Attachment 2 - Drawing1 Bldg 107.pdf

PDF 35 KB Posted

Attached to
BLDG 107 Epoxy Floors
Solicitation number
W50S8Q-23-R-0004
Issued by

View the file

Other files

File Type Posted
RFI Answers.pdf PDF
Attachment 1 - SOW Bldg.107 WAAR232002.docx DOCX document
Attachment 3 - Material Submittals - WAAR232002.xlsx XLSX spreadsheet
W50S8Q-23-R-0004.pdf PDF
Attachment 5 - DBIDs -Base Entry Request.pdf PDF
Attachment 4 - RFI Format.docx DOCX document
Attachment 2 - Drawing2 Bldg 107.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PH #1

PH#2 PH#3

Drawing#1

Notes: 1.)The CONTRACTOR shall prep all bay areas and hallway indicated on Drawing #1 by making sure they are free of dirt, waxes, curing agents, and other foreign materials. If the sub-floor or slab has cracks in it they must be filled with an Epoxy repair material to keep the new flooring from having any issues.

2.)The CONTRACTOR shall demo cove base that has been indicate on Drawing #1. (Approx. SQFT 315 +/-) 3.)The CONTRACTOR shall install seamless Quartz Epoxy flooring that has two color design in the following areas indicated on Drawing #1. The epoxy flooring will first consist of an elastomeric membrane then an epoxy bond coat followed by a matrix of colored granules with epoxy and finally an epoxy clear coat. (Approx. SQFT 4,150 +/-) 4.) The CONTRACTOR shall install new black cove base on walls indicated on Drawing #1. (Approx. LF 315+/-) 5.) The CONTRACTOR will be required to install a threshold in areas where there is a transition between two flooring types.

Legend:

Indicates the phasing and area where the slab is to be prepped and epoxy installed

Indicates where cove base needs demolished and new cove base installed.

File details come from the government source that posted it. Updated .