About this file
This is an elevator modernization specification document prepared by the State of Colorado, Office of the State Architect, for the Annex Building located at 1375 Sherman Street in Denver, Colorado (Project 2024-024P23-01CA). The scope of work encompasses the modernization of three passenger elevators and one freight/service elevator. The three passenger elevators will be upgraded to operate at 350 feet per minute with 2,500-pound capacity, serving eight to nine floors with stops marked SB, B, 1-7. Key components include replacement of Westinghouse gearless hoist machines with new Permanente Magnet AC gearless units, installation of new microprocessor controllers with A17.1 2022 compliance, new ReGen VVVF motor drive units, and new Hollister-Whitney Type "B" safeties. The freight elevator will retain its 100 feet per minute speed and 4,000-pound capacity while receiving a new PM AC gearless hoist machine, programmable microprocessor controller, new ReGen motor drive unit, and upgraded hoistway components. Both elevator systems will receive new traveling cables, wiring, hall pushbutton stations with LED illumination, digital position indicators, safety edges, and modernized cab interiors with finishes selected by the owner.
The specification document provides a comprehensive equipment summary and outlines work to be performed across the hoistway, machine room, car, pit, and signal fixtures for all four elevators. Notable retention items include existing hoistway door tracks, closers, interlocks, governors (to be relocated), compensation sheaves, oil buffers, and hall lantern faceplates. New installations include Elsco roller guides, Janus 3D safety edges, satin finish bronze car door panels, new flooring with green/black marble design, LED lighting fixtures, and code-compliant inspection stations. The document emphasizes that this summary serves as a general outline and that the complete technical specifications document should take precedence in case of discrepancies. The project document is dated June 12, 2026, and references the current ASME A17.1 2022 code standards for all modernized elevator systems.
View the file
Other files
Show all 12
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
State of Colorado - Annex Building 1375 Sherman Street
Elevator Modernization Specifications Denver, CO 80203
State of Colorado – Office of the State Architect June 12, 2026
Project: 2024-024P23-01CA
2.01 GEARLESS PASSENGER ELEVATOR SCHEDULE/EQUIPMENT SUMMARY (1)
Three (3) Pass. Elevators Existing After Modernization
Description:
Speed/Capacity 500 FPM @ 2,500 Lbs. 350 FPM @ 2,500 Lbs.
Stops/Openings Cars 1 & 3 Eight (8) Floors - Car 2 Nine (9) Floors {Marking: SB, B, 1, 2, 3, 4, 5,6,7}
Travel: Approximately 110 feet Contractor to verify
Operation Triplex Operation Microprocessor – Three (3) Car Group
Machine Room:
Hoist Machine Remove the existing Westinghouse Gearless Hoist Machines and install new Permanente
Magnet AC Gearless Hoist Machines with Auxiliary Brake. Clean and paint Machine.
Hoist Ropes 6 – ½ inch Double Wrap – 2:1. Install new Hoist Cables
Controller Provide new 3 Car Group Microprocessor Controllers. (A17.1 2022)
Power Conversion Provide new "ReGen" VVVF Motor Drive Unit.
Governors Retain and relocate the existing Hollister-Whitney Governors from the Secondary Level, up to the Elevator Machine Room. Retain the existing Governor Tension Sheave and in-stall new Governor Cable.
Hoistway:
Hoistway Door equipment Clean and retain the existing hoistway door tracks, closers, interlocks, pickup rollers, and door gibs. Replace worn Rollers and Closers. Retain existing hoistway door panels
Hoistway Doors & En-trances
Clean and refinish the existing hoistway entrances and hoistway door panels
Hoistway limit switches Install new TLS Slowdown, ETS, and Limit Switches.
Car & Cwt Rails Realign as needed for smooth/quiet ride.
Wiring/Duct Install new traveling cables, hoistway, and machine room wiring.
Car & Cwt. Roller Guides Install new Elsco Type “A” Tandem Car Roller Guides and new Elsco Type “D” Cwt
Roller Guides.
Safeties Remove the existing Wind-Up Safeties and install new Hollister-Whitney Type “B” Safe-ties.
Car:
Car-top-control Provide new
Door Operator Clean, lubricate, and adjust the existing GAL – MOVFR Car Operators.
Car Door Panels Install new #4 satin finish Bronze Car Door Panels, Tracks, Hanger Rollers, Headers, and
Gate Switch.
Safety Edge Provide new Janus 3D or approved equal.
Top of Car Railing Provide per current code
Elevator Cab: Refinish the existing #4 satin finish Bronze Front Return Transom, Trim, Reveals, Base Plates, and
Bronze Cab interior. Install new Rear and Side Plastic laminated Panels (7 each) similar in design as the existing. Paint the Cab Ceiling. Install new “Green/Black Marble” flooring similar to First Floor design. Clean and refinish the existing bronze circular Handrails. Owner to select final finishes. Provide two (2) sets of Cab Pads and Cab Hooks
Pit:
Stop Switch Provide in compliance with code.
Compensation Sheave Retain the existing Comp Sheave and Comp Cables
Buffers Retain the existing Oil Buffers. Clean and paint.
Signal Fixtures
Car Operating Panel Provide new Main and Auxiliary COP. A17.1 2022 compliant with a 4X4 “Smoked
Glass” cutout/window for a Security Card Reader. Provide Digital PI’s.
Hall PB Station Install new A17.1 - 2022 compliant LED illuminated Hall Pushbutton fixtures at each floor. Install new three position Firefighters’ key switch, Operating Instructions, Emer-gency Power indicator “Jewel”, and "Communication Failure" indicator at First Floor.
Hall Lanterns Retain the existing Hall Lantern faceplates on each floors and install new electronic
Chimes and LED illumination. Retain the existing 1st floor “In Line” Position Indicators.
State of Colorado - Annex Building 1375 Sherman Street
Elevator Modernization Specifications Denver, CO 80203
State of Colorado – Office of the State Architect June 12, 2026
Project: 2024-024P23-01CA
Hoistway Access SWs. Provide Top and Bottom Hoistway Access per code
2.02 FREIGHT/SERVICE ELEVATOR SCHEDULE/EQUIPMENT SUMMARY (1)
Freight Elevator # S-4 Existing After Modernization
Description:
Quantity 1 1
Speed/Capacity 100 FPM / 4,000 Lbs. 100 FPM / 4,000 Lbs.
Stops/Openings 9 front Center Openings. Floor Marking: SB, B, *1, 2, 3, 4, 5, 6, 7
Operation Simplex Simplex Operation with Emergency Power
Machine Room:
Machine Install a new PM AC Gearless Hoist Machine with Main and Emergency Brake.
Controller Provide new programmable microprocessor controllers. A17.1- 2022 compliant.
Power Conversion Provide new "ReGen" VVVF Motor Drive Unit.
Governor and Tail Sheave Retain the existing Hollister-Whitney Governor and Governor Tension Sheave. Install new Governor Cable.
Hoistway:
Overhead Deflector Sheave Install new Machine Room mounted Deflector Sheave.
Hoistway Entrances, and
Door Panels
Retain the existing Hoistway Entrances and Door Panels.
Hoistway Door Equipment Clean, lubricate, adjust and replace worn Hoistway Door Tracks, Hanger Rollers, Inter-locks, Closers, Retainers, Door Gibs, Fire-Stops, and Pick-Up Rollers.
Car Door Operator & Car
Door Panels
Clean, lubricate, and adjust the existing GAL-MOVFR Car Door Operator, Header, Linkage, Clutch, Restrictor, Retainers, Gibs, Install new Bronze Car Door Panels.
Car & Cwt Guide Shoes Install new Car and Counterweight Rollers.
Wiring/Duct Provide all new wiring and duct.
Counterweight Add/Remove weight for properly balance
Car:
Car Top Control Install new Inspection Station and Top of Car Controls.
Cab Interiors Retain the existing Elevator Cab Interiors. Clean and Paint Cab walls and Ceiling.
Install new aluminum Car Sill. Install new aluminum “Boiler Plate flooring. Refasten
Cab Handrails and Bumper Rails. Remove the existing Cab Light fixture and install a metal cover. Install two (2) new 48-inch double LED Light Fixtures at the top of each
Side Wall Panels
Car Sling, Platform, Safeties
Retain existing Car Sling, and Type “A” Safeties. Replace worn Safeties. Clean, lubri-cate, adjust, and paint.
Top of Car Railing Provide per current code
Pit:
Ladder & Stop Switch Provide new in accordance with ASME 17.1 2022 code.
Hoistway Illumination Provide new Manual and Automatic Hoistway Illumination in compliance with code.
Buffers Refurbish as needed. Clean and paint.
Signal Fixtures
Car Operating Panel Install new Main COP w/ digital PI. A17.1 2022 compliant.
Hall Call Fixtures Retain the existing Hall Push Button Sstations.
Hall Lanterns Install new dual Car Traveling Lanterns. Replace existing 1st floor Hall Station with
Code compliant Hall Pushbutton Station.
Hoistway Access Sws. Provide Top and Bottom Hoistway Access per code
(1) Summary is just a brief outline to give general scope of work. If a discrepancy exists between the summary and body of the technical specifications, or if an item is not included in the summary, the body of the technical specifications should take precedence.