ATTACHMENT 2.A. Sample Project Elecrical Scope of Work B1579.pdf
PDF 1001 KB Posted
- Solicitation number
- W912CN
About this file
This document outlines the scope of work for an electrical renovation project at Fort Wainwright, Alaska. The project involves renovating an existing building to accommodate new office spaces for the Criminal Investigative Division. Work includes upgrading interior and exterior lighting to LED fixtures, installing new electrical panels and wiring, and running conduit and cabling for closed-circuit television cameras, intrusion detection systems, and voice/data lines to various rooms. Specific lighting levels, power receptacle placements, and telecommunications outlet counts are defined for each room. Electrical and lighting load calculations are provided. The project will be completed through the Fort Wainwright Job Order Contract program by the local Department of Public Works following 35% design by the U.S. Army Corps of Engineers.
The related federal contract opportunity is a multiple award task order contract to acquire real property repair, maintenance, and minor construction services for Army installations in Alaska under the Directorate of Public Works, Alaska. Offerors are advised to review the solicitation attachments for additional requirement details. The contracting agency is the U.S. Department of the Army.
View the file
Other files
Show all 15
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
2.6 ELECTRICAL AND TELECOMMUNICATION DESIGN ANALYSIS
2.6.1 Scope of Work
This project is located at Fort Wainwright, Alaska (FTW) and is to renovate the existing building 1579 to accommodate Criminal Investigative Division (CID) needs. This section will outline the electrical, telecommunication, and Closed Circuit Television (CCTV) and Intrusion Detection System(IDS) security requirements of the project to maintain compliance with the current regulations, to include power and telecommunications. UFC 1-200-02 High Performance and Sustainability Building Requirements and ASHRAE 90.1 Requirements from UFC 3-501-01 Electrical Engineering, will not be included in this scope of work. All work performed up to the 35% by the USACE will be transferred to FTW Department of Public Works (DPW), to be completed by DPW and proceed through the FTW Job Order Contract (JOC) Program.
2.6.2 References
Specific requirements listed herein take precedence over conflicting requirements in the referenced documents. When referenced documents have conflicting criteria, the most stringent criteria shall take precedence.
Construction shall comply with most current applicable industry codes and standards, federal regulations and guidelines, Department of Defense criteria and Fort Wainwright specific criteria.
Industry Codes and Standards:
ANSI C84.1, Electric Power Systems and Equipment—Voltage Ratings (60 Hz).
ANSI Z535.4-2007, Product Safety Signs and Labels.
IEEE C2, National electrical Safety Code
IEEE C62.41, IEEE Recommended Practice on Surge Voltages in Low-Voltage AC Power Circuits.
IEEE Std 241, IEEE Recommended Practice for Electric Power Systems in Commercial Buildings
IEEE Std 399, IEEE Recommended Practice for Industrial and Commercial Power System Analysis.
IEEE Std 446, IEEE Recommended Practice for Emergency and Standby Power Systems for Industrial and Commercial Applications.
IEEE Std 551, IEEE Recommended Practice for Calculating Short-Circuit Currents in Industrial and Commercial Power Systems.
IEEE Std 1584, IEEE Guide for Performing Arc-Flash Hazard Calculations, including Amendments 1 and 2.
IES Lighting Handbook
NFPA 70, National Electrical Code
NFPA 70E, Standard for Electrical Safety in the Workplace
NFPA 110, Standard for Emergency and Standby Power Systems
NFPA 111, Standard on Stored Electrical Energy, Emergency, and Standby Power Systems
NFPA 780, Standard for the Installation of Lightning Protection Systems
I3A Technical Guide for Installation Information Infrastructure Architecture (I3A)
TIA 606C Administration Standard for Telecommunication Infrastructure
TIA-758B Customer Owned Outside Plant Telecommunications Infrastructure
Doyon Utilities Electrical System Design and Construction Standards 2019
UL467 Grounding and Bonding Equipment
Criminal Investigative Division Command (CIDC) Resident Agent (RA) Field Facility Requirements
Government Criteria (Copies of these criteria can be downloaded from http://www.wbdg.org/references/docs_refs.php, except for the base specific criteria):
UFC 3-501-01 Electrical Engineering
UFC 3-520-01 Interior Electrical Systems
UFC 3-530-01 Interior and Exterior Lighting Systems and Controls
UFC 3-550-01 Exterior Electrical Power Distribution
UFC 3-580-01 Telecommunication Interior Infrastructure Planning and Design
2.6.3 ELECTRICAL
2.6.3.1 Medium Voltage Distribution
2.6.3.1.1 Aerial Distribution
Currently Building 1579 shares three pole mounted 50 KVA transformers with an adjacent building. The pole mounted transformers, power the building mounted utility meter and a 200 amp breaker, the Point of Demarcation (POD) between Department of Public Works and Doyon. The utility meter provides power to Building 1579’s Main Distribution Panel (MDP). No work is expected to be performed from the MDP to the pole mounted transformers.
2.6.3.2 Exterior Lighting and Electrical work
No exterior lighting work shall be performed within this projects scope of work.
A L14-30 weatherproof Plug will be installed on the exterior of Building 1579, to allow the customer to power mission essential equipment from a generator.
2.6.3.3 Secured Parking
No exterior lighting or power will be required for the secured parking area, at this point in time. The gates shall be manually opened and closed/locked. One receptacle/J-box will be installed on the outside wall of the building to support the CCTV camera.
2.6.3.4 Interior Electrical work
All existing interior lighting is assumed to be four bulb, T8 fluorescent light fixtures. All room lighting will be retrofitted for LEDs.
2.6.3.4.1 Public Waiting Room
The Public Waiting Room will be provided one 120 volt duplex power receptacles every 25 ft. of wall space, as required by UFC 3-520-01. Additionally, one J-box with 12 volt power will be installed on the wall and a 3/4" EMT conduit with pull string will be installed between the Public Waiting room and Administrative room to support the CCTV camera. LED lighting fixtures will be installed and they will provide a minimum of 10 foot-candles (100 lux) at 30 inches above finished floor. Lighting controls
(occupancy sensor and daylighting) are not included in the scope of work for this project at the request of the customer.
2.6.3.4.2 Vestibules
One duplex receptacle shall be installed every 25 ft. of wall space, as required by UFC 3-520-01. One duplex receptacle will be installed at the main entry vestibule, to support a GFGI metal detector, and one J-box with 12 volt power will be installed on the wall and a 3/4" EMT conduit with pull string will be installed between the vestibules and Administrative room to support the CCTV cameras. Additionally, the Center North vestibule will have two j-boxes installed outside, to allow for an additional camera to be mounted, to supervise the LED lighting fixtures will be installed and they will provide a minimum of 10 foot-candles (100 lux) at 30 inches above finished floor. Lighting controls (occupancy sensor and daylighting) are not included in the scope of work for this project at the request of the customer.
2.6.3.4.3 Administrative Room
One duplex receptacle shall be installed every 10 ft of wall space, as required by UFC 3-520-01. LED lighting fixtures will be installed and they will provide a minimum of 10 foot-candles (100 lux) at 30 inches above finished floor. Lighting controls (occupancy sensor and daylighting) are not included in the scope of work for this project at the request of the customer.
2.6.3.4.4 Intelligence Analysts Room
One duplex receptacle shall be installed every 25 ft of wall space, as required by UFC 3-520-01. LED lighting fixtures will be installed and they will provide a minimum of 30 foot-candles (300 lux) at 30 inches above finished floor. Lighting controls (occupancy sensor and daylighting) are not included in the scope of work for this project at the request of the customer.
2.6.3.4.5 Digital Media Room
One duplex receptacle shall be installed every 25 ft of wall space, as required by UFC 3-520-01. LED lighting fixtures will be installed and they will provide a minimum of 30 foot-candles (300 lux) at 30 inches above finished floor. Lighting controls (occupancy sensor and daylighting) are not included in the scope of work for this project at the request of the customer.
2.6.3.4.6 Storage
One duplex receptacle shall be installed every 25 ft of wall space, as required by UFC 3-520-01. LED lighting fixtures will be installed and they will provide a minimum of 10 foot-candles (100 lux) at 30 inches above finished floor. Lighting controls (occupancy sensor and daylighting) are not included in the scope of work for this project at the request of the customer.
2.6.3.4.7 Witness Interview Room
One duplex receptacle shall be installed every 25 ft of wall space, as required by UFC 3-520-01.
Additionally, J-box with 12 volt DC power will be installed on the wall to support the CCTV camera. LED lighting fixtures will be installed and they will provide a minimum of 30 foot-candles (300 lux) at 30 inches above finished floor. Lighting controls (occupancy sensor and daylighting) are not included in the scope of work for this project at the request of the customer.
2.6.3.4.8 Interview Rooms
One tamperproof duplex receptacle shall be installed every 25 ft of wall space, as required by UFC 3-520-
01. One of the Interview rooms will have a single duplex outlet that will be powered from a new panel board that will have the option to manually transfer to generator power. Additionally, J-box with 12 volt DC power will be installed on the wall of each interview room to support the CCTV camera. LED lighting fixtures will be installed and they will provide a minimum of 30 foot-candles (300 lux) at 30 inches above finished floor. Lighting controls (occupancy sensor and daylighting) are not included in the scope of work for this project at the request of the customer.
2.6.3.4.9 Suspect Processing Room
One duplex receptacle shall be installed every 25 ft of wall space, as required by UFC 3-520-01. The Suspect Processing room will have a single duplex outlet (for the LiveScan equipment) that will be powered from a new panel board that will have the option to manually transfer to generator power. LED lighting fixtures will be installed and they will provide a minimum of 30 foot-candles (300 lux) at 30 inches above finished floor. Lighting controls (occupancy sensor and daylighting) are not included in the scope of work for this project at the request of the customer.
2.6.3.4.10 Polygraph Room
One duplex receptacle shall be installed every 25 ft of wall space, as required by UFC 3-520-01. LED lighting fixtures will be installed and they will provide a minimum of 30 foot-candles (300 lux) at 30 inches above finished floor. Lighting controls (occupancy sensor and daylighting) are not included in the scope of work for this project at the request of the customer.
2.6.3.4.11 Detachment Sergeant (SGT) Room
One duplex receptacle shall be installed every 10 ft of wall space, as required by UFC 3-520-01. LED lighting fixtures will be installed and they will provide a minimum of 30 foot-candles (300 lux) at 30 inches above finished floor. Lighting controls (occupancy sensor and daylighting) are not included in the scope of work for this project at the request of the customer.
2.6.3.4.12 Special Agent in Charge (SAC) and Assistant Special Agent in Charge (ASAC) Office Rooms
Both offices will be provided at least four 120 volt duplex power receptacles. One duplex receptacle shall be installed every 10 ft of wall space, as required by UFC 3-520-01. LED lighting fixtures will be installed and they will provide a minimum of 30 foot-candles (300 lux) at 30 inches above finished floor. Lighting controls (occupancy sensor and daylighting) are not included in the scope of work for this project at the request of the customer.
2.6.3.4.13 Meeting Room
One duplex receptacle shall be installed every 12 ft of wall space, adjacent to the voice/data outlets, as required by UFC 3-520-01. Additionally, one receptacle will be installed on the ceiling to support a projector and two other duplex receptacle will be installed high on the wall to support a clock and a GFGI motorized screen. No floor mounted receptacles will be installed, as requested by the client. LED lighting fixtures will be installed and they will provide a minimum of 30 foot-candles (300 lux) at 30 inches above finished floor. Lighting controls (occupancy sensor and daylighting) are not included in the scope of work for this project at the request of the customer.
2.6.3.4.14 Drug Suppression Team
The Drug Suppression Team Room will be provided at least four 120 volt duplex power receptacles. One duplex receptacle shall be installed every 10 ft of wall space, as required by UFC 3-520-01. LED lighting fixtures will be installed and they will provide a minimum of 30 foot-candles (300 lux) at 30 inches above finished floor. Lighting controls (occupancy sensor and daylighting) are not included in the scope of work for this project at the request of the customer.
2.6.3.4.15 Break Room
One duplex receptacle will be installed every 4 ft of countertop space and one duplex receptacle every 10ft of wall space, as required by UFC 3-520-01. LED lighting fixtures will be installed and they will provide a minimum of 15 foot-candles (150 lux) at 30 inches above finished floor. Lighting controls
(occupancy sensor and daylighting) are not included in the scope of work for this project at the request of the customer.
2.6.3.4.16 Corridors
One duplex receptacle shall be installed every 50 ft of wall space, as required by UFC 3-520-01. LED lighting fixtures will be installed and they will provide a minimum of 10 foot-candles (100 lux) at 30 inches above finished floor. Local occupancy lighting controls will be included in the corridors, but daylighting controls are not included in the scope of work for this project at the request of the customer.
2.6.3.4.17 Restrooms
One GFCI duplex receptacle shall be installed at counter height for every two sinks, as required by UFC 3-520-01. LED lighting fixtures will be installed and they will provide a minimum of 15 foot-candles (150 lux) at 30 inches above finished floor. Local occupancy lighting controls will be included in the restrooms, but daylighting controls are not included in the scope of work for this project at the request of the customer.
2.6.3.4.18 Vehicle Holding area
The Vehicle Holding area will be an “unclassified” hazardous location, per NFPA 70, as the area will be used for parking or storage. One GFCI duplex receptacle shall be installed every 25 ft of wall space, as required by UFC 3-520-01. LED lighting fixtures will be installed and they will provide a minimum of 20 foot-candles (200 lux) at 30 inches above finished floor. Lighting controls (occupancy sensor and daylighting) are not included in the scope of work for this project at the request of the customer.
2.6.3.4.19 Evidence Processing Room
One duplex receptacle shall be installed every 25 ft of wall space, as required by UFC 3-520-01. LED lighting fixtures will be installed and they will provide a minimum of 50 foot-candles (500 lux) at 30 inches above finished floor. Lighting controls (occupancy sensor and daylighting) are not included in the scope of work for this project at the request of the customer.
2.6.3.4.20 Evidence Control Office
One duplex receptacle shall be installed every 25 ft of wall space, as required by UFC 3-520-01. LED lighting fixtures will be installed and they will provide a minimum of 30 foot-candles (300 lux) at 30 inches above finished floor. Lighting controls (occupancy sensor and daylighting) are not included in the scope of work for this project at the request of the customer.
2.6.3.4.21 Evidence Storage Room
One duplex receptacle shall be installed every 25 ft of wall space, as required by UFC 3-520-01. Two dedicated circuit duplex receptacles shall be installed, in support of the mission essential equipment. The receptacles will be powered from a new panel board that will have the option to manually transfer to generator power. LED lighting fixtures will be installed and they will provide a minimum of 10 foot-candles (100 lux) at 30 inches above finished floor. Lighting controls (occupancy sensor and daylighting) are not included in the scope of work for this project at the request of the customer.
2.6.3.4.22 General Crimes Rooms
The Drug Suppression Team Room will be provided at least four 120 volt duplex power receptacles. One duplex receptacle shall be installed every 10 ft of wall space, as required by UFC 3-520-01. A maximum of four workstations shall be powered from a 20 amp circuit, as required by UFC 3-520-01. LED lighting fixtures will be installed and they will provide a minimum of 30 foot-candles (300 lux) at 30 inches above finished floor. Lighting controls (occupancy sensor and daylighting) are not included in the scope of work for this project at the request of the customer.
2.6.3.4.23 Electrical Room
A new manual transfer switch and panel board shall be installed, to allow CID to manually transfer power for mission essential equipment to a GFGI standby generator (8.4kW Model: Honda GX630RHVD). The generator shall support two duplex receptacles (for two refrigerators) in the Evidence Storage Room, one duplex receptacle in an interview room, and one duplex receptacle (for LiveScan equipment) in the Suspect Processing Room. One duplex receptacle shall be installed every 25 ft of wall space, as required by UFC 3-520-01. LED lighting fixtures will be installed and they will provide a minimum of 20 foot-candles (200 lux) at 30 inches above finished floor. Lighting controls (occupancy sensor and daylighting) are not included in the scope of work for this project at the request of the customer.
2.6.3.4.24 Telecommunication Room
A dedicated 120/208 volt, 3-phase, 30-space, 100 amp electrical panel board shall be installed in the telecommunications room. One duplex receptacle will be installed every 6 ft. of wall space, as required by I3A. Furthermore, a dedicated 20 amp circuit and receptacle shall be installed for each rack or backboard for the CCTV, CATV, Voice and Data systems, as required by UFC 3-520-01. LED lighting fixtures will be installed and they will provide a minimum of 50 foot-candles (500 lux) at 3 ft. above finished floor. Lighting controls (occupancy sensor and daylighting) are not included in the scope of work for this project at the request of the customer.
2.6.3.4.25 CATV Room
A dedicated 20 amp circuit and receptacle shall be installed for each rack or backboard for the CCTV, CATV, Voice and Data systems, as required by UFC 3-520-01. LED lighting fixtures will be installed and they will provide a minimum of 50 foot-candles (500 lux) at 30 inches above finished floor. Lighting controls (occupancy sensor and daylighting) are not included in the scope of work for this project at the request of the customer.
2.6.3.4.26 Shower Room
One GFCI duplex receptacle shall be installed at counter height for every two sinks, as required by UFC 3-520-01. One GFCI duplex receptacle shall be installed within 6 ft. of the shower stall, per NEC2017.
LED lighting fixtures will be installed and they will provide a minimum of 10 foot-candles (100 lux) at 30 inches above finished floor. Light fixtures shall be rated for damp or wet locations. Lighting controls (occupancy sensor and daylighting) are not included in the scope of work for this project at the request of the customer.
2.6.3.4.27 Training Room
No electrical work shall be performed within this room during this project. If new LED lighting fixtures will be installed and they will provide a minimum of 40 foot-candles (400 lux) at 30 inches above finished floor. Lighting controls (occupancy sensor and daylighting) are not included in the scope of work for this project at the request of the customer.
2.6.4 TELECOMMUNICATION
2.6.4.1 Underground Exterior Distribution
Telecommunications is routed to the building underground from the existing telecommunication duct bank system at Fort Wainwright (FTW). The Telecommunications cables (four 25 pair copper lines and a 12 strand Single-Mode (SM) fiber line) come to Building 1579’s North-East corner of the building and are then mounted and ran across the east outside wall of Building 1579, through two 4 inch PVC conduits.
Telecommunication wires enter from the South-East corner of the building.
This infrastructure shall remain in place and not be affected within the scope of this project.
2.6.4.2 Interior Telecommunication work
The scope of this project will include centralizing and replacing the existing telecommunication equipment. Currently there are two wall mounted telecommunication racks, one in the South-East corner of the building (where the telecommunication lines enter the building) and the second is on the North- West corner of the building. The telecommunication lines are currently switched from Outside Plant (OSP) line to interior lines at the South-East Telecommunication rack, and then two of the 25 pair copper lines and a 12 strand SM fiber line connect to the North-West telecommunications rack. It is assumed that both rack are supported by 50 pair copper lines and 6 strands of SM fiber.
No wireless network system will be installed, as it was not included as a part of this projects scope of work. No centralized clock system will be installed, as required by the CIDC RA Field Facility Requirements.
All existing wall outlets are single gang four position or six position faceplates, with CAT5 cable. All wall outlet faceplates shall be replaced with the same number of positions and rewired with CAT6 cable wired to the TIA/EIA T568A wire configuration. All fiber optic cables will be terminated in dual 568SC connectors. All conduits, J-hooks, D-rings, and wire-ways will be utilized for the rewiring of the building telecommunications system.
2.6.4.2.1 Public Waiting Room
The Public Waiting room will have two 8-pin modular (RJ45 type) outlets with two connectors for data use and VoIP Phone. The offices will only have NIPRNET access and no SIPRNET ports will be installed in the rooms
2.6.4.2.2 Vestibules
No telecommunication wall outlets will be installed in the vestibules.
2.6.4.2.3 Administrative Room
The Administrative room will have two 8-pin modular (RJ45 type) outlets with two connectors for data use and VoIP Phone. The offices will only have NIPRNET access and no SIPRNET ports will be installed in the rooms
2.6.4.2.4 Intelligence Analysis Room
The Intelligence Analysis room will have four 8-pin modular (RJ45 type) outlets with two connectors for data use and VoIP Phone. The offices will only have NIPRNET access and no SIPRNET ports will be installed in the rooms
2.6.4.2.5 Digital Media Room
The Digital Media room will have four 8-pin modular (RJ45 type) outlets with two connectors for data use and VoIP Phone. The digital media room will only have NIPRNET access and no SIPRNET ports will be installed in the rooms
2.6.4.2.6 Storage
The storage rooms will have two 8-pin modular (RJ45 type) outlets with two connectors for data use and VoIP Phone.
2.6.4.2.7 Witness Interview Room
The Witness interview room will have two 8-pin modular (RJ45 type) outlets with two connectors for data use and VoIP Phone. The offices will only have NIPRNET access and no SIPRNET ports will be installed in the rooms.
2.6.4.2.8 Interview Rooms
The Interview rooms will have two 8-pin modular (RJ45 type) outlets with two connectors for data use and VoIP Phone. The offices will only have NIPRNET access and no SIPRNET ports will be installed in the rooms.
2.6.4.2.9 Suspect Processing Room
The Suspect Processing room will have two 8-pin modular (RJ45 type) outlets with two connectors for data use and VoIP Phone. The offices will only have NIPRNET access and no SIPRNET ports will be installed in the rooms.
2.6.4.2.10 Polygraph Room
The Polygraph room will have two 8-pin modular (RJ45 type) outlets with two connectors for data use and VoIP Phone. The offices will only have NIPRNET access and no SIPRNET ports will be installed in the rooms.
2.6.4.2.11 Detachment Sergeant (SGT) Room
The Detachment SGT room will have two 8-pin modular (RJ45 type) outlets with two connectors for data use and VoIP Phone. The offices will only have NIPRNET access and no SIPRNET ports will be installed in the rooms.
2.6.4.2.12 Special Agent in Charge (SAC) and Assistant Special Agent in Charge (ASAC) Office Rooms
Each office will have two 8-pin modular (RJ45 type) outlets with two connectors for data use and VoIP Phone. The offices will only have NIPRNET access and no SIPRNET ports will be installed in the rooms.
2.6.4.2.13 Meeting Room
Four 8-pin modular (RJ45 type) outlets with two connectors for data use and VoIP Phone. No telecommunication voice or data outlets will be installed on the floor.
2.6.4.2.14 Drug Suppression Team
The Drug Suppression Team room will have four 8-pin modular (RJ45 type) outlets with two connectors for data use and VoIP Phone. The offices will only have NIPRNET access and no SIPRNET ports will be installed in the rooms.
2.6.4.2.15 Break Room
No renovation work shall be performed in this room within this project. With the exception of rewiring an existing communication wall outlet.
2.6.4.2.16 Corridors
No public address system or telecommunications wall outlets will be installed in the corridors, as requested by the customer during the design charrette.
An appropriately sized (minimum of 12 inch) cable tray will be installed in the ceiling area of the corridors for distribution of the telecommunications cables.
2.6.4.2.17 Restrooms
No telecommunication wall outlets will be installed in the restroom.
2.6.4.2.18 Vehicle Holding area
The Vehicle Holding area will have two 8-pin modular (RJ45 type) outlets with two connectors for data use and VoIP Phone. The offices will only have NIPRNET access and no SIPRNET ports will be installed in the room.
2.6.4.2.19 Evidence Processing Room
The Evidence Processing room will have two 8-pin modular (RJ45 type) outlets with two connectors for data use and VoIP Phone. The offices will only have NIPRNET access and no SIPRNET ports will be installed in the room.
2.6.4.2.20 Evidence Control Office
The Evidence control room will have two 8-pin modular (RJ45 type) outlets with two connectors for data use and VoIP Phone. The offices will only have NIPRNET access and no SIPRNET ports will be installed in the room.
2.6.4.2.21 Evidence Storage Room
The Evidence Storage room will have four 8-pin modular (RJ45 type) outlets with two connectors for data use and VoIP Phone. The offices will only have NIPRNET access and no SIPRNET ports will be installed in the room.
2.6.4.2.22 General Crimes Rooms
The General Crimes room will have four 8-pin modular (RJ45 type) outlets with two connectors for data use and VoIP Phone. The offices will only have NIPRNET access and no SIPRNET ports will be installed in the rooms.
2.6.4.2.23 Electrical Room
One wall-outlet will be installed near the entry door, per UFC 3-580-01.
2.6.4.2.24 Telecommunication Room
Two new racks will be installed in the Telecommunications room. The floor mounted racks will be connected to the 12 strands of single Mode fiber and 100 pair of 20 awg copper wire, that will be ran from the existing building penetration/telecommunications entrance through two 2 inch RMC conduit. The 2 inch RMCs will be grounded by a #6 AWG copper ground wires, to allow the OSP copper and OSP fiber lines to be extended to the new Telecommunication room. A new surge arrestor/protected entrance terminal, plywood backboard, 110-type Insulation Displacement Connector (IDC) terminal blocks will be required in the Telecommunication room. One wall-outlet will be installed near the entry door, as required by I3A.
2.6.4.2.25 CATV Room
A single 2 inch RMC conduit will be ran from the existing building penetration/telecommunications entrance to the CATV room next to the Telecommunications room, a #6 AWG copper ground wire, RG-11 and pull wire will be installed to support CATV capability. One wall-outlet will be installed near the entry door, per UFC 3-580-01.
2.6.4.2.26 Shower Room
No telecommunication wall outlets will be installed in the shower room and existing telecommunication wall outlets will be removed.
2.6.4.2.27 Training Room
The Training Room will have the telecommunications rack and cables (Cat5) removed from the room.
New Category 6 cables shall be ran and installed in the room’s wall ports, from the new centralized Telecommunications room. Additionally, a section of the existing 12 inch cable tray will be re-attached to the ceiling and additional supports shall be installed.
2.6.5 CCTV AND IDS SECURITY SYSTEMS
Building 1579 will have the infrastructure installed to allow for CCTV and IDS system to be installed by others. All other rooms not listed here do not require any CCTV or IDS.
2.6.5.1.1 Public Waiting Room
A 3/4 inch RMC conduit and pull string will be installed between the Public Waiting room and the Administrative room, to install a CCTV camera.
2.6.5.1.2 Vestibules
A 3/4 inch RMC conduit and pull string will be installed between the main entrance vestibule (on the plan North-East section of the building) and the Administrative room, to install a CCTV camera. An additional 1 inch RMC conduit and pull string will be installed between the entrance vestibule to the secured parking area (on the plan North section of the building) and the Administrative room, to install a CCTV camera.
2.6.5.1.3 Interview Rooms
The Interview rooms will each have a 3/4 inch RMC conduit and pull string installed from the interview rooms to the Digital Media room.
2.6.5.1.4 Evidence Storage Room
The Evidence Storage room will be required to have an IDS security system installed inside, with the alarm going to the officer’s rooms and Administrative room. Conduit and J-boxes outside of the Evidence Storage room will be welded or security bolt sealed with tamper switches.
2.6.6 Lightning Protection and Grounding
No Lighting protection calculations will be performed with this projects scope of work. The building’s exterior structure is not changing within the scope of this project.
The main panels and utility breaker will be remaining in place and are assumed to have proper grounding.
The scope of work for this project is to renovate the interior of the building to support CID’s room type and number of rooms CID requires.
The Telecommunication room and CATV room will each have a Telecommunication Main Grounding Busbar (TMGB) installed and connected to the new electrical panel board in the Telecommunications room.
Electrical
Calculations
UFC 3‐501‐01; SECTION 3‐2.3.1
10000 SQ‐FT BUILDING SIZE 12 VA/SQ‐FT 120000 VA
NET LOAD 120 KVA
NFPA 70; 220.12 LIGHTING
10000 SQ‐FT LIGHTING 3.5 SQ‐FT 35000 VA
NET LOAD 35 KVA
NFPA 70; 220.14(k) RECEPTACLE
220.14(k)(2)
10000 SQ‐FT RECEPTACLE 1 VA/SQ‐FT 10000 VA
NET LOAD 10 KVA
OR
220.14(k)(1)
RM 101
8 EA RECEPTACLE 180 VA 1440 VA
NET LOAD 1.44 KVA
RM 102
7 EA RECEPTACLE 180 VA 1260 VA
NET LOAD 1.26 KVA
RM 103
5 EA RECEPTACLE 180 VA 900 VA
NET LOAD 0.9 KVA
RM 104
6 EA RECEPTACLE 180 VA 1080 VA
NET LOAD 1.08 KVA
RM 105
7 EA RECEPTACLE 180 VA 1260 VA
NET LOAD 1.26 KVA
RM 106
9 EA RECEPTACLE 180 VA 1620 VA
NET LOAD 1.62 KVA
RM 107
7 EA RECEPTACLE 180 VA 1260 VA
NET LOAD 1.26 KVA
RM 108
4 EA RECEPTACLE 180 VA 720 VA
NET LOAD 0.72 KVA
RM 109
9 EA RECEPTACLE 180 VA 1620 VA
NET LOAD 1.62 KVA
RM 110
4 EA RECEPTACLE 180 VA 720 VA
NET LOAD 0.72 KVA
RM 111
LOAD CALCULATION (EXISTING)
9 EA RECEPTACLE 180 VA 1620 VA
NET LOAD 1.62 KVA
RM 112
4 EA RECEPTACLE 180 VA 720 VA
NET LOAD 0.72 KVA
RM 113
4 EA RECEPTACLE 180 VA 720 VA
NET LOAD 0.72 KVA
RM 114
3 EA RECEPTACLE 180 VA 540 VA
NET LOAD 0.54 KVA
RM 115
3 EA RECEPTACLE 180 VA 540 VA
NET LOAD 0.54 KVA
RM 116
12 EA RECEPTACLE 180 VA 2160 VA
NET LOAD 2.16 KVA
RM 117
11 EA RECEPTACLE 180 VA 1980 VA
NET LOAD 1.98 KVA
RM 118
13 EA RECEPTACLE 180 VA 2340 VA
NET LOAD 2.34 KVA
RM 119
1 EA RECEPTACLE 180 VA 180 VA
NET LOAD 0.18 KVA
TRAINING RM
81 EA RECEPTACLE 180 VA 14580 VA
NET LOAD 14.58 KVA
RESTROOMS
2 EA RECEPTACLE 180 VA 360 VA
NET LOAD 0.36 KVA
BREAK RM
9 EA RECEPTACLE 180 VA 1620 VA
NET LOAD 1.62 KVA
CORRIDORS & VEHICLE BAY
17 EA RECEPTACLE 180 VA 3060 VA
NET LOAD 3.06 KVA
SUBNET TOTAL LOAD 26.15 KVA
EST. TOTAL LOAD 61.15 KVA
170 AMPS
UFC 3‐501‐01; SECTION 3‐2.3.1
10000 SQ‐FT BUILDING SIZE 12 VA/SQ‐FT 120000 VA
NET LOAD 120 KVA
NFPA 70; 220.12 LIGHTING
10000 SQ‐FT LIGHTING 3.5 SQ‐FT 35000 VA
NET LOAD 35 KVA
NFPA 70; 220.14(k) RECEPTACLE
220.14(k)(2)
10000 SQ‐FT RECEPTACLE 1 VA/SQ‐FT 10000 VA
NET LOAD 10 KVA
OR
220.14(k)(1)
WITNESS & INTERVIEW
10 EA RECEPTACLE 180 VA 1800 VA
NET LOAD 1.8 KVA
SUSPECT PROCESSING & POLYGRAPH
5 EA RECEPTACLE 180 VA 900 VA
NET LOAD 0.9 KVA
PUBLIC WAITING & ADMIN
5 EA RECEPTACLE 180 VA 900 VA
NET LOAD 0.9 KVA
INTELLIGENCE ANALYSIS
5 EA RECEPTACLE 180 VA 900 VA
NET LOAD 0.9 KVA
RM106 DETACHMENT SGT
7 EA RECEPTACLE 180 VA 1260 VA
NET LOAD 1.26 KVA
RM107 SAC OFFICE
7 EA RECEPTACLE 180 VA 1260 VA
NET LOAD 1.26 KVA
RM 108 ASAC OFFICE
4 EA RECEPTACLE 180 VA 720 VA
NET LOAD 0.72 KVA
RM 109 DIGITAL MEDIA
8 EA RECEPTACLE 180 VA 1440 VA
NET LOAD 1.44 KVA
STORAGE
3 EA RECEPTACLE 180 VA 540 VA
NET LOAD 0.54 KVA
BREAK RM
4 EA RECEPTACLE 180 VA 720 VA
NET LOAD 0.72 KVA
RM 110/112 DRUG SUPPRESSION TEAM
9 EA RECEPTACLE 180 VA 1620 VA
NET LOAD 1.62 KVA
RM 111 MEETING ROOM
11 EA RECEPTACLE 180 VA 1980 VA
NET LOAD 1.98 KVA
RM 113 EVIDENCE PROCESSING
4 EA RECEPTACLE 180 VA 720 VA
NET LOAD 0.72 KVA
RM 114 EVIDENCE CONTROLE OFICE
LOAD CALCULATION (NEW)
4 EA RECEPTACLE 180 VA 720 VA
NET LOAD 0.72 KVA
RM 116 EVIDENCE STORAGE
14 EA RECEPTACLE 180 VA 2520 VA
NET LOAD 2.52 KVA
RM 117 GENERAL CRIMES
11 EA RECEPTACLE 180 VA 1980 VA
NET LOAD 1.98 KVA
RM 118 GENERAL CRIMES
13 EA RECEPTACLE 180 VA 2340 VA
NET LOAD 2.34 KVA
RM 119 SHOWER
2 EA RECEPTACLE 180 VA 360 VA
NET LOAD 0.36 KVA
TRAINING RM
81 EA RECEPTACLE 180 VA 14580 VA
NET LOAD 14.58 KVA
RESTROOMS
2 EA RECEPTACLE 180 VA 360 VA
NET LOAD 0.36 KVA
ELECTRICAL, TELECOM, & CATV
13 EA RECEPTACLE 180 VA 2340 VA
NET LOAD 2.34 KVA
GENERAL STORAGE
3 EA RECEPTACLE 180 VA 540 VA
NET LOAD 0.54 KVA
CORRIDORS & VEHICLE BAY
18 EA RECEPTACLE 180 VA 3240 VA
NET LOAD 3.24 KVA
SUBNET TOTAL LOAD 26.87 KVA
NEW MECHANICAL EQUIPMENT
SUPPLY FANS 131 VA
HEATHING AND VENTILATING 2378 VA
UNIT HEATER 264 VA
SUBNET TOTAL LOAD 2.8 KVA
EST. TOTAL LOAD 64.64 KVA
179 AMPS
FT
W
Designer
Z.SAM
Date 5/6/2020 Scale Not to Scale Drawing No.
Summary
WEST SIDE OF BUILDING
Scale: 1" = 25ft
EAST SIDE OF BUILDING
Scale: 1" = 25ft
Designer
Z.SAM
Date 5/6/2020 Scale Not to Scale Drawing No.
Summary
Statistics
Description Symbol Avg Max Min Max/Min Avg/Min
Calc Zone (RM101 VESTIBULE) 11.3 fc 13.6 fc 9.6 fc 1.4:1 1.2:1 Calc Zone (RM101 VESTIBULE)(EMERGENCY) 7.9 fc 9.5 fc 6.7 fc 1.4:1 1.2:1 Calc Zone (RM102 TOILET) 14.9 fc 16.3 fc 14.1 fc 1.2:1 1.1:1 Calc Zone (RM102 TOILET)(EMERGENCY) 10.4 fc 11.4 fc 9.9 fc 1.2:1 1.1:1 Calc Zone (RM103B UTILITY) 21.1 fc 23.8 fc 17.1 fc 1.4:1 1.2:1 Calc Zone (RM103B UTILITY)(EMERGENCY) 7.4 fc 11.6 fc 2.7 fc 4.3:1 2.7:1 Calc Zone (RM104 TOILET) 14.9 fc 16.3 fc 14.2 fc 1.1:1 1.0:1 Calc Zone (RM104 TOILET)(EMERGENCY) 10.4 fc 11.4 fc 9.9 fc 1.2:1 1.1:1 Calc Zone (RM105 SUSPECT INTERVIEW) 32.7 fc 39.7 fc 24.5 fc 1.6:1 1.3:1 Calc Zone (RM105 SUSPECT INTERVIEW)(EMERGENCY) 4.3 fc 8.2 fc 1.2 fc 6.8:1 3.6:1 Calc Zone (RM106 SUSPECT INTERVIEW) 33.1 fc 41.0 fc 23.8 fc 1.7:1 1.4:1 Calc Zone (RM106 SUSPECT INTERVIEW)(EMERGENCY) 4.4 fc 8.5 fc 1.2 fc 7.1:1 3.7:1 Calc Zone (RM107 SUSPECT INTERVIEW) 33.4 fc 40.3 fc 25.1 fc 1.6:1 1.3:1 Calc Zone (RM107 SUSPECT INTERVIEW)(EMERGENCY) 4.4 fc 8.3 fc 1.3 fc 6.4:1 3.4:1 Calc Zone (RM108 SUSPECT INTERVIEW) 33.4 fc 40.4 fc 25.0 fc 1.6:1 1.3:1 Calc Zone (RM108 SUSPECT INTERVIEW)(EMERGENCY) 4.4 fc 8.3 fc 1.3 fc 6.4:1 3.4:1 Calc Zone (RM109 SUSPECT PROCESSING) 35.8 fc 42.3 fc 28.1 fc 1.5:1 1.3:1 Calc Zone (RM109 SUSPECT PROCESSING)(EMERGENCY) 4.7 fc 8.7 fc 1.3 fc 6.7:1 3.6:1 Calc Zone (RM110 VESTIBULE) 11.2 fc 13.5 fc 9.5 fc 1.4:1 1.2:1 Calc Zone (RM110 VESTIBULE)(EMERGENCY) 7.9 fc 9.5 fc 6.6 fc 1.4:1 1.2:1 Calc Zone (RM111 SUSPECT INTERVIEW) 35.8 fc 41.9 fc 27.9 fc 1.5:1 1.3:1 Calc Zone (RM111 SUSPECT INTERVIEW)(EMERGENCY) 4.7 fc 8.7 fc 1.3 fc 6.7:1 3.6:1 Calc Zone (RM112 POLYGRAPH) 32.2 fc 39.8 fc 23.2 fc 1.7:1 1.4:1 Calc Zone (RM112 POLYGRAPH)(EMERGENCY) 4.3 fc 8.3 fc 1.3 fc 6.4:1 3.3:1 Calc Zone (RM113 CORRIDOR) 8.0 fc 9.7 fc 2.2 fc 4.4:1 3.6:1 Calc Zone (RM113 CORRIDOR)(EMERGENCY) 3.5 fc 5.7 fc 0.5 fc 11.4:1 7.0:1 Calc Zone (RM114 INTELLIGENCE ANALYSTS) 37.1 fc 44.5 fc 23.9 fc 1.9:1 1.6:1 Calc Zone (RM114 INTELLIGENCE ANALYSTS)(EMERGENCY) 5.0 fc 8.6 fc 2.0 fc 4.3:1 2.5:1 Calc Zone (RM115 ADMIN) 42.0 fc 50.6 fc 35.7 fc 1.4:1 1.2:1 Calc Zone (RM115 ADMIN)(EMERGENCY) 6.8 fc 8.2 fc 5.8 fc 1.4:1 1.2:1 Calc Zone (RM116 WAITING) 18.8 fc 21.5 fc 16.3 fc 1.3:1 1.2:1 Calc Zone (RM116 WAITING)(EMERGENCY) 5.0 fc 8.3 fc 2.7 fc 3.1:1 1.9:1 Calc Zone (RM117 DIGITAL MEDIA) 44.5 fc 51.9 fc 20.9 fc 2.5:1 2.1:1 Calc Zone (RM117 DIGITAL MEDIA)(EMERGENCY) 7.2 fc 9.5 fc 4.2 fc 2.3:1 1.7:1 Calc Zone (RM118 MECHANICAL) 28.5 fc 31.1 fc 27.1 fc 1.1:1 1.1:1 Calc Zone (RM118 MECHANICAL)(EMERGENCY) 0.0 fc 0.0 fc 0.0 fc N/A N/A Calc Zone (RM119 STORAGE) 27.1 fc 31.7 fc 22.6 fc 1.4:1 1.2:1 Calc Zone (RM119 STORAGE)(EMERGENCY) 4.4 fc 5.2 fc 3.7 fc 1.4:1 1.2:1 Calc Zone (RM120 BREAK ROOM) 17.6 fc 20.3 fc 14.0 fc 1.5:1 1.3:1 Calc Zone (RM120 BREAK ROOM)(EMERGENCY) 2.7 fc 4.1 fc 1.3 fc 3.2:1 2.1:1 Calc Zone (RM122 ASAC OFFICE) 39.1 fc 44.9 fc 30.9 fc 1.5:1 1.3:1 Calc Zone (RM122 ASAC OFFICE)(EMERGENCY) 6.2 fc 9.1 fc 3.0 fc 3.0:1 2.1:1 Calc Zone (RM123 CORRIDOR) 8.0 fc 10.7 fc 5.4 fc 2.0:1 1.5:1 Calc Zone (RM123 CORRIDOR)(EMERGENCY) 3.4 fc 6.3 fc 1.1 fc 5.7:1 3.1:1 Calc Zone (RM124 DETACHMENT SGT) 41.6 fc 47.0 fc 33.0 fc 1.4:1 1.3:1 Calc Zone (RM124 DETACHMENT SGT)(EMERGENCY) 6.6 fc 9.1 fc 3.5 fc 2.6:1 1.9:1 Calc Zone (RM125 SAC OFFICE) 33.2 fc 40.1 fc 22.1 fc 1.8:1 1.5:1 Calc Zone (RM125 SAC OFFICE)(EMERGENCY) 5.2 fc 8.4 fc 2.2 fc 3.8:1 2.4:1 Calc Zone (RM126 DRUG SUPPRESSION TEAM) 36.6 fc 45.6 fc 21.5 fc 2.1:1 1.7:1 Calc Zone (RM126 DRUG SUPPRESSION TEAM)(EMERGENCY) 5.8 fc 9.2 fc 2.3 fc 4.0:1 2.5:1 Calc Zone (RM128 MEETING ROOM) 33.8 fc 41.1 fc 24.9 fc 1.7:1 1.4:1 Calc Zone (RM128 MEETING ROOM)(EMERGENCY) 3.4 fc 8.0 fc 1.0 fc 8.0:1 3.4:1 Calc Zone (RM129 VEHICLE HOLDING) 61.1 fc 73.5 fc 46.1 fc 1.6:1 1.3:1 Calc Zone (RM129 VEHICLE HOLDING)(EMERGENCY) 3.9 fc 4.7 fc 2.6 fc 1.8:1 1.5:1 Calc Zone (RM130 CORRIDOR) 9.5 fc 13.7 fc 0.7 fc 19.6:1 13.6:1 Calc Zone (RM130 CORRIDOR)(EMERGENCY) 3.5 fc 5.7 fc 0.3 fc 19.0:1 11.7:1 Calc Zone (RM131 VESTIBULE) 7.8 fc 10.2 fc 5.0 fc 2.0:1 1.6:1 Calc Zone (RM131 VESTIBULE)(EMERGENCY) 2.9 fc 6.5 fc 0.2 fc 32.5:1 14.5:1 Calc Zone (RM132 EVIDENCE PROCESSING) 51.2 fc 65.7 fc 34.4 fc 1.9:1 1.5:1 Calc Zone (RM132 EVIDENCE PROCESSING)(EMERGENCY) 6.8 fc 9.5 fc 3.5 fc 2.7:1 1.9:1
Designer
Z.SAM
Date 5/6/2020 Scale Not to Scale Drawing No.
Summary
Statistics
Description Symbol Avg Max Min Max/Min Avg/Min
Calc Zone (RM133 EVIDENCE CONTROL) 34.8 fc 46.1 fc 24.6 fc 1.9:1 1.4:1 Calc Zone (RM133 EVIDENCE CONTROL)(EMERGENCY) 4.6 fc 8.5 fc 1.9 fc 4.5:1 2.4:1 Calc Zone (RM134 EVIDENCE STORAGE) 35.7 fc 42.1 fc 23.7 fc 1.8:1 1.5:1 Calc Zone (RM134 EVIDENCE STORAGE)(EMERGENCY) 6.7 fc 8.6 fc 4.8 fc 1.8:1 1.4:1 Calc Zone (RM135 ELECTRICAL ROOM) 26.2 fc 30.9 fc 20.7 fc 1.5:1 1.3:1 Calc Zone (RM135 ELECTRICAL ROOM)(EMERGENCY) 3.5 fc 5.2 fc 1.5 fc 3.5:1 2.3:1 Calc Zone (RM136 TER) 52.7 fc 59.5 fc 46.0 fc 1.3:1 1.1:1 Calc Zone (RM136 TER)(EMERGENCY) 3.3 fc 4.0 fc 2.5 fc 1.6:1 1.3:1 Calc Zone (RM137 CCTV/CATV) 52.1 fc 58.6 fc 47.5 fc 1.2:1 1.1:1 Calc Zone (RM137 CCTV/CATV)(EMERGENCY) 4.3 fc 5.0 fc 3.6 fc 1.4:1 1.2:1 Calc Zone (RM138 STORAGE) 17.9 fc 20.3 fc 15.1 fc 1.3:1 1.2:1 Calc Zone (RM138 STORAGE)(EMERGENCY) 2.3 fc 3.0 fc 1.3 fc 2.3:1 1.8:1 Calc Zone (RM139 SHOWER) 30.5 fc 41.3 fc 19.3 fc 2.1:1 1.6:1 Calc Zone (RM139 SHOWER)(EMERGENCY) 12.4 fc 16.3 fc 7.9 fc 2.1:1 1.6:1 Calc Zone (RM139B MECH) 20.7 fc 22.3 fc 19.1 fc 1.2:1 1.1:1 Calc Zone (RM139B MECH)(EMERGENCY) 5.4 fc 5.9 fc 5.0 fc 1.2:1 1.1:1 Calc Zone (RM140 GENERAL CRIMES) 39.5 fc 50.8 fc 22.4 fc 2.3:1 1.8:1 Calc Zone (RM140 GENERAL CRIMES)(EMERGENCY) 7.5 fc 11.2 fc 4.5 fc 2.5:1 1.7:1 Calc Zone (RM141 GENERAL CRIMES) 43.1 fc 51.7 fc 27.1 fc 1.9:1 1.6:1 Calc Zone (RM141 GENERAL CRIMES)(EMERGENCY) 7.8 fc 10.8 fc 4.8 fc 2.3:1 1.6:1 Calc Zone (RM142 WOMEN'S TOILET) 15.6 fc 20.6 fc 9.0 fc 2.3:1 1.7:1 Calc Zone (RM142 WOMEN'S TOILET)(EMERGENCY) 5.9 fc 8.9 fc 2.5 fc 3.6:1 2.4:1 Calc Zone (RM143 MEN'S TOILET) 17.9 fc 21.3 fc 12.7 fc 1.7:1 1.4:1 Calc Zone (RM143 MEN'S TOILET)(EMERGENCY) 6.7 fc 9.1 fc 3.3 fc 2.8:1 2.0:1 Calc Zone (RM144 1ST STEP) 4.4 fc 4.4 fc 4.4 fc 1.0:1 1.0:1 Calc Zone (RM144 1ST STEP)(EMERGENCY) 3.1 fc 3.1 fc 3.1 fc 1.0:1 1.0:1 Calc Zone (RM144 2ND STEP) 4.9 fc 4.9 fc 4.9 fc 1.0:1 1.0:1 Calc Zone (RM144 2ND STEP)(EMERGENCY) 3.5 fc 3.5 fc 3.5 fc 1.0:1 1.0:1 Calc Zone (RM144 TOP STEP) 7.1 fc 7.4 fc 6.7 fc 1.1:1 1.1:1 Calc Zone (RM144 TOP STEP)(EMERGENCY) 5.2 fc 5.5 fc 4.9 fc 1.1:1 1.1:1 Calc Zone (RM1443RD STEP) 5.5 fc 5.5 fc 5.5 fc 1.0:1 1.0:1 Calc Zone (RM1443RD STEP)(EMERGENCY) 4.0 fc 4.0 fc 4.0 fc 1.0:1 1.0:1 Calc Zone (TRAINING ROOM 1ST STEP) 66.4 fc 77.3 fc 49.8 fc 1.6:1 1.3:1 Calc Zone (TRAINING ROOM 1ST STEP)(EMERGENCY) 5.5 fc 6.5 fc 3.4 fc 1.9:1 1.6:1 Calc Zone (TRAINING ROOM 2ND STEP) 64.8 fc 76.5 fc 48.1 fc 1.6:1 1.3:1 Calc Zone (TRAINING ROOM 2ND STEP)(EMERGENCY) 5.4 fc 6.5 fc 3.6 fc 1.8:1 1.5:1 Calc Zone (TRAINING ROOM 3RD STEP) 70.1 fc 83.0 fc 48.9 fc 1.7:1 1.4:1 Calc Zone (TRAINING ROOM 3RD STEP)(EMERGENCY) 5.9 fc 7.3 fc 3.1 fc 2.4:1 1.9:1 Calc Zone (TRAINING ROOM FLOOR) 56.2 fc 71.9 fc 34.7 fc 2.1:1 1.6:1 Calc Zone (TRAINING ROOM FLOOR)(EMERGENCY) 4.6 fc 5.9 fc 2.4 fc 2.5:1 1.9:1 Calc Zone (TRAINING ROOM TOP STEP) 60.6 fc 80.4 fc 33.1 fc 2.4:1 1.8:1 Calc Zone (TRAINING ROOM TOP STEP)(EMERGENCY) 5.5 fc 10.6 fc 2.3 fc 4.6:1 2.4:1 Calc Zone Calc Zone (RM144 FLOOR) 5.9 fc 7.8 fc 4.0 fc 2.0:1 1.5:1 Calc Zone Calc Zone (RM144 FLOOR)(EMERGENCY) 2.7 fc 4.5 fc 0.4 fc 11.3:1 6.8:1
Designer
Z.SAM
Date 5/6/2020 Scale Not to Scale Drawing No.
Summary
WEST SIDE OF BUILDING - GENERAL LIGHTING
Scale: 1" = 14ft
Designer
Z.SAM
Date 5/6/2020 Scale Not to Scale Drawing No.
Summary
EAST SIDE OF BUILDING - GENERAL LIGHTING
Designer
Z.SAM
Date 5/6/2020 Scale Not to Scale Drawing No.
Summary
WEST SIDE OF BUILDING - EMERGENCY LIGHTING
Designer
Z.SAM
Date 5/6/2020 Scale Not to Scale Drawing No.
Summary
EAST SIDE BUILDING - EMERGENCY LIGHTING
Designer
Z.SAM
Date 5/6/2020 Scale Not to Scale Drawing No.
Summary
Schedule
Symbol Label Quantity Manufacturer Catalog Number Description Lamp Number
Lamps Filename Lumens Per Lamp
Light Loss Factor Wattage
A
20 Lithonia Lighting
2BLT4 72L
ADPT LP840
BLT 2X4, 7200
Nominal Lumens, Curved Linear Prismatic lens with trim rings, 4000K CCT
1 2BLT4_72L_AD
PT_LP840.ies
7262.246 0.8 58.74
B
26 Lithonia Lighting
2BLT4 48L
ADPT LP840
BLT 2X4, 4800
Nominal Lumens, Curved Linear Prismatic lens with trim rings, 4000K CCT
1 2BLT4_48L_AD
PT_LP840.ies
4971.805 0.8 37.63
C
16 Lithonia Lighting
BLWP4 15L
ADPT LP840
BLWP 4ft 1500 Nominal Lumens, Curved Linear Prismatic lens with trim rings, 4000K CCT, 80CRI
LED 1 BLWP4_15L_A
DPT_LP840.ies
1419.636 0.8 10.83
D
8 Lithonia Lighting
2BLT4 85L
ADPT LP840
BLT 2X4, 8500
Nominal Lumens, Curved Linear Prismatic lens with trim rings, 4000K CCT
1 2BLT4_85L_AD
PT_LP840.ies
8587.392 0.8 73.58
E 2 Lithonia
Lighting
WF8 LED 40K
MVOLT 90CRI
8" ROUND
WAFER 4000K
120-277V
LED 1 WF8_LED_40K
_MVOLT_90CR
I.ies
1628.723 0.8 19.67
F
64 Lithonia Lighting
2BLT4 40L
ADPT LP840
BLT 2X4, 4000
Nominal Lumens, Curved Linear Prismatic lens with trim rings, 4000K CCT
1 2BLT4_40L_AD
PT_LP840.ies
4009.521 0.8 30.99
G
28 Lithonia Lighting
BLT4 15L ADPT
LP840
BLT 1X4, 1500
Nominal Lumens, Curved Linear Prismatic lens with trim rings, 4000K CCT
1 BLT4_15L_ADP
T_LP840.ies
1429 1 11.06
Designer
Z.SAM
Date 5/6/2020 Scale Not to Scale Drawing No.
Summary
Schedule
Symbol Label Quantity Manufacturer Catalog Number Description Lamp Number
Lamps Filename Lumens Per Lamp
Light Loss Factor Wattage
B-EM
14 Lithonia Lighting
2BLT4 48L
ADPT LP840
BLT 2X4, 4800
Nominal Lumens, Curved Linear Prismatic lens with trim rings, 4000K CCT
1 2BLT4_48L_AD
PT_LP840.ies
4971.805 0.21 10
A-EM
11 Lithonia Lighting
2BLT4 72L
ADPT LP840
BLT 2X4, 7200
Nominal Lumens, Curved Linear Prismatic lens with trim rings, 4000K CCT
1 2BLT4_72L_AD
PT_LP840.ies
7262.246 0.13 10
C-EM
9 Lithonia Lighting
BLWP4 15L
ADPT LP840
BLWP 4ft 1500 Nominal Lumens, Curved Linear Prismatic lens with trim rings, 4000K CCT, 80CRI
LED 1 BLWP4_15L_A
DPT_LP840.ies
1419.636 0.6 10
D-EM
4 Lithonia Lighting
2BLT4 85L
ADPT LP840
BLT 2X4, 8500
Nominal Lumens, Curved Linear Prismatic lens with trim rings, 4000K CCT
1 2BLT4_85L_AD
PT_LP840.ies
8587.392 0.1 10
F-EM
33 Lithonia Lighting
2BLT4 40L
ADPT LP840
BLT 2X4, 4000
Nominal Lumens, Curved Linear Prismatic lens with trim rings, 4000K CCT
1 2BLT4_40L_AD
PT_LP840.ies
4009.521 0.25 10
G-EM
17 Lithonia Lighting
BLT4 15L ADPT
LP840
BLT 1X4, 1500
Nominal Lumens, Curved Linear Prismatic lens with trim rings, 4000K CCT
1 BLT4_15L_ADP
T_LP840.ies
1429 0.7 10
H 1 Lithonia
Lighting
LHQM LED QUANTUM LED
EMERGENCY
COMBO (ONE
HEAD ONLY)
1 LHQM_LED.ies Absolute 0.8 3
Electrical
Cut Sheets