Attachment 2 - RFP APPA Carwash_XLWU 22-4006_22Jun2022.pdf
PDF 868 KB Posted
- Attached to
- Design-Build Car Wash Federal contract opportunity
- Solicitation number
- FA481922R0037
About this file
This is a synopsis for a Design-Build project for a Car Wash at Tyndall Air Force Base, Florida. The solicitation will be issued on or about July 26, 2022 on SAM.gov as a single-award, firm-fixed price contract. The contractor will be responsible for design, permits, equipment, labor, materials, and ancillary items to complete the tasks defined in the statement of work. Construction must adhere to UFCs, UBC, IBC, Air Force standards, DOD directives, FDOT, Tyndall AFB regulations, NEC, OSHA, DEP, and EPA requirements. The North American Industry Classification System code is 236220 with a $39.5M size standard. This requirement is set aside as a total small business. The period of performance is 365 calendar days for design and build after notice to proceed. The selection method will be LPTA. A site visit date will be identified in the solicitation. Interested parties should monitor SAM.gov and register as interested vendors for notifications.
View the file
Other files for this federal contract opportunity
Show all 26
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
FA4819-22-R0031
XLWU-22-4006
22 June 2022
APPENDIX A Page 1 of 40
Construct Car Wash
Appendix A Description of Work
Tyndall Air Force Base, Bay County, Florida
APPENDIX A Page 2 of 40
TABLE OF CONTENTS
1.0 INTRODUCTION
1.1 PROJECT PURPOSE AND SCOPE
1.2 DESIGN CRITERIA
1.3 APPLICABLE STANDARDS
1.4 FORCE PROTECTION DESIGN
2.0 CIVIL
2.1 SITE DESCRIPTION
2.2 SITE WORK
2.3 ANTICIPATED QUANTITY OF VEHICLES DAILY
2.4 TOPOGRAPHIC UTILITY AND SURVEY
2.5 COORDINATION AND COLLABORATION WITH OTHER ADJACENT SITE PROJECTS ON BASE
2.6 DEMOLITION AND REMOVAL
2.7 SITE GEOMETRY AND PAVEMENT DESIGN
3.0 STORMWATER, WATER AND SANITARY SEWER
3.1 STORMWATER COLLECTION AND MANAGEMENT
3.2 SITE CONTROL - EROSION AND SEDIMENT
3.3 STORMWATER RETENTION
4.0 WATER SUPPLY AND SANITARY SEWER
4.1 BACKFLOW PREVENTER
4.2 WATER METER
4.3 VALVES
5.0 WASTEWATER COLLECTION AND CONVEYANCE SYSTEMS
5.1 WASTEWATER PIPING
5.2 OIL WATER SEPARATOR
6.0 EARTHWORK
6.1 GEOTECHNICAL DESIGN
6.2 CONTRACTOR’S GEOTECHNICAL REPORT
6.3 GEOTECHNICAL ENGINEERING
6.4 BORROW MATERIAL
6.5 SOIL TREATMENT
6.6 CAPILLARY WATER BARRIER
7.0 LANDSCAPE
7.1 LANDSCAPE PLAN
7.2 LANDSCAPE PLANTINGS
7.3 PLANTING SOIL MATERIAL
7.4 SODDING
7.5 TEMPORARY IRRIGATION FOR PLANTS
7.6 COMPLETION, INSPECTION AND ACCEPTANCE
8.0 STRUCTURAL
9.0 ARCHITECTURE
9.1 MOCK-UP
10.0 AIR BARRIER REQUIREMENTS
10.1 INSPECTION
APPENDIX A Page 3 of 40
11.0 MECHANICAL
12.0 PLUMBING SYSTEM
13.0 ELECTRICAL
13.1 POWER DISTRIBUTION SYSTEMS
13.2 LIGHTNING AND GROUNDING PROTECTION
13.3 CONVENIENCE AND POWER RECEPTACLES
13.4 LIGHTING AND LIGHTING CONTROLS
14.0 TELECOMMUNICATIONS
14.1 COMMUNICATIONS BACKBONE, POINT OF SALE SYSTEM (POS)
14.2 COMMUNICATIONS BACKBONE: TAFB NIPR NETWORK
14.3 COMMUNICATIONS ROOM INFRASTRUCTURE
14.4 COMMUNICATIONS OUTLETS AND RECEPTACLES:
15.0 FACILITY RELATED CONTROL SYSTEMS REQUIREMENTS (FRCS)
16.0 FIRE PROTECTION SYSTEM
16.1 LIFE SAFETY
16.2 FIRE ALARM SYSTEM
17.0 SUSTAINABLE DESIGN
18.0 FURNITURE, FIXTURES AND EQUIPMENT (FF&E) REQUIREMENTS (INCLUDES AUDIO
VISUAL (AV)) (NOT APPLICABLE)
19.0 SIGNAGE
20.0 RENDERINGS
21.0 SYSTEM PLATFORM AND FILE FORMATS
21.1. GOVERNMENT FURNISHED GIS
21.2 OWNERSHIP AND RIGHTS OF DATA
APPENDIX A Page 4 of 40
1.0 INTRODUCTION
1.1 PROJECT PURPOSE AND SCOPE
The scope of the project includes the design and construction of a new car wash facility and associated site and utilities work. The new car wash facility will contain three covered wash bays, a fully enclosed, equipment room, and an open-air vacuum area with four dedicated vacuum areas. When complete the car wash will include these areas:
1. One (1) Automated Touch-Free Wash Bay: One wash bay with a minimum clear width of 14 feet wide by 30 feet long and contain an automated touch-free vehicle washing system servicing passenger vehicles up to 11 feet high.
a. Open Bay Configuration
b. Remote Monitoring and Configuration
c. Low Maintenance Cost
d. Energy-Efficient Design
e. Low Water and Chemical Consumption
f. Local Distributor Support
g. 24/7Technical Service Support
h. Non-corrosive materials used Stainless steels and aluminum
i. New stainless steel pump station design focused on Improved functionally and low maintenance costs
j. Virtual Treadle System utilizing sensors to direct the vehicle into the bay. The wash system shall have an electronic safety envelope surrounding the entire vehicle allowing the system to maintain optimum cleaning distance from the vehicle regardless of position in bay.
k. Automatic Obstacle Guidance System to avoid obstacles protruding from the vehicle
l. Front Bug Prep
m. Smart Drying System
2. Two (2) self‐service Wash Bays: The two wash bays will have a minimum clear width of
14 feet wide by 50 feet long to accommodate passenger vehicles and recreational vehicles up to 14 feet high. Both self-service wash bays will have a complete commercial “in-bay” self-serve multifunction cleaning system.
a. One of the self-serve wash bays will have raised platform systems on each side of the wash bay to allow user access to upper portions of the vehicles for cleaning.
3. Car Wash Equipment Room: The equipment room will provide an enclosed space adjacent to the wash bays for the equipment required for the functioning of the car wash.
The equipment room will also contain separate closets for electrical equipment and communications equipment.
a. Dedicated Communications Room
APPENDIX A Page 5 of 40
b. Dedicated Electrical Room
4. Four (4) Vacuum stations to accommodate 4 vehicles simultaneously is required. The vacuum facilities shall be located separately from the car wash bays in a location outside of the traffic patterns of vehicles entering and exiting the wash bays. The vacuum stations will be placed on 24” high concrete foundations.
1.2 DESIGN CRITERIA
A. Complete Issue for Construction deliverables including, but not exhaustive, construction drawings, specifications, and design analysis/calculations. The Issue for Construction
Contract documents shall be of high professional quality, signed and sealed, technically accurate and compliant with all applicable codes, standards, memorandums and UFGS specifications.
1.3 APPLICABLE STANDARDS
A. All work shall be designed and constructed to meet all state and federal codes, standards and laws, including, but not exhaustive:
● Applicable Uniform Facilities Criteria (UFC)
● USACE Safety and Health Requirements Manual (EM 385‐1‐1)
● OSHA Requirements
● ABA Requirements
● Tyndall AFB IFS www.tyndallifs.com
● Applicable Technical Manuals
● Applicable Air Force Instructions (AFIs)
● Applicable Air Force Manuals (AFMAN)
B. Refer to the Project Request for Proposal, as well as, www.wbdg.org for a further list of codes and standards.
1.4 FORCE PROTECTION DESIGN
A. The facility is routinely occupied by fewer than 11 personnel and has a population density of less than one person per 430 gross square feet. It is designated as low occupancy, therefore, the UFC 4-010-01 Department of Defense Minimum Antiterrorism
Standards for Buildings does not apply.
2.0 CIVIL
2.1 SITE DESCRIPTION
APPENDIX A Page 6 of 40
A. This project is in Bay County, Florida at Tyndall Air Force Base, on the “support” side of the main base. The site is an undeveloped parcel at the corner of Suwannee Avenue and
Barnes Drive. The project location, per cartesian nomenclature, is described as: “east side
Suwannee Ave.; south of Barnes Rd.; north of Future Commercial Gate Entry road; and west of the existing drainage swale that generally flows from north to south.”
B. The primary soil type is sand. It is recommended, per historical reports, is to use the sand soil type to design foundations, slabs on grade, pavement, and the infiltration capabilities of the soil for storm water management.
2.2 SITE WORK
A. The site work design required for this project, shall include but may not necessarily be limited to, the following items: utilities, electrical power, telecom, potable water, sanitary sewer, natural gas systems, clearing, grubbing, paving, grading, drainage, storm water collection, conveyance, and management facilities.
B. The water, electric, and natural gas infrastructure on Tyndall AFB has been privatized. Any infrastructure which must be constructed from the facility's points of demarcation to the privatized utility, shall be completed by the system owner.
The prime contractor shall enter into a service connection agreement with the system owner and will be responsible for paying the associated lump sum connection charge.
C. The Contractor is advised that the concept site layout and requirements shown on the criteria drawings shall be observed. Any proposed changes from the concept site layout shall be submitted for review and approval. Provide UFGS marked-up specifications supporting work in this category.
D. Unless otherwise stated, all utilities crossing under existing paved roadways shall be "jack and bored".
2.3 ANTICIPATED QUANTITY OF VEHICLES DAILY
A. The anticipated number of vehicles entering the site is 100 POV trips a day. The following vehicle proportions are:
1. Ninety (90) POV cars per day
2. Ten (10) POV trucks/motorhomes/boat trailers per day
2.4 TOPOGRAPHIC UTILITY AND SURVEY
A. The Contractor shall provide a detailed topographic survey of the project site as part of the Scope of Work. The Government will not provide topographic survey for this project.
APPENDIX A Page 7 of 40
It shall be the responsibility of the contractor to provide topographic and utility survey of the site verify actual locations of all existing site features and utilities and shall coordinate with the Government regarding any future utility installations that affect the work under this contract.
B. Existing conditions shown on the criteria drawings are based upon Geographic
Information System (GIS) data provided by Tyndall AFB, Base Civil Engineer (BCE) and commercially available aerial photography. Plans presented herein are not final site plans but are criteria drawings. These drawings do not purport to show all existing site features accurately.
2.5 COORDINATION AND COLLABORATION WITH OTHER ADJACENT SITE
PROJECTS ON BASE
A. A new, Zone 4, Commercial Vehicle Inspection Gate and entry roadway is planned from
US HWY 98 to Suwanee Ave., south of Barnes Rd. The preliminary Future Commercial
Gate Entry road alignment is shown on the criteria drawings. The Contractor shall coordinate with Base Civil Engineering to acquire final design plans for new Commercial
Gate Entry road and incorporate same into site design for this project.
B. There will be other adjacent construction sites, “IROC”, “Zone 5”, etc. to the car wash area or work. The contractor is required to collaborate and coordinate with these adjacent construction sites in order to keep the project on time and schedule. It is a mandatory requirement that the contractor coordinate the design of the Car Wash facility with the adjacent projects and contractors for those contracts.
2.6 DEMOLITION AND REMOVAL
A. The site demolition at the car wash site will require the topsoil stripping, clearing, and grubbing of all the existing vegetation on the site. The Contractor shall provide the clearing and grubbing limits.
B. The Contractor shall provide layout surveying as necessary to locate the new work items prior to initiating demolition work. Erosion and sediment control Best Management Practices (BMP's) shall be in place and approved by the Contracting Officer's Representative prior to initiating demolition work.
C. All demolition debris shall be removed from the limits of Tyndall AFB and disposed of in a manner as required by law and Air Force regulations. The Contractor shall be responsible for all disposal permits and regulations requirements. If at any time during or after the performance of this contract, it is determined by the Contracting Officer or their authorized representative that the Contractor has not complied with the requirements of the contract pertaining to the disposal of waste material, the Contractor shall be required to take any corrective action directed by the Contracting Officer or other competent authority at no additional cost to the government. Any fine, fee, or penalty assessed by
APPENDIX A Page 8 of 40 the regulating authority as a result of the Contractor's failure to comply with this provision shall be paid by the Contractor. If any part of the performance of this contract is subcontracted, a provision substantially similar to the above shall be included in all such subcontracts. Such provision does not, however, relieve the prime Contractor from ultimate responsibility under the contract.
D. Some noted items, for this project, of demolition and removal include:
1. The contractor will be required to remove a portion of existing abandoned water main on the north edge of the project to allow for the relocation of a drainage swale as well as the installation of a culvert beneath the new north entrance/exit.
2. A portion of the existing curb will need to be removed to allow the north entrance/exit to be constructed. Pavements, curbs and sidewalks to be demolished shall be saw cut to a clean even edge.
3. The existing utilities along Suwannee Avenue and the sign on the northwest corner of the site will be protected as part of this project.
4. The existing swale along the east side of the project will be preserved.
5. The Contractor may utilize the utilities during construction operations as approved by the Contracting Officer's Representative and may incorporate the utilities as part of the final project.
6. Existing utilities that interfere with this project shall be relocated or removed.
7. Existing Trees: Contractor shall clear trees as required to develop the site. The
Contractor is encouraged to save on-site existing trees to the greatest extent possible.
The Contractor shall erect and maintain existing tree protection fencing a minimum of 10-feet outside of the drip line of all existing trees proximate to the project site that will remain. Tree protection fencing shall be removed by the contractor at the end of construction activities. Refer to landscaping section for replacement criteria.
E. The Contractor shall demolish existing Site features, as generally shown on the Site criteria drawings. See Appendix B, notional drawings, for further information.
2.7 SITE GEOMETRY AND PAVEMENT DESIGN
A. The site geometry for the car wash site has vehicles entering or exiting Barnes Drive or the “Zone 4 Commercial Gate” future entrance control facility road on the south side of the site. Traffic flow through the main parking lot shall be two way. In Appendix B of this RFP, The concept site geometry plan presents the general geometric layout for the site work.
B. The Contractor shall design the horizontal and vertical control, drainage, sidewalks, landscaping, site grading, stormwater management facilities, asphalt vehicular circulation area for personal vehicle (POV) ingress, egress and parking, water, sewer and other utilities (including fire hydrants, vacuum stations and area lighting) for the new Car Wash Facility
APPENDIX A Page 9 of 40
C. All new facility downspouts shall connect into the new underground piped storm drainage collection system with a cast iron boot.
D. NFPA: The Contractor shall ensure that the layout for the entire site, vehicular circulation areas, and access drives shall accommodate emergency and fire fighting vehicles and are in accordance with NFPA Standards for Fire Prevention Code. Special care shall be exercised to minimize traffic congestion in parking areas and hardstand areas. The Contractor shall ensure that all radii and widths of parking lots, access drives, and channelized turn lanes shall accommodate emergency and fire fighting vehicles.
E. ABA/ADA Accessibility Code and Standards: All of the paved area/grades for pedestrians shall be designed for ABA/ADA standard criteria.
F. Parking areas and vehicle circulation pavements shall be provided as generally indicated in the drawings. Concrete bumper blocks shall be installed in all parking stalls that abut sidewalks. Parking areas shall have lighting and be adequately drained.
1. Parking lot drainage shall be designed to provide adequate sheet flow drainage to a collection system. The slopes of the surface shall be held to the minimum required for drainage and to prevent ponding but shall not be less than 0.5%.
2. For safety, the maximum slope for parking is 5% along the isles through the parking area and 2% for the transverse slope. The Contractor shall construct the collection drainage system such that parking areas and paved areas adjacent to the new facility drain adequately with storm water flowing away from the new facility.
G. Curbs: The edges of pavement will be constructed with a concrete curb with a 6” reveal.
The curb will have periodic curb cuts to allow the storm water runoff to exit the pavement and enter the dry detention basin on the south portion of the site. The removed curb Along Barnes Drive at the north entrance will be replaced with a valley gutter to allow for storm water runoff to continue to the west along the road.
H. Pavement: All asphalt and concrete pavements structures shall be based on UFC 3 250-01 and UFC 3-260-02, Pavement Design for Roads, Streets, Walks, and Open Storage Areas. The design software is located at www.pcase.com.
1. Based on information provided in a geotechnical report, the existing subgrade on the site has an LBR of 30. The pavement design program PCASE was utilized to design the flexible pavement on the car wash site. PCASE requires a CBR value for the subgrade to design flexible pavement. CBR is approximately 80% of the stated LBR value in the geotechnical report. Therefore, it is assumed the CBR value for the car wash site is 24. The HMA pavement section for the car wash site will be 2” of surface course (paved in two lifts) on 6” of graded crushed aggregate.
2. New connections to existing asphalt or concrete pavements shall be accomplished by saw cutting the adjacent existing pavement. Minimum access drive pavement width shall be 26 feet from edge of pavement to edge of pavement, unless noted otherwise.
http://www.pcase.com/
APPENDIX A Page 10 of 40
All traffic aisles shall be 26-feet wide within the vehicular circulation area, unless noted otherwise on the Site drawings. Traffic flow through the paved areas shall be two way unless shown otherwise. The Contractor shall consider the types of vehicles traversing and parking on these facilities and shall incorporate their requirements in the site design.
I. Vehicle Circulation Area shall be provided as generally indicated in the drawings. The layout design of vehicular circulation areas shall conform to SSDCTEA 55-17 standards.
Vehicular Circulation Area and Access Drives shall be designed for a 20-year design life and an anticipated Average Daily Traffic (ADT) is estimated at 100 POV trips per day with 10% AASHTO Designation Single Unit (SU) Trucks and Motor Home and Boat Trailer (MH/B).
J. The Contractor shall provide traffic control signs and pavement markings per the applicable codes and standards. See Signage within this document for further information.
K. Contractor shall coordinate with Zone 4 Commercial Gate DB Contractor regarding access tie-in location and the Zone 4 Final Denial Barriers. This access tie in must be outside the final position of Zone 4's Final Denial Barriers.
3.0 STORMWATER, WATER AND SANITARY SEWER
3.1 STORMWATER COLLECTION AND MANAGEMENT
A. The Contractor shall develop a storm drain/grading plan that will incorporate/include any off-site stormwater runoff. In particular to the site scope of work:
1. Stormwater discharge from the site may outfall to the existing swale east of the site.
2. The storm drainage shall consist of shallow ponds or swales, storm drainage structures, curb cuts, and piping. The structures may include concrete drop or curb inlets, concrete headwalls, flared end sections and outlet control structures, as necessary. All storm drainage structures located in traffic areas shall be rated to withstand heavy vehicle loading.
3. All grading shall be completed such that parking areas and areas adjacent to the new building drain adequately with storm water flowing away from the building. All side slopes shall not be steeper than 4-feet horizontal to 1-foot vertical.
B. The site storm drainage system shall be designed for treatment of volume of stormwater as specified in the Florida Department of Environmental Protection ENVIRONMENTAL
RESOURCE PERMIT APPLICANT'S HANDBOOK VOLUME II to retain runoff volume from the 25-year, 24-hour storm event and in accordance with requirements of the Technical Guidance on Implementing the Storm water Runoff Requirements for
Federal Projects under Section 438 of the Energy Independence and Security Act.
APPENDIX A Page 11 of 40
C. In the event a positive discharge outfall from the storm water treatment facility cannot be achieved, the treatment facility shall retain runoff volume from the 100-year, 24-hour storm event. The stormwater treatment facility system must provide the capacity for the appropriate treatment volume of stormwater as specified in the Florida Department of
Environmental Protections ENVIRONMENTAL RESOURCE PERMIT APPLICANT’S
HANDBOOK, VOLUME II (Design and Performance Standards Including Basin Design and Criteria) within 72-hours following a storm event assuming average antecedent moisture conditions. All runoff onto the site from adjacent properties shall be included in the storm drainage calculations. Storm drainage system design shall be checked for a
100-year return event to ensure no flooding of the new facility. Storm drainage design shall be in accordance with Tyndall AFB's Municipal Separate Storm Sewer System
(MS4), TM-5-820-4, Florida Statute (F.S.) Section 373.4145 (1) (a), and Florida
Administrative Code (FAC) 62-346
D. Stormwater Pipes:
1. Minimum pipe velocities shall be 2.0-ft/sec and the maximum shall be 5.0-ft/sec with outlet erosion protection.
2. The minimum pipe size for an open pipe system shall be 18-inches and 15-inch for a closed system.
3. The allowable pipe types under parking areas and areas subject to vehicular traffic shall include reinforced concrete pipe, type III or IV, as required. Pipe joints shall be watertight with gaskets. Drainage pipes not under areas of vehicular traffic may be
HDPE or PVC.
4. Storm drainpipes shall be grouted into the concrete structures to provide a watertight connection.
E. Stormwater Pavement:The maximum allowable stormwater pavement spread shall not exceed 4-feet in width for a 10-year storm event. Sufficient inlets or flumes shall be provided to control drainage spread. The maximum interval for inlets or flumes shall be
300 feet. No inlets shall be provided in curb radii. The storm drainage system shall be designed to the 10-year storm frequency. There shall be no ponding at inlets for a 10-year storm.
F. Concrete inlets/catch basins may be poured in-place or precast concrete. Precast manhole or inlet rings shall connect with industry standard gaskets. Locate stormwater inlets so that no collection swales flow across a street or sidewalk to reach a storm sewer other than where cross gutters are used.
G. Metal grates or manholes shall be galvanized. Where grating is to be used, it shall be of
"Bicycle Tire Proof" design.
H. Basins shall have 3-inch weep holes cast into the walls. The exterior of the weep holes shall receive a 1/4-inch wire mesh with a 12-inch width belt of crushed rock, ASTM 357.
APPENDIX A Page 12 of 40
3.2 SITE CONTROL - EROSION AND SEDIMENT
A. The proposed swales on the car wash site will have check dams placed in the bottoms to prevent illicit discharges of sediment from the site.
B. The site will have a contractor staging area where the concrete wash out area, hazardous material (i.e. fuel and oil storage, fertilizers, construction materials), and sanitary facilities will be stored and regulated for the site. The Contractor will submit an environmental resource plan for Government approval of the BMPs to control oils, fuels, waste, and chemicals on the site.
3.3 STORMWATER RETENTION
A. As a part of the contractor's geotechnical investigation, the contractor shall be responsible for securing all the required information necessary, e.g. soil infiltrometer test, as applicable for the design of storm water retention ponds and drainage swales in accordance with State regulations.
4.0 WATER SUPPLY AND SANITARY SEWER
A. The Contractor shall design and construct the new water supply utility services for the new facility. The Contractor shall provide water service line and connection to the existing water mains. The water utility facilities shall be designed and constructed in accordance with the criteria contained herein. The design of the water service line shall provide an adequate quantity of water at sufficient pressure for domestic use.
B. The Contractor shall coordinate construction sequencing of utility installation with the
Contracting Officer and adjacent contractors to ensure the systems are tested and flushed properly before being connected to the existing system. The Contractor shall confirm the exact location of existing utilities and new utilities being installed.
C. Placement of buried utility mains under new building structures is not allowed. The
Contractor's design shall limit of utility main installation beneath the pavement.
1. Water main alignments shall follow existing streets or utility corridors.
D. The contractor shall be responsible for saw cutting and patching of pavements and sidewalks as required for installation of the water and wastewater system and shall repair any areas damaged by the system installation activities, including but not limited to sod, landscaping, pavement damage, pavers and/or concrete removal and replacement.
APPENDIX A Page 13 of 40
E. GCEC will review and comment on the water system design as developed by the design-build contractor's water system's designer of record (DOR), and the DOR must coordinate with GCEC for domestic water design during the design process.
F. After the water system design completion, with all review comments incorporated, GCEC will construct all domestic water (not including fire) system exterior components up to the new facility's building 5-foot line.
G. The Defense Logistics Agency (DLA) will work the construction contract with GCEC to perform this work which will include all physical connections and tie-ins to the existing water systems in accordance with the design-build Request for Proposal (RFP) solicitation documents, criteria, requirements and criteria drawings, including but not limited to trenching, dewatering, filling and compaction for installation of the water system service components.
H. The design build contractor is to coordinate with GCEC to schedule the inspection of this work to be completed within the required Construction Completion date. The design build contractor shall coordinate all domestic water utility work with GCEC during design and construction.
I. Building supply lines shall be sized to meet peak demands with no more than 10-psi pressure loss between the mains and the building.
J. Piping for Water:
1. Water service lines shall be polyvinyl chloride (PVC) except where use dictates otherwise.
2. The domestic water service for the car wash site will be a 2.5” line.
3. All water piping 4-inches in diameter or greater shall be push-on joint PVC. Piping less than 4-inches in diameter shall be solvent-weld PVC.
4.1 BACKFLOW PREVENTER
A. The contractor shall provide a backflow preventer on the new potable water lines in accordance with Rule 62-555.360, Florida Administrative Code, and the AWWA Manual
M14, Recommended Practice for Backflow Prevention and Cross-Connection Control.
Reduced pressure principle assemblies and double check valve assemblies shall be tested, approved, and listed in accordance with FCCHR-01.
B. All backflow preventers shall be on the list of approved devices published by the
Foundation for Cross-Connection Control and Hydraulic Research, University of
Southern California.
C. Air gaps in plumbing systems shall be in accordance with ASME A112.1.2.
APPENDIX A Page 14 of 40
D. All test cocks on all backflow preventers shall be equipped with 1/4-inch flare adapters to facilitate attachment of test equipment.
E. In addition to being approved by the FCCHR, all backflow preventers shall have bronze valve seats. A "Re-Build Kit" (poppet replacement kit) shall be provided with each backflow preventer.
F. The reduced pressure backflow preventer will be placed inside the building.
4.2 WATER METER
A. The connection to the existing water main and the installation of the water meter will be provided and installed by the contractor in accordance with the Utility Metering requirements of the FRCS Guide.
B. The water meter will be placed inside the building.
4.3 VALVES
A. Curb stops or valves shall be installed near the point of connection to the main and on both the inlet and outlet sides of the water meter and backflow preventer. Valve connections shall be as required for the piping in which they are installed.
B. Flanges shall not be buried.
C. All valves shall be resilient- seat gate valves or approved equal.
D. All service stops and valves shall be provided with service boxes.
5.0 WASTEWATER COLLECTION AND CONVEYANCE SYSTEMS
A. The scope of this construction includes the connection of the new wastewater collection system and new oil/water separator located adjacent to the site to the existing utility. The
Contractor shall obtain written authorization from the sanitary sewer authority to connect sanitary sewer outfall from the Car Wash Facility to the existing system.
B. The wastewater collection and conveyance system shall be designed in accordance with
UFC 3-240-01 Wastewater Collection and the Water Pollution Control Federation
Manual of Practice No. FD-5, Gravity Sanitary Sewer Design and Construction. In addition, the designer shall comply with state and local regulations that apply, such as
Chapter 62-600 of the Florida Administrative Code. The wastewater conveyance system shall comply with all the above requirements and shall be compatible with the wastewater to be conveyed.
APPENDIX A Page 15 of 40
C. The 4” domestic sanitary service will tie into an existing sanitary lateral on the south side of the project site. Prior to the sanitary lateral the discharge flow from the facility will be treated by a 500 gallon oil/water separator. The OWS will also be placed in the grassed area between Suwannee Avenue and the west edge curb of the facility.
D. A single building service by gravity does not require an FDEP permit.
5.1 WASTEWATER PIPING
A. Sanitary Sewer piping shall be PVC. Lines shall be tested for leakage by low pressure air testing, infiltration tests, or exfiltration tests in accordance with the requirements set forth in Specification Section 33 30 00 SANITARY SEWERS. The specification section shall be completed and submitted in accordance with section UFGS Submittal Procedures
B. New sanitary sewer lines shall be laid on adequate slopes in order to obtain the proper cleansing velocities.
C. Minimum gravity sewer pipe size outside the building 5-foot line is 6-inches in diameter.
D. Minimum slopes, and flow velocities shall be as required by the Florida Department of
Environmental Protection (FDEP) standards for an individual facility service.
E. The materials specified shall withstand the effects of the wastewater and not deteriorate as a result of pollutants in the wastewater.
5.2 OIL WATER SEPARATOR
A. A gravity oil/water separator shall be designed and installed to pretreat the car wash effluent before discharge to the Base wastewater collection system. The separator shall be designed to accommodate the wastewater flow of the car wash. The design shall conform to UFC 3-240-01 Wastewater Collection
B. Industrial Drainage System: Bay areas shall drain to an oil-water separator. This drainage system shall be separate from the building sanitary system. The trench drains shall be parallel to the bay door.
6.0 EARTHWORK
6.1 GEOTECHNICAL DESIGN
A. The Contractor is required to retain a Geotechnical Engineer experienced and licensed in the geographic region of the project interpret the Government provided information as
APPENDIX A Page 16 of 40 related to his design concept and develop geotechnical requirements to support design and construction.
1. Minor variations in subsurface conditions between borings should be anticipated. The
Contractor’s Geotechnical Engineer shall perform additional subsurface investigating and testing as required to adequately determine all applicable geotechnical factors including the type and capacity of the project foundations. The Contractor’s
Geotechnical Engineer shall consider the provided information and any additional information obtained and prepare a report as described in other portions of this RFP.
The minimum requirements for the subsurface investigation and report are as required by UFC 3-220-01 with associated references.
B. The Contractor shall bear costs associated with the site preparation, ground improvement and foundations except as allowed by Contract Clause FAR 52.236-2, “Differing Site
Conditions”.
C. It is the DBC’s responsibility for obtaining all required drilling permits.
6.2 CONTRACTOR’S GEOTECHNICAL REPORT
A. The DBC's geotechnical report shall be complete with recommendations specific to the geotechnical design requirements at the Scope of Work “site”.
B. The report shall be performed under the direction of and signed by a Florida licensed
Professional Geotechnical engineer.
C. All soil borings shall be abandoned in accordance with the following, minimum requirements:
1. Each boring shall be measured for depth before it is sealed to ensure freedom from obstructions that may interfere with effective sealing operations.
2. All borings shall be sealed by backfilling with concrete, grout, neat cement or a bentonite/cement mixture. All backfill material shall be placed into the borehole from the bottom to the top by pressure grouting with the positive displacement method
(tremie method). Each borehole sealed shall be given time allowing the backfill material to settle and set in the borehole. If the backfill material settles 2-feet or more below ground surface (BGS), then the contractor shall place more backfill material, as described above, in the borehole to the top. If the backfill material is less than 2-feet
BGS, then the contractor may backfill the borehole using properly compacted native material.
3. A measurement of the borehole's theoretical volume, the amount of grout introduced into the borehole and the depth of the top of the grout or cement backfill shall be included in the borehole log.
APPENDIX A Page 17 of 40
4. The DBC shall obtain soil samples, disturbed and/or undisturbed, for testing as required for the computation of bearing capacities, settlement calculations, lateral earth pressure calculations, temporary and permanent dewatering designs, etc.
a. All borings shall be continuously sampled by a split spoon sampler and standard penetration blow counts recorded.
5. A dated drilling log shall be provided for each boring drilled. The drilling logs, results of soils test data if any, and a plan showing the location of each boring as drilled.
6. It is not acceptable to advance the borehole for subsequent insertion of the sampler solely by means of previous sampling with the SPT sampler.
7. The hole shall be cleaned and stable between sampling intervals.
8. The approximate elevations and locations of borings drilled shall be provided on each boring log. Coordinates shall be in state plane +/- 1-foot horizontal.
D. Should unusual or unexpected subsurface conditions be encountered that require additional investigation the contractor shall provide such as deemed necessary to design the proposed structure(s).
E. The contractor shall use the data from his investigation to provide bearing capacity analyses, settlement calculations, lateral earth pressure calculations, temporary and permanent dewatering designs, and/or deep foundation design such as piling, as applicable. NOTE: The DBC-provided report shall include all applicable calculations.
F. The report shall specifically address the following:
1. Structures
a. The report shall recommend the type of foundation system to be used, lateral load resistance capacities for foundation systems, allowable bearing capacity(ies), seismic site class, depth(s) of placement and bearing elevations for footings, grade beams, slabs, pile tips, etc., utilizing the recommendations and restrictions presented in the report. An assessment of post-construction settlement potentials, including total and differential, shall be provided.
2. Pavements
a. The report shall recommend the allowable design CBR and modulus of subgrade reaction along with the required compaction effort for subgrades. Guidance shall be offered on the types of base course materials available in the area and design strengths.
3. General Earthwork and Special Features
a. The report shall recommend any undercutting requirements, proof rolling requirements for subgrades, fill and backfill placement procedures, and types of compaction equipment to be used. The report shall outline earthwork procedures for special features such as retaining walls, buried utilities, and slope stability if applicable.
4. Cathodic Protection and Grounding Systems
APPENDIX A Page 18 of 40
a. The report shall include all pH tests, salinity tests, resistivity measurements, sulfate testing, etc., required to design corrosion control and/or grounding systems. The raw field data shall be provided in the report. The contractor shall design all corrosion control and grounding systems required for the project.
5. Dewatering
a. The report shall determine project dewatering requirements. Based on historical geotechnical information, it is anticipated that groundwater will be encountered. If temporary construction dewatering is required due to high water table, the contractor shall prepare and present a dewatering plan in accordance with
Specification 01 57 19 Temporary Environmental Controls (Tyndall AFB
Specific from Base Environmental).
b. The contractor shall be responsible for securing all the required information necessary for the design of the dewatering plan selected. Boring logs show groundwater table depths/elevations encountered by preliminary planning efforts by the Government.
6.3 GEOTECHNICAL ENGINEERING
A. Personnel under the supervision of a registered Geotechnical Engineer shall provide inspection of excavations and soil/groundwater conditions throughout construction.
B. The engineer shall be responsible for performing pre-construction and periodic site visits throughout construction to assess site conditions.
C. The Geotechnical Engineer, with the concurrence of the DBC and the Contracting
Officer, shall update the excavation, sheeting, shoring, and dewatering plans as construction progresses to reflect actual site conditions and shall submit the updated plan and a written report (with professional stamp “signed and sealed”) at least monthly informing the Contractor and Contracting Officer of the status of the plan and an accounting of Contractor adherence to the plan; specifically addressing any present or potential problems.
D. The Geotechnical Engineer shall be available to meet with the Contracting Officer at any time throughout the contract duration.
E. The DBC shall bear all costs of the registered Geotechnical Engineer.
6.4 BORROW MATERIAL
A. Borrow material will be obtained off site.
B. Costs in connection with borrow material and disposal of materials shall be at the DBC's expense.
APPENDIX A Page 19 of 40
C. Liability of any nature resulting from borrow operations including transportation of, and those resulting from disposal of material shall be the responsibility of the DBC.
6.5 SOIL TREATMENT
A. Just prior to placing concrete slab on grade and just prior to backfilling around concrete or masonry foundations for structures, soil treatment shall be applied. Pesticide applications shall be made by state licensed and certified pest control personnel and in strict accordance with manufacturer's label instructions. The Contractor shall formulate, treat, store and dispose of the pesticides in accordance with manufacturer's instructions, and both State and Federal regulations. Applications shall be made in accordance with
UFGS §31 31 16.13 CHEMICAL TERMITE CONTROL to be included in DB project specifications and Tyndall Base Standards.
B. Coordinate with TAFB Environmental for the approval of termite control.
6.6 CAPILLARY WATER BARRIER
A. Floor slabs of all buildings shall be underlain by a minimum 6-inch (loose thickness) aggregate capillary barrier and 15 mil vapor barrier above aggregate capillary barrier as described in UFGS §31 00 00 EARTHWORK.
7.0 LANDSCAPE
A. The Contractor shall personally examine the site and become fully acquainted with existing conditions, the character and extent of work to be performed, and identify all precautions to be taken in order to avoid injury to property or persons.
B. All areas disturbed by construction shall receive landscape treatment.
C. Follow the TAFB landscape management requirements, including low maintenance grasses and sod that will be placed in and around each facility. (Found at www.tyndallifs.com) Three feet of sod will be placed along all road and building edges.
All other disturbed areas will be seeded and hardwood mulched. The Contractor will either use Bahia or Bermuda grass to accomplish this task.
D. Any plant that cannot survive the grade alterations required by the civil design, shall be removed.
7.1 LANDSCAPE PLAN
A. A landscape plan, prepared by a Registered “Landscape Architect”, will be required to develop the landscaped area around the New Car Wash Facility and parking area. The
Landscape Architect shall develop a landscape concept plan based on the criteria herein and on the RFP drawings for Government review and approval. During design, the plan will be modified to reflect Government comments and will be developed in compliance with the RFP. The DBC is advised that the concept site layout and requirements shown http://www.tyndallifs.com/
APPENDIX A Page 20 of 40 on the criteria drawings are intended to describe the overall concepts and scopes of work.
B. The DBC is responsible for development of the final, Issue for Construction, landscape design. Provide drawings, narrative, and supporting documentation incorporating work as shown for all submittal deliverable phases. Provide marked-up specifications supporting work in this category.
C. The DBC shall bear all costs of the registered Landscape Architect.
7.2 LANDSCAPE PLANTINGS
A. Provide complete landscaping consisting of trees, shrubs, groundcover, and turf as required to provide a quality, cost effective, functional, and visually appealing landscaping that will visually enhance the proposed building facility while complying with all applicable requirements.
B. Landscape plantings shall be native/locally adaptive species of trees, shrubs, and groundcovers requiring minimal water and maintenance. Plant materials shall be selected on the basis of plant hardiness, climate, soil characteristics, low maintenance, and high quality and be included in the approved list for Tyndall AFB. See www.tyndallifs.com for Plant List. All selected plant material must be tolerable of the site’s soil conditions.
Landscaping shall utilize Xeriscape concepts of planting adaptive species requiring low to moderate water consumption.
C. Trees:
1. Balled and Burlapped trees (B&B) shall be grown in and acclimated to the local geographic area for a period of six-months prior to planting. Small shrubs shall be minimum 18-inches to 24-inches in height, 3-gallon containers. Large shrubs shall be
5-feet to 6-feet in height, 30-gallon container or B&B. Groundcover plants shall be 4-inches to 6-inches maximum in height and be 1-gallon containers.
2. Plants with broken, damaged, or insufficient root balls will be rejected. All rejected material shall be immediately removed from the site and replaced with acceptable material at no cost to the Government.
3. All plant materials shall be protected from possible bark injury or breakage of branches. All plants transported by open trucks shall be adequately covered to prevent windburn, drying, or damage to plants.
4. Remove dead and broken branches from all plant material. Prune to retain typical growth habit of individual plants and in a manner which will preserve the plant's natural character.
5. Make all cuts with sharp instruments flush with trunk or adjacent branch, in such a manner as to ensure elimination of stubs. Cuts made of right angles to line of growth will not be permitted.
6. Trees shall not be poled or topped. Remove all trimmings from site. Point all cuts half inch in diameter and larger with waterproof antiseptic tree point.
D. Edging:
http://www.tyndallifs.com/
APPENDIX A Page 21 of 40
1. All plant beds not bordered by pavement, walks, and curbs shall be edged with commercial quality, zinc-coated, steel edging, 3/16-inch by 4-inch, black in color.
E. Install weed barrier fabric in all planting beds.
F. Mulch all planting beds with Base approved hardwood mulch.
1. Mulch material shall be hardwood mulch distributed evenly over the planting beds to a minimum depth of 4 inches. Inert materials such as lava rock, crushed stone or river rock are not acceptable mulch materials.
2. Mulch trees planted in lawn areas with a minimum 5-feet diameter mulch bed around the base of the tree and separate tree from the lawn area by steel edging 5- feet in diameter.
G. Planting shall be located where it is shown on the plans or as otherwise approved. No planting holes shall be dug until the proposed locations have been staked on the ground by the contractor.
H. Planting pits shall be excavated to the following dimensions and refilled with a mixture of planting soil (1/2 muck and 1/2 existing native soil):
1 gal. Material (1 gal.): 12 inches x 12 inches x 12 inches min.
3 gallon Material (3 gallon): 20 inches x 20 inches x 18 inches min.
Lerio material (7 gallon): 30 inches x 30 inches x 24 inches min.
Field grown material and trees: 3 times width of ball and depth of ball plus 12 inches min.
P. All plants shall be set to finished grade. No filling will be permitted around trunks or stems. All ropes, wire, stakes, etc. shall be removed from sides and tops of the ball and removed from hole before filling in.
Q. All flagging ribbon shall be removed from trees and shrubs before planting.
R. All fertilizers, pesticides, or other chemical amendments shall comply with federal, state, and base requirements.
7.3 PLANTING SOIL MATERIAL
A. Topsoil: Fertile, agricultural topsoil, typical for project locality, capable of sustaining vigorous plant growth, taken from drained site free of subsoil, clay, plants, weeds, and roots, pH range of 5.5 to 7.0 minimum 4 percent, maximum 20-percent organic matter.
B. Peat Moss: Shredded, loose, sphagnum moss, free of lumps, roots, inorganic material, minimum 85-percent organic material measured by oven dry weight, 4 to 5-pH range, moisture content of 30 percent.
APPENDIX A Page 22 of 40
C. Sand: Coarse, washed, builder's sand.
D. Planting Soil Mixture: Provide mixture of imported topsoil or approved topsoil from site, peat, sand, and other amendments as recommended by the independent soil testing laboratory for the specified plants.
7.4 SODDING
A. Graded and scarred areas around the project shall be sodded.
B. At all new paved drives, paved parking area and concrete sidewalks, the DBC will provide and install solid sodding, a minimum of 3-feet in width, on edges of all new paved surfaces (parking, roads, sidewalks, mowing strips, etc.) and on the complete perimeter of all new pavement in this project.
C. All other areas disturbed in this project shall be seeded and mulched.
D. Solid sodding shall be installed on all stormwater treatment facility slopes from pond bottom elevation to top of bank slope.
E. If disturbed areas will be left for more than ten calendar days without construction activity, the Contractor shall install temporary seeding and mulching.
F. Prior to sodding, loosen existing soil to a minimum depth of 4-inches. Top 4-inches shall be mixed with soil amendments including 2-inches topsoil.
G. Provide 2-inch offsite topsoil for all sodded areas. Amend existing soil by applying agricultural lime at a rate of 50-pounds per 1,000 square feet and 12-12-12 commercial fertilizer at the rate of 1½-pounds per 1,000 square feet. Sodding shall be specified in
Section 32 92 23 SODDING.
H. The sod shall be firm, tough texture, having compacted growth of grass with good root development. It shall contain no noxious weeds, or any other objectionable vegetation, fungus, insects, or disease. The soil embedded in the sod shall be good clean earth, free from stones and debris.
I. Before being cut and lifted the sod shall have been mowed at least three times with a lawn mower, with the final mowing not more than 7 days before the sod is cut.
J. Solid sod shall be laid with closely abutted joints with a tamped or rolled, even surface.
K. The finish level of all sod areas after settlement shall be 2 inches below the top of abutting curbs, walks, paving and wood borders to allow for building turf.
7.5 TEMPORARY IRRIGATION FOR PLANTS
A. A permanent irrigation system is not to be provided.
B. The contractor shall provide temporary irrigation for landscaping installed and plant
APPENDIX A Page 23 of 40 establishment that will be utilized for a period of one full year from the date of final acceptance.
C. The contractor will use a fire hydrant to supply the irrigation water during this period.
Above-ground system is not allowed. After the one-year establishment period, the contractor will remove the temporary system and repair all disturbed areas.
D. The contractor shall provide complete landscape maintenance including routine mowing, pruning, watering, weeding, and fertilizer for a period of 365 days. Maintenance shall be specified in Section 32 05 33, Landscape Establishment.
7.6 COMPLETION, INSPECTION AND ACCEPTANCE
A. Completion of the work shall mean the full and exact compliance and conformity with the provisions expressed or implied in the drawings and in the specifications including the complete removal of all trash, debris, soil or other waste created by the landscape contractor.
B. Inspection of work to determine completion of contract, exclusive of the possible replacement of plants, will be made by the Government at the formal Facility Substantial
Completion.
C. All plant material shall be alive and in good growing condition for each specified kind of plant at the time of acceptance. The rating of each plant according to Florida grades and standards shall be equal to or better than that called for on the plans and in these specifications at the time of final inspections and acceptance.
D. After inspection, the landscape contractor will be notified by the Government on the acceptance of all plant material and workmanship, exclusive of the possible replacement of plants subject to…
This is the start of the file's text. The full file is on GovTribe.