This is a Statement of Work (SOW) for re-establishing a Mexfly Citrus Research Grove at the Insect Management and Molecular Diagnostics Lab (IMMDL) in Edinburg, Texas. The project involves preparing a 2.5-acre site at Moore Air Base for a citrus research grove in support of fruit fly eradication efforts by Plant Protection and Quarantine (PPQ). The contractor is required to complete six primary tasks: 1) purchase materials including a sand filtration tank, irrigation lines, wind break panels, and a remote weather station, 2) clear the land and prepare soil, 3) install sand filtration tank and irrigation lines, 4) construct raised beds with specific dimensions and configurations, 5) install wind break panel fencing, and 6) install a comprehensive weather monitoring system.
The solicitation is a Total Small Business Set-Aside with a small business size standard of $9.5 million, targeting the North American Industry Classification Standard Code 561730. The project must be completed before March 30, 2026, with specific milestone deadlines including material procurement by January 30, 2026, and various construction tasks completed by February and March 2026. The work will be performed at the Animal and Plant Health Inspection Service location at 22675 N Moorefield Road, Edinburg, TX, with contractors required to complete background screening and daily security check-ins.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Attachment 1 - Solicitation Terms and Conditions.docx 1.docx | DOCX document | |
| Attachment 2 SOW Grove Construction IMMDL Modified 1.docx | DOCX document | |
| Attachment 2 SOW Grove Construction IMMDL Modified.docx | DOCX document | |
| Site Visit handout.pdf | ||
| 20260122_Questions from Contractors_ds.docx | DOCX document | |
| Attachment 1 - Solicitation Terms and Conditions.docx LD.docx | DOCX document | |
| Attachment 3 - SCA Wage Rates Hidalgo County.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Attachment 2: STATEMENT OF WORK Re-Establish a Mexfly Citrus Research Grove at S&T Insect Management and Molecular Diagnostics Lab (IMMDL)
GENERAL INFORMATION
1.0 Scope of work:
This project aims to re-establish the research citrus grove at the Insect Management and Molecular Diagnostics Lab in Edinburg, TX during FY26 in support of fruit fly eradication and detection efforts by PPQ.
2.0 Background:
The new grove construction site is located in a previously unused part of Moore Air Base along the main road and between the IMMDL facilities and the air craft hangar (26°23’36”N, 98°20’02”W). To install a new planting, we will need to contract for ground debris removal and soil prep, running new drip irrigation lines, installing a new sand filtration tank, and building raised beds for the trees. The total grove size is approximately 2.5 acres.
CONTRACTOR REQUIREMENTS
3.0 Technical requirements/tasks
3.1 Task 1 – Purchase required materials
The contractor shall provide the materials needed for the project including:
1) a sufficiently sized sand filtration tank,
2) irrigation lines (estimated 6000 linear feet required),
3) valves and fittings sufficient for dual drip line irrigation along each raised bed,
4) ground cover for the raised beds,
5) soil and compost for the raised beds,
6) 650 linear feet of 50% wind break panels (3 m high), posts, and installation components,
7) and a remote weather station (Onset RX300).
a. Solar powered with 15 Watt panel
b. Hobonet Temp/RH sensor
c. Smart Barometric pressure sensor
d. Hobonet Solar Radiation sensor
e. Hobonet Rainfall sensor
f. Hobonet Windspeed and director sensor
3.2 Task 2 – Clear land and prepare soil
The contractor shall remove weeds, tree stumps, and all other debris including old irrigation lines from the construction site. The ground shall be cleared completely to make the 2.5 acre area suitable for grove installation.
3.3 Task 3 – Install sand filtration tank and irrigation lines Raw water lines that feed the MAB Water Treatment Plant will be tapped into as a water source to supply the citrus research grove. The contractor shall install the sand filtration tank and irrigation lines. New water lines of sufficient size/volume will be trenched in, valved, and buried on site.
3.4 Task 4 – Construct raised beds
The contractor shall construct raised beds for the grove (Figure 1). Each row should be spaced 20 ft apart with a dual drip line inside each bed. The beds should be 8 ft wide at the base, 6 ft wide at the top, and 1.5 ft deep with ground soil topped with 6” of compost. The beds will be covered with a ground cover material and secured. Rows should be constructed in parallel continuously to allow a vehicle or tractor to pass between rows for pruning and spraying.
3.5 Task 5 – Install wind break panel fencing
Wind break panels shall be installed along the South East and South West perimeter of the new grove. Posts for the fencing shall be installed 16 ft apart (4 m), each measuring 10 ft high. Each post must be secured in concrete footing at the base to prevent movement. The artificial wind break netting shall be 50 % windbreak mesh netting measuring 3 m tall along the posts (https://eyouagro.com/product/50-windscreen/). The netting shall be pulled taut and tightly affixed to the posts.
3.6 Task 6 – Install weather station
The contractor shall follow weather installation guidelines provided by the manufacturer. Sensors for temperature, relative humidity, barometric pressure, wind speed and direction, rainfall, and light (solar radiation) shall be installed.
Figure 1. Grove planting plan with row and tree spacing guidelines. Green lines on map indicate rows in the 2.5 acre plot. Wind screen placement is indicated by the dashed blue line.
4.0 Delivery schedule
| Task Number |
| Work |
Milestones Projected Completion Date
| 3.1 |
| Purchase required materials |
| Jan 30, 2026 |
| 3.2 |
| Clear land and prepare soil |
| Feb 15, 2026 |
| 3.3 |
| Install sand filtration tank and irrigation lines |
| Feb 30, 2026 |
| 3.4 |
| Construct raised beds |
| Mar 15, 2026 |
| 3.5 |
| Install wind break panels |
| Mar 30, 2026 |
| 3.6 |
| Install weather station |
| Mar 30, 2026 |
5.0 Government-furnished property, material, or information (GFP, GFM, GFE, GFI) None
6.0 Security
On-site contractors are required to complete background screening. Entry to the facility requires daily check-in with the security guards at the front gate.
7.0 Travel
None
8.0 Special material requirements and considerations
None
9.0 Place of performance
The construction project will take place at Animal and Plant Health Inspection Service (APHIS), 22675 N Moorefield Road, Edinburg, TX 78541.
10.0 Period of performance
The project must be completed, in its entirety, before March 30, 2026.
image1.png image2.png