Attachment 15 668-18-109_Contractor Qualification Standards for Construction Services_R3.pdf

PDF 159 KB Posted

Attached to
Y1DA--CON-NRM 668-18-109 Refurbish and Upgrade Elevators in Bldg 1 and 27 Taminie Panich
Solicitation number
36C26024R0009
Issued by

About this file

This document outlines qualification standards for construction services for Project 668-18-109 to refurbish and upgrade elevators in Buildings 1 and 27 at the MannGrandstaff VA Medical Center in Spokane, WA. Key requirements include the general contractor having a CQC system manager with a bachelor's degree in engineering, construction management, or architecture and 5 years' experience as a CQC manager on similar projects. The project superintendent and alternate must have 5 years' experience as superintendents on comparable projects. Elevator contractors must have 10 years' experience and mechanics 5 years' experience, with all mechanics holding appropriate certifications. Welding and electrical work must be done by certified personnel. Offerors must demonstrate experience on projects meeting the criteria outlined in the document.

View the file

Other files

Show all 19

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Project 668-18-109, Refurbish and Upgrade Elevators in Bldg 1 and 27 Page 1 of 3

QUALIFICATION STANDARDS FOR CONSTRUCTION SERVICES

Refurbish and Upgrade Elevators in Bldg 1 and 27

Project No. 668‐18‐109 Mann‐Grandstaff VA Medical Center

Spokane, WA August 15, 2023

1. Example projects shall include the following information:

1.1. Project title and location.

1.2. Original contract award amount.

1.3. Original contract finish date.

1.4. Points of Contact:

1.4.1. Point of Contact (POC) as well as two alternate Points of Contact, to include the name, job title of the POC, address, telephone, and e‐mail address. The POC and alternates shall be familiar with the construction performance of the proposer and be a representative of the owner/customer, not affiliated with the proposer. The POC and alternates shall be able to verify the experience cited.

1.5. Role of the proposing firm on the project, including a clear designation of whether the Offeror was the prime contractor.

1.6. Personnel on the project that are proposed to be utilized for this project.

2. Qualifications

2.1. Contractor shall submit certificates stating the following:

2.1.1. Elevator contractor is currently and regularly engaged in the installation of elevator equipment as one of his/her principal products.

2.1.2. Elevator contractor shall have ten (10) years of successful experience, trained supervisory personnel, and facilities to install elevator equipment required by this contract.

2.1.2.1. Provide at least three (3) example projects the elevator contractor has completed in the past ten (10) years. Projects submitted shall include the following:

new elevator installation, traction elevator with at least six (6) stops, hydraulic elevator with at least three (3) stops.

2.1.2.1.1. Each project submitted does not need to feature all these criteria, but the three (3) submitted projects together need to feature all these criteria.

2.1.3. Elevator contractor is currently and regularly engaged in the maintenance of elevator equipment as one of his/her principal products and shall maintain elevators until Government acceptance. Maintenance services shall be rendered within one hour of receipt of notification. Contractor maintains the quantity and quality of replacement parts in stock necessary to warranty continued operation of the elevator installation.

2.2. Elevator mechanics (installer) shall have at least five (5) years (post apprenticeship) of successful experience, trained supervisory experience, and be appropriately certified. This requirement applies to any elevator mechanic that works on the MGVAMC elevators.

Certificates shall be submitted for all workers employed in this capacity.

2.2.1. All elevator mechanics shall be licensed.

Project 668-18-109, Refurbish and Upgrade Elevators in Bldg 1 and 27 Page 2 of 3

2.2.2. All elevator mechanics shall be licensed technicians who are approved through the National Association of Elevator Contractors (NAEC) as (CET) Certified Elevator Technicians.

2.2.3. All elevator mechanics shall provide a certificate of completion indicating they have successfully passed a Mechanic Examination approved by the U.S. Department of Labor, or a certificate of completion of a registered apprenticeship program.

2.2.4. Elevator Apprentices shall be involved in the (CET) Training Program.

2.3. Welding at the project site shall be performed by certified welders who have previously qualified by test as prescribed in American Welding Society Publications AWS Dl.1 to perform the type of work required. Certificates shall be submitted for all workers employed in this capacity.

2.4. Electrical work shall be performed by a Licensed Master Electrician and Licensed Journeymen Electricians as requirements by NEC. Certificates shall be submitted for all workers employed in this capacity.

2.5. Approval will not be given to elevator contractors who have established on prior projects, either government, municipal, or commercial, a record of unsatisfactory elevator installations or do not have the requisite record of satisfactory performing elevator installations of similar type and magnitude.

3. Quality Control

3.1. Identify as Contractor Quality Control (CQC) System Manager an individual within the onsite work organization that is responsible for overall management of CQC and has the authority to act in all CQC matters for the Contractor.

3.1.1. The CQC system manager is on the site at all times during construction and is employed by the General Contractor.

3.1.2. The CQC system manager is required to have a bachelor’s degree in Engineering, Construction Management, or Architecture from an accredited university.

3.1.3. The CQC system manager is required to have a minimum of 5 years’ experience (within the last 10 years) performing as a CQC system manager on projects similar in monetary size and/or scope to this project.

3.1.3.1. Provide qualifications (in resume format). Include information regarding bachelor’s degree.

3.1.3.2. Provide at least two (2) projects, which included elevator work, completed in the past ten (10) years for which the proposed person served as the CQC system manager. Projects submitted shall include the following: a new elevator installation and an elevator with at least six (6) stops.

3.1.3.2.1. Each project submitted does not need to feature all these criteria, but the two (2) submitted projects together need to feature all these criteria.

3.1.3.3. Provide certificate of completion from the Construction Quality Management (CQM) for Construction course. This course is periodically offered by the Naval Facilities Engineering Command and the Army Corps of Engineers.

4. Project Superintendent

4.1. Identify the project superintendent for this project.

4.1.1. The project superintendent is on the site at all times during construction and is employed by the General Contractor.

Project 668-18-109, Refurbish and Upgrade Elevators in Bldg 1 and 27 Page 3 of 3

4.1.2. The project superintendent is required to have a minimum of 5 years’ experience (within the last 10 years) performing as a project superintendent on projects similar in monetary size and/or scope to this project.

4.1.2.1. Provide qualifications (in resume format).

4.1.2.2. Provide at least two (2) projects, which included elevator work, completed in the past ten (10) years for which the proposed person served as the project superintendent. Projects submitted shall include the following: a new elevator installation and an elevator with at least six (6) stops.

4.1.2.2.1. Each project submitted does not need to feature all these criteria, but the two (2) submitted projects together need to feature all these criteria.

4.2. Identify the project superintendent alternate for this project.

4.2.1. The project superintendent alternate is employed by the General Contractor.

4.2.2. The project superintendent alternate is required to have a minimum of 5 years’ experience

(within the last 10 years) performing as a project superintendent on projects similar in monetary size and/or scope to this project.

4.2.2.1. Provide qualifications (in resume format).

4.2.2.2. Provide at least one (1) project, which included elevator work, completed in the past ten (10) years for which the proposed person served as the project superintendent. Projects submitted shall include the following: a new elevator installation.

5. Site Safety and Health Officer (SSHO)

5.1. Identify the SSHO for this project.

5.1.1. The SSHO is on the site at all times during construction and is employed by the General

Contractor.

5.1.2. The SSHO is required to have a minimum of 5 years’ experience (within the last 10 years) performing as the SSHO on projects similar in monetary size and/or scope to this project.

5.1.2.1. Provide qualifications (in resume format).

5.1.2.2. Provide at least one (1) project, which included elevator work, completed in the past ten (10) years for which the proposed person served as the SSHO. Projects submitted shall include the following: a new elevator installation.

6. Changes to Personnel

6.1. Replacement personnel shall be required to have qualifications and experience meeting or exceeding those identified in the Contractor’s original proposal. The Contractor shall obtain the Contracting Officer's written consent before making any substitutions for the personnel designated in the Contractor’s original proposal.