The file's text, extracted by GovTribe without its formatting.
SUMMARY
CONTRACT SUMMARY
| BASE YEAR |
| OPTION 1 |
| OPTION 2 |
| OPTION 3 |
| OPTION 4 |
TOTAL CONTRACT
Base Year
| Solicitation No. TBD |
| INDEFINITE QUANTITY CONSTRUCTION CONTRACT FOR: |
| CONSTRUCTION MAINTENANCE AND REPAIR OF UTILITY DISTRIBUTION SYSTEMS |
| (Repair and Replacement of Steam Distribution, Sewer, Storm Drain, Oily Water Waste Oil (OWWO), |
| Rehabilitation of Lines, Fresh Water, Salt Water, Compressed Air, Natural Gas, and LPG (Propane) Distribution Systems) |
Work shall include sustainability efforts to minimize environmental impacts. The Contractor shall provide all labor, materials, equipment, tools, facilities, transportation, incidental engineering, supervision, safety, safety measures including gas free certification for all confined spaces, surveys, scoping, layout work, testing, and management necessary to fulfill the requirements of this contract and each task order issued by the Contracting Officer in a timely manner with safety as a high priority and quality work as a final product to provide the services outlined below and described in this Performance Work Statement (PWS).
This is an Indefinite Quantity contract to provide maintenance, inspection, cleaning, painting, repair, testing, and replacement of various utility systems located outside of facilities and buildings, inside of facilities and buildings where connected to the building systems, under facilities and buildings, underground, above ground, above piers, on piers, under piers, inside double deck piers, in trenches, in manholes and pits, in valve pits, in wet wells, and in pump station facilities and in accordance with the bid schedule or as negotiated non-prepriced work, and including but not limited to: steam and condensate distribution including pre-engineered, pre-manufactured and pre-insulated conduit systems and pre-insulated conduit systems, sanitary sewage collection systems, sanitary sewage distribution systems, storm water drainage systems, rehabilitation of lines, water tanks, fire protection water systems, hydrants, water distribution systems, oily water - waste oil (OWWO) collection and distribution systems, compressed air distribution systems, natural gas distribution systems, and propane distribution systems, road and sidewalk repairs, valves, control valves, relief valves, strainers, piping accessories, pumps, pump stations, motors, manholes, wet wells, controls, and structural and pipe supports, including all related appurtenances and incidental work. Work shall include all necessary permits. Electrical specifications also apply to all Electrical work performed.
| REFER TO THE LINE ITEM DESCRIPTION TAB FOR ADDITIONAL DESCRIPTIVE |
| INFORMATION ABOUT THE ELINS BELOW |
| EXHIBIT A, EXHIBIT LINE ITEMS | | | | |
| SCHEDULE OF PRICES FOR SUPPLIES/SERVICES | | | | |
| ELIN | Description | Est. Qty | Unit | Unit Price | Total Price |
INDEFINITE QUANTITY (IQ) WORK ITEMS - BASE YEAR - CLIN 0001
| A01 | ABOVE GROUND STEAM DISTRIBUTION |
| Work includes utility tunnels, manholes, on piers, below piers, in double decker piers. Confine space inspection includes gas free, time limits in confined space, confined space procedures, cool air, protective suits respirators, work shields, safety procedures , proper hydration, etc. |
| A01.01 | EXPANSION JOINTS (For above ground steam and Condensate lines) | | | | |
| Gun Pak type expansion joints are externally pressurized stainless steel bellows type, ASME Code stamped -Exterior Aboveground Steam Distribution. Work includes inspection and replacement. | | | | |
| A01.01.01 | Replace 2” single bellows expansion joint with welded ends and anchor base. | 6 | EA | $ - 0 | $ - 0 |
| A01.01.02 | Replace 2” double bellows expansion joint with welded ends and anchor base. | 6 | EA | $ - 0 | $ - 0 |
| A01.01.03 | Replace 3” single bellows expansion joint with welded ends and anchor base. | 5 | EA | $ - 0 | $ - 0 |
| A01.01.04 | Replace 3” double bellows expansion joint with welded ends and anchor base. | 5 | EA | $ - 0 | $ - 0 |
| A01.01.05 | Replace 4” single bellows expansion joint with welded ends and anchor base. | 8 | EA | $ - 0 | $ - 0 |
| A01.01.06 | Replace 4” double bellows expansion joint with welded ends and anchor base. | 9 | EA | $ - 0 | $ - 0 |
| A01.01.07 | Replace 5” or 6” single bellows expansion joint with welded ends and anchor base. | 9 | EA | $ - 0 | $ - 0 |
| A01.01.08 | Replace 5” or 6” double bellows expansion joint with welded ends and anchor base. | 9 | EA | $ - 0 | $ - 0 |
| A01.01.09 | Replace 8” single bellows expansion joint with welded ends and anchor base. | 5 | EA | $ - 0 | $ - 0 |
| A01.01.10 | Replace 8” double bellows expansion joint with welded ends and anchor base. | 7 | EA | $ - 0 | $ - 0 |
| A01.01.11 | Replace 10” single bellows expansion joint with welded ends and anchor base. | 6 | EA | $ - 0 | $ - 0 |
| A01.01.12 | Replace 10” double bellows expansion joint with welded ends and anchor base. | 6 | EA | $ - 0 | $ - 0 |
| A01.01.13 | Replace 12" single bellows expansion joint with welded ends and anchor base | 6 | EA | $ - 0 | $ - 0 |
| A01.01.14 | Replace 14" single bellows expansion joint with welded ends and anchor base | 6 | EA | $ - 0 | $ - 0 |
| A01.02 | VALVES (For Steam and Condensate Service) | | | | |
| Work includes inspection, replacement, and adjustment. | | | | |
| A01.02.01 | Replace 2” thru 3” 150# flanged or welded steel gate, globe or check valves. | 70 | EA | $ - 0 | $ - 0 |
| A01.02.02 | Replace 4” 150# steel flanged gate, check, or globe valves. | 35 | EA | $ - 0 | $ - 0 |
| A01.02.03 | Replace 5” thru 6” 150# flanged steel gate, globe or check valves. | 30 | EA | $ - 0 | $ - 0 |
| A01.02.04 | Replace 8” 150# flanged steel gate, check, or globe valves. | 13 | EA | $ - 0 | $ - 0 |
| A01.02.05 | Replace 10” thru 12” 150# flanged steel gate, globe or check valves. | 11 | EA | $ - 0 | $ - 0 |
| A01.02.06 | Replace 14” 150# flanged gate, globe or check valves. | 2 | EA | $ - 0 | $ - 0 |
| A01.02.07 | Replace 16” 150# flanged steel gate, globe or check valves | 2 | EA | $ - 0 | $ - 0 |
| A01.02.08 | Replace steam pressure regulating valve, 2” - 4” 150# or 300# class, 150# to 15#. | 8 | EA | $ - 0 | $ - 0 |
| A01.02.09 | Replace steel safety relief valve, Type III, Class 10, Style D or E with 150# class flanges flanged end connections 4” x 6” - Orifice size 6.379 sq. in | 2 | EA | $ - 0 | $ - 0 |
| A01.02.10 | Replace steel safety relief valve, Type III, Class 10, Style D or E with 150# class flanges flanged end connections 6” x 8” - Orifice size 11.05 sq. in | 2 | EA | $ - 0 | $ - 0 |
| A01.02.11 | Replace 1/4 thru 3/4” 125# or 200# bronze/steel threaded gate, check, globe valves | 40 | EA | $ - 0 | $ - 0 |
| A01.02.12 | Replace 1” thru 1 -1/2” 125# or 200# bronze/steel threaded gate, check, globe valves | 52 | EA | $ - 0 | $ - 0 |
| A01.02.13 | Replace 2” thru 3” 200# bronze threaded gate, check or globe valves | 8 | EA | $ - 0 | $ - 0 |
| A01.03 | FLANGES | | | | |
| These are flat face flanges for steam and condensate service. | | | | |
| A01.03.01 | Replace 1-13/4” 150# screwed or slip on flange with 1’ of pipe | 36 | EA | $ - 0 | $ - 0 |
| A01.03.02 | Replace 2” thru 3” 150# screwed or slip on flange with 1’ of pipe | 28 | EA | $ - 0 | $ - 0 |
| A01.03.03 | Replace 2” thru 3” 300# slip on flange with 1’ of pipe | 4 | EA | $ - 0 | $ - 0 |
| A01.03.04 | Replace 4” thru 6” 150# screwed or weld or slip on flange with 1’ of pipe | 39 | EA | $ - 0 | $ - 0 |
| A01.03.05 | Replace 4” thru 6” 300# screwed or weld flange with 1’ of pipe | 18 | EA | $ - 0 | $ - 0 |
| A01.03.06 | Replace 8” 150# screwed or weld flange with 1’ of pipe | 12 | EA | $ - 0 | $ - 0 |
| A01.03.07 | Replace 8” 300# screwed or weld flange with 1’ of pipe | 4 | EA | $ - 0 | $ - 0 |
| A01.03.08 | Replace 10” 150# weld flange with 1’ of pipe | 6 | EA | $ - 0 | $ - 0 |
| A01.03.09 | Replace 10” 300# weld flange with 1’ of pipe | 4 | EA | $ - 0 | $ - 0 |
| A01.03.10 | Replace 12” 150-300# weld flange with 1’ of pipe | 4 | EA | $ - 0 | $ - 0 |
| A01.04 | GASKETS | | | | |
| Flat face gaskets for steam and condensate service. | | | | |
| A01.04.01 | Replace 2” thru 3” flange, flexitallic or bonnet gaskets | 55 | EA | $ - 0 | $ - 0 |
| A01.04.02 | Replace 4” thru 8” flange, flexitallic or bonnet gaskets | 43 | EA | $ - 0 | $ - 0 |
| A01.04.03 | Replace 10” thru 12” flange, flexitallic or bonnet gaskets | 20 | EA | $ - 0 | $ - 0 |
| A01.04.04 | Replace 14” thru 16” flange, flexitallic or bonnet gaskets | 12 | EA | $ - 0 | $ - 0 |
| A01.05 | WELDS | | | | |
| Welding Pressure Piping, Certified ASME welder, Cost includes shutting down steam system, preparation, preparing pipe, inspection, set up, certified procedure, remove defect, welding, inspect, inspect weld by certified inspector - certified inspection procedure (ultrasonic method), pass or fail - if failed do over - put stamp on weld, test system, start-up, and clean-up. | | | | |
| A01.05.01 | Repair welds including window welds on 1-1/2” thru 6” pipe, Weld length: full pipe circumference | 40 | EA | $ - 0 | $ - 0 |
| A01.05.02 | Repair welds including window welds on 8” thru 12” pipe, Weld length: full pipe circumference | 60 | EA | $ - 0 | $ - 0 |
| A01.05.03 | Repair welds including window welds on 14” thru 16” pipe, Weld length: full pipe circumference | 3 | EA | $ - 0 | $ - 0 |
| A01.06 | STEAM & CONDENSATE PIPE, ABOVE GROUND | | | | |
| Steam and Condensate Service Piping - Work includes remove existing pipe and provide new pipe. Welded pressure pipe, welds inspected by certified inspector - ultrasonic method | | | | |
| A01.06.01 | Replace 1/4” thru 1-1/2” welded or threaded pipe | 600 | FT | $ - 0 | $ - 0 |
| A01.06.02 | Replace 2” thru 2-1/2” welded or threaded pipe | 600 | FT | $ - 0 | $ - 0 |
| A01.06.03 | Replace 3” thru 5” welded or threaded pipe | 600 | FT | $ - 0 | $ - 0 |
| A01.06.04 | Replace 6” thru 8” welded or threaded pipe | 600 | FT | $ - 0 | $ - 0 |
| A01.06.05 | Replace 10” thru 12” welded or threaded pipe | 350 | FT | $ - 0 | $ - 0 |
| A01.06.06 | Replace 14” thru 16” welded pipe | 40 | FT | $ - 0 | $ - 0 |
| A01.07 | STEAM AND CONDENSATE PIPE, ABOVE GROUND, PRE-ENGINEERED, PRE-FABRICATED, PRE-INSULATED ABOVE GROUND | | | | |
| Steam and Condensate Service Piping - Work includes remove existing pipe and provide new complete system - metal jacketed (spiral wound, lock seamed type, internal seam, and air and water tight), pre-engineered, factory fabricated, and factory pre-insulated by piping system manufacturer pipe. Welded pressure pipe, welds inspected by certified inspector - ultrasonic method | | | | |
| A01.07.01 | Replace 1/4” thru 1-1/2” welded or threaded pipe | 600 | FT | $ - 0 | $ - 0 |
| A01.07.02 | Replace 2” thru 2-1/2” welded or threaded pipe | 600 | FT | $ - 0 | $ - 0 |
| A01.07.03 | Replace 3” thru 5” welded pipe | 600 | FT | $ - 0 | $ - 0 |
| A01.07.04 | Replace 6” thru 8” welded pipe | 600 | FT | $ - 0 | $ - 0 |
| A01.07.05 | Replace 10” thru 12” welded pipe | 350 | FT | $ - 0 | $ - 0 |
| A01.07.06 | Replace 14” thru 16” welded pipe | 40 | FT | $ - 0 | $ - 0 |
| A01.08 | FITTINGS FOR STEAM AND CONDENSATE PIPE, ABOVE GROUND, PRE-FABRICATED, PRE-INSULATED | | | | |
| Fittings for Steam and Condensate Service Piping - Work includes remove existing fittings and provide new fittings on pipe. Fittings are for above ground. pre-fabricated, pre-insulated systems and for pre-fabricated, pre-insulated, and pre-engineered systems. Pipe is metal jacketed (spiral wound, lock seamed type, internal seam, and air and water tight). Welded pressure pipe, welds inspected by certified inspector - ultrasonic method For Steam and Condensate Service. | | | | |
| A01.08.01 | Replace 1/4” thru 3/4” welded fitting (tee, ell, reducer, etc.) | 30 | EA | $ - 0 | $ - 0 |
| A01.08.02 | Replace 1” thru 1-1/2” welded fitting (tee, ell, reducer, etc.) | 30 | EA | $ - 0 | $ - 0 |
| A01.08.03 | Replace 2” thru 3” welded fitting (tee, ell, reducer, etc.) | 30 | EA | $ - 0 | $ - 0 |
| A01.08.04 | Replace 4” thru 6” welded fitting (tee, ell, reducer, etc.) | 30 | EA | $ - 0 | $ - 0 |
| A01.08.05 | Replace 8” thru 10” welded fitting (tee, ell, reducer, etc.) | 20 | EA | $ - 0 | $ - 0 |
| A01.08.06 | Replace 12” welded fitting (tee, ell, reducer, etc.) | 12 | EA | $ - 0 | $ - 0 |
| A01.08.07 | Replace 14” welded fitting (tee, ell, reducer, etc.) | 8 | EA | $ - 0 | $ - 0 |
| A01.08.08 | Replace 16” welded fitting (tee, ell, reducer, etc.) | 8 | EA | $ - 0 | $ - 0 |
| A01.08.09 | Replace 1/4” thru 3/4” NPT fitting (elbow, tee, reducer, etc.) | 25 | EA | $ - 0 | $ - 0 |
| A01.08.10 | Replace 1” thru 1-1/2” NPT fitting (elbow, tee, reducer, etc.) | 25 | EA | $ - 0 | $ - 0 |
| A01.08.11 | Replace 2” thru 3” NPT fitting (elbow, tee, reducer, etc.) | 20 | EA | $ - 0 | $ - 0 |
| A01.09 | PIPE HANGERS | | | | |
| A01.09.01 | Replace 1/4” thru 4” pipe hangers on all distribution systems | 120 | EA | $ - 0 | $ - 0 |
| A01.09.02 | Replace 5” thru 12” pipe hangers on all distribution systems | 200 | EA | $ - 0 | $ - 0 |
| A01.09.03 | Replace 14” thru 16” pipe hangers on all distribution systems | 8 | EA | $ - 0 | $ - 0 |
| A01.10 | INSULATION | | | | |
| A01.10.01 | Replace insulation on 3/4” thru 4” 45 or 90 elbow, tee or flange | 130 | EA | $ - 0 | $ - 0 |
| A01.10.02 | Replace insulation on 5” thru 8” 45 or 90 elbow, tee or flange | 50 | EA | $ - 0 | $ - 0 |
| A01.10.03 | Replace insulation on 10” thru 12” 45 or 90 elbow, tee or flange | 22 | EA | $ - 0 | $ - 0 |
| A01.10.04 | Replace insulation on 14” thru 16” 45 or 90 elbow, tee or flange | 10 | EA | $ - 0 | $ - 0 |
| A01.10.05 | Replace insulation on 3/4 thru 4” valves | 50 | EA | $ - 0 | $ - 0 |
| A01.10.06 | Replace insulation on 5” thru 8” valves | 25 | EA | $ - 0 | $ - 0 |
| A01.10.07 | Replace insulation on 10” thru 12” valves | 20 | EA | $ - 0 | $ - 0 |
| A01.10.08 | Replace insulation on 14” thru 16" valves | 7 | EA | $ - 0 | $ - 0 |
| A01.10.09 | Replace insulation on 3/4” thru 3" pipe | 550 | LF | $ - 0 | $ - 0 |
| A01.10.10 | Replace insulation on 3-1/2” thru 5” pipe | 900 | LF | $ - 0 | $ - 0 |
| A01.10.11 | Replace insulation on 6” thru 8” pipe | 1,000 | LF | $ - 0 | $ - 0 |
| A01.10.12 | Replace insulation on 10” thru 12” pipe | 500 | LF | $ - 0 | $ - 0 |
| A01.10.13 | Replace insulation on 14" thru 16" pipe | 80 | LF | $ - 0 | $ - 0 |
| A01.11 | PIPE JACKET | | | | |
| For Steam and Condensate Service - Remove, and Replace existing pipe jacket with new Anodized Aluminum Jacket, color as approved by Contracting Officer | | | | |
| A01.11.01 | Replace jacket on 3/4” thru 4” 45 or 90 elbow, tee or flange | 130 | EA | $ - 0 | $ - 0 |
| A01.11.02 | Replace jacket on 5” thru 8” 45 or 90 elbow, tee or flange | 50 | EA | $ - 0 | $ - 0 |
| A01.11.03 | Replace jacket on 10” thru 12” 45 or 90 elbow, tee or flange | 22 | EA | $ - 0 | $ - 0 |
| A01.11.04 | Replace jacket on 14” thru 16” 45 or 90 elbow, tee or flange | 10 | EA | $ - 0 | $ - 0 |
| A01.11.05 | Replace jacket on 3/4 thru 4” valves | 50 | EA | $ - 0 | $ - 0 |
| A01.11.06 | Replace jacket on 5” thru 8” valves | 25 | EA | $ - 0 | $ - 0 |
| A01.11.07 | Replace jacket on 10” thru 12” valves | 20 | EA | $ - 0 | $ - 0 |
| A01.11.08 | Replace jacket on 14” thru 16" valves | 7 | EA | $ - 0 | $ - 0 |
| A01.11.09 | Replace jacket on 3/4” thru 3" pipe | 550 | LF | $ - 0 | $ - 0 |
| A01.11.10 | Replace jacket on 3-1/2” thru 5” pipe | 900 | LF | $ - 0 | $ - 0 |
| A01.11.11 | Replace jacket on 6” thru 8” pipe | 1,300 | LF | $ - 0 | $ - 0 |
| A01.11.12 | Replace jacket on 10” thru 12” pipe | 500 | LF | $ - 0 | $ - 0 |
| A01.11.13 | Replace jacket on 14" thru 16" pipe | 80 | LF | $ - 0 | $ - 0 |
| A01.12 | FITTINGS | | | | |
| For Steam and Condensate Service - Work includes remove existing fittings and provide new fittings on pipe. | | | | |
| A01.12.01 | Replace 1/4” thru 3/4” welded fitting (tee, ell, etc.) | 200 | EA | $ - 0 | $ - 0 |
| A01.12.02 | Replace 1” thru 1-1/2” welded fitting (tee, ell, etc.) | 110 | EA | $ - 0 | $ - 0 |
| A01.12.03 | Replace 2” thru 3” welded fitting (tee, ell, etc.) | 100 | EA | $ - 0 | $ - 0 |
| A01.12.04 | Replace 4” thru 6” welded fitting (tee, ell, etc.) | 80 | EA | $ - 0 | $ - 0 |
| A01.12.05 | Replace 8” thru 10” welded fitting (tee, ell, etc.) | 30 | EA | $ - 0 | $ - 0 |
| A01.12.06 | Replace 12” welded fitting (tee, ell, etc.) | 8 | EA | $ - 0 | $ - 0 |
| A01.12.07 | Replace 14” welded fitting (tee, ell, etc.) | 4 | EA | $ - 0 | $ - 0 |
| A01.12.08 | Replace 16” welded fitting (tee, ell, etc.) | 4 | EA | $ - 0 | $ - 0 |
| A01.12.09 | Replace 1/4” thru 3/4” NPT fitting | 50 | EA | $ - 0 | $ - 0 |
| A01.12.10 | Replace 1” thru 1-1/2” NPT fitting | 55 | EA | $ - 0 | $ - 0 |
| A01.12.11 | Replace 2” thru 3” NPT fitting | 20 | EA | $ - 0 | $ - 0 |
| A01.13 | UNIONS | | | | |
| For Steam and Condensate Service - Work includes removal of existing unions and provide new unions. | | | | |
| A01.13.01 | Replace 1/4" thru 3/4" NPT unions | 80 | EA | $ - 0 | $ - 0 |
| A01.13.02 | Replace 1" thru 1-1/2" NPT unions | 55 | EA | $ - 0 | $ - 0 |
| A01.13.03 | Replace 2" thru 3" NPT unions | 20 | EA | $ - 0 | $ - 0 |
| A01.14 | STEAM TRAPS | | | | |
| For Steam and Condensate Service - work for replacement includes removal of existing trap and provide new steam traps. | | | | |
| A01.14.01 | Repair of 1/2" thru 1” steam trap assembly (threaded) | 100 | EA | $ - 0 | $ - 0 |
| A01.14.02 | Replace 1/2" thru 1" steam trap assembly (threaded) to include isolation valve, strainer, blowdown valve off of the strainer, trap, 20 feet of piping, and up to 3 fittings | 150 | EA | $ - 0 | $ - 0 |
| A01.14.03 | Repair of 1/2" thru 1” steam trap assembly (socket weld connections) | 100 | EA | $ - 0 | $ - 0 |
| A01.14.04 | Replace 1/2" thru 1" steam trap assembly (socket weld connections) to include isolation valve, strainer, blowdown valve off of the strainer, trap, 20 feet of piping, and up to 3 fittings | 150 | EA | $ - 0 | $ - 0 |
| A01.14.05 | Provide new 4' DIAM x 8' DEEP Drywell for steam traps | 25 | EA | $ - 0 | $ - 0 |
| A01.15 | STRAINERS | | | | |
| For Steam and Condensate Service - Work includes removal of existing steam strainer and provide new steam strainer | | | | |
| A01.15.01 | Replace NPT steam Strainer 1/2” thru 1” | 45 | EA | $ - 0 | $ - 0 |
| A01.15.02 | Replace NPT steam Strainer 1-1/4” thru 1-1/2 | 16 | EA | $ - 0 | $ - 0 |
| A01.15.03 | Replace NPT steam Strainer 2” thru 3” | 12 | EA | $ - 0 | $ - 0 |
| A01.15.04 | Replace NPT steam Strainer 1/2” thru 1”, class 150# or 300# | 45 | EA | $ - 0 | $ - 0 |
| A01.15.05 | Replace NPT steam Strainer 1-1/4” thru 1-1/2, class 150# or 300# | 16 | EA | $ - 0 | $ - 0 |
| A01.15.06 | Replace NPT steam Strainer class 150# or 300# Size 2” | 6 | EA | $ - 0 | $ - 0 |
| A01.15.07 | Replace NPT steam Strainer class 150# or 300# Size 2-1/2” thru 3” | 4 | EA | $ - 0 | $ - 0 |
| A01.15.08 | Replace NPT steam Strainer class 150# or 300# Size 4” | 4 | EA | $ - 0 | $ - 0 |
| A01.15.09 | Replace NPT steam Strainer class 150# or 300# Size 5” thru 6” | 4 | EA | $ - 0 | $ - 0 |
| A01.15.10 | Replace NPT steam Strainer class 150# or 300# Size 8” | 2 | EA | $ - 0 | $ - 0 |
| A01.15.11 | Replace NPT steam Strainer class 150# or 300# Size 10” | 2 | EA | $ - 0 | $ - 0 |
| A01.16 | SUMP PUMPS | | | | |
| For Steam and Condensate Service - Replacement work includes removal of existing steam operated sump pump and provide new steam operated sump pump. | | | | |
| A01.16.01 | Repair of steam operated sump pump assembly and clean-out pit. | 30 | EA | $ - 0 | $ - 0 |
| A01.16.02 | Replace steam sump pump | 22 | EA | $ - 0 | $ - 0 |
| A01.17 | GAGES | | | | |
| For Steam and Condensate Service -Work includes removal of existing and provide new. Factory Calibrated | | | | |
| A01.17.01 | Replace gages, includes replacing valves, fittings and nipples | 40 | EA | $ - 0 | $ - 0 |
| A01.17.02 | Replace gages only | 25 | EA | $ - 0 | $ - 0 |
| A01.18 | SUPPORTS | | | | |
| For Steam and Condensate Service - Work includes removal of existing and provide new | | | | |
| A01.18.01 | Replace 2" thru 4" pipe alignment guide supports | 100 | EA | $ - 0 | $ - 0 |
| A01.18.02 | Replace 5" thru 12" pipe alignment guide supports | 100 | EA | $ - 0 | $ - 0 |
| A01.18.03 | Replace 2" thru 4" pipe stanchion saddle supports | 23 | EA | $ - 0 | $ - 0 |
| A01.18.04 | Replace 5" thru 8" pipe stanchion saddle supports | 23 | EA | $ - 0 | $ - 0 |
| A01.18.05 | Replace 10" thru 12" pipe stanchion saddle supports | 28 | EA | $ - 0 | $ - 0 |
| A01.18.06 | Replace angle iron used in construction of pipe supports, up thru 4” x 4” x 1/2” | 500 | LF | $ - 0 | $ - 0 |
| A01.18.07 | Replace channel iron used in construction of pipe supports Up thru 4” | 250 | LF | $ - 0 | $ - 0 |
| A01.18.08 | Replace channel iron used in construction of pipe supports 5” thru 8” | 300 | LF | $ - 0 | $ - 0 |
| A01.18.09 | Replace channel iron used in construction of pipe supports 10”thru 12” | 135 | LF | $ - 0 | $ - 0 |
| A01.18.10 | Replace channel iron used in construction of pipe supports up to 15" | 20 | EA | $ - 0 | $ - 0 |
| A01.18.11 | Replace base plates used in construction of pipe supports over 12” x 12” x 1/2” thick up through 12” x 12” 1” thick | 175 | EA | $ - 0 | $ - 0 |
| A01.18.12 | Replace expansion shields or drop-in type anchor bolts Up thru 5/8” diameter | 2,200 | EA | $ - 0 | $ - 0 |
| A01.18.13 | Replace expansion shields or drop-in type anchor bolts 3/4” thru 1” diameter | 1,160 | EA | $ - 0 | $ - 0 |
| A01.18.14 | Replace missing hanger bolts | 105 | EA | $ - 0 | $ - 0 |
| A01.19 | RIGGING | | | | |
| A01.19.01 | Rigging/jacking 2-1/2" thru 6" steam mains back into place each 10’ length | 1,032 | EA | $ - 0 | $ - 0 |
| A01.19.02 | Rigging/jacking 8" thru 12" steam mains back into place each 10’ length | 1,032 | EA | $ - 0 | $ - 0 |
| A01.19.03 | Rigging/jacking 14" thru 16" steam mains back into place each 10’ length | 10 | EA | $ - 0 | $ - 0 |
| A01.20 | ANCHORS (Replacement of capsule type ANCHORS on all utility distribution systems) | | | | |
| Capsule type anchoring system is a heavy duty anchoring system that uses a high strength 2-part epoxy adhesive to retain a threaded rod and other materials in concrete or other masonry material. The system consists of a glass capsule containing the proper amount of resin, hardener and aggregate for the anchor, a stud rod with washer, nut, and drive unit to allow the stud to be inserted into a standard hammer drill. | | | | |
| A01.20.01 | 5/8" diameter | 160 | EA | $ - 0 | $ - 0 |
| A01.20.02 | 3/4" diameter | 500 | EA | $ - 0 | $ - 0 |
| A01.21 | SAFETY RELIEF VALVES | | | | |
| For Steam and Condensate Service - Work includes inspection, removal, and replacement of Safety Relief Valves. ASME code stamped. | | | | |
| A01.21.01 | Replacement of Safety Relief Valves 1/2” thru 1” | 20 | EA | $ - 0 | $ - 0 |
| A01.21.02 | Replacement of Safety Relief 1-1/4” thru 1-1/2” | 10 | EA | $ - 0 | $ - 0 |
| A01.21.03 | Replacement of Safety Relief Valves 2” thru 2-1/2” | 7 | EA | $ - 0 | $ - 0 |
| A01.21.04 | Replacement of Safety Relief Valves 3” | 5 | EA | $ - 0 | $ - 0 |
| A01.22 | STEAM PRESSURE REGULATING VALVES | | | | |
| For Steam and Condensate Service - Work includes inspection, removal, and provide new pressure reducing valves. | | | | |
| A01.22.01 | Replacement of threaded steam pressure regulators 1/2” thru 1” | 20 | EA | $ - 0 | $ - 0 |
| A01.22.02 | Replacement of threaded steam pressure regulators 1-1/4” thru 1-1/2” | 10 | EA | $ - 0 | $ - 0 |
| A01.22.03 | Replacement of threaded steam pressure regulators 2” thru 2-1/2” | 7 | EA | $ - 0 | $ - 0 |
| A01.22.04 | In-Service testing of Pressure Reducing Valves for proper operation | 16 | EA | $ - 0 | $ - 0 |
| A01.22.05 | Replacement of threaded steam pilot valves on main pressure regulators 1/4” thru 1/2” (3-150 psig) | 12 | EA | $ - 0 | $ - 0 |
| A01.22.06 | Replacement of threaded steam pilot valves on main pressure regulators 1/4” thru 1/2” (1-25 psig) | 9 | EA | $ - 0 | $ - 0 |
| A01.22.07 | Repair steam pressure regulators threaded or flange 1/2” thru 1-1/2” | 10 | EA | $ - 0 | $ - 0 |
| A01.22.08 | Repair steam pressure regulators threaded or flange 2” thru 2-1/2"” | 13 | EA | $ - 0 | $ - 0 |
| A01.22.09 | Repair 3" steam pressure regulator flanged class 150# to 300# | 5 | EA | $ - 0 | $ - 0 |
| A01.22.10 | Repair 4" steam pressure regulator flanged class 150# to 300# | 5 | EA | $ - 0 | $ - 0 |
| A01.22.11 | Adjust steam pressure regulator / pilot valve | 32 | EA | $ - 0 | $ - 0 |
| A01.23 | STEAM FLOW METERS | | | | |
| For Steam and Condensate Service - Exterior Aboveground Steam Distribution. Provide certificated calibration from a NIST certified calibration facility. Provide a temporary flanged pipe spool piece with insulation in place of meter to allow continuation of steam flow. Remove & Re-install meter. Replace meter when non functioning. | | | | |
| A01.23.01 | Calibrate and certify the calibration of a steam flow meter. | 1 | EA | $ - 0 | $ - 0 |
| A01.23.02 | Replacement of steam flow meter | 1 | EA | $ - 0 | $ - 0 |
| A02 | UNDERGROUND STEAM DISTRIBUTION |
| Underground steam distribution is for pre-engineered, factory manufactured, pre-insulated, drainable, dryable, and testable steam pipe and conduit systems. Work includes utility tunnels, manholes, and vaults. Confine space inspection includes gas free, time limits in confine space, confined space procedures, cool air, protective suits respirators, work shields, safety procedures , proper hydration, etc. Underground line is steam pipe with steel conduit and HDPE jacket. Condensate is not returned in same conduit. On some locations condensate is returned by separate conduit system. |
| A02.01 | UTILITY SYSTEMS SURVEY AND ASSESSMENT | | | | |
| A02.01.01 | Underground survey for individual systems, 500 feet each | 10 | EA | $ - 0 | $ - 0 |
| A02.01.02 | Compressed air test conduit systems for leakage, 500 feet each | 10 | EA | $ - 0 | $ - 0 |
| A02.02 | CONDUIT/PIPE REMOVAL OF EXISTING UNDERGROUND STEAM DISTRIBUTION | | | | |
| Composite Rate for various sizes. This ELIN covers pipe removal and pipe disposal. (extra fill may be ordered on other line items if needed). Underground line is steam pipe with steel conduit and HDPE jacket. Condensate is not returned. Prices do not include shoring, dewatering, excavation to the bottom of each pipe (steam conduit and insulation), backfill with excavated materials, grade, seeding, and cleanup - these items are covered by separate ELIN. | | | | |
| A02.02.01 | 1-1/2" Steam in 8-5/8" conduit | 250 | LF | $ - 0 | $ - 0 |
| A02.02.02 | 2" Steam in 8-5/8" conduit | 250 | LF | $ - 0 | $ - 0 |
| A02.02.03 | 3" Steam in 10-3/4"" conduit | 250 | LF | $ - 0 | $ - 0 |
| A02.02.04 | 4" Steam in 12-3/4" conduit | 250 | LF | $ - 0 | $ - 0 |
| A02.02.05 | 6" Steam in 14" conduit | 250 | LF | $ - 0 | $ - 0 |
| A02.02.06 | 8" Steam 18" conduit | 250 | LF | $ - 0 | $ - 0 |
| A02.02.07 | 10" Steam in 20" conduit | 250 | LF | $ - 0 | $ - 0 |
| A02.02.08 | 12" Steam in 22" conduit | 250 | LF | $ - 0 | $ - 0 |
| A02.02.09 | 14" Steam in 24" conduit | 250 | LF | $ - 0 | $ - 0 |
| A02.02.10 | 16" Steam 26" conduit | 250 | LF | $ - 0 | $ - 0 |
| A02.02.11 | Cap existing pipe and Conduit, where steam line is removed and not replaced. 1-1/2" to 3" steam pipe | 25 | EA | $ - 0 | $ - 0 |
| A02.02.12 | Cap existing pipe and Conduit, where steam line is removed and not replaced. 4" to 10" steam pipe | 10 | EA | $ - 0 | $ - 0 |
| A02.02.13 | Cap existing pipe and Conduit, where steam line is removed and not replaced. 12" to 16" steam pipe | 5 | EA | $ - 0 | $ - 0 |
| A02.03 | NEW CONDUIT / PIPE REPLACEMENT FOR REPAIR OF UNDERGROUND STEAM DISTRIBUTION | | | | |
| Composite Rate for various sizes. Old already removed, trench is open, ready for repair of existing system. Prices include new bedding, connection to existing system, repair distribution system, Replace old with new pre-engineered factory manufactured system, drainable dryable, testable steam and conduit system. Costs includes connection to manhole and existing piping. Work includes inspection and testing of piping and conduit system. Work includes start-up of existing & new system. Underground line is steam pipe with steel conduit and HDPE jacket. Condensate is not returned in same conduit. Welded pressure pipe system. On some locations condensate is returned in separate conduit system. Excavation already performed. Costs for excavation, backfill, dewatering, shoring, sheeting, fill, grad, and seed is covered by separate ELIN item. | | | | |
| A02.03.01 | 1-1/2" Steam in 8-5/8" conduit | 250 | LF | $ - 0 | $ - 0 |
| A02.03.02 | 2" Steam in 8-5/8" conduit | 250 | LF | $ - 0 | $ - 0 |
| A02.03.03 | 3" Steam in 10-3/4"" conduit | 250 | LF | $ - 0 | $ - 0 |
| A02.03.04 | 4" Steam in 12-3/4" conduit | 250 | LF | $ - 0 | $ - 0 |
| A02.03.05 | 6" Steam in 14" conduit | 250 | LF | $ - 0 | $ - 0 |
| A02.03.06 | 8" Steam 18" conduit | 250 | LF | $ - 0 | $ - 0 |
| A02.03.07 | 10" Steam in 20" conduit | 250 | LF | $ - 0 | $ - 0 |
| A02.03.08 | 12" Steam in 22" conduit | 250 | LF | $ - 0 | $ - 0 |
| A02.03.09 | 14" Steam in 24" conduit | 100 | LF | $ - 0 | $ - 0 |
| A02.03.10 | 16" Steam 26" conduit | 100 | LF | $ - 0 | $ - 0 |
| A02.04 | FITTINGS FOR NEW CONDUIT/PIPE REPLACEMENT FOR REPAIR OF UNDERGROUND STEAM DISTRIBUTION | | | | |
| New fittings for underground pre-engineered factory manufactured system, drainable dryable, testable steam and conduit system. Composite Rate for various sizes. Old already removed, trench is open, ready for repair of existing system, excavation already performed under another ELIN . Prices include new bedding, connection to existing system, repair distribution system, Replace old with new pre-engineered factory manufactured system, drainable dryable, testable steam and conduit system. Costs includes connection to manhole and existing piping. Work includes inspection and testing of piping and conduit system. Work includes start-up of existing & new system. Costs for backfill, dewatering, shoring, excavation, fill, grad, and seed is covered by separate ELIN. Underground line is steam pipe with steel conduit and HDPE jacket. Condensate is not returned in same conduit. On some locations condensate is returned in separate conduit system. | | | | |
| A02.04.01 | Replace 4” welded fitting (tee, ell, reducer, etc.) in 12-5/8" conduit | 10 | EA | $ - 0 | $ - 0 |
| A02.04.02 | Replace 6” welded fitting (tee, ell, reducer, etc.) in 14" conduit | 10 | EA | $ - 0 | $ - 0 |
| A02.04.03 | Replace 8” welded fitting (tee, ell, reducer, etc.) in 18" conduit | 10 | EA | $ - 0 | $ - 0 |
| A02.04.04 | Replace 10” welded fitting (tee, ell, reducer, etc.) in 20" conduit | 8 | EA | $ - 0 | $ - 0 |
| A02.04.05 | Replace 12" welded fitting (elbow, tee, reducer, etc.) in 22" conduit | 8 | EA | $ - 0 | $ - 0 |
| A02.04.06 | Replace 14” welded fitting (elbow, tee, reducer, etc.) in 24 " conduit | 8 | EA | $ - 0 | $ - 0 |
| A02.04.07 | Replace 16" welded fitting (elbow, tee, reducer, etc.) in 26" conduit | 8 | EA | $ - 0 | $ - 0 |
| A02.05 | EXPANSION ELBOW FOR NEW CONDUIT/PIPE REPLACEMENT FOR REPAIR OF UNDERGROUND STEAM DISTRIBUTION | | | | |
| New Pressure balanced Expansion Elbow Joint (PBEEJ) for underground pre-engineered factory manufactured system, drainable dryable, testable steam and conduit system. Composite Rate for various sizes. Old already removed, trench is open, ready for repair of existing system, excavation already performed under another ELIN . Prices include new bedding, connection to existing system, repair distribution system, Replace old with new pre-engineered factory manufactured system, drainable dryable, testable steam and conduit system. Costs includes connection to manhole and existing piping. Work includes inspection and testing of piping and conduit system. Work includes start-up of existing & new system. Underground line is steam pipe with steel conduit and HDPE jacket. Condensate is not returned in same conduit. On some locations condensate is returned in separate conduit system. | | | | |
| A02.05.01 | Replace 4” welded fitting PBEEJ in 12-5/8" conduit | 4 | EA | $ - 0 | $ - 0 |
| A02.05.02 | Replace 6” welded fitting PBEEJ in 14" conduit | 4 | EA | $ - 0 | $ - 0 |
| A02.05.03 | Replace 8” welded fitting PBEEJ in 18" conduit | 4 | EA | $ - 0 | $ - 0 |
| A02.05.04 | Replace 10” welded fitting PBEEJ in a 20" conduit | 4 | EA | $ - 0 | $ - 0 |
| A02.05.05 | Replace 12" welded fitting PBEEJ in 22" conduit | 4 | EA | $ - 0 | $ - 0 |
| A02.05.06 | Replace 14” welded fitting PBEEJ in 24 " conduit | 4 | EA | $ - 0 | $ - 0 |
| A02.05.07 | Replace 16" welded fitting PBEEJ in 26" conduit | 4 | EA | $ - 0 | $ - 0 |
| A02.06 | DRIP TEE, MODIFIED DRIP TEE, & RISER FOR NEW CONDUIT/PIPE REPLACEMENT FOR REPAIR OF UNDERGROUND STEAM DISTRIBUTION | | | | |
| New Drip Tee, Modified Drip Tee, and Riser for underground pre-engineered factory manufactured system, drainable dryable, testable steam and conduit system. Composite Rate for various sizes. Old already removed, trench is open, ready for repair of existing system, excavation already performed under another ELIN. Prices include new bedding, connection to existing system, repair distribution system, Replace old with new pre-engineered factory manufactured system, drainable dryable, testable steam and conduit system. Costs includes connection to manhole and existing piping. Work includes inspection and testing of piping and conduit system. Work includes start-up of existing & new system. Underground line is steam pipe with steel conduit and HDPE jacket. Condensate is not returned in same conduit. On some locations condensate is returned in separate conduit system. | | | | |
| A02.06.01 | 1-1/2” welded fitting Drip Tee, Modified Drip Tee in 8-5/8" conduit with 3/4" riser | 30 | EA | $ - 0 | $ - 0 |
| A02.06.02 | 2” welded fitting Drip Tee, Modified Drip Tee in 8-5/8" conduit with 3/4" riser | 30 | EA | $ - 0 | $ - 0 |
| A02.06.03 | 3” welded fitting Drip Tee, Modified Drip Tee in 10-5/8" conduit with 3/4" riser | 30 | EA | $ - 0 | $ - 0 |
| A02.06.04 | 4” welded fitting Drip Tee, Modified Drip Tee in 12-5/8" conduit with 3/4" riser | 30 | EA | $ - 0 | $ - 0 |
| A02.06.05 | 6” welded fitting Drip Tee, Modified Drip Tee in 14" conduit with 3/4" riser | 30 | EA | $ - 0 | $ - 0 |
| A02.06.06 | Replace 8” welded fitting Drip Tee, Modified Drip Tee in 18" conduit with 1" riser | 30 | EA | $ - 0 | $ - 0 |
| A02.06.07 | Replace 10” welded fitting Drip Tee, Modified Drip Tee in a 20" conduit with 1" riser | 30 | EA | $ - 0 | $ - 0 |
| A02.06.08 | 12" welded fitting Drip Tee, Modified Drip Tee in 22" conduit with 1" riser | 30 | EA | $ - 0 | $ - 0 |
| A02.06.09 | 14” welded fitting Drip Tee, Modified Drip Tee in 24 " conduit with 1" riser | 30 | EA | $ - 0 | $ - 0 |
| A02.06.10 | 16" welded fitting Drip Tee, Modified Drip Tee in 26" conduit with 1" riser | 30 | EA | $ - 0 | $ - 0 |
| A02.07 | UNDERGROUND PIPE ANCHOR FOR NEW CONDUIT/PIPE REPLACEMENT FOR REPAIR OF UNDERGROUND STEAM DISTRIBUTION | | | | |
| New Underground Pipe Anchor for underground pre-engineered factory manufactured system, drainable dryable, testable steam and conduit system. Composite Rate for various sizes. Old already removed, trench is open, ready for repair of existing system, excavation already performed under another ELIN. Prices include new bedding, connection to existing system, repair distribution system, Replace old with new pre-engineered factory manufactured system, drainable dryable, testable steam and conduit system. Costs includes connection to manhole and existing piping. Work includes inspection and testing of piping and conduit system. Work includes start-up of existing & new system. Underground line is steam pipe with steel conduit and HDPE jacket. Condensate is not returned in same conduit. On some locations condensate is returned in separate conduit system. | | | | |
| A02.07.01 | Pipe Anchor for 4” Pipe in 12-5/8" conduit | 4 | EA | $ - 0 | $ - 0 |
| New Underground Pipe Anchor for underground pre-engineered factory manufactured system, drainable dryable, testable steam and conduit system. Composite Rate for various sizes. Old already removed, trench is open, ready for repair of existing system, excavation already performed under another ELIN. Shoring, backfill and dewatering being performed by separate ELIN item, see A06. Prices include new bedding, connection to existing system, repair distribution system, Replace old with new pre-engineered factory manufactured system, drainable dryable, testable steam and conduit system. Costs includes connection to manhole and existing piping. Work includes inspection and testing of piping and conduit system. Work includes start-up of existing & new system. Costs for backfill, dewatering, shoring, excavation, fill, grad, and seed is covered by separate ELIN item. Underground line is steam pipe with steel conduit and HDPE jacket. Condensate is not returned in same conduit. Welded pressure pipe system, Spec 33 63 13 and 40 17 26.00 20. On some locations condensate is returned in separate conduit system. | | | | |
| A02.08.02 | Pipe Anchor for 6” Pipe in 14" conduit | 4 | EA | $ - 0 | $ - 0 |
| A02.08.03 | Pipe Anchor for 8” Pipe in 18" conduit | 4 | EA | $ - 0 | $ - 0 |
| A02.08.04 | Pipe Anchor for 10” Pipe in a 20" conduit | 4 | EA | $ - 0 | $ - 0 |
| A02.08.05 | Pipe Anchor for 12" Pipe in 22" conduit | 3 | EA | $ - 0 | $ - 0 |
| A02.08.06 | Pipe Anchor for 14” Pipe in 24 " conduit | 3 | EA | $ - 0 | $ - 0 |
| A02.08.07 | Pipe Anchor for 16" pipe in 26" conduit | 3 | EA | $ - 0 | $ - 0 |
A03 SANITARY SEWER, FRESH WATER, SALT WATER, AND STORM DRAIN DISTRIBUTION
| A03.01 | PROVIDE FLOWABLE FILL FOR PIPES TO BE ABANDONED IN PLACE | | | | |
| A03.01.01 | Install flowable fill in Utility pipes to be abandoned in place | 100 | CY | $ - 0 | $ - 0 |
| A03.02 | PIPE REMOVAL FOR SEWER, WATER AND STORM DRAIN DISTRIBUTION | | | | |
| Composite Rate for various sizes and materials. Composite Prices do cover pipe removal and pipe disposal. (Extra fill may be ordered on line items excavation.) | | | | |
| A03.02.01 | Composite rate for sewer pipe removal of 1/2" through 6" -IRON | 3,000 | LF | $ - 0 | $ - 0 |
| A03.02.02 | Composite rate for pipe removal of 8" through 16" -IRON | 3,000 | LF | $ - 0 | $ - 0 |
| A03.02.03 | Composite rate for pipe removal of 18" through 24" -IRON | 3,000 | LF | $ - 0 | $ - 0 |
| A03.02.04 | Composite rate for pipe removal of 12" through 16" -REINFORCED CONCRETE | 1,000 | LF | $ - 0 | $ - 0 |
| A03.02.05 | Composite rate for pipe removal of 18" through 27" -REINFORCED CONCRETE | 1,000 | LF | $ - 0 | $ - 0 |
| A03.02.06 | Composite rate for pipe removal of 30" through 36" - REINFORCED CONCRETE | 1,000 | LF | $ - 0 | $ - 0 |
| A03.02.07 | Composite rate for pipe removal of 38" through 48" - REINFORCED CONCRETE | 250 | LF | $ - 0 | $ - 0 |
| A03.02.08 | Composite rate for pipe removal of 48" through 54" -REINFORCED CONCRETE | 250 | LF | $ - 0 | $ - 0 |
| A03.02.09 | Composite rate for pipe removal of 56" through 72" -REINFORCED CONCRETE | 250 | LF | $ - 0 | $ - 0 |
| A03.02.10 | Composite rate for pipe removal of 1" through 12" -POLYVINYL CHLORIDE (PVC) | 3,000 | LF | $ - 0 | $ - 0 |
| A03.02.11 | Composite rate for pipe removal of 14" through 16" -POLYVINYL CHLORIDE (PVC) | 1,500 | LF | $ - 0 | $ - 0 |
| A03.02.12 | Composite rate for pipe removal of 18" through 30" -POLYVINYL CHLORIDE (PVC) | 500 | LF | $ - 0 | $ - 0 |
| A03.02.13 | Composite rate for pipe removal of 12" through 16" -CORRUGATED METAL PIPE | 250 | LF | $ - 0 | $ - 0 |
| A03.02.14 | Composite rate for pipe removal of 18" through 27" -CORRUGATED METAL PIPE | 250 | LF | $ - 0 | $ - 0 |
| A03.02.15 | Composite rate for pipe removal of 30" through 36" - CORRUGATED METAL PIPE | 250 | LF | $ - 0 | $ - 0 |
| A03.02.16 | Composite rate for pipe removal of 38" through 48" - CORRUGATED METAL PIPE | 250 | LF | $ - 0 | $ - 0 |
| A03.02.17 | Composite rate for pipe removal of 48" through 54" -CORRUGATED METAL PIPE | 250 | LF | $ - 0 | $ - 0 |
| A03.02.18 | Composite rate for pipe removal of 56" through 72" -CORRUGATED METAL PIPE | 250 | LF | $ - 0 | $ - 0 |
| A03.03 | HYDRANT REMOVAL | | | | |
| Composite Rate for removal of fire hydrant from water line. Prices include service line removal including valve, pipe disposal and cleanup. (extra fill may be ordered on other line items if needed) Dispose of hydrant if not ordered to be reinstalled on other line items. | | | | |
| A03.03.01 | Fire Hydrant Removal | 30 | EA | $ - 0 | $ - 0 |
| A03.04 | WATER LINE VALVE REMOVAL | | | | |
| Composite Rate for removal of valves from water line, all valve sizes, includes valve box disposal. Dispose of if not ordered to be reinstalled on other line item. (extra fill may be ordered on other line items if needed) | | | | |
| A03.04.01 | Water Line Valve Removal | 30 | EA | $ - 0 | $ - 0 |
| A03.05 | WATER METER REMOVAL | | | | |
| Composite Rate for removal of meters from water line, all valve sizes, includes meters box disposal. Dispose of if not ordered to be reinstalled on other line items. (extra fill may be ordered on other line items if needed) | | | | |
| A03.05.01 | Water Meter Removal | 30 | EA | $ - 0 | $ - 0 |
| A03.06 | CONCRETE & PRECAST MANHOLE OR WET WELL REMOVAL | | | | |
| Composite Rate for removal of Manhole or Wet Well from water line, all Manhole or Wet Well sizes. Dispose of if not ordered to be reinstalled on other line items. (extra fill may be ordered on other line items if needed) | | | | |
| A03.06.01 | 4' Diameter or Square Manhole or Wet Well removal, Per Vertical LF | 100 | VLF | $ - 0 | $ - 0 |
| A03.06.02 | 6' Diameter or Square Manhole or Wet Well removal, Per Vertical LF | 100 | VLF | $ - 0 | $ - 0 |
| A03.06.03 | 8' Diameter or Square Manhole or Wet Well removal, Per Vertical LF | 100 | VLF | $ - 0 | $ - 0 |
| A03.06.04 | 10' Diameter or Square Manhole or Wet Well removal, Per Vertical LF | 100 | VLF | $ - 0 | $ - 0 |
| A03.07 | MASONRY MANHOLE OR WET WELL REMOVAL | | | | |
| Composite Rate for removal of Manhole or Wet Well from water line, all Manhole or Wet Well sizes. Dispose of if not ordered to be reinstalled on other line items. (extra fill may be ordered on other line items if needed) | | | | |
| A03.07.01 | 4' Diameter or Square Manhole or Wet Well removal, Per Vertical LF | 100 | VLF | $ - 0 | $ - 0 |
| A03.07.02 | 6' Diameter or Square Manhole or Wet Well removal, Per Vertical LF | 5 | VLF | $ - 0 | $ - 0 |
| A03.07.03 | 8' Diameter or Square Manhole or Wet Well removal, Per Vertical LF | 5 | VLF | $ - 0 | $ - 0 |
| A03.07.04 | 10' Diameter or Square Manhole or Wet Well removal, Per Vertical LF | 5 | VLF | $ - 0 | $ - 0 |
| A03.08 | FLOW BYPASSING OF MANHOLES | | | | |
| Composite Rate for bypassing sewer flow around manhole - diameter or square. Bypassing flow occurs during sewer cleaning, manhole cleaning, manhole rehabilitation, sewer lift station work, sewer line rehabilitation, sewer inspection, manhole inspection, and manhole removal. Prices include flow blockage, bypass discharge lines, temporary controls of pumps and standby equipment, standby power, operating equipment during bypass, fuel for operation, coning and barricading, dewatering, temporary pump station, temporary plugs, reports, temporary connections to lines for bypass, clean-up of any sewage, and noise control. (Excavation, shoring, backfill for temporary lines and connections, clean-up, disposal, grade, and cleanup may be ordered on other line items if needed.) Cleaning of manhole covered by separate ELINS. Manholes cover both round and square sizes. | | | | |
| A03.08.01 | Diameter or Square Manhole - Flow Bypassing Diesel per day | 90 | DA | $ - 0 | $ - 0 |
| A03.08.02 | Diameter or Square Manhole - Flow Bypassing Diesel per week | 120 | WK | $ - 0 | $ - 0 |
| A03.08.03 | Diameter or Square Manhole - Flow Bypassing Diesel per month | 18 | MO | $ - 0 | $ - 0 |
| A03.08.04 | Diameter or Square Manhole - Flow Bypassing Electric per day | 90 | DA | $ - 0 | $ - 0 |
| A03.08.05 | Diameter or Square Manhole - Flow Bypassing Electric per week | 120 | WK | $ - 0 | $ - 0 |
| A03.08.06 | Diameter or Square Manhole - Flow Bypassing Electric per month | 18 | MO | $ - 0 | $ - 0 |
| A03.09 | FLOW BYPASSING OF WET WELLS AT PUMP STATIONS | | | | |
| Control Sewer Flow, Composite Rate for bypassing flow around wet wells - diameter or square. Bypassing flow occurs during wet well and pump station cleaning, pumps repair, wet well rehabilitation, pump station repair and overhaul work, water and sewer line rehabilitation, water line inspection, wet well inspection, and wet well removal. Prices include flow blockage, bypass discharge lines, temporary controls of pumps and standby equipment, standby power, operating equipment during bypass, fuel for operation, coning and barricading, dewatering, temporary pump station, temporary plugs, reports, temporary connections to lines for bypass, clean-up of any sewage, and noise control. (Excavation, shoring, backfill for temporary lines and connections, clean-up, disposal, grade, and cleanup may be ordered on other line items if needed.) Cleaning of manhole covered by separate ELINS. Wet wells cover both round and square sizes. | | | | |
| A03.09.01 | Diameter or Square Wet well - Flow Bypassing Diesel per day | 90 | DA | $ - 0 | $ - 0 |
| A03.09.02 | Diameter or Square Wet Well - Flow Bypassing Diesel per week | 120 | WK | $ - 0 | $ - 0 |
| A03.09.03 | Diameter or Square Wet Well - Flow Bypassing Diesel per month | 18 | MO | $ - 0 | $ - 0 |
| A03.09.04 | Diameter or Square Wet well - Flow Bypassing Electric per day | 90 | DA | $ - 0 | $ - 0 |
| A03.09.05 | Diameter or Square Wet Well - Flow Bypassing Electric per week | 120 | WK | $ - 0 | $ - 0 |
| A03.09.06 | Diameter or Square Wet Well - Flow Bypassing Electric per month | 18 | MO | $ - 0 | $ - 0 |
| A03.10 | MANHOLE AND/OR WET WELL FLOW MONITORING (Payment will be made at the lowest applicable rate based on actual Months of Monitoring for Each unit.) | | | | |
| Flow Monitoring Manhole, Wet Well, water, sanitary sewer, storm water, oily water waste oil, Record, report, measure flow rates; includes installation, set-up, removal, calibration, collection of data, data analyses, relocation of flow meters, flow meters equipment, pressure transducer, ultrasonic doppler sensors, NEMA 4X enclosures, battery operated, secure data storage, monitor multiple flow streams at once, high speed communication, handle all influent and infiltration flows, Measure on 5 minutes increments, SCADA capable, Manholes and wet wells cover both round and square sizes. Cost should include relocating to another manhole and /or wet well. | | | | |
| A03.10.01 | Diameter or Square - Flow Monitoring, Each manholes and or wet wells / Month | 4 | EA | $ - 0 | $ - 0 |
| A03.10.02 | Diameter or Square - Flow Monitoring, Each manholes and or wet wells / 2 to 6 Months | 2 | EA | $ - 0 | $ - 0 |
| A03.10.03 | Diameter or Square - Flow Monitoring, Each manholes and or wet wells / 7 to 12 Months | 2 | EA | $ - 0 | $ - 0 |
| A03.11 | RAIN GAUGE PROVIDE AND MONITOR WITH REPORT, TIPPING BUCKET TYPE EACH (Payment will be made at the lowest applicable rate based on actual Months of Monitoring for Each unit.) | | | | |
| A03.11.01 | Rain Gauge and Monitoring Each manholes and or wet wells / Month | 6 | MO | $ - 0 | $ - 0 |
| A03.11.02 | Rain Gauge and Monitoring Each manholes and or wet wells / 2 to 4 Months | 12 | MO | $ - 0 | $ - 0 |
| A03.11.03 | Rain Gauge and Monitoring Each manholes and or wet wells / 5 to 7 Months | 24 | MO | $ - 0 | $ - 0 |
| A03.12 | CLEANING OF SEWER AND STORM DRAIN LINES | | | | |
| Cleaning Storm and Sanitary Sewers, Composite Rate for high velocity high pressure water or fluid - remove sediment, rocks, debris, roots, grease, accumulations, and obstructions - cleaning sanitary and storm drain and sewer lines. Include site and sewer inspection prior to and after cleaning. Television inspection will be performed after cleaning. (During cleaning perform manhole bypass of sewer flow around line being cleaned - Separate ELIN.) | | | | |
| A03.12.01 | 4" to 14" Dia. | 60000 | LF | $ - 0 | $ - 0 |
| A03.12.02 | 15" to 30" Dia. | 10000 | LF | $ - 0 | $ - 0 |
| A03.13 | CLEANING OF SEWER AND STORM DRAIN LINES (to clear blockage) | | | | |
| Composite Rate for high velocity high pressure water or fluid - remove sediment, rocks, debris, roots, grease, accumulations, and obstructions - cleaning sanitary and storm drain sewer lines. Intent is to remove blockage and restore pipe to service. No television inspection required. | | | | |
| A03.13.01 | Clear Blockage | 2500 | LF | $ - 0 | $ - 0 |
| A03.14 | CLEANING OF MANHOLES, VAULTS, AND WET WELLS | | | | |
| Cleaning Storm and Sanitary Sewers, Composite Rate for high velocity high pressure water or fluid - remove sediment, rocks, debris, roots, grease, accumulations, and obstructions - cleaning of manholes, wet wells, and vaults. Include site and sewer inspection prior to and after cleaning. Television inspection will be performed after cleaning. Clean manhole and wet wells to sewer line invert. (During manhole and wet well cleaning perform manhole and wet well bypass of sewage flow - separate ELIN.) | | | | |
| A03.14.01 | Manhole, Valve Pits, & Wet Well surface Cleaning | 10000 | SF | $ - 0 | $ - 0 |
| A03.15 | CLEANING OF OILY WATER WASTE OIL PIPING | | | | |
| Cleaning Storm and Sanitary Sewers, Composite Rate for high velocity high pressure water or fluid - remove sediment, rocks, debris, roots, grease, accumulations, and obstructions - cleaning oily water waste oil lines. Include site and sewer inspection prior to and after cleaning. Television inspection will be performed after cleaning. (During cleaning perform manhole bypass of sewer flow around line being cleaned - Separate ELIN.) Work includes testing, removal, and disposal of non-hazardous oil contaminated water, oily solids, and oily sludge. | | | | |
| A03.15.01 | 4" to 14" Dia. | 1000 | LF | $ - 0 | $ - 0 |
| A03.16 | INSPECT / CLEAN OIL/WATER SEPARATOR | | | | |
| A03.16.01 | Inspect Oil/Water Separator System | 4 | EA | $ - 0 | $ - 0 |
| A03.16.02 | Clean Oil/Water Separator System | 4 | EA | $ - 0 | $ - 0 |
| A04 | CONTAMINATED SOIL, MATERIAL, WATER, OILY SOLIDS, WASTE, ETC. - TESTING, HAULING AND DISPOSAL |
| For testing, removal, pump, disposal, excavation hauling of contaminated soil and water from work areas. Not associated with cleaning of piping, sewer lines, and manholes. |
| A04.01 | TESTING CONTAMINATED SOIL, MATERIAL, WATER, OILY SOLIDS, WASTE, ETC. | | | | |
| A04.01.01 | Perform TCLP test method 6010 | 40 | EA | $ - 0 | $ - 0 |
| A04.01.02 | Perform TPH test method 8010 Diesel | 40 | EA | $ - 0 | $ - 0 |
| A04.01.03 | Perform TPH test method 8015 Modified Gas | 40 | EA | $ - 0 | $ - 0 |
| A04.01.04 | Perform Flammability test method SW 7.1 | 40 | EA | $ - 0 | $ - 0 |
| A04.02 | OIL CONTAMINATED WATER | | | | |
| A04.02.01 | Remove, Hall and dispose of non-hazardous oil contaminated water (3000 gallons minimum) | 50000 | GL | $ - 0 | $ - 0 |
| A04.03 | NON-HAZARDOUS OILY SOLIDS, SLUDGE | | | | |
| A04.03.01 | Remove, Hall and Dispose of Oily Solids | 5000 | GL | $ - 0 | $ - 0 |
| A04.03.02 | Pump, Haul and Dispose of oily solids | 200 | GL | $ - 0 | $ - 0 |
| A04.03.03 | Pump, Haul and Dispose of oily sludge | 1000 | GL | $ - 0 | $ - 0 |
| A04.04 | POTABLE WATER SYSTEM WASTE | | | | |
| A04.04.01 | Remove, Hall and Dispose of non-hazardous contaminated water (3000 gallons minimum) from potable water storage tank | 10000 | GL | $ - 0 | $ - 0 |
| A04.04.02 | Pump, Haul and Dispose of non-hazardous sediments from potable water Storage Tank | 148 | CY | $ - 0 | $ - 0 |
| A04.04.03 | Pump, Haul and Dispose of non-hazardous sludge from potable water storage tank | 15 | CY | $ - 0 | $ - 0 |
| A04.05 | SOIL | | | | |
| A04.05.01 | Excavate and Dispose of non-hazardous contaminated soil (22 CY minimum) | 80 | CY | $ - 0 | $ - 0 |
| A04.06 | HAZARDOUS CONTAMINATED MATERIALS | | | | |
| A04.06.01 | Excavate and Dispose of characteristic hazardous contaminated waste (20 CY minimum) | 20 | CY | $ - 0 | $ - 0 |
| A04.06.02 | Pump, haul and Dispose of hazardous oil contaminated water | 5000 | GL | $ - 0 | $ - 0 |
| A05 | TV INSPECTIONS OF SEWER AND STORM DRAINS | | | | |
| TV inspection must be by NASSCO certified inspector. Inspections shall include reports, logs, DVDs, footage counters, and all applicable documentation. | | | | |
| A05.01.01 | 4" to 14" Dia. | 50000 | LF | $ - 0 | $ - 0 |
| A05.01.02 | 15" to 30" Dia. | 7000 | LF | $ - 0 | $ - 0 |
| A06 | EXCAVATION AND FILL FOR ANY UTILITY PIPE | | | | |
| This covers work for excavation and fill for any type of a single utility pipe regardless of width and covers the composite price for sheeting / shoring, benching, dewatering with well points, excavation, backfilling, and seeding. Depth as measured to the invert of the pipe plus allowance for bed depth. Utility pipe costs is not included and is covered by separate ELIN. Separate ELIN for pipe preparation, new bedding, and installation. | | | | |
| A06.01.01 | 0' To 4' depth for 1/2" to 16" Pipe | 6000 | LF | $ - 0 | $ - 0 |
| A06.01.02 | 4' To 7' depth for 1/2" to 16" Pipe | 6000 | LF | $ - 0 | $ - 0 |
| A06.01.03 | 7' To 10' depth for 1/2" to 16" Pipe | 1500 | LF | $ - 0 | $ - 0 |
| A06.01.04 | 0' To 4' depth for 18" to 36" Pipe | 2000 | LF | $ - 0 | $ - 0 |
| A06.01.05 | 4' To 7' Deep for 18" to 36" Pipe | 2000 | LF | $ - 0 | $ - 0 |
| A06.01.06 | 7' To 10' Deep for 18" to 36" Pipe | 1000 | LF | $ - 0 | $ - 0 |
| A06.01.07 | 0' To 4' Deep for 38" to 54" Pipe | 50 | LF | $ - 0 | $ - 0 |
| A06.01.08 | 4' To 7' Deep for 38" to 54" Pipe | 50 | LF | $ - 0 | $ - 0 |
| A06.01.09 | 7' To 10' deep for 38" to 54" Pipe | 50 | LF | $ - 0 | $ - 0 |
| A06.01.10 | 0' To 4' Deep for 56" to 72" Pipe | 20 | LF | $ - 0 | $ - 0 |
| A06.01.11 | 4' To 7' Deep for 56" to 72" Pipe | 20 | LF | $ - 0 | $ - 0 |
| A06.01.12 | 7' To 10' Deep for 56" to 72" Pipe | 10 | LF | $ - 0 | $ - 0 |
| A06.01.13 | Provide extra backfill where excavated material will not fill area, includes grading and seeding. | 500 | CY | $ - 0 | $ - 0 |
| A06.01.14 | Additional Width required for multiple pipes | 7500 | LF | $ - 0 | $ - 0 |
| A07 | NEW PIPE FOR SANITARY SEWER |
| This covers work for, Sanitary Sewer and OWWO, Gravity and Pressure Pipe. Includes pipe material, installation, clean-up, new pipe, bedding. |
| A07.01 | DUCTILE IRON | | | | |
| A07.01.01 | Ductile Iron 6" Pipe | 400 | LF | $ - 0 | $ - 0 |
| A07.01.02 | Ductile Iron 8" Pipe | 800 | LF | $ - 0 | $ - 0 |
| A07.01.03 | Ductile Iron 10" Pipe | 200 | LF | $ - 0 | $ - 0 |
| A07.01.04 | Ductile Iron 12" Pipe | 200 | LF | $ - 0 | $ - 0 |
| A07.01.05 | Ductile Iron 14" Pipe | 200 | LF | $ - 0 | $ - 0 |
| A07.01.06 | Ductile Iron 16" Pipe | 400 | LF | $ - 0 | $ - 0 |
| A07.01.07 | Ductile Iron 18" Pipe | 100 | LF | $ - 0 | $ - 0 |
| A07.01.08 | Ductile Iron 20" Pipe | 100 | LF | $ - 0 | $ - 0 |
| A07.01.09 | Ductile Iron 24" Pipe | 100 | LF | $ - 0 | $ - 0 |
| A07.02 | CERAMIC EPOXY COATED & LINED INSTEAD OF CEMENT LINED | | | | |
| A07.02.01 | Ductile Iron, 6" Pipe ceramic epoxy coated & lined | 400 | LF | $ - 0 | $ - 0 |
| A07.02.02 | Ductile Iron 8" Pipe ceramic epoxy coated & lined | 800 | LF | $ - 0 | $ - 0 |
| A07.02.03 | Ductile Iron 10" Pipe ceramic epoxy coated & lined | 200 | LF | $ - 0 | $ - 0 |
| A07.02.04 | Ductile Iron 12" Pipe ceramic epoxy coated & lined | 200 | LF | $ - 0 | $ - 0 |
| A07.02.05 | Ductile Iron 14" Pipe ceramic epoxy coated & lined | 200 | LF | $ - 0 | $ - 0 |
This is the start of the file's text. The full file is on GovTribe.