ATTACHMENT 11 Past Performance Questionnaire.docx

DOCX document 36 KB Posted

Attached to
Design-Build construction contract for the Construction and Renovation of Ntsasa Primary School in Pumlani, South Africa
Solicitation number
W912GB23R0005
Issued by

About this file

This document contains a past performance questionnaire for evaluation of contractor performance on a previous federal contract. It requests ratings on quality, schedule, customer satisfaction, management, cost, safety, and general contractor performance. Details include evaluation criteria such as ability to meet quality standards, timeliness of issue resolution, adherence to quality plans, compliance with delivery schedules, customer end user satisfaction, effectiveness of on-site management and oversight of subcontractors, ability to control costs and budgets, maintenance of a safe work environment, and compliance with contractual terms. The client is asked to provide an overall rating of the contractor and any relevant comments on strengths, weaknesses, or other observations.

A separate section describes a federal contract opportunity to design and construct renovations to Ntsasa Primary School in Pumlani, South Africa. Work will be performed under a firm-fixed-price construction contract between $500,000 to $1,000,000 awarded using a best value tradeoff method. The solicitation is open to full and open competition. Award and payment will be made in US dollars by the US Department of the Army European Command.

View the file

Other files

File Type Posted
B.08.03 23R0005_Ntsasa Primary School Amendment 0004.pdf PDF
B.08.02 W912GB23R0005-0004_Ntsasa Primary School Renovation_Conformed.pdf PDF
ProjNet Inquiry Report 9JAN23 Final.pdf PDF
B.08.03 23R0005_Ntsasa Primary School Renovation 0002.pdf PDF
ATTACHMENT 14 _ (Amendment 1) Pay Terms Bid Schedule-Price Schedule.docx DOCX document
B.08.02 W912GB23R0005_Ntsasa Primary School Renovation_Conformed.pdf PDF
ProjNet Inquiry Report.pdf PDF
ATTACHMENT 5.1 Revised Statement of Work (SOW).pdf PDF
ATTACHMENT 13 VAT Information.docx DOCX document
ATTACHMENT 6 Dedication Plaque.pdf PDF
ATTACHMENT 9 Bank Letter of Guarantee Sample.docx DOCX document
ATTACHMENT 7 SPECIFICATIONS BINDER.pdf PDF
ATTACHMENT 1 Project Location Map.pdf PDF
B.08.02 W912GB23R0005_Ntsasa Primary School Renovation_Full.pdf PDF
ATTACHMENT 4 Structural calculations Guideline.pdf PDF
ATTACHMENT 5 Rainwater Tank Example.pdf PDF
ATTACHMENT 14 Pay Terms Bid Schedule-Price Schedule.docx DOCX document
ATTACHMENT 8 Bank Letter of Assurance Sample.docx DOCX document
ATTACHMENT 2 Concept Site Plan.pdf PDF
ATTACHMENT 10 Commitment Letters.docx DOCX document
ATTACHMENT 3 Conceptual Architecture Plans.pdf PDF
ATTACHMENT 15 Site Visit Attendee Worksheet.xlsx XLSX spreadsheet
ATTACHMENT 5.1 Statement of Work (SOW).pdf PDF
Show all 23

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

USACE PAST PERFORMANCE QUESTIONNAIRE ATTACHMENT 11

CONTRACT INFORMATION (Contractor to complete Blocks 1-4)

1. Contractor Information Firm Name:

Address:

Phone Number:

Email Address:

Point of Contact:Contact Phone Number:
CAGE Code:

DUNS Number:

2. Work Performed as: ❑ Prime Contractor Percent of project work performed:

If subcontractor, who was the prime (Name/Phone #):

❑ Sub
Contractor❑ Joint
Venture❑ Other (Explain)

3. Contract Information Contract Number:

Delivery/Task Order Number (if applicable):

❑ Other (Please specify):

Contract Type: ❑ Firm Fixed Price ❑ Cost Reimbursement Contract Title:

Contract Location:

Award Date (mm/dd/yy):

Contract Completion Date (mm/dd/yy):

Actual Completion Date (mm/dd/yy):

Explain Differences:

Original Contract Price (Award Amount):

Final Contract Price (to include all modifications, if applicable):

Explain Differences:

4. Project Description:
Complexity of Work ❑ High❑ Med❑ Routine

How is this project relevant to project of submission? (Please provide details such as similar equipment, requirements, conditions, etc.)

CLIENT INFORMATION (Client to complete Blocks 5-8)

5. Client Information Name:

Title:

Phone Number:

Email Address:

6. Describe the client's role in the project:

7. Date Questionnaire was completed (mm/dd/yy):

8. Client's Signature:

NOTE: USACE REQUESTS THAT THE CLIENT COMPLETES THIS QUESTIONNAIRE AND SUBMITS DIRECTLY BACK TO THE OFFEROR. THE OFFEROR WILL SUBMIT THE COMPLETED QUESTIONNAIRE TO USACE WITH THEIR PROPOSAL, AND MAY DUPLICATE THIS QUESTIONNAIRE FOR FUTURE SUBMISSION ON USACE SOLICITATIONS. CLIENTS ARE HIGHLY ENCOURAGED TO SUBMIT QUESTIONNAIRES DIRECTLY TO THE OFFEROR. HOWEVER, QUESTIONNAIRES MAY BE SUBMITTED DIRECTLY TO USACE. PLEASE CONTACT THE OFFEROR FOR USACE POC INFORMATION. THE GOVERNMENT RESERVES THE RIGHT TO VERIFY ANY AND ALL INFORMATION ON THIS FORM

TO BE COMPLETED BY CLIENT - ATTACHMENT 11

PLEASE CIRCLE THE ADJECTIVE RATING WHICH BEST REFLECTS YOUR EVALUATION OF THE CONTRACTOR'S PERFORMANCE.

E = EXCELLENT, VG = VERY GOOD, S = SATISFACTORY, M = MARGINAL,

U = UNSATISFACTORY, N= NOT APPLICABLE

1. QUALITY:

a) Quality of technical data/report preparation efforts
E
VG
S
M
U
N
b) Ability to meet quality standards specified for technical performance
E
VG
S
M
U
N
c) Timeliness/effectiveness of contract problem resolution without extensive customer guidance
E
VG
S
M
U
N
d) Adequacy/effectiveness of quality control program and adherence to contract quality assurance requirements (without adverse effect on performance)
E
VG
S
M
U
N

2. SCHEDULE/TIMELINESS OF PERFORMANCE:

a) Compliance with contract delivery/completion schedules including any significant intermediate milestones. (If liquidated damages were assessed or the schedule was not met, please address below)
E
VG
S
M
U
N
b) Rate the contractor's use of available resources identified in the contract
E
VG
S
M
U
N

3. CUSTOMER SATISFACTION:

a) To what extent were the end users satisfied with the project?
E
VG
S
M
U
N
b) Contractor was reasonable and cooperative in dealing with your staff (including the ability to successfully resolve disagreements/disputes; responsiveness to administrative reports, businesslike and communication)
E
VG
S
M
U
N
c) To what extent was the contractor cooperative, businesslike, and concerned with the interests of the customer?
E
VG
S
M
U
N
d) Overall customer satisfaction
E
VG
S
M
U
N

4. MANAGEMENT PERSONEL/LABOR:

a) Effectiveness of on-site management, including management of subcontractors, suppliers, materials, and/or labor force.
E
VG
S
M
U
N
b) Ability to hire, apply, and retain a qualified workforce to this effort
E
VG
S
M
U
N
c) Government Property Control
E
VG
S
M
U
N
d) Knowledge/expertise demonstrated by contractor personnel
E
VG
S
M
U
N
e) Utilization of Small Business concerns
E
VG
S
M
U
N
f) Ability to simultaneously manage multiple projects with multiple disciplines
E
VG
S
M
U
N
g) Ability to assimilate and incorporate changes in requirements and/or priority, including planning, execution and response to Government changes
E
VG
S
M
U
N
h) Effectiveness of overall management (including ability to effectively lead, manage and control the program)
E
VG
S
M
U
N

E = EXCELLENT, VG = VERY GOOD, S = SATISFACTORY, M = MARGINAL,

U = UNSATISFACTORY, N= NOT APPLICABLE

5. COST/FINANCIAL MANAGEMENT

a) Ability to meet the terms and conditions within the contractually agreed price(s)
E
VG
S
M
U
N
b) Contractor proposed innovative alternative methods/processes that reduced cost, improved maintainability or other factors that benefited the client
E
VG
S
M
U
N
c) If this is/was a Government cost type contract, please rate the Contractor's timeliness and accuracy in submitting monthly invoices with appropriate backup documentation, monthly status reports/budget variance reports, compliance with established budgets and avoidance of significant and/or unexplained variances (under runs or overruns)
E
VG
S
M
U
N
d) Is the Contractor's accounting system adequate for management and tracking of costs? If no, please explain in Remarks section.
E
VG
S
M
U
N
e) If this is/was a Government contract, has/was this contract been partially or completely terminated for default or convenience or are there any pending terminations? Indicate if show cause or cure notices were issued, or any default action in comment section below.
E
VG
S
M
U
N

f) Have there been any indications that the contractor has had any financial problems? Ifyes, please explain below.

YES

NO

6. SAFETY/SECURITY

a) To what extent was the contractor able to maintain an environment of safety, adhere to its approved safety plan, and respond to safety issues? (Includes: following the users rules, regulations, and requirements regarding housekeeping, safety, correction of noted deficiencies, etc.)
E
VG
S
M
U
N
b) Contractor complied with all security requirements for the project and personnel security requirements.
E
VG
S
M
U
N

7. GENERAL

a) Ability to successfully respond to emergency and/or surge situations (including notifying COR, PM or Contracting Officer in a timely manner regarding urgent contractual issues).
E
VG
S
M
U
N
b) Compliance with contractual terms/provisions (explain if specific issues)
E
VG
S
M
U
N

c) Would you hire or work with this firm again? (If no, please explain below)

YES

NO

d) In summary, provide an overall rating for the work performed by this contractor.
E
VG
S
M
U
N

Please provide responses to the questions above (if applicable) and/or additional remarks. Furthermore, please provide a brief narrative addressing specific strengths, weaknesses, deficiencies, or other comments which may assist our office in evaluating performance risk (attach additional pages if necessary):