This is a Statement of Work (SOW) for the installation of fiber optic infrastructure at Craters of the Moon National Monument and Preserve in Arco, Idaho, issued under RFQ 140P8326Q0040 by the National Park Service—South Idaho Parks.
The project requires the contractor to install a complete fiber optic cable and conduit infrastructure connecting eight designated park buildings, originating from a service connection point in Arco and extending to the park boundary along the highway corridor. The scope includes fiber installation (minimum 24-strand, single-mode cable) inside conduit with full terminations, splicing, labeling, testing, and certification of all fiber strands. Installation methods are specified as plowing in existing disturbed corridors (current analog line routes, road shoulders, previously disturbed soils) and horizontal directional boring in paved areas, sidewalks, road crossings, and sensitive resource zones. Conduit shall be primarily HDPE with pull tape installed throughout and include traffic-rated, NPS-approved vaults and handholes per design specifications. The contractor must perform end-to-end OTDR and light-loss testing, provide electronic test results and redlined as-built drawings in PDF and GIS-compatible formats reflecting route alignment, handhole locations, conduit sizes, fiber strand counts, and building entry points. All disturbed ground must be restored to pre-construction condition using native materials where feasible, with all waste removed from the park. The contractor is responsible for coordinating permits, traffic control plans, and 811 utility locates, maintaining OSHA-compliant safe work zones, and ensuring minimal disruption to park operations and visitors. The period of performance is 100 days, and work will be accepted upon completion of installation, restoration, submission and approval of all test results and as-built documentation, and final inspection by the NPS Contracting Officer and IT representative.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Sol_140P8326Q0040.pdf | ||
| Attachment_C_Forms_to_Return_With_Quote.pdf | ||
| Attachement_D_Relevant_Experience.pdf | ||
| Attachment_A_Highway_Route_Map.pdf | ||
| Attachment_B_Wage_Determination.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Attachment 1 Scope of Work Craters of the Moon Monument and Preserve
RFQ 140P8326Q0040 Install Fiber Optic Infrastructure
STATEMENT OF WORK (SOW)
Project Title: Installation of Fiber Optic Infrastructure
Location: Craters of the Moon National Monument and Preserve (CRMO), Arco, Idaho
Prepared For: National Park Service – South Idaho Parks
Prepared By: Project Manager
Date: 04/09/2026
1.0 PURPOSE
The purpose of this project is to install new fiber optic cable and associated conduit infrastructure to all designated park buildings at Craters of the Moon National Monument and
Preserve (CRMO). This upgrade will enhance telecommunications reliability, computer network performance, and operational safety for park staff and visitors.
2.0 BACKGROUND
CRMO currently experiences limitations in connectivity between critical operational buildings.
The installation of new fiber will provide a stable, high-bandwidth network backbone to support administration, visitor services, facility management, and emergency operations. Work will follow National Park Service (NPS) standards, methods, and environmental compliance requirements.
Attachment A shows the highway route. There will be 8 building tie-ins. A project map showing exact fiber routes, building tie-ins, and transition points between plowing and boring methods will be provided to the contractor prior to mobilization.
3.0 SCOPE OF WORK
The contractor shall provide all labor, equipment, supervision, materials, and incidentals necessary to complete the installation of fiber optic infrastructure in accordance with NPS standards.
Work includes, but is not limited to, the following:
3.1 Fiber Installation
• Install new fiber optic cable along the designated route connecting all identified park buildings.
• Fiber shall be installed inside conduit unless otherwise specified.
• Terminations, splicing, labeling, testing, and certification of all fiber strands are required.
3.2 Installation Methods
3.2.1 Plowing Method
• Plowing shall be used in areas following existing disturbed corridors, such as:
o Current analog line route, o road shoulders, o previously disturbed soils,
3.2.2 Boring Method
• Horizontal directional boring shall be used at:
o paved areas, o sidewalks, o road crossings, o sensitive resource zones where ground disturbance must be minimized.
• Boring depth must allow sufficient cover to protect conduit from future pavement maintenance.
3.3 Conduit Requirements
• Conduit - (typically HDPE for primary runs; smaller for building entry if required).
• All conduit installations must include pull tape and be free of obstructions.
• All vaults/handholes shall be NPS-approved, traffic-rated where appropriate, and located per provided design map.
3.4 Site Restoration
• All disturbed ground must be restored to pre-construction condition.
• Native materials (e.g., CRMO cinders) must be preserved and replaced where feasible.
• All waste materials shall be removed from the park.
3.5 Protection of Resources
The contractor shall:
• Avoid undisturbed native areas unless shown on the project map.
• Follow all CRMO environmental compliance requirements (NEPA, NHPA, ESA, etc.).
• Report any inadvertent discoveries (cultural or natural).
• Flag work limits prior to excavation or plowing.
3.6 Testing and Documentation
• Conduct end-to-end OTDR and light-loss testing on all installed fiber.
• Provide electronic test results to the NPS COR / IT representative.
• Provide a redlined as-built reflecting:
o route alignment, o handhole locations, o conduit sizes, o fiber strand counts, o building entry points.
3.7 Fiber Transport Route from Arco, Idaho
• The fiber backbone serving Craters of the Moon National Monument and Preserve shall originate from the designated service connection point in Arco, Idaho.
• The contractor shall install conduit and fiber along the highway corridor between Arco and the park boundary, following the alignment indicated on the project map that will be provided by NPS.
• Installation must remain within previously disturbed areas along the highway to the greatest extent feasible, minimizing new ground disturbance.
• All installation methods along the highway corridor shall follow NPS and Idaho
Transportation Department requirements, including:
• Plowing within approved disturbed shoulders or utility easements where allowed.
• Boring under paved surfaces, intersections, or protected areas as required.
• Contractor must coordinate any required permits, traffic control plans, or access approvals in collaboration with the NPS COR.
4.0 PROJECT DELIVERABLES
The contractor shall submit:
1. Work Schedule and Sequencing Plan
2. Fiber Test Certification Results
3. Redlined As-Built Drawings (PDF + GIS-compatible format)
5.0 PERIOD OF PERFORMANCE
The period of performance shall be 100 days (or as otherwise specified in contract documents).
Any changes must be approved in writing by the NPS Contracting Officer.
6.0 MATERIALS AND STANDARDS
Fiber shall be:
• 24-strand minimum, or as directed by NPS IT.
• Single-mode unless otherwise specified.
7.0 NPS RESPONSIBILITIES
NPS will provide:
• Route map and building list
• Access permissions
• Points of contact for safety, and IT coordination
• Utility locates (NPS-owned only; contractor must coordinate 811)
8.0 CONTRACTOR RESPONSIBILITIES
The contractor shall:
• Maintain safe work zones and comply with OSHA requirements.
• Coordinate with the NPS COR before starting new work segments.
• Secure equipment and materials each day.
• Ensure minimal disruption to visitors and park operations.
9.0 ACCEPTANCE CRITERIA
Work will be accepted upon:
• Completion of all fiber installation and restoration
• Submission and approval of all test results
• Approval of as-built documentation
• Final inspection by NPS COR and IT representative.