ATTACHMENT 2 Paving IDIQ Specifications - Supplement.pdf
PDF 454 KB Posted
- Attached to
- PAVING IDIQ Maxwell AFB and Gunter Annex - AMENDMENT 2 Federal contract opportunity
- Solicitation number
- FA330024R0025
About this file
This document is the construction specifications for an Indefinite Delivery Indefinite Quantity (IDIQ) paving contract at Maxwell Air Force Base in Alabama. The specifications cover demolition, concrete, asphalt, pavement markings, and other site work required for various paving projects.
Key details include:
- This will be a competitive Total Service-Disabled Veteran Owned Small Business set-aside contract awarded by the Department of the Air Force Air Education and Training Command.
- A site visit is scheduled for June 6, 2024 and proposals are due by June 24, 2024.
- The contract will be firm-fixed-price and the contracting officer has determined there is a high probability of adequate price competition.
- The specifications provide detailed requirements for materials, construction methods, quality control, and submittals related to paving, concrete, demolition, erosion control, and other site work.
View the file
Other files for this federal contract opportunity
Show all 13
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
CONSTRUCTION SPECIFICATIONS
PAVEMENTS
INDEFINITE DELIVERY INDEFINITE QUANTITY
(IDIQ)
For
MAXWELL AIR FORCE BASE, ALABAMA
12 Feb 2024
Maxwell Paving IDIQ
INDEX
DIVISION 01 GENERAL REQUIREMENTS
01 14 19 Coordination 01 30 00 Submittal Procedures 01 45 00 Regulatory Requirements 01 50 00 Construction Facilities and Temporary Controls 01 57 23 Storm Water Pollution Prevention Measures
DIVISION 02 EXISTING CONDITIONS
02 41 19 Selective Structure Demolition 02 60 00 Asphalt and Concrete Removal
DIVISION 03 CONCRETE
03 11 14 Concrete Formwork 03 20 00 Concrete Reinforcement 03 30 00 Cast-In-Place Concrete
DIVISIONS 04-09 NOT USED
DIVISION 10 SPECIALTIES
10 14 00 Signage
DIVISIONS 11-30 NOT USED
DIVISION 31 EARTHWORK
31 05 13 Soils for Earthwork 31 10 00 Site Clearing 31 23 16 Excavation, Fill and Backfill
DIVISION 32 EXTERIOR IMPROVEMENTS
32 12 10 Paving 32 17 23 Pavement Markings 32 92 19 Seeding
DIVISIONS 33-49 NOT USED
SECTION 01 14 19
COORDINATION
1.0 WORK SCHEDULE
A. Maxwell Air Force Base (AFB) work hours are 7:00 a.m. to 5:00 p.m. all days of the week except Saturday, Sunday, and Federal Holidays. Contractor shall not perform any work outside of these work hours without obtaining written approval from the Contracting Officer. If weekend or evening work is required due to utility outages or other requirements, such work shall not be performed without prior written approval of the Contracting Officer and such work shall be accomplished at no additional cost to the Government. The Contracting Officer requires at least seven (7) calendar days’ notice, in writing, from the Contractor to provide written approval or disapproval.
B. Observed federal holidays include:
New Year’s Day Labor Day Martin Luther King Jr.’s Birthday Columbus Day Washington’s Birthday Veteran’s Day Juneteenth Thanksgiving Day Memorial Day Christmas Day Independence Day
1.1 UTILITIES
A. Existing electrical service to the facility shall be maintained until new electrical service is in place and ready for operation.
B. Utility interruptions shall be approved by the Contracting Officer. The following shall apply:
1. Electrical primary power outages will be performed by 42nd Civil Engineer Squadron and shall be fully coordinated with the Contract Administrator/TM.
The Contractor shall submit to the Contracting Officer a written request for such work at least two (2) weeks prior to the desired date. Electrical primary outages shall be limited to four (4) hours.
2. Water outages will be performed by the 42nd Civil Engineer Squadron and shall be fully coordinated with the Contract Administrator/TM. The Contractor shall submit to the Contracting Officer a written request for such work at least two (2) weeks prior to the desired date.
3. Communications Utilities The Contractor shall not disturb communication wiring to facilities. Where such facilities require removal of communication equipment and wiring to accomplish the work involved, the Contractor shall notify the Contract Administrator/TM at least five (5) workdays in advance of the requirement, for scheduling such removals by the Government. The Contractor shall allow for the accomplishment of such removals by the telephone company or communications personnel for the systems they service. If construction activities damage any communication equipment or wiring, the Contractor shall restore services as soon as possible, but no later than 24-hours, and at no cost to the Government.
4. Excavation Around or Locating Existing Utilities
Prior to the start of work, the Contractor shall identify and locate all valve or utility shut-off locations for use in the event of accidental damage. To preclude accidental damage, the Contractor shall locate all known utilities (i.e., communication, natural gas, fuel supply, etc.) by hand digging prior to any excavation with power equipment. The Contractor shall note any utilities discovered during excavations that are missing or incorrect on the contract drawings (including any erroneous dimensions on Government record drawings), or those utilities staked by the user, and clearly identify those discoveries on the as-built drawings.
1.2 PROTECTION OF EXISTING FACILITIES
A. The Contractor shall conduct and schedule all work in a manner to cause as little disruption as possible to the existing facilities and operation. Phase work as may be indicated on drawings or required by these specifications. (Use if phasing is required).
B. The Contractor shall ensure that the existing building is maintained weatherproof at all times. The buildings’ HVAC system shall also be maintained in full operating order by the Contractor. The Contractor shall provide and install 40 percent efficient construction filters and shall maintain the filters throughout the construction timeframe in all return air, outside air and exhaust air inlets in the construction area or where dust and debris may enter the duct.
1.3 SITE VISITATION
A. The Contractor shall be responsible to visit the project site prior to, and during, the course of construction to verify existing conditions, actual sizes, and other requirements outlined in the other sections of the specifications.
B. Existing Facilities/Job Site Verification
Record drawings, showing existing facilities and underground utilities, are available to the Contractor through the Base Civil Engineer office. The Government does not guarantee the accuracy, availability or adequacy of existing as-built/record drawings. The Contractor is responsible to verify all dimensions and actual conditions when developing their contract proposal. Failure to verify the dimensions and locations will be at the Contractor’s risk and shall not relieve the Contractor from accomplishing the work required by the contract at the price awarded by the Government. The Contractor shall immediately repair any utility line shown on a record drawing (or made known to the Contractor) and damaged during construction work, at no cost to the Government.
1.4 BASE REGULATIONS
The Contractor shall conform to all base regulations and directives pertaining to security, safety, debris removal, fire, traffic, and personnel clearances, insofar as they pertain to the Contractor’s activities on Maxwell AFB. The Contractor shall ensure conformance by all employees and Subcontractors.
1.5 FIRE PROTECTION
The Contractor shall be responsible for conformance with base fire regulations and NFPA 241, including Appendix A. These regulations are available for review during duty hours at the Base Fire Station located in Building 1092. Fire extinguishers required during the construction period shall be furnished and maintained by the Contractor and removed by the Contractor upon acceptance of the facility by the Contracting Officer. No welding/cutting and open flame operation shall be allowed in facilities when automatic fire detection and suppression systems are out of service unless the Contractor posts a fire guard for 24 hours after welding/cutting and open flame operation or certifies the facility fire safe.
1.6 CONSTRUCTION PERMIT (DIGGING PERMIT)
A. A properly completed AF Form 103, Base Civil Engineering Work Clearance Request, shall be obtained by the Contractor prior to performing any excavation.
B. A separate AF Form 103 shall be obtained by the Contractor for each excavation to be accomplished.
C. Contractor shall submit a request for AF Form 103 a minimum of 14 calendar days and a maximum of 28 days prior to desired start of excavation. The Contractor shall allow a minimum of 14 calendar days for processing.
D. Each request shall be in writing and designate the location of the proposed excavation and the scheduled date.
E. The completed AF Form 103 will contain information for locating existing utilities and telephone lines. The Contractor shall keep the AF Form 103 at the excavation site and shall comply with instructions for hand excavation and with other methods of safeguarding the buried utilities.
F. In addition to the requirement to obtain a construction permit and prior to any excavation, the Contractor shall perform a pipe/cable location survey using a variety of modern locating equipment suitable for locating various types of pipe and cable. The Contractor shall mark all locations on the ground. The Contractor shall submit a sketch showing the found locations of utilities to the Contracting Officer for approval prior to beginning excavation. The Contracting Officer will provide available information as to the existence and location of known utilities with the approved construction permit. The Contractor shall be responsible for repairing damage to utilities, whether known or unknown, due to any failure on the Contractor’s part to perform a rigorous survey.
END OF SECTION
SECTION 01 30 00
SUBMITTAL PROCEDURES
1.0 SUMMARY DESCRIPTION OF REQUIREMENTS
A. This section specifies procedural requirements for non-administrative submittals, including but not limited to shop drawings, product data, manufacturer’s certificate, design data, calculations, and verifications, manufacturer’s instructions, manufacturer’s field service reports, samples, operation and maintenance manuals, and other miscellaneous work- related submittals. These submittals are required to amplify, expand, and coordinate other information contained in the contract.
B. The Contracting Officer may request submittals in addition to those specified when deemed necessary to adequately describe the work covered in the respective sections of the specification or statement of work.
C. Definition: For the purposes of this section, the term “Contractor” denotes the prime Contractor.
1.1 REFERENCES (Not Applicable)
1.2 SUBMITTAL CLASSIFICATION
A. Submittals are classified as follows:
1. Contracting Officer Approval: The Contracting Officer (CO) approval is required for extensions of design, critical materials, deviations, equipment whose compatibility with the entire system must be checked, and other items as designated by the CO. Within the terms of the Contract Clause entitled "Specifications and Drawings for Construction", they are considered to be "shop drawings.”
2. Information Only: All submittals not requiring the Government approval will be for information only. They are not considered to be "shop drawings" within the terms of the Contract Clause referred to above.
1.3 APPROVED SUBMITTALS:
A. The approval of submittals by the CO shall not be construed as a complete check, but will indicate only that the general method of construction, materials, detailing and other information are satisfactory.
B. Approval will not relieve the Contractor of the responsibility for any error, which may exist, as the Contractor is responsible for the dimensions and design of adequate connections, details, and satisfactory construction of all work. After submittals have been approved by the CO, no resubmittal for the purpose of substituting materials or equipment will be given consideration unless accompanied by an explanation as to why a substitution is necessary.
1.4 DISAPPROVED SUBMITTALS:
The Contractor shall make all corrections required by the CO and promptly furnish a corrected submittal in the form and number of copies as specified for the initial submittal. If the Contractor considers any correction indicated on the submittals to constitute a change to the contract, notice as required under the Contract Clause entitled "Changes" shall be given promptly to the CO.
1.5 GENERAL:
A. The Contractor shall submit all items listed on the Submittal Register (Material Submittal Schedule (MSS), or equivalent) or specified in the other sections of these specifications. The CO may request submittals in addition to those listed when deemed necessary to adequately describe the work covered in the respective sections. Units of weights and measures used on all submittals shall be the same used in the contract drawings. Submittals shall be made in three (3) copies unless otherwise noted on the Submittal Register to the CO. Each submittal shall be complete and in sufficient detail to allow ready determination of compliance with contract requirements.
B. Prior to submittal, all items shall be checked and approved and each respective transmittal form or material approval submittal (AF 3000, Material Approval Submittal) shall be stamped, signed and dated by the Contractor certifying that the accompanying submittal complies with the contract requirements. Submittals shall include line number of item from Government-prepared Submittal Register.
Proposed deviations from the contract requirements shall be clearly identified.
Submittals shall include items such as: Contractor's, manufacturer's, or fabricator's drawings; descriptive literature including (but not limited to) catalog cuts, diagrams, operating charts, or curves; test reports; test cylinders; samples; O&M manuals including parts list; certifications; warranties and other such required submittals.
Submittals requiring CO approval shall be scheduled and made prior to the acquisition of the material or equipment covered thereby.
1.6 SUBMITTAL REGISTER: Material Submittal Schedule (MSS):
A submittal register on the MSS shall be provided to the Contractor as an attachment to the awarded contract. During the pre-construction meeting, the Contractor shall meet with the CO to jointly review the prepared Submittal Register.
The Contractor shall be responsible for providing all items listed on the Submittal Register in accordance with the scheduled submittal dates.
1.7 SCHEDULING:
A. Submittals covering component items forming a system or items that are interrelated, shall be scheduled to be coordinated and submitted concurrently.
Certifications to be submitted with the pertinent drawings shall be so scheduled.
The Contractor shall take special care to timely schedule the submittal date required for long lead-time items and shall allow 30 days for CO review action on all submittals except as noted below. No delays, damages, or time extensions will be allowed for time lost in late submittals.
B. All submittals will be made on AF 3000, Material Approval Submittal as specified below.
1. The number of days for CO action on the following submittals will be as indicated:
a. Submittals required on the MSS – 10 calendar days
b. Any submittal that requests or requires deviation from contract drawings or specifications – 14 calendar days
1.8 TRANSMITTAL FORM (AF 3000, Material Approval Submittal):
A. AF 3000, Material Approval Submittal shall be used for submitting both Government approved and information only submittals in accordance with the instructions on the reverse side of the form. These forms will be furnished to the Contractor by the CO. This form shall be properly completed by filling out all the heading blank spaces and identifying each item submitted.
B. Special care will be exercised to ensure proper listing of the specification paragraph and/or sheet number of the contract drawings pertinent to the data submitted for each item.
1.9 CONTROL OF SUBMITTALS:
The Contractor shall carefully control his procurement operations to ensure that each individual submittals made on or before the Contractor scheduled submittal date shown on the provided Submittal Register.
1.10 CO APPROVED SUBMITTALS:
A. Upon completion of review of submittals requiring CO approval, the submittals will be identified as having received approval by being so noted on AF 3000, Material Approval Submittal. Such submittals shall be made in accordance with the Construction Contract Clause entitled "Specifications and Drawings for Construction" and the following: unless otherwise noted on the Submittal Register and when submitting physical documents, three (3) prints of all drawings; or, if catalog cuts, printed specifications or similar publications are used as submittals, three (3) original copies shall be submitted. One corrected copy shall be returned to the Contractor. When submitting documents for review and approval via email, only one copy is required. In cases where "trade names or equal" specifications are used, any equal substitution by the Contractor will be considered a deviation and will require approval. Any submittal requesting a deviation shall be considered as one requiring "approval" action. Payment for materials incorporated into the work will not be allowed if required approvals have not been obtained. Upon completion of review of submittals requiring CO approval, the submittals will be identified as having received approval by being so noted on AF 3000, Material Approval Submittal.
B. Risk: Do not proceed with the part of the work covered by an item submittal including purchasing, fabricating, and delivering until approval is received.
Machinery, equipment, material, and articles that do not have the required approval shall be installed or used at the risk of subsequent rejection. Any fabrication or other work performed in advance of the receipt of accepted item submittals and approvals shall be entirely at the Contractor’s risk and expense.
1.11 INFORMATION ONLY SUBMITTALS:
All other submittals are considered to be "Information Only" submittals and may be subject to review action by the CO or may be simply receipt acknowledged. Any submittal “For Information Only” shall be clearly marked “FIO”. Normally, submittals for information only will not be returned. Approval of the Construction Manager (CM) is not required on information only submittals. These submittals will be used for information purposes. The CO reserves the right to require the Contractor to resubmit any item found not to comply with the contract. This does not relieve the Contractor from the obligation to furnish material conforming to the plans and specifications and will not prevent the CO from requiring removal and replacement if nonconforming material is incorporated in the work. This also does not relieve the Contractor of the requirement to furnish samples for testing by the CO laboratory or check testing by the CO, in those instances where the technical specifications so prescribe. It shall be the Contractor's responsibility of assuring that the materials and/or equipment covered by that submittal meets the contract requirements. Any such "For Information Only" submittal found to contain errors or omissions shall be resubmitted as one requiring "approval" action. All "For Information Only" submittals shall be made in triplicate unless otherwise specified.
1.12 PROCEDURES
A. Listing: At the end of this section is a summarized listing of item submittals requiring approval for the work. The listing is included for the convenience of users of the contract documents. The listing is not all-inclusive and additional item submittals may be required. Within 10 calendar days after receiving contract award, Contractor shall submit a copy of the summarized submittal listing with calendar dates assigned to each item submittal indicating when submittal will be received by the Government. If contract requires a pre-construction conference, Contractor may submit completed submittal listing at the conference. The list will be supplemented by submittals required for each task delivery order.
B. Transmittal Timing: Coordinate the preparation and processing of item submittals with the performance of the work. Prepare and transmit each item submittal to the Contracting Officer sufficiently in advance of the performance of related work and other applicable activities. Transmit related item submittals for the same unit of work so that processing will not be delayed by the Government's need to review submittals concurrently for coordination. No delay damages or time extensions will be allowed for time lost in late submittals.
C. Content: Each submittal shall be complete and in sufficient detail to allow ready determination of compliance with contract requirements. All submittals which are generic and list more information than is specifically required shall be marked to identify required information. Complete AF Form 3000 and attach as cover sheet for each submittal. Contractor may include multiple item numbers on an AF Form 3000. (See paragraph 5.0A and 5.0B)
D. Language: All item submittals shall be written in English, including documents, notes on drawings, sketches, and/or samples, calculations, manuals, and all other instances of written text and communication.
E. Units: All item submittals shall be written in English, including documents, notes on drawings, sketches, and/or samples, calculations, manuals, and all other instances of written text and communication.
F. Review Time: Allow sufficient time so that contract performance will not be delayed as a result of the time required to properly process submittals, including time for re-submittals, if necessary. Allow 10 calendar days for initial Government processing of each submittal. No extension of time will be authorized because of the Contractor's failure to transmit submittals to the Government sufficiently in advance of the work.
G. Contractor Certification: All submittals shall be carefully reviewed by an authorized representative of the Contractor prior to submission to the Government. Each submittal shall be dated, signed, and certified by the Contractor as being correct and in strict conformance with the contract documents. No consideration for review by the Government of any Contractor’s submittal will be made for any items which have not been so certified by the Contractor. All noncertified submittals will be returned to the Contractor without action taken by the Government, and any delays caused thereby shall be the total responsibility of the Contractor.
H. Deviations: Should any item submittals required by the contract documents show deviations from the contract requirement, the Contractor shall make specific mention of such deviations in the letter of transmittal, including stating cost effects, and product and system limitations which may adversely affect the work, in order that if acceptable, suitable action may be taken for proper adjustment of the contract; otherwise the Contractor will not be relieved of the responsibility for executing the work in accordance with the contract documents and the approved submittals. Contractor shall clearly mark the proposed variation in all documentation and specifically point out deviations from contract requirements in transmittal letters. Failure to point out deviations may result in the Government requiring rejection and removal of such work at no additional cost to the Government. Deviations from contract requirements require Government approval and will only be considered when advantageous to the Government. When proposing deviations, deliver written request to the Contracting Officer, with documentation of the nature and features of the deviation and why the deviation is desirable and beneficial to the Government. If lower cost is a benefit, include an estimate of the cost savings. In addition to documentation required for deviation, include the submittal information required for the item. Allow an additional 14 calendar days beyond normal submittal review period for consideration by the Government of submittals with deviations.
I. Approval Submittals: The part of the work covered by the approved item submittal may proceed provided it complies with the requirements of the contract documents. Final acceptance will depend upon that compliance. The term “Approved” shall only indicate that there is no exception taken to the submittal.
Approval of the item submittal shall not be construed as a complete check and indicates only that the general method or other information appears to meet the contract requirements. Approval does not relieve the Contractor of the responsibility for any error which may exist. After item submittals have been approved by the Contracting Officer, no resubmittal for the purpose of substituting materials or equipment, or changes to any other information will be considered unless accompanied by an explanation of why a substitution or change is necessary.
J. Disapproved Submittals: Contractor shall correct disapproved item submittals and resubmit for approval within timeframe noted. If no date is given, Contractor shall submit corrected submittal within 14 calendar days. If the Contractor considers any correction or notation on the returned submittal to constitute a change to the contract drawings, specification, or statement of work the Contractor shall notify the Contracting Officer.
K. Responsibility: The Government’s review of Contractor submittals shall not relieve the Contractor of the entire responsibility for the correctness of details and dimensions and conformance to the specifications. The Contractor shall assume all responsibility and risk for any mistakes and/or costs due to any errors in submittals.
L. Inconsistencies: If a conflict or inconsistency arises between an approved item submittal and the contract documents, the contract documents shall govern.
1.13 SPECIFIC SUBMITTAL DESCRIPTIONS AND REQUIREMENTS:
Submittal requirements for individual units of work are specified in the applicable specification section or Statement of Work (SOW). Except as otherwise indicated in the individual specification sections or SOW, comply with the following requirements for each type of submittal.
A. Shop Drawings: These are technical drawings and data specially prepared for these specifications including fabrication and installation drawings, setting and seaming diagrams, and coordination drawings (for use on-site). Shop drawings include drawings, diagrams and schedules specifically prepared to illustrate some portion of the work, diagrams and instructions from a manufacturer or fabricator for use in producing the product and as aids to the Contractor for integrating the product or system into the project, or drawings prepared by or for the Contractor to show how multiple systems and interdisciplinary work will be coordinated.
Information required on shop drawings includes dimensions, identification of specific products and materials which are included in the work, compliance with specified standards, and notations of coordination requirements with other work.
Provide special notations of dimensions that have been established by field measurements. Highlight, encircle, or otherwise indicate deviations from the contract documents on the shop drawings. Furnish one hard copy and one electronic copy.
B. Product Data: This data includes standard printed information on manufactured products that has not been specially prepared for these specifications, including manufacturers' product specifications illustrating size, physical appearance and other characteristics of materials, installation instructions, standard color charts, catalog cuts, illustrations, schedules, standard wiring diagrams, standard product operating and maintenance manuals, and samples of warranty language when the contract requires extended product warranties. General information required specifically as product data includes manufacturers' standard printed recommendations for application and use, compliance with recognized standards of trade associations and testing agencies, the application of their labels and seals (if any), special notation of dimensions which have been verified by way of field measurement, and special coordination requirements for interfacing the material, product, or system with other work. Furnish three hard copies and one electronic copy.
C. Samples: These are physical examples of work, including, swatches showing color, texture, and pattern, color-range sets, and units of work to be used for independent inspection and testing. Samples include fabricated or unfabricated physical examples of materials, equipment or workmanship that illustrate functional and aesthetic characteristics of a material or product and establish standards by which the work can be judged, color samples from the manufacturer’s standard line (or custom color samples if specified) to be used in selecting or approving colors for the project, and field samples and mock-ups constructed on the project site to establish standards by which the ensuring work can be judged. This includes assemblies or portions of assemblies which are to be incorporated into the project and those which will be removed at conclusion of the work. Submit samples for the Contracting Officer's visual review of general kind, color, pattern, and texture for a final check of the coordination of these characteristics with other related elements of the work and for quality control comparison of these characteristics between the final sample submittal and the actual work as it is delivered and installed. Submit one (1) each.
D. Design Data: Design data includes design calculations, mix designs, analyses, or other data pertaining to a part of work. Refer to individual sections of the specification or statement of work for required quantities, formats, and signatures or certifications required. Furnish three hard copies and one electronic copy.
E. Test Plans and Reports: Test plans shall include planned testing, including a description of the test, equipment and supplies needed, and step-by- step notation of test activities and tasks. Test reports include reports signed by an authorized official of a testing laboratory that a material, product. or system identical to the material, product, or system to be provided has been tested in accordance with the specified requirements. Testing shall have been within three years of date of contract award for the project. Reports also include findings of tests required to be performed by the Contractor on an actual portion of the work or prototype prepared for the project before shipment to the job site, findings of tests made at the job site or on a sample taken from the job site, investigation reports, daily logs and checklists, and final acceptance test and operational test procedures. Furnish three hard copies and one electronic copy of each such report required.
F. Certificates: These include statements printed on the manufacturer’s letterhead and signed by the responsible officials of the manufacturer of a product, system or material attesting that the product, system, or material meets specification requirements. Certificates include documentation required of the Contractor, or of a manufacturer, supplier, installer, or subcontractor through the Contractor, to further demonstrate the quality of orderly progressions of a portion of the work by documenting procedures, acceptability of methods or personnel qualifications.
Examples include confined space entry permits, and text of posted operating instructions. Certificates shall be dated after award of the project contract and clearly name the project. Furnish three hard copies and one electronic copy of each certificate required.
G. Manufacturer’s Instructions: Preprinted material describing installation of a product, system, or material, including special notices and Material Safety Data sheets concerning impedances, hazards, and safety precautions. Furnish three
(3) hard copies and one electronic copy.
H. Manufacturer’s Field Reports: Documentation of the testing and verification actions taken by a manufacturer’s representative at the jobsite, in the vicinity of the job site, or on a sample taken from the job site, on a portion of the work, during or after installation, to confirm compliance with the manufacturer’s standards or instructions. The documentation shall be signed by an authorized official of a testing laboratory or agency and shall state the test results, and indicate whether the material, product, or system has passed or failed the test. Furnish three hard copies and one electronic copy.
I. Operation and Maintenance Data: Data furnished by the manufacturer, or the system provider, to the equipment operating and maintenance personnel, including manufacturer’s help and product line documentation necessary to maintain and install the equipment, and needed by operating and maintenance personnel for the safe and efficient operation, maintenance, and repair of the item. The data is intended to be incorporated in an operations and maintenance manual or control system. Furnish two hard copies and one electronic copy.
J. Final Design Drawings and Documentation: Final design documentation including drawings, specifications, estimates, and other required deliverables. Electronic documentation submitted shall include every associated component file of drawings and other documentation, including raster images, jpeg, tiff, Excel, and any related items required to view, modify, or manipulate the electronic files.
Furnish a CD-ROM of all final design documentation, and drawings in AutoCAD 2005 format or later, to the Contracting Officer for approval prior to applying for final payment.
K. Record (As-Built) Drawings: Record drawings showing final configuration of work accomplished. Show all changes, additions, and deviations from the original contract drawings and documentation. If no changes occur, furnish certification to that effect. Drawings may be redlined hardcopies or electronic drawings and shall accurately show as-built conditions during the progress of the job. If electronic, furnish drawings on a CD-ROM, in AutoCAD 2005 format or later, including every associated component file of the drawings, including raster images, jpeg, tiff, Excel, and any related items required to view, modify, or manipulate the electronic files. Submit to the Contracting Officer for approval prior to applying for final payment.
L. Miscellaneous Submittals: These are work-related, non-administrative submittals that do not fit in the previous categories, including the following:
1. Maintenance agreements. Furnish one hard copy and one (1) electronic copy.
2. Survey data and reports. Furnish one hard copy and one (1) electronic copy.
3. Project photographs. Furnish both hard copies and digital files.
4. Keys and other security protection devices.
5. Maintenance tools, spare parts, and overrun or maintenance stock. Refer to individual sections of the specification for required quantities of spare parts, extra and overrun stock, maintenance tools and devices, keys, and similar physical units to be submitted.
6. Qualification certificates. Furnish one hard copy and one (1) electronic copy.
7. Employee training certificates and documentation showing successful completion of training.
8. Documentation of percentage of recovered material content used during contract.
9. Contractor safety and work plans and schedules.
10. Warranties.
1.14 REQUIRED SUBMITTALS
No. Submittal Description Due
1 Outage Request 2 weeks prior to outage
2 Proposed Scaffolding Before beginning work
3 Record As-Built Drawings Before final inspection
Existing conditions report which could be construed as damage resulting from work
Before beginning work
5 Safety and health plan 10 days after contract award
6 Percentage of recovered material content Before final inspection
7 Disallowed products locations Before final inspection
8 Asbestos locations Before final inspection
9 Forms GC-565 and GC-1337 Before final inspection
10 Hazardous material information Before beginning work
11 Summarized submittal listing with delivery dates
10 days after contract award
12 Work sequence schedule Before beginning work 13 Stormwater Permit Before beginning work
Stormwater Pollution Prevention Plan and Notice of Intent
Five (5) days after contract award
15 Notice of termination When area is approved as stabilized
16 Proposed Demolition Methods and Operations Before beginning work
17 Asphalt Coring Samples As sampling is completed
18 Lights/Barricades quantity and size Prior to placement
19 Shop Drawings Prior to placement 20 Manufacturers’ Certificate Prior to placement 21 Mill Test Reports Prior to placement 22 Concrete Mix Design Prior to placement
23 Non-Shrink Grout Product Data Prior to placement
24 Slump Test Day of placement
Compression Test
First test – seven days after placement; second test – 28 days after placement
26 Shop Drawings Prior to placement
27 Reflective Sheeting and Graphic Product Information Prior to placement
28 Imported Material Source Prior to placement 29 Site Clearing Plan Before beginning work
30 Erosion Control Plan Using Best Management Practices Before beginning work
31 Traffic Control Plan Before beginning work
32 Demolition and Excavation Plan Before beginning work
Bituminous Binder Course and Surface Course Job – Mix Design Formula
Prior to placement
Soil or Existing Material In- Place Density and Moisture Test Report
Prior to placement of aggregate
35 Base Course In-Place Density and Moisture Test Report
Prior to placement of pavement and concrete
Bituminous Binder and Surface Course In-Place Density Test Report
10 days after placement
Bituminous Binder and Surface Course Extraction Test Report
Day of placement
38 Hot-Mix Asphalt Core Samples Test Reports
10 days after taking sample
39 Aggregates Certification Prior to Placement 40 Tack Coat Certification Prior to Placement
41 Bituminous Materials Certification Prior to Placement
42 Catch Basins or Drainage Structures Product Data Prior to Placement
43 Storm Drain Pipes Product Data Prior to Placement
44 Culverts Product Data Prior to Placement
45 Other Appurtenances Product Data Prior to Placement
Manufacturer’s Product Data for Pavement Marking Material and Reflective Media
Prior to Placement
Manufacturer’s Material Safety Data Sheets for Pavement Marking Materials
Seed Mis, Fertilizer, Mulch, and other Accessories Product Data
Table I. Required Submittal List – Complete
SECTION 01 45 00
REGULATORY REQUIREMENTS
PART 1 GENERAL
1.1 This section lists regulations, codes, and standards which specify procedural and administrative requirements imposed upon the work.
1.2 The Contractor shall comply with provisions of the following documents to the extent referenced herein.
A. Government documents:
1. Air Force Federal Acquisition Regulation (AFFARS):
a. AFFARS 52.223-9 Estimate of Percentage of Recovered Material Content for EPA-Designated Items, 2008.
b. 5352.223-9000 Elimination of Use of Class I Ozone Depleting Substances (ODS), April2003.
2. Architectural Barriers Act, 1968
3. Code of Federal Regulations:
a. 29 CFR 1926.650 Excavation, 2008.through 652
b. 29 CFR 1926.1101 Asbestos, 2008.
c. 40 CFR 261 Identification and Listing of Hazardous Wastes, 2008.
d. 40 CFR 370 EPA Hazardous Chemical Reporting and Community Right to Know Requirement, 2008.
4. Federal Highway Administration Manual on Uniform Traffic Control Devices
(MUTCD) for Sheets and Highways, Latest Edition.
5. Alabama Department of Environment and Conservation:
a. Alabama Erosion and Sediment Control Handbook, Latest Edition.
6. Alabama Department of Transportation Standard Specifications for Road and
Bridge Construction (SSRBC), Latest Edition.
7. Unified Facilities Criteria:
a. UFC 3-120-01-03 Air Force Sign Standard.
8. US Army Corp of Engineers:
a. USACE EM 385-1-1 Safety and Health Requirements Manual, 2014.
B. Non-Governmental documents:
1. American Architectural Manufacturers Association:
a. AAMA 603.8-98 Voluntary Performance Requirements and Test Procedures for Pigmented Organic Coatings on Extruded Aluminum.
2. American Association of State Highway and Transportation Officials:
a. AASHTO M111-09 Specification for Zinc (Hot-Dip Galvanized) Coatings on Iron and Steel Products
3. American Concrete Institute:
a. ACI SP-66-04 ACI Detailing Manual.
b. ACI 301-10 Specification for Structural Concrete.
c. ACI 305.1-06 Specification for Hot Weather Concreting.
d. ACI 306.1-02 Specification for Cold Weather Concreting.
e. ACI 308.1-98 Specification for Curing Concrete.
f. ACI 318-08 Building Code Requirements for Structural Concrete.
4. ASTM International:
a. ASTM A36-08 Standard Specification for Carbon Structural Steel.
b. ASTM A53-10 Specification for Pipe, Steel, Black and Hot-Dipped, Zinc-Coated, Welded and Seamless.
c. ASTM A82-07 Specification for Steel Wire, Plain, for Concrete
Reinforcement.
d. ASTM A123-09 Specification for Zinc (Hot-Dip Galvanized) Coatings on Iron and Steel Products.
e. ASTM A153-09 Specification for Zinc Coating (Hot-Dip) on Iron and
Steel Hardware.
f. ASTM A307-10 Specification for Carbon Steel Bolts and Studs, 60,000
PSI Tensile Strength.
g. ASTM A500-10 Standard Specification for Cold-Formed Welded and
Seamless Carbon Steel Structural Tubing in Rounds and Shapes.
h. ASTM A501-07 Specification for Hot-Formed Welded and Seamless Carbon Steel Structural Tubing.
i. ASTM A615-09 Specification for Deformed and Plain Carbon-Steel Bars for Concrete Reinforcement.
j. ASTM B209-07 Specification for Aluminum and Aluminum-Alloy Sheet and Plate.
k. ASTM B211-03 Specification for Aluminum and Aluminum-Alloy Bar, Rod, and Wire.
l. ASTM B221-08 Specification for Aluminum and Aluminum-Alloy Extruded Bars, Rods, Wire, Profiles, and Tubes.
m. ASTM C33-11 Specification for Concrete Aggregates.
n. ASTM C39-10 Test Method for Compressive Strength of Cylindrical
Concrete Specimens.
o. ASTM C94-11 Specification for Ready-Mixed Concrete.
p. ASTM C143-10 Test Method for Slump of Hydraulic-Cement Concrete.
q. ASTM C150-09 Specification for Portland Cement.
r. ASTM C172-10 Practice for Sampling Freshly Mixed Concrete.
s. ASTM C173-10 Test Method for Air Content of Freshly Mixed Concrete by Volumetric Method.
t. ASTM C260-10 Specification for Air-Entraining Admixtures for
Concrete.
u. ASTM C494-10 Specification for Chemical Admixtures for Concrete.
v. ASTM C602-07 Specification for Agricultural Liming Materials.
w. ASTM C618-08 Specification for Coal Fly Ash and Raw or Calcined
Natural Pozzolan for Use in Concrete.
x. ASTM C1107-11 Specification for Packaged, Dry, Hydraulic-Cement
Grout (Non-shrink)
y. ASTM D98-05 Specification for Calcium Chloride.
z. ASTM D638-10 Test Method for Tensile Properties of Plastics.
aa. ASTM D698-07 Test Method for Laboratory Compaction
Characteristics of Soil Using Standard Effort (12,400 ft-lbf/ft3).
bb. ASTM D790-10 Test Methods for Flexural Properties of Unreinforced and Reinforced Plastics and Electrical Insulating Materials.
cc. ASTM D1556-07 Test Method for Density and Unit Weight of Soil in Place by the Sand-Cone Method.
dd. ASTM D2487-10 Practice for Classification of Soils for Engineering Purposes (Unified Soil Classification System).
ee. ASTM D3363-05 Test Method for Film Hardness by Pencil Test.
ff. ASTM D4956-07 Specification for Retroreflective Sheeting for Traffic
Control.
gg. ASTM E329-11 Specification for Agencies Engaged in Construction
Inspection, Special Inspection, or Testing Materials Used in Construction.
C. SUBSTITUTION OF TITLES: Substitute “Contracting Officer” for “Engineer” and
“Government” for “Department” or “State” whenever those words are used in all codes and standards.
D. Drawings: Furnished with each task order.
SECTION 01 50 00
CONSTRUCTION FACILITIES & TEMPORARY CONTROLS
1.0 CONTRACTOR’S USAGE OF FACILITIES:
A. The Contractor shall provide a properly and regularly maintained portable toilet for use by workers.
B. Contractor shall not enter the occupied portion of the building to use restrooms, telephones, or other facilities.
C. Smoking and vaping is prohibited in all Government facilities under these specifications.
1.1 GRADE AND ALIGNMENT CONTROL:
The Contractor shall furnish a competent construction surveyor and survey party on the job site as needed to establish and maintain proposed grades and alignment for all increments of construction. The party shall be composed of skillful and competent personnel equipped with accurate and latest model equipment.
1.2 WORK SEQUENCE
In addition to Progress Schedule, the Contractor shall submit for approval by the Contracting Officer two (2) copies of a work sequence schedule showing the sequence of work by area including estimated dates for beginning work in each area. No work shall commence until approval of the work sequence schedule. A written schedule shall be provided for each road, parking lot, etc. within a delivery order.
1.3 POLICE PROTECTION
The 81st Security Forces Squadron (SFS) is responsible for overall base security and traffic control of vehicles entering or leaving Maxwell AFB. The Contractor is required to conform to all appropriate Air Force Security Regulations and shall not interfere with the performance of Security Forces duties and responsibilities. The Contractor shall be responsible for obtaining all necessary security passes for personnel, Subcontractor’s personnel, and all vehicles.
1.4 STREET CLOSINGS
Street closings will be limited to partial, one lane closings whenever possible. Any partial or full street closing shall be requested in writing at least two (2) weeks prior to the desired date.
1.5 ROCK REMOVAL:
A. Excavate and remove exposed rock where encountered. Do not use explosives.
Excavate and remove by mechanical methods. The Contract Administrator/TM shall determine when rock is to be excavated. Measurement and agreement of rock removed shall be accomplished before rock is removed and both the Contractor and Government must agree and sign.
B. Rock shall consist of boulders measuring 1/2 cubic yard or more and material that cannot be excavated without systematic drilling and blasting such as rock material in ledges, bedded deposits, unstratified masses and conglomerate deposits, and below ground concrete or masonry structures exceeding 1/2 cubic yard in volume, except that pavements will not be considered as rock. Rock removal shall include all authorized over depth rock excavation and include all necessary mechanical methods and all incidentals necessary to excavate and dispose the rock.
C. Remove excavated materials to an off-base location secured by the Contractor.
1.6 CONTRACTOR FURNISHED COMMUNICATIONS
Contractor’s Superintendent shall be equipped with a cellular telephone and be reachable by telephone at any time during the normal workday.
1.7 CLEANUP
Construction debris, waste materials, packaging material and the like shall be removed from the work site daily. Any dirt or mud which is tracked onto paved or surfaced roadways shall be cleaned away. Materials resulting from demolition activities which are salvageable shall be stored within the fenced area described above or at the supplemental storage area. Stored material not in trailers, whether new or salvaged, shall be neatly stacked when stored.
SECTION 01 57 23
STORMWATER POLLUTION PREVENTION MEASURES
PART 1 – GENERAL
1.0 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
ASTM INTERNATIONAL (ASTM)
ASTM D 4439 (2004) Geosynthetics ASTM D 4491 (1999; R 2004) Water Permeability of Geotextiles by
Permittivity
ASTM D 4533 (2004)
ASTM D 4632 (1991; R 2014) Grab Breaking Load and Elongation of
Geotextiles ASTM D 4751 (2004) Determining Apparent Opening Size of a Geotextile ASTM D 4873 (2002) Identification, Storage and Handling of Geosynthetic
Rolls and Samples
1.1 GENERAL REQUIREMENTS
The Contractor shall implement the storm water pollution prevention measures specified in this section in a manner which will meet the requirements of the National Pollution Discharge Elimination System (NPDES) permit attached to that Section.
1.2 SUBMITTALS
A. The Contractor shall prepare an Erosion Control Plan and Storm Water Pollution Prevention Plan for this project that meets the requirements of this section.
B. The Contractor shall submit an Erosion Control Plan and a Storm Water Pollution
Prevention Plan for review and approval prior to being released to start construction activities.
1.3 EROSION AND SEDIMENT CONTROLS
The controls and measures required by the Contractor are described below.
A. Stabilization Practices The stabilization practices to be implemented shall include, but not be limited to, temporary seeding, mulching, sod stabilization, vegetative buffer strips, protection of trees, preservation of mature vegetation, silt fences, ditch checks, hay bale buffers, etc. The Contractor shall record the dates when the major grading activities occur, (e.g., clearing and grubbing, excavation, embankment, and grading); when construction activities temporarily or permanently cease on a portion of the site; and when stabilization practices are initiated.
B. Structural Practices
Structural practices shall be implemented to divert flows from exposed soils, temporarily store flows, or otherwise limit runoff and the discharge of pollutants from exposed areas of the site. Structural practices shall be implemented in a timely manner during the construction process to minimize erosion and sediment runoff. Structural practices may include some or all of the following devices:
a. Silt fences
b. Straw bales
c. Diversion dikes
d. Drainage swales
e. Check dams
f. Subsurface drains
g. Pipe Slope drains
h. Level spreaders
i. Storm drain inlet protection
j. Rock outlet protection
k. Sediment traps
l. Reinforced soil retaining systems
m. Gabions
n. Sediment basins
o. Other devices are the jobsite requires
C. The permanent stabilization practices which are to be installed under the contract may be specified in other section of the specifications. These are measures that shall be installed during the construction process to control pollutants in storm water discharges that will occur after construction operations have been completed. Structural measures should be placed on upland soils to the degree attainable. The installation of these devices may be subject to Section 404 of the Clean Water Act.
D. A goal of 80 percent removal of total suspended solids from these flows which exceed predevelopment levels should be used in designing and installing storm water management controls (where practicable). Where this goal is not met, the Contractor shall provide justification for rejecting each practice listed above based on site conditions.
E. Velocity dissipation devices shall be placed at discharge locations and along the length of any outfall channel as necessary to provide a non-erosive velocity flow from the structure to a water course so that the natural physical and biological characteristics and functions are…
This is the start of the file's text. The full file is on GovTribe.