ATTACHMENT 14 Pay Terms Bid Schedule-Price Schedule.docx
DOCX document 42 KB Posted
- Solicitation number
- W912GB23R0005
- Issued by
-
Department of the Army European Command
About this file
This document includes an attachment related to pricing terms for a design-build construction contract solicitation for the construction and renovation of Ntsasa Primary School in Pumlani, South Africa. The solicitation requires the contractor to complete the entire work ready for use within 455 calendar days of receiving the notice to proceed, and includes liquidated damages of $426 per day for each calendar day of delay in completion. The estimated magnitude of construction is between $500,000 and $1,000,000. The solicitation is issued by the Department of the Army European Command and contemplates award of a single firm-fixed price contract using a best value tradeoff acquisition method under full and open competition in US dollars. Pricing is required for base items including construction of one 5-classroom building and renovation of an existing children's latrine building, as well as an option for construction of a kitchen building.
View the file
Other files
Show all 23
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
POP and LD Clauses
SECTION 01 22 00
PRICE AND PAYMENT PROCEDURES
01/21
PART 1 GENERAL
PAYMENT TYPES
The costs for performance of any work required by the contract which is not associated with a specific base or option item description shall be included in the first base item (Base Item 0001).
Single Job Payment Items
Payment items for the work of this contract for which contract lump sum payments will be made are listed in the PRICE SCHEDULE and described below. All costs for items of work, which are not specifically mentioned to be included in a particular job or unit price payment item, are included in the listed job item most closely associated with the work involved.
The job price and payment made for each item listed constitutes full compensation for furnishing all plant, labor, materials, and equipment, and performing any associated Contractor quality control, environmental protection, meeting safety requirements, tests and reports, and for performing all work required for which separate payment is not otherwise provided.
SCHEDULE OF ITEMS: BASE ITEMS
Base Item 0001: Construct one (1) 5-classroom Building
Unit of Measure: Job.
Payment will be made for costs associated with the design and construction for one (1) 5-classroom buildings as indicated in the SECTION 01 10 10 and shown on the conceptual layout, with the exceptions of the bid options listed below. This work shall include all applicable demolition and removals work to support the work elements contained in this item.
Base Item 0002: Renovation of Existing Children’s Latrine Building
Unit of Measure: Job.
Payment will be made for costs associated with the design and renovation of the existing children’s latrine building as indicated in SECTION 01 10 10 and the conceptual layout, with the exceptions of the bid options listed below. This work shall include all applicable demolition and removals work to support the work elements contained in this item.
SCHEDULE OF ITEMS: OPTION ITEMS
Option 1: Item 0003: Construct Kitchen Building
Unit of Measure: Job.
Payment will be made for costs associated with the design and construction of the new kitchen building as indicated in SECTION 01 10 10 and the conceptual layout, with the exceptions of the bid options listed below.
PART 2 PRODUCTS
Not Used
PART 3 EXECUTION
Not Used
-- End of Section -
V7 Aug 2020
SECTION 01 22 00 Page 1 Offerors shall provide pricing for all base and option items.
The following items include providing all labor, materials, equipment, and services necessary to complete the design and construction of the work identified in the attached Plans, Specifications, Statement of Work (SOW), Solicitation/Request for Proposal. It also includes preparation of all documents, submittals, and schedules; inspections; and compliance with all technical, quality control, administrative, and safety requirements. All work shall be performed in accordance with these documents. Refer to Specification Section 01 22 00 Price and Payment Procedures for additional description of the work associated with each of the items.
Period of Performance: Refer to clause COMMENCEMENT PROSECUTION AND EXECUTION OF WORK (52.211-10) in the Solicitation/Request for Proposal for the period of performance for all base and option items.
Liquidated Damages: Refer to clause LIQUIDATED DAMAGES-CONSTRUCTION (52.211-12) in the Solicitation/Request for Proposal for the liquidated damages for all base and option items.
Option Items: The Government reserves the right to award the options up to 90 calendar days from contact award. See Section 01 22 00 for additional information regarding the award of options.
| Item No. |
| Description |
| Quantity |
| Unit |
| Unit Price |
| Amount |
BASE ITEMS
| 0001 |
| Construct one (1) 5-classroom Building |
| 1 |
| Job |
| $ |
| $ |
| 0002 |
| Renovation of Existing Children’s Latrine Building |
| 1 |
| Job |
| $ |
| $ |
| Total of Base Items 0001 thru 0002 |
| $ |
OPTION ITEMS
| 0003 |
| Construct Kitchen Building |
| 1 |
| Job |
| $ |
| $ |
| Total of Option Items 0003 |
| $ |
| Total of all Base and Option Items |
| $ |
EXTENSIONS: All extensions of the unit prices shown will be subject to verification by the Government. In case of variation between the unit price and the extension, the unit price will be considered to be the offer.
PRICE SCHEDULE
Ntsasa Primary School Pumlani, South Africa
-- END OF PROPOSAL SCHEDULE --
Oct 2020
Masons Clinic Copesville Pietermaritzburg, South Africa
COMMENCEMENT PROSECUTION AND EXECUTION OF WORK (52.211-10)
The Contractor shall be required to (a) commence work under this contract within 7 calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use no later than 455 calendar days after the contractor receives the Notice to Proceed. Any options, if awarded, shall be completed concurrently with all other work.
The time stated for completion shall include final cleanup of the premises. The Government intends to issue a single Notice to Proceed for all work.
LIQUIDATED DAMAGES-CONSTRUCTION (52.211-12)
If the Contractor fails to complete the work within the time specified in clause 52.211-10 COMMENCEMENT PROSECUTION AND EXECUTION OF WORK, the Contractor shall pay liquidated damages to the Government in the amount of $426.00 for each calendar day of delay until the work is completed or accepted.
If the Government terminates the Contractor's right to proceed, liquidated damages will continue to accrue until the work is completed. These liquidated damages are in addition to excess costs of repurchase under the Termination clause.
File details come from the government source that posted it. Updated .