demolition debris, nails, glass, etc., from falling on walkways and road areas. Site shall be left in a neat and safe condition at the end of each working day.

F. Contractor shall not remove or otherwise damage existing trees unless otherwise directed by COR.

G. Protect Government structures, sidewalks and improvements that are to remain. Cover and protect fixtures, furnishings, and equipment that are to remain.

H. Saw cut any concrete slabs that are to remain. Neatly cut openings and holes plumb, square, and true to dimensions required. Use cutting methods least likely to damage construction to remain or adjoining construction.

I. Promptly remove demolished materials from Government property and legally dispose of them. Do not burn demolished materials.

SECTION 02210

SITE GRADING AND EXCAVATION

A. This item covers all required site grading, including building excavation, borrow material, waterlines and the final dressing of all areas.

B. All work shall be in accordance with details shown in the plans and herein specified.

PART 2 - PRODUCTS

A. Existing topsoil removed from excavations, stockpiled on site.

B. Topsoil availabe onsite will be reapplied to filled excavations. Any topsoil furnished by the

Contractor must be approved by the COR in advance.

C. Borrow material, as needed and specified, furnished by the Contractor and approved by the

COR.

D. Material for interior fills of buildings shall consist of crushed stone, ranging in size from 1/2 inch to 2-1/2 inches. No fines shall be allowed.

PART 3 - EXECUTION

A. Excavation and fills shall produce surfaces to the lines and grades to restore the site grades to match that of surrounding land.

B. All excess excavated soil shall be disposed of on the project site at a location designated by the COR. The material shall be spread evenly and seeded and mulched as directed.

G. Contractor shall not remove or otherwise damage existing trees unless otherwise directed by

COR.

SECTION 02485

SEEDING AND MULCHING

PART 1 – GENERAL

A. This section covers the seeding and mulching of areas disturbed during construction.

PART 2 – PRODUCTS

A. Seeding shall be a mixture of the following weed-free seeds:

Nurse crop:

Sept.1 to April 1: Wheat/Oats/Grain Rye: 80 lb/acre; Crimson Clover 10 lb /acre April 2 to August 31: Brown Top Millet 30 lb/acre

Native perennial grasses

Big Bluestem 2 lb/acre Indiangrass 3 lb/acre Little Bluestem 5 lb/acre

Sources of native ecotype seed:

Roundstone Native Seed 1-888-531-2352 or 1-270-531-3032, roundstoneseed.com Ernst Conservation Seeds 1-800-873-3321 or 1-814-336-2404, ernstseed.com National Wild Turkey Federation, Conservation Seed Program, outdoordealhound.com/c-

179-warm-season-grasses-forbs, Southeast Coastal Plains or Southeast Upland Mix, respectively, 1-800-THE-NWTF

Mellow Marsh Farm 1-919-742-1200, mellowmashfarm.com

B. Mulch shall be straw, pine straw or approved equal.

PART 3 – EXECUTION

A. All disturbed areas shall be lightly graded, seeded, and mulched.

B. Mulch shall be applied to a thickness such that the soil material can not be seen.

SECTION 02221

TRENCH EXCAVATION, BACKFILL AND COMPACTION

A. This item covers all trenching, backfilling and compacting. These items may be needed for repair of infrastructure damaged during the contract.

B. All excavation work shall be unclassified.

PART 2 - PRODUCTS

A. Gravel shall be as specified and or agreed by COR.

B. Cold Bituminous Mix shall be a paving material as manufactured by Perma-Patch or equal.

PART 3 - EXECUTION

A. The trenches receiving the pipe shall be the minimum width possible with consideration being given to working room and safety within the trench.

B. The depth of the trench shall be as shown on the drawings.

C. The trench bottom shall be raked smooth and compacted to form proper bed for pipe and prevent settlement at the bottom of the trench.

D. Pumping, Bailing and Draining

1. The Contractor shall remove by pumping, bailing, or draining any water which may accumulate, or be found, in the trenches and other excavation made under this contract and shall form all dams, flumes or other works necessary to keep them entirely clear of water while the utility lines are being constructed.

E. Trench Backfilling and Compaction

1. Trench backfilling shall be carefully performed so as not to cause movement of the pipe within the trench.

1. Backfill shall be carefully deposited and compacted on both sides of the pipe to avoid damaging pipe.

2. Warning tape shall be installed in all water line trenches as shown on the drawings.

SECTION 024230

ASBESTOS ABATEMENT

PART 1 - GENERAL

1.1 SCOPE

A. This section applies to the required state notification of asbestos inspection prior to demolition projects, and the removal of asbestos-containing materials that may be required prior to or as part of the demolition work.

B. Work shall consist of furnishing all labor material, equipment and supervision to perform asbestos removal and disposal in accordance with these specifications, EPA (AHERA, Asbestos NESHAPS), OSHA, NIOSH, DOT, State of South Carolina, Department of Health and Environmental Control (DHEC), Asbestos Section, and any other applicable federal, state, or local regulations.

1.2 DESCRIPTION OF WORK

A. The Forest Service sites consists of multiple facilities, located on the Sumter National Forest. See attached location information for structures to be demolished. A recent inspection by a certified asbestos inspector has not revealed the presence of friable or non-friable asbestos in the buildings. The asbestos inspection report is included as a reference to the contract documents. Notify the COR if additional asbestos is found during the demolition process.

A pre-demolition inspection by Crossroads Environmental, LLC. has identified the following asbestos materials:

Woods Ferry: The bathhouses interior surfaces of the cinderblocks are coated with an asbestos-containing skim coat, which is under layers of paint. We have a SC DHEC variance for abatement as a “demo in place” for this structure. Asbestos was detected in the silver coating on the top of the Pump House/Storage Tank.

Chattooga River Cabin: asbestos was detected in the white/green vinyl flooring and window glaze. The scope of the abatement work is or would be described in the inspection report.

B. All asbestos abatement work will be performed prior to building demolition activities unless otherwise approved by SC DHEC.

1.3 QUALIFICATIONS

A. The contracting firm must be certified by SC DHEC as a licensed Asbestos Abatement Contractor. Employed workers are required to be SC licensed certified asbestos workers, in accordance with applicable State and federal regulations and for the work areas in which they are accredited. In addition, the asbestos contractor must carry active “occurrence” type liability insurance while performing any work under this contract.

1.4 APPLICABLE REGULATIONS AND PUBLICATIONS

A. The regulations listed below form a part of this specification to the extent referenced.

The publications are referred to in the text by the basic designation only. The latest version of applicable regulations shall take precedence over the requirements of this specification when the regulation results in a higher standard of performance.

1. Code of Federal Regulations (CFR) Publications:

a. 29 CFR 1910.20 Access to Employee Exposure and Medical Records

b. 29 CFR 1910.134 Respiratory Protection

c. 29 CFR 1910.145 Specifications for Accident Prevention Signs and

Tags

d. 29 CFR 1926.1101 Asbestos’ Tremolite, Anthophyllite, and Actinolite

e. 40 CFR 61, Subpart A General Provisions

f. 40 CFR 61, Subpart M National Emission Standard for Hazardous Air

Pollutants (NESHAP)

g. 40 CFR 241 Guidelines for the Land Disposal of Solid Wastes

h. 40 CFR 257 Criteria for Classification of Solid Waste Disposal

Facilities

i. 40 CFR 763 Appendix C to Subpart E Asbestos Model

Accreditation Plan

j. 49 CFR 171 and 172 Department of Transportation (DOT) General

Information

k. 49 CFR 171 and 172 Hazardous Material Transportation

2. State of South Carolina Regulation:

a. Regulation 61-86.1, Standards of Performance for Asbestos Projects

b. Contact SC DHEC Asbestos Section (803) 898-4289 for specific requirements.

3. American National Standards Institute (ANSI) Publications:

a. Z9.2-79 Fundamentals Governing the Design and Operation of Local Exhaust Systems

b. Z88.2-80 Practices for Respiratory Protection

4. National Institute of Occupational Safety and Health (NIOSH) Publications:

a. Manual of Analytical Methods, 2nd Ed., Vol. 1, Physical and Chemical Analysis Method (P&CAM):

1) Method 239 Asbestos Fibers in Air

2) Method 7400 Fibers (NI, 3rd Ed., Vol. 1)

5. Underwriters Laboratories, Inc. (UL) Publication:

a. 586-77 (R 1982) Test Performance of High Efficiency Particulate, Air Filter Units

1.5 DEFINITIONS

A. (Refer to Federal Regulations for definitions of terms used in this document.)

1.6 PROTECTION OF GOVERNMENT PROPERTY

A. All abatement work shall be performed without damage to or contamination of adjacent areas, equipment or materials. Should existing equipment or materials become damaged or contaminated by work done under this contract, the contractor shall restore all areas to original condition at no additional cost to the government.

1.7 MEDICAL REQUIREMENTS

A. Upon request of the Government, the contractor shall provide documentation for the workers initial and annual medical surveillance requirements.

1.8 TRAINING

A. The contractor shall provide documentation (as required in the Submittals, Section 1.12) that the workers are trained and certified in accordance with federal regulations and applicable State regulations and have completed the requirements for the annual 8-hour refresher course(s) for the work areas in which they are certified. Training for asbestos abatement professionals is required under the Asbestos Hazard Emergency Response Act of 1986 (AHERA), which is the authority under which EPA issued the EPA Asbestos Model Accreditation Plan (MAP) (40 CFR Part 763, Appendix C to Subpart E). The MAP established five required training disciplines (worker, contractor/supervisor, inspector, management planner, and project designer) and one recommended discipline (project monitor).

1.9 LICENSES, PERMITS, AND NOTIFICATIONS

B. The contractor is responsible for obtaining all necessary permits in conjunction with asbestos removal, hauling, and disposal. Provide timely notification of such actions as may be required by federal, state, regional, and/or local authorities.

C. Notify the SC DHEC 10 days prior to the commencement of work in accordance with applicable regulations. Submit a copy of this notification to the Contracting Officers Representative (COR) prior to beginning any work.

D. Notify the COR at least 48 hours prior to beginning work. Failure to obtain proper permits, or failure to make proper State/EPA notification, or beginning work without first coordinating with the COR in advance, will be sufficient grounds for termination of this contract.

E. South Carolina asbestos certification/license is required for all individuals engaged in any aspect of asbestos abatement or design. This certification shall be current.

1.10 SAFETY AND HEALTH COMPLIANCE

A. In addition to detailed requirements of this specification, comply with laws, ordinances, rules, and regulations of federal, state, regional, and local authorities regarding handling, storing, transporting, and disposing of asbestos waste materials. Comply with the applicable requirements of the current issue of 29 CFR 1926.1101 and 40 CFR 61, Subparts A and M. Where specification requirements and performance documents vary, the most stringent requirement shall apply.

1.11 RESPIRATOR PROGRAM

A. Upon request by the Government, the contractor shall submit documentation of an established respiratory protection program as required by ANSI Z88.2 and 29 CFR 1910.134.

1.12 SUBMITTALS

A. Submittals shall be provided to the COR for approval 10 working days prior to commencing work involving asbestos materials.

B. Qualifications: Submit evidence that the contracting firm is licensed by SC DHEC as an “Asbestos Contractor” in accordance with the provisions of South Carolina regulation 61-86.1 and that the employed workers are trained and certified/licensed for their respective discipline.

C. Asbestos Work Plan: Submit a detailed, project design plan of the work procedures to be used in the removal and abatement of materials containing asbestos. The plan shall be prepared and signed by the certified Project Designer. Such plan shall include a sketch showing the location, size, and details of asbestos control areas, location, layout, and details of the decontamination area, and locations of local exhaust equipment. The plan shall indicate all temporary utilities and include interface of trades involved in the construction, sequencing of asbestos-related work, disposal plan, type of wetting agent to be used, air monitoring, respirators, protective equipment, and a detailed description of the method to be employed in order to control site access and the generation of airborne asbestos including contingencies for containment breach, and fire. The plan must be approved by the government prior to the start of any asbestos work. Prior to beginning work, the Contractor shall meet with the COR to discuss in detail the asbestos plan, including work procedures and safety precautions.

D. Air Monitoring Plan: Submit a detailed air monitoring plan to address monitoring of the site and adjacent areas prior to, during, and (if required for demolition projects) after completion of the asbestos work. The air monitoring section shall address the use of a qualified independent third party (such as an Industrial Hygienist) not employed by the abatement contractor to perform any required air monitoring for this contract. This qualified person shall be EPA Contractor/Supervisor or Project Monitor certified for asbestos projects. If monitoring outside the asbestos control area shows airborne concentrations have reached the action level, stop work, correct the condition(s) causing the increase, and notify the COR immediately. In areas where the construction of an enclosed asbestos control area is not required, after initial Time Weighted Averages (TWA’s) are established, and provided the same type of work is performed, provide personal and area monitoring at the designated limits of the asbestos work area at a frequency noted in the asbestos work plan. This plan must be approved by the government prior to the start of any asbestos work. Prior to beginning work, the Contractor shall meet with the COR to discuss in detail the asbestos air monitoring plan.

F. Testing Laboratory: Submit the name, address, and certification documents of the testing laboratory selected to perform all sample analysis when required by this contract. The lab shall be certified under the National Voluntary Lab Accreditation program (NVLAP) and American Industrial Hygiene Agency (AIHA) accredited.

G. Landfill: Submit evidence that the landfill selected is approved for disposal of asbestos by the EPA, State, and local regulatory agencies.

H. Submit Proof of Insurance: Contractor shall submit proof of an active occurrence type liability insurance policy that covers asbestos abatement. Claims made policies are unacceptable.

I. Submit evidence of notification: Contractor shall submit documentation of the required NESHAP notification to the SC DHEC Asbestos Section, as specified in paragraph “Licenses, Permits, and Notifications” above, prior to starting work.

J. Air Monitoring results: Submit documentation of fiber counts. Submit monitoring results to the COR within 24 hours of receipt, signed by the testing laboratory. Note:

Containment work areas shall not be torn down until post-removal air monitoring results meet the clearance level requirements AND the COR has approved the testing results and provided written permission.

K. Waste shipment records: Submit completed waste shipment records for regulated asbestos containing materials RACM as required by the National Emission Standards for Hazardous Air Pollutants NESHAPS regulations. The term “owner” shall refer to the Government. The term “operator” shall refer to the contractor. The signature block for the operator shall be signed by an authorized agent of the contractor. At the completion of the project, submit a final report. This report shall contain, all air monitoring results, all clearance testing results, and the WSR record for disposal of the asbestos removed.

1.13 MEASUREMENT AND PAYMENT

1. Asbestos abatement is included in demolition price by structure.

PART 2 - PRODUCTS

2.1 EQUIPMENT

A. Warning Signs and Labels: Provide warning signs in accordance with OSHA 29 CFR

1926.1101 at all approaches to asbestos control areas. Provide all drums, bags, wrapped components, or other similar asbestos laden containers with appropriate warning labels.

B. Back-up Generator: During abatement of friable asbestos, the contractor may be required to provide an auxiliary back-up generator to supply power automatically to negative air system should commercial power fail. This requirement will be spelled out specifically in the Statement of Work if required.

C. Local Exhaust System: Local exhaust systems (for enclose work areas) must be installed and operated in accordance with ANSI Z9.2. The contractor shall notify the COR immediately of any variance in the pressure differential which could cause exposure of adjacent unsealed areas to asbestos fiber concentrations in excess of 0.01 fibers/cc.

D. Temporary Utilities: If required, the contractor must supply water and power to the work site as necessary. In most cases, though not always, electrical power and cold water for use will be available at or within 200 feet of work site. The contractor may be required to provide electricity with an electric generator or to transport water onto the work site for use. However, hot water in quantities needed for showers will not be available and must be provided by the contractor. Location of power/water requirements to be used shall be addressed in the design plan.

PART 3 - EXECUTION

3.1 WORK AREA

L. Perform asbestos-related work in accordance with OSHA, EPA, and SC DHEC regulations, and as specified herein.

M. Asbestos Control Area Requirements: The construction of a totally enclosed asbestos control area may at times be impractical or impossible within the project limits (such as for outdoor asbestos work). When this determination is made, the contractor may submit the details of alternative control measures as part of the Asbestos Work Plan. Provide a 20-foot roped off perimeter around the area where the asbestos handling procedures are performed and maintain other requirements for asbestos control areas.

N. Control Area Requirements for Removal of Non-friable Asbestos Materials: For interior surfaces where the non-friable asbestos surface material (such as Resilient Floor Coverings, Vinyl Asbestos Tiles, or Asbestos Cement panels) can be removed intact, perform the work in accordance with applicable OSHA regulations.

O. Monitoring: Monitoring of airborne concentrations of asbestos fibers shall be in accordance with 29 CFR 1926.1101 and as specified herein using NIOSH Method 7400.

The Government shall have the option to perform independent monitoring.

P. Site Inspection: While performing asbestos removal work, the Contractor shall be subject to on-site inspection by the COR who may be assisted by Government safety or environmental personnel. If the work is found to be in violation of any part of these specifications, the COR will issue a stop work order which will take effect immediately and remain in place until the violation is resolved. Standby time and expenses required to resolve the violation shall be at the Contractor’s expense.

3.2 CLEARANCE SAMPLING AFTER FINAL CLEANUP

Q. For asbestos abatement projects conducted with an enclosed containment area, the contractor shall perform an aggressive air sample of the area (at least 3 samples per removal site, with minimum volume of 2,400 liters of air per sample with a flow rate and sample time to yield a sample result that will provide statistical confidence that the air concentration is below 0.01 f/cc.). Submit the results of these samples to the COR. The contractor shall not remove the containment area until written permission is received from the COR. Before authorization to tear down the containment structure will be granted, the fiber counts from all three samples must be less than 0.01 fibers per cubic centimeter of air. If the baseline TWA, established before work began, is greater than 0.01 f/cc, then all three samples must not exceed the baseline count. Should any of the three final samples indicate a higher value, the Contractor shall re-clean the area and shall repeat the clearance process until the fiber count is equal to or below that set by the above limits.

All costs associated with re-cleaning and re-testing as a result of failure to meet clearance sampling limits shall be borne by the contractor.

3.3 DISPOSAL OF ASBESTOS

R. Collect asbestos waste, scrap, debris, bags, containers, equipment, and asbestos-contaminated clothing which may produce airborne concentrations of asbestos fibers, in sealed double 6 mil plastic bags labeled in accordance with 29 CFR sec. 1910.100 (j) (2) or 1926.1101 (k) (2) (iii). The name “US Forest Service” and the location of the site where the asbestos waste was generated must be clearly and permanently affixed to the container label or wrapping. Where the asbestos material is hard or otherwise has sharp edges the material shall be prepackaged in burlap, nylon or other material to prevent puncture of the plastic. Dispose of waste asbestos material in the approved landfill designated in the submittals. Before transporting off site, complete the required waste shipping record (WSR) and have it signed by the COR or designated government representative. No asbestos waste will be permitted to leave the site without a completed and signed waste shipping record. Upon arrival at the approved disposal site, the WSR is to be signed by the site personnel and a copy of the signed WSR is to be sent to the contractor within the time frame as required by 40 CFR 61.149(e). A copy of the returned WSR is to be provided to the COR. If the signed copy of the WSR is not received by the contractor within 35 days, the contractor must contact the site to determine the status of the waste shipment. If after 45 days a copy has still not been received, the contractor must notify U.S. EPA Regional Asbestos NESHAPS Coordinator in writing and provide the following information: (a.) A copy of the WSR for the load in question, and (b.) A cover letter signed by the contractor explaining his efforts to locate the waste shipment and the results of those efforts. Failure to comply with this or other requirements of the specification will constitute sufficient grounds for termination of this contract. For temporary storage if necessary, an area for interim storage of asbestos waste will be assigned by the COR or by an authorized representative. Procedure for hauling and disposal shall comply with 40 CFR 61, Subpart M, 49 CFR 172-177, 40 CFR 241 and 257, and state, regional, and local standards.

END OF SECTION 024230

Appendix A

List of primary buildings in contract:

FMS NF Demolition list 2020

DISTRICT_NAME SITE/BUILDING_NAME SITE_TYPE Notes Approximate Square Feet

Year Constructed

ENOREE RD

WOODS FERRY

CAMPGROUND

BATHHOUSE LOOP A CAMPGROUND

Building #714.

Cinderblock constr. 464 1964

ENOREE RD

WOODS FERRY

CAMPGROUND

BATHHOUSE LOOP B CAMPGROUND

Building #715.

Cinderblock constr. 464 1964

ENOREE RD

WOODS FERRY PUMP

HOUSE CAMPGROUND

#724.

Cinderblock constr. 72 1964

LONG CANE RD

PARSONS MOUNTAIN

PICNIC AREA

BATHHOUSE PICNIC SITE

#310.

Cinderblock constr. 864 1992

LONG CANE RD

PARSONS MTN LAKE

CAMGROUND

BATHHOUSE CAMPGROUND

#316.

Cinderblock constr. 400 1967

LONG CANE RD

PARSONS MTN LAKE

FORMER PUMP

HOUSE CAMPGROUND

#334.

Reinforced concrete 120 1966

LONG CANE RD

LICK FORK LAKE PICNIC

PUMPHOUSE

RECREATION

AREA

#810.

Cinderblock constr. 300 1970

LONG CANE RD

LICK FORK LAKE PICNIC

AREA BATHHOUSE

RECREATION

AREA

#809.

Cinderblock constr. 864 1992

ANDREW

PICKENS RD

CHATTOOGA RIVER

CABIN

RIVERFRONT

AQUISITION

Wood frame on cinderblock.no# 591 1958

Appendix B

Google map locations of sites:

Woods Ferry Campground, Union County, SC:

https://www.google.com/maps/place/Woods+Ferry+Recreation+Area/@34.7016642,- 81.4561903,15.39z/data=!4m5!3m4!1s0x88564db60fddc8ff:0xfa4ae185ee6ee88a!8m2!3d34.700 6923!4d-81.4506528?hl=en

Parsons Mountain Campground, near Abbeville, SC:

https://www.google.com/maps/place/Parsons+Mountain+Lake+Campground/@34.1019799,- 82.358126,15.71z/data=!4m5!3m4!1s0x88f7fa84ecbc8343:0x4a1d99ecd2cd96f4!8m2!3d34.100 1189!4d-82.3542931?hl=en

Lick Fork Lake recreation area, near Edgefield, SC:

https://www.google.com/maps/search/Lick+fork+lake+campground/@33.728943,- 82.0440297,17z/data=!3m1!4b1?hl=en

Chattooga River Cabin, Oconee County, 119 Beaver Lane, Mountain Rest, SC:

https://www.google.com/maps/dir//119+Beaver+Ln,+Mountain+Rest,+SC+29664/@34.9052481 83.1826191,17z/data=!4m9!4m8!1m0!1m5!1m1!1s0x8858e69179da2ce5:0x670ce6c5ce4f520b!

2m2!1d-83.1804304!2d34.9052437!3e0?hl=en

Appendix C

Building photos

Woods Ferry Campground:

Bathhouses, front and rear view. Both bathhouses are the same.

Pumphouse in front of water tank/cistern

Concrete, steel, and wood debris staged for removal

Parsons Mountain Campground:

1. Bath house- at rec area

2. Bath house at campground

3. Former pumphouse (concrete); buried 10,000 gallon tank manhole at far right.

Lick Fork Lake Picnic Area

1. Old Pump house with well; 10,000 gallon cistern manhole

2. Bathhouse at day-use area

Multiple location Optional components for demolition:

3. Fountains, yard hydrants, picnic tables, electrical pedestal

Chattooga River Cabin: front, access from highway, and interior