Attachment 2- PBP Milestones .pdf
PDF 197 KB Posted
- Attached to
- TR-302D and 355 Transducers
- Solicitation number
- N6660425R0468
About this file
This document is a Proposed Milestone Progress Payment Plan for Solicitation N66604-25-R-0468 involving TR-302D and TR-355 Transducers. The payment plan outlines two distinct milestone-based payment structures: one for First Article Projectors and another for Production CLINs. For the First Article Projectors, the milestone payment plan includes four stages totaling 80% of the contract price, with verification methods involving reviews by the Technical Point of Contact (TPOC) and government receipt of materials and projectors. The Production CLINs milestone payment plan includes three stages totaling 50% of the contract price, with verification methods involving DCMA (Defense Contract Management Agency) representative reviews of documentation, material ordering, and material receipt. Each milestone is either severable or cumulative, with specific percentage allocations and detailed completion verification requirements, providing a structured approach to contract payment progression based on specific project achievements.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Solicitation Amendment N6660425R04680002.pdf | ||
| Solicitation Amendment N6660425R04680001.pdf | ||
| Attachment 3- DD Form 254 .pdf | ||
| Exhibit B_CDRLs.pdf | ||
| Exhibit A_CDRLs .pdf | ||
| Solicitation - N6660425R0468.pdf | ||
| Attachment 1- Pricing Tables .docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
TR-302D and TR-355 First Article CLIN Milestones
(First Article Projectors) Severable/Cumulative Percent CLIN Price Milestone Completion Verification Method
1. Preliminary Configuration Review (PCR) Completion
Severable 20% PCR is conducted IAW the SOW. TPOC receives, reviews, and accepts contractor-submitted PCR presentation package and supporting technical documentation.
2. Final Configuration Review (FCR) Completion
Cumulative - based on milestone #1 20% FCR is conducted IAW the SOW. TPOC receives, reviews, and accepts contractor-submitted FCR presentation package and supporting technical documentation.
3. First Article material received Cumulative - based on milestones #1 and
#2.
20%
Contractor provides internal report to TPOC which provides proof of purchased material receipt (receipt report and date received).
4. Delivery of First Article Projectors Cumulative - based on milestones #1, #2, and #3.
20%
Contractor delivers First Article Projectors and the Government receives them.
TOTAL: 80%
TR-302D and TR-355 PRODUCTION CLINs Milestones
Severable/Cumulative Percent CLIN Price Milestone Completion Verification Method
1. Drawings and Production Documentation released.
Severable 15%
DCMA representative receives, reviews, and accepts contractor-submitted Product Baseline Drawing listing and supporting technical documentation. Contractor provides internal report to DCMA representative which provides proof of release of production documentation.
2. Material Ordered Cumulative - based on milestone #1 15% Contractor provides internal report to DCMA representative which provides proof that the material was ordered (PO number and date issued).
3. 90% of material line items received.
Cumulative - based on milestones #1 and
#2 20%
Contractor provides internal report to DCMA representative which provides proof that the material was received against the purchase orders
(PO) which were placed.
TOTAL: 50%
Solicitation N66604-25-R-0468 for TR-302D and TR-355 Transducers Proposed Milestone Progress Payment Plan
Solicitation N66604-25-R-0468 for TR-302D and TR-355 Transducers Proposed Milestone Progress Payment Plan
File details come from the government source that posted it. Updated .