Attachment 17 Project Implementation Schedule.xlsx

XLSX spreadsheet 29 KB Posted

Attached to
Electric Vehicle Charging Program RFP 3
Solicitation number
RFP 605 2500000072 2
Issued by
Kentucky

About this file

This is a Project Implementation Schedule template for an electric vehicle supply equipment (EVSE) installation project, designed to be completed by proposers responding to a state or local contract opportunity. The schedule requires proposers to provide estimated start dates, duration in days, and responsible parties for each task across six major project phases. Task 0 covers pre-agreement activities including site host agreement, bonds, insurance, and environmental clearance. Task 1 addresses pre-design work such as final agreements and site planning. Task 2 encompasses design and permitting activities including utility agreements, final site plans, and commissioning plans. Task 3 involves construction work including site upgrades, EVSE installation, testing, and customer service system implementation. Task 4 establishes a five-year operations and maintenance phase with quarterly and annual reporting requirements, uptime reporting, and cybersecurity event notification obligations. Task 6 addresses final invoicing. The contract term extends a minimum of five years from the operations and maintenance phase start date, with quarterly reports due one month after each quarter ends and annual reports due March 1 following each contract year.

Proposers must submit the completed schedule as an Excel file (.XLSX format) rather than a PDF, with all dates in subsequent tasks occurring after the completion of preceding tasks. The schedule template includes optional invoicing tasks within design and pre-design phases and allows for additional construction detail lines if needed. The document does not specify pricing terms, set-asides, funding amounts, or sources, as this is a scheduling and planning tool intended to ensure sequential and logical project execution across all implementation phases.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Cover Sheet

Attachment 17 Project Implementation Schedule
Site Information
Proposer Name:
Designated Zone:
Exit Number:
Proposal Number:
Guidance & Recommendations
Please provide an estimate for when you will begin each task, how many days you expect each task to take, and what team (or subcontractor) will be beforming the task.
Instructions
Complete the light blue boxes on this tab. Then on the "Project Schedule" tab of this spreadsheet, fill in the project start date at the top and then fill in each light blue boxes next to each task. When completed, please submit this file as an XLSX file and not a PDF.

Project Schedule

Project Implementation Schedule Project Start:

TaskActivityParty/Team Completing TaskSTART# of DaysENDDAYS
ERROR:#NUM!ERROR:#NUM!3/1/06ERROR:#NUM!
Task 0Pre-AgreementERROR:#NUM!ERROR:#NUM!12/31/99ERROR:#NUM!
0.0Draft Site Host Agreement12/31/99
0.1Draft Payment and Performance Bonds12/31/99
0.2Project Confirmation12/31/99
0.3Project Schedule (this document)12/31/99
0.4Utility Information12/31/99
0.5Proof of Insurance12/31/99
0.6EVSE Vendor Information and Specifications12/31/99
0.7Buy America (BA) / Buy America, Build America (BABA)12/31/99
0.8Environmental Clearance (NEPA)12/31/99
Task 1Pre-Design (DATES IN THIS SECTION MUST BE AFTER TASK 0)ERROR:#NUM!ERROR:#NUM!12/31/99
1.0Notification of Pre-Construction Work12/31/99
1.1Final Site Host Agreement12/31/99
1.2Final Payment and Performance Bonds12/31/99
1.3Final Proof of Insurance12/31/99
1.4Project Information & Draft Site Plan12/31/99
1.5Invoicing (THIS TASK IS OPTIONAL)12/31/99
Task 2Design (DATES IN THIS SECTION MUST BE AFTER TASK 1)ERROR:#NUM!ERROR:#NUM!12/31/99
2.0Notification of Final Design and Permitting Work12/31/99
2.1Utility Agreement12/31/99
2.2Final Site Plan12/31/99
2.3Item Summary12/31/99
2.4Permitting12/31/99
2.5Final EVSE Information12/31/99
2.6Operations and Maintenance Plan12/31/99
2.7EVSE Commissioning Plan and Test Report12/31/99
2.8Quality Control Plan12/31/99
2.9Invoicing (THIS TASK IS OPTIONAL)12/31/99
Task 3Construction (DATES IN THIS SECTION MUST BE AFTER TASK 2)ERROR:#NUM!ERROR:#NUM!12/31/99
3.0Pre-Constructioon Conference and Notification of Construction Work12/31/99
3.1Project Site Upgrades (Construction Work)12/31/99
If details of construction are known, please add additional lines for them.12/31/99
3.2EVSE Installation12/31/99
3.3EVSE Commissioning and Testing12/31/99
3.4Site Inspection12/31/99
3.5NACS Connectors (if not included with 3.2)12/31/99
3.6Customer Service System12/31/99
3.7Invoicing12/31/99
Task 4Operations & Maintenance (DATES IN THIS SECTION MUST BE AFTER TASK 3)12/31/9922523/1/06
4.0Notification of Operations and Maintenance Work12/31/99
4.1Operations & Maintenance (this will continue for 5 years)12/31/99182612/30/04
4.2Uptime Reporting4/30/0017331/26/05
Quarterly Reporting 1 (Quarterly reports are due one month after the end of each quarter)4/30/004/30/00
Quarterly Reporting 27/29/007/29/00
Quarterly Reporting 310/28/0010/28/00
Quarterly Reporting 41/27/011/27/01
Quarterly Reporting 54/28/014/28/01
Quarterly Reporting 67/29/017/29/01
Quarterly Reporting 710/28/0110/28/01
Quarterly Reporting 81/27/021/27/02
Quarterly Reporting 94/28/024/28/02
Quarterly Reporting 107/29/027/29/02
Quarterly Reporting 1110/28/0210/28/02
Quarterly Reporting 121/27/031/27/03
Quarterly Reporting 134/28/034/28/03
Quarterly Reporting 147/29/037/29/03
Quarterly Reporting 1510/28/0310/28/03
Quarterly Reporting 161/27/041/27/04
Quarterly Reporting 174/27/044/27/04
Quarterly Reporting 187/28/047/28/04
Quarterly Reporting 1910/27/0410/27/04
Quarterly Reporting 201/26/051/26/05
Annual Reporting 1 (Annual reports are due 3/1 after the end of the year)3/1/013/1/01
Annual Reporting 23/1/023/1/02
Annual Reporting 33/1/033/1/03
Annual Reporting 42/29/042/29/04
Annual Reporting 53/1/053/1/05
Annual Reporting 6 (if applicable)3/1/063/1/06
4.3Cybersecurity Event Notification (as required)N/AN/AN/AN/A
4.4Reporting (LEAVE BLANK IF THESE DATES ARE THE SAME AS 4.2)4/30/0017341/27/05
Quarterly Reporting 14/30/004/30/00
Quarterly Reporting 27/30/007/30/00
Quarterly Reporting 310/29/0010/29/00
Quarterly Reporting 41/28/011/28/01
Quarterly Reporting 54/30/014/30/01
Quarterly Reporting 67/30/017/30/01
Quarterly Reporting 710/29/0110/29/01
Quarterly Reporting 81/28/021/28/02
Quarterly Reporting 94/30/024/30/02
Quarterly Reporting 107/30/027/30/02
Quarterly Reporting 1110/29/0210/29/02
Quarterly Reporting 121/28/031/28/03
Quarterly Reporting 134/30/034/30/03
Quarterly Reporting 147/30/037/30/03
Quarterly Reporting 1510/29/0310/29/03
Quarterly Reporting 161/28/041/28/04
Quarterly Reporting 174/29/044/29/04
Quarterly Reporting 187/29/047/29/04
Quarterly Reporting 1910/28/0410/28/04
Quarterly Reporting 201/27/051/27/05
Annual Reporting 13/1/013/1/01
Annual Reporting 23/1/023/1/02
Annual Reporting 33/1/033/1/03
Annual Reporting 42/29/042/29/04
Annual Reporting 53/1/053/1/05
Annual Reporting 6 (if applicable)3/1/063/1/06
4.5Invoicing12/31/99
Task 5NO INFORMATION REQUIRED.
Task 6Final Invoicing (DATES IN THIS SECTION MUST BE AFTER TASK 4)
6.0Final Invoice3/1/063/1/06

Insert new rows ABOVE this one