Attachment 13 BCTE PWS Crosswalk.xlsx

XLSX spreadsheet 25 KB Posted

Attached to
Amendment 0002, Battle Command Training Equipment (BCTE)
Solicitation number
W900KK-23-R-0009RFP
Issued by

View the file

Other files

File Type Posted
Attachment 4 BCTE Notational Schedule.xlsx XLSX spreadsheet
Attachment 10 BCTE Cost-Pricing Workbook FINAL rev 3 5-9-2023.xlsx XLSX spreadsheet
W900KK-23-R-0009 Amendment 0002.pdf PDF
W900KK-23-R-0009 (SF 30) Amendment 0002.pdf PDF
Attachment 3 BCTE QASP.pdf PDF
Attachment 7 BCTE Past Performance Questionnaire.docx DOCX document
Attachment 0001 BCTE Amendment 0002 Letter additional responses to Questions.xlsx XLSX spreadsheet
Attachment 5 - DD-254 BCTE.pdf PDF
Attachment 6 - BCTE Question Comment Form.xlsx XLSX spreadsheet
Attachment 9 - BCTE Pre-Award Survey.pdf PDF
Attachment 11 - BCTE Proposal Adequacy Checklist.pdf PDF
Attachment 12 - BCTE PWS Crosswalk.xlsx XLSX spreadsheet
Exhibit A-1 BCTE IDIQ CDRLs.pdf PDF
Exhibit A-2 BCTE TO 0001 CDRLs.pdf PDF
W900KK-23-R-0009 (SF 30) Amendment 0001.pdf PDF
BCTE Amendment 0001 Letter.pdf PDF
Attachment 2 BCTE TO 0001 PWS.pdf PDF
Attachment 4 BCTE Notational Schedule.xlsx XLSX spreadsheet
Attachment 5 - DD-254 BCTE.pdf PDF
Exhibit A-2 BCTE TO 0001 CDRLs.pdf PDF
BCTE Amendment 0001 Letter Attachment 0001 Responses to Questions.xlsx XLSX spreadsheet
Attachment 3 BCTE QASP.pdf PDF
Attachment 8 - BCTE L and M PWS References.xlsx XLSX spreadsheet
Attachment 10 BCTE Cost-Pricing Workbook.xlsx XLSX spreadsheet
Attachment 11 - BCTE Proposal Adequacy Checklist.pdf PDF
W900KK-23-R-0009 Amendment 0001.pdf PDF
Attachment 1 BCTE IDIQ_PWS.pdf PDF
Attachment 6 - BCTE Question Comment Form.xlsx XLSX spreadsheet
Attachment 7 - BCTE Past Performance Questionnaire.docx DOCX document
Attachment 9 - BCTE Pre-Award Survey.pdf PDF
Attachment 12 - BCTE PWS Crosswalk.xlsx XLSX spreadsheet
BCTE Update 0001 Letter.pdf PDF
Attachment 10 BCTE Cost-Pricing Workbook.xlsx XLSX spreadsheet
Consolidation Determination for CBCSE_BCTC-ES.pdf PDF
Attachment 1 BCTE IDIQ_PWS.pdf PDF
Attachment 8 BCTE L and M PWS References.xlsx XLSX spreadsheet
Attachment 10 BCTE Cost-Pricing Workbook.xlsx XLSX spreadsheet
Exhibit A-1 BCTE IDIQ CDRLs.pdf PDF
Attachment 3 BCTE QASP.pdf PDF
Attachment 5 BCTE DD 254.pdf PDF
Attachment 4 BCTE Notational Schedule.xlsx XLSX spreadsheet
W900KK-23-R-0009 (BCTE Solicitation).pdf PDF
Exhibit A-2 BCTE TO 0001 CDRLs.pdf PDF
Attachment 2 BCTE TO 0001 PWS.pdf PDF
BCTE Draft Solicitation Questions and Comments.xlsx XLSX spreadsheet
Attachment 7 BCTE Past Performance Questionnaire.docx DOCX document
Attachment 9 BCTE Pre-Award Survey of Prospective Contractor Accounting System Checklist.pdf PDF
Attachment 11 BCTE Cost Pricing Proposal Adequacy Checklist.pdf PDF
Attachment 12 BCTE Section B CLIN Structure Spreadsheet with Options.xlsx XLSX spreadsheet
Attachment 6- BCTE Question Comment Form.xlsx XLSX spreadsheet
Show 40 more

50 files listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Sheet1

BCTE CLIN-Crosswalk
CLINDescriptionTypeIDIQ PWS/ParagraphTO 0001 PWS/ParagraphExplanation
BASE
0001Program ManagementFFP1.6, 5.1, 5.1.1, 5.1.2, 5.1.3, 5.1.4, 5.1.5, 5.1.6, 5.1.7, 5.1.7.1, 5.1.8,All of 8Labor only. The Contractor shall provide the overall management and administrative effort necessary to ensure the requirements of this contract are accomplished.
0002Help Desk Support (includes: RWIS Help Desk, IA Support, and Video Telecon Help Desk Support)FFP5.3, 5.412Labor associated with Helpdesk support per the PWS and requirements to provide the activities necessary to ensure that Systems Engineering and sustainment principles, processes and practices are applied throughout its lifecycle. The Help Desk support shall be available Monday-Friday during your organization’s normal business hours. The objective is for users to have the ability to submit request for support twenty-four (24) hours per day via email, website or voicemail and receive a callback the next business day. The RWIS ELA shall include unlimited licenses and support for the BCTE program. The current MTC RWIS system is the Advanced Simulations Technologies, Inc. (ASTi) Voisus radio wire integration system.

Travel is on Travel CLIN.

0003BCTC-ES Site SurveysFFP4.11.4, 4.11.2, 4.11.3, 4.11.6, 4.10.2, 4.11.6, 4.12, 4.4.3, 4.6, 4.13, 5.2.5.6, 5.2.8, 5.2.9,5.2.10,5.2.11,5.2.12,5.2.13,5.2.14All of 9.1Labor Only associated with technology refresh for sites per the PWS and requirements. The Contractor shall collect detailed information about the facility to ensure the COTS products and FFE can be properly operated, maintained, and oriented within the available space.
0004CBCSE Site SurveysFFP4.11.4, 4.11.2, 4.11.3, 4.11.6, 4.10.2, 4.11.6, 4.12, 4.4.3, 4.6, 4.13, 5.2.5.6, 5.2.8, 5.2.9,5.2.10,5.2.11,5.2.12,5.2.13,5.2.15All of 9.2Labor Only associated with technology refresh for sites per the PWS and requirements. The Contractor shall collect detailed information about the facility to ensure the COTS products and FFE can be properly operated, maintained, and oriented within the available space.
0005BCTC-ES Installation Services, LaborCPFF4.1.1, 4.1.11, 4.2.3, 4.2.4, 4.2.5.2, 4.4.1, 4.4.3, 4.5, 4.8, 4.13, 5.2.5.6, 5.2.8, 5.2.9,5.2.10,5.2.11,5.2.12,5.2.13,5.2.14, 5.2.6.1-5.2.711, 12, 13, 14, 15, 16, 17, 18, 19, 20, 21, 22Labor, Travel, Material and ODCs associated with hardware, FFE and software licensces activities per the PWS and requirements. The integration of mature technological solutions to increase readiness, reduce life cycle costs, and reduce the logistics footprint.
0006CBCSE Installation Services, LaborCPFF4.1.1, 4.1.11, 4.2.3, 4.2.4, 4.2.5.2, 4.4.1, 4.4.3, 4.5, 4.8, 4.13, 5.2.5.6, 5.2.8, 5.2.9,5.2.10,5.2.11,5.2.12,5.2.13,5.2.14, 5.2.6.1-5.2.811, 12, 13, 14, 15, 16, 17, 18, 19, 20, 21, 22Labor, Travel, Material and ODCs associated with hardware, FFE and software licensces activities per the PWS and requirements. The integration of mature technological solutions to increase readiness, reduce life cycle costs, and reduce the logistics footprint.
0007ESS SupportFFP5.6, 5.6.1, 5.6.2, 5.6.3, 5.6.4, 5.7, 5.7.1, 5.7.2, 5.8, 5.9, 5.9.1, 5.10, 5.10.1, 5.10.2, 5.10.3, 5.10.4, 5.10.4.1, 5.10.4.2, 5.10.4.3, 5.10.4.4, 5.10.5, 5.10.6, 5.10.7, 5.10.8, 5.10.9, 5.10.10, 5.10.11, 5.10.12, 5.10.13, 5.10.14, 5.10.1523Maintenance & Service (M&S) of all integrated NIPR Electronic Security Systems (ESS), and the supporting communications and power equipment. The current ESS consists of an IDS, Access Control System (ACS) and Closed-Circuit Televisions (CCTV) systems. This task order applies only to the ACS and the CCTV systems at each MTC in NIPR locations.
0008BCTC-ES Materials, Equipment, and ODCsCPFF1.6.14, 5.2.59.1Material associated with LVC-IA Concurrency, PDSS, and tech refresh per the PWS and requirements. Labor, Travel, Material and ODCs associated with Technology Insertion activities per the PWSand requirements. The integration of mature technological solutions (e.g. cloud capability) to increase readiness, reduce life cycle costs, and reduce the logistics footprint.
0009CBCSE Materials, Equipment, and ODCsCPFF1.6.14, 5.2.59.2Material associated with LVC-IA Concurrency, PDSS, and tech refresh per the PWS and requirements. Labor, Travel, Material and ODCs associated with Technology Insertion activities per the PWSand requirements. The integration of mature technological solutions (e.g. cloud capability) to increase readiness, reduce life cycle costs, and reduce the logistics footprint.
0010BCTC-ES Software LicensesCost4.1.5.3, 4.1.11, 4.5, 4.7, 4.7.5, 4.7.7.1, 4.7.7.4, 4.7.7.5., 4.1311, 18, 26.3Material associated with spares per the PWS and requirements. Labor and ODCs associated with spares would fall under PDSS.
0011CBCSE Software LicensesCost4.1.5.3, 4.1.11, 4.5, 4.7, 4.7.5, 4.7.7.1, 4.7.7.4, 4.7.7.5., 4.1311, 18Material associated with spares per the PWS and requirements. Labor and ODCs associated with spares would fall under PDSS.
0012BCTC-ES TravelCost1.6.13, 4.10.45, 9.1The Contractor shall be required to travel to both CONUS and OCONUS MTC locations identified in PWS Addendum 1, BCTE Fielding Locations and PEO STRI during the performance of this contract to attend meetings, for site surveys, for installation services and on-site training services. Contractor shall be authorized travel expenses IAW the Joint Travel Regulation (JTR) and the limitation of funds specified in this contract.
0013CBCSE TravelCost1.6.13, 4.10.45, 9.2The Contractor shall be required to travel to both CONUS and OCONUS MTC locations identified in PWS Addendum 1, BCTE Fielding Locations and PEO STRI during the performance of this contract to attend meetings, for site surveys, for installation services and on-site training services. Contractor shall be authorized travel expenses IAW the Joint Travel Regulation (JTR) and the limitation of funds specified in this contract.
0014CMRANSP5.1.3NANot Seperately Priced (NSP)
0015CDRLsNSP5.1.1, 5.1.2, 5.1.7.1, 5.2.1, 5.2.5.1, 5.2.5.3, 5.2.5.6, 5.2.6.1, 5.2.7.1, 5.2.8, 5.2.926.1The following list represents deliverables that the Contractor shall provide per the instructions specified in DD Form 1423
0016Customer SupportFFP5.521Customer Support Mission Requirements represent tasks to support or customers through the life of the contract based on mission requirements and available funding.
0017Phase InFFP1.6.17.16Transition to full development and support capability. (1) Non-recurring labor and travel unique to Transition Phase-In, including hiring and training of personnel to staff facility (contractor); and (2) Non-recurring labor for set-up of computing equipment, network infrastructure, and associated ODC required to transition to contractor's facility. 60 day transition period.
CLINPWS/Paragraph
1st OPTION
1001Program ManagementFFP1.6, 5.1, 5.1.1, 5.1.2, 5.1.3, 5.1.4, 5.1.5, 5.1.6, 5.1.7, 5.1.7.1, 5.1.8,TBDLabor only. The Contractor shall provide the overall management and administrative effort necessary to ensure the requirements of this contract are accomplished.
1002Help Desk Support (includes: RWIS Help Desk, IA Support, and Video Telecon Help Desk Support)FFP5.3, 5.4TBDLabor associated with Helpdesk support per the PWS and requirements to provide the activities necessary to ensure that Systems Engineering and sustainment principles, processes and practices are applied throughout its lifecycle. The Help Desk support shall be available Monday-Friday during your organization’s normal business hours. The objective is for users to have the ability to submit request for support twenty-four (24) hours per day via email, website or voicemail and receive a callback the next business day. The RWIS ELA shall include unlimited licenses and support for the BCTE program. The current MTC RWIS system is the Advanced Simulations Technologies, Inc. (ASTi) Voisus radio wire integration system.

Travel is on Travel CLIN.

1003BCTC-ES Site SurveysFFP4.11.4, 4.11.2, 4.11.3, 4.11.6, 4.10.2, 4.11.6, 4.12, 4.4.3, 4.6, 4.13, 5.2.5.6, 5.2.8, 5.2.9,5.2.10,5.2.11,5.2.12,5.2.13,5.2.14TBDLabor Only associated with technology refresh for sites per the PWS and requirements. The Contractor shall collect detailed information about the facility to ensure the COTS products and FFE can be properly operated, maintained, and oriented within the available space.
1004CBCSE Site SurveysFFP4.11.4, 4.11.2, 4.11.3, 4.11.6, 4.10.2, 4.11.6, 4.12, 4.4.3, 4.6, 4.13, 5.2.5.6, 5.2.8, 5.2.9,5.2.10,5.2.11,5.2.12,5.2.13,5.2.15TBDLabor Only associated with technology refresh for sites per the PWS and requirements. The Contractor shall collect detailed information about the facility to ensure the COTS products and FFE can be properly operated, maintained, and oriented within the available space.
1005BCTC-ES Installation Services, LaborCPFF4.1.1, 4.1.11, 4.2.3, 4.2.4, 4.2.5.2, 4.4.1, 4.4.3, 4.5, 4.8, 4.13, 5.2.5.6, 5.2.8, 5.2.9,5.2.10,5.2.11,5.2.12,5.2.13,5.2.14, 5.2.6.1-5.2.7TBDLabor, Travel, Material and ODCs associated with hardware, FFE and software licensces activities per the PWS and requirements. The integration of mature technological solutions to increase readiness, reduce life cycle costs, and reduce the logistics footprint.
1006CBCSE Installation Services, LaborCPFF4.1.1, 4.1.11, 4.2.3, 4.2.4, 4.2.5.2, 4.4.1, 4.4.3, 4.5, 4.8, 4.13, 5.2.5.6, 5.2.8, 5.2.9,5.2.10,5.2.11,5.2.12,5.2.13,5.2.14, 5.2.6.1-5.2.8TBDLabor, Travel, Material and ODCs associated with hardware, FFE and software licensces activities per the PWS and requirements. The integration of mature technological solutions to increase readiness, reduce life cycle costs, and reduce the logistics footprint.
1007ESS SupportFFP5.6, 5.6.1, 5.6.2, 5.6.3, 5.6.4, 5.7, 5.7.1, 5.7.2, 5.8, 5.9, 5.9.1, 5.10, 5.10.1, 5.10.2, 5.10.3, 5.10.4, 5.10.4.1, 5.10.4.2, 5.10.4.3, 5.10.4.4, 5.10.5, 5.10.6, 5.10.7, 5.10.8, 5.10.9, 5.10.10, 5.10.11, 5.10.12, 5.10.13, 5.10.14, 5.10.15TBDMaintenance & Service (M&S) of all integrated NIPR Electronic Security Systems (ESS), and the supporting communications and power equipment. The current ESS consists of an IDS, Access Control System (ACS) and Closed-Circuit Televisions (CCTV) systems. This task order applies only to the ACS and the CCTV systems at each MTC in NIPR locations.
1008BCTC-ES Materials, Equipment, and ODCsCPFF1.6.145.2.5TBDMaterial associated with LVC-IA Concurrency, PDSS, and tech refresh per the PWS and requirements. Labor, Travel, Material and ODCs associated with Technology Insertion activities per the PWSand requirements. The integration of mature technological solutions (e.g. cloud capability) to increase readiness, reduce life cycle costs, and reduce the logistics footprint.
1009CBCSE Materials, Equipment, and ODCsCPFF1.6.145.2.5TBDMaterial associated with LVC-IA Concurrency, PDSS, and tech refresh per the PWS and requirements. Labor, Travel, Material and ODCs associated with Technology Insertion activities per the PWSand requirements. The integration of mature technological solutions (e.g. cloud capability) to increase readiness, reduce life cycle costs, and reduce the logistics footprint.
1010BCTC-ES Software LicensesCost4.1.5.3, 4.1.11, 4.5, 4.7, 4.7.5, 4.7.7.1, 4.7.7.4, 4.7.7.5., 4.13TBDMaterial associated with spares per the PWS and requirements. Labor and ODCs associated with spares would fall under PDSS.
1011CBCSE Software LicensesCost4.1.5.3, 4.1.11, 4.5, 4.7, 4.7.5, 4.7.7.1, 4.7.7.4, 4.7.7.5., 4.13TBDMaterial associated with spares per the PWS and requirements. Labor and ODCs associated with spares would fall under PDSS.
1012BCTC-ES TravelCost1.6.13, 4.10.4TBDThe Contractor shall be required to travel to both CONUS and OCONUS MTC locations identified in PWS Addendum 1, BCTE Fielding Locations and PEO STRI during the performance of this contract to attend meetings, for site surveys, for installation services and on-site training services. Contractor shall be authorized travel expenses IAW the Joint Travel Regulation (JTR) and the limitation of funds specified in this contract.
1013CBCSE TravelCost1.6.13, 4.10.4TBDThe Contractor shall be required to travel to both CONUS and OCONUS MTC locations identified in PWS Addendum 1, BCTE Fielding Locations and PEO STRI during the performance of this contract to attend meetings, for site surveys, for installation services and on-site training services. Contractor shall be authorized travel expenses IAW the Joint Travel Regulation (JTR) and the limitation of funds specified in this contract.
1014CMRANSP5.1.3TBDNot Seperately Priced (NSP)
1015CDRLsNSP5.1.1, 5.1.2, 5.1.7.1, 5.2.1, 5.2.5.1, 5.2.5.3, 5.2.5.6, 5.2.6.1, 5.2.7.1, 5.2.8, 5.2.9,TBDThe following list represents deliverables that the Contractor shall provide per the instructions specified in DD Form 1423
1016Customer SupportFFP5.5TBDCustomer Support Mission Requirements represent tasks to support or customers through the life of the contract based on mission requirements and available funding.
CLINPWS/Paragraph
2nd OPTION
2001Program ManagementFFP1.6, 5.1, 5.1.1, 5.1.2, 5.1.3, 5.1.4, 5.1.5, 5.1.6, 5.1.7, 5.1.7.1, 5.1.8,TBDLabor only. The Contractor shall provide the overall management and administrative effort necessary to ensure the requirements of this contract are accomplished.
2002Help Desk Support (includes: RWIS Help Desk, IA Support, and Video Telecon Help Desk Support)FFP5.3, 5.4TBDLabor associated with Helpdesk support per the PWS and requirements to provide the activities necessary to ensure that Systems Engineering and sustainment principles, processes and practices are applied throughout its lifecycle. The Help Desk support shall be available Monday-Friday during your organization’s normal business hours. The objective is for users to have the ability to submit request for support twenty-four (24) hours per day via email, website or voicemail and receive a callback the next business day. The RWIS ELA shall include unlimited licenses and support for the BCTE program. The current MTC RWIS system is the Advanced Simulations Technologies, Inc. (ASTi) Voisus radio wire integration system.

Travel is on Travel CLIN.

2003BCTC-ES Site SurveysFFP4.11.4, 4.11.2, 4.11.3, 4.11.6, 4.10.2, 4.11.6, 4.12, 4.4.3, 4.6, 4.13, 5.2.5.6, 5.2.8, 5.2.9,5.2.10,5.2.11,5.2.12,5.2.13,5.2.14TBDLabor Only associated with technology refresh for sites per the PWS and requirements. The Contractor shall collect detailed information about the facility to ensure the COTS products and FFE can be properly operated, maintained, and oriented within the available space.
2004CBCSE Site SurveysFFP4.11.4, 4.11.2, 4.11.3, 4.11.6, 4.10.2, 4.11.6, 4.12, 4.4.3, 4.6, 4.13, 5.2.5.6, 5.2.8, 5.2.9,5.2.10,5.2.11,5.2.12,5.2.13,5.2.15TBDLabor Only associated with technology refresh for sites per the PWS and requirements. The Contractor shall collect detailed information about the facility to ensure the COTS products and FFE can be properly operated, maintained, and oriented within the available space.
2005BCTC-ES Installation Services, LaborCPFF4.1.1, 4.1.11, 4.2.3, 4.2.4, 4.2.5.2, 4.4.1, 4.4.3, 4.5, 4.8, 4.13, 5.2.5.6, 5.2.8, 5.2.9,5.2.10,5.2.11,5.2.12,5.2.13,5.2.14, 5.2.6.1-5.2.7TBDLabor, Travel, Material and ODCs associated with hardware, FFE and software licensces activities per the PWS and requirements. The integration of mature technological solutions to increase readiness, reduce life cycle costs, and reduce the logistics footprint.
2006CBCSE Installation Services, LaborCPFF4.1.1, 4.1.11, 4.2.3, 4.2.4, 4.2.5.2, 4.4.1, 4.4.3, 4.5, 4.8, 4.13, 5.2.5.6, 5.2.8, 5.2.9,5.2.10,5.2.11,5.2.12,5.2.13,5.2.14, 5.2.6.1-5.2.8TBDLabor, Travel, Material and ODCs associated with hardware, FFE and software licensces activities per the PWS and requirements. The integration of mature technological solutions to increase readiness, reduce life cycle costs, and reduce the logistics footprint.
2007ESS SupportFFP5.6, 5.6.1, 5.6.2, 5.6.3, 5.6.4, 5.7, 5.7.1, 5.7.2, 5.8, 5.9, 5.9.1, 5.10, 5.10.1, 5.10.2, 5.10.3, 5.10.4, 5.10.4.1, 5.10.4.2, 5.10.4.3, 5.10.4.4, 5.10.5, 5.10.6, 5.10.7, 5.10.8, 5.10.9, 5.10.10, 5.10.11, 5.10.12, 5.10.13, 5.10.14, 5.10.15TBDMaintenance & Service (M&S) of all integrated NIPR Electronic Security Systems (ESS), and the supporting communications and power equipment. The current ESS consists of an IDS, Access Control System (ACS) and Closed-Circuit Televisions (CCTV) systems. This task order applies only to the ACS and the CCTV systems at each MTC in NIPR locations.
2008BCTC-ES Materials, Equipment, and ODCsCPFF1.6.145.2.5TBDMaterial associated with LVC-IA Concurrency, PDSS, and tech refresh per the PWS and requirements. Labor, Travel, Material and ODCs associated with Technology Insertion activities per the PWSand requirements. The integration of mature technological solutions (e.g. cloud capability) to increase readiness, reduce life cycle costs, and reduce the logistics footprint.
2009CBCSE Materials, Equipment, and ODCsCPFF1.6.145.2.5TBDMaterial associated with LVC-IA Concurrency, PDSS, and tech refresh per the PWS and requirements. Labor, Travel, Material and ODCs associated with Technology Insertion activities per the PWSand requirements. The integration of mature technological solutions (e.g. cloud capability) to increase readiness, reduce life cycle costs, and reduce the logistics footprint.
2010BCTC-ES Software LicensesCost4.1.5.3, 4.1.11, 4.5, 4.7, 4.7.5, 4.7.7.1, 4.7.7.4, 4.7.7.5., 4.13TBDMaterial associated with spares per the PWS and requirements. Labor and ODCs associated with spares would fall under PDSS.
2011CBCSE Software LicensesCost4.1.5.3, 4.1.11, 4.5, 4.7, 4.7.5, 4.7.7.1, 4.7.7.4, 4.7.7.5., 4.13TBDMaterial associated with spares per the PWS and requirements. Labor and ODCs associated with spares would fall under PDSS.
2012BCTC-ES TravelCost1.6.13, 4.10.4TBDThe Contractor shall be required to travel to both CONUS and OCONUS MTC locations identified in PWS Addendum 1, BCTE Fielding Locations and PEO STRI during the performance of this contract to attend meetings, for site surveys, for installation services and on-site training services. Contractor shall be authorized travel expenses IAW the Joint Travel Regulation (JTR) and the limitation of funds specified in this contract.
2013CBCSE TravelCost1.6.13, 4.10.4TBDThe Contractor shall be required to travel to both CONUS and OCONUS MTC locations identified in PWS Addendum 1, BCTE Fielding Locations and PEO STRI during the performance of this contract to attend meetings, for site surveys, for installation services and on-site training services. Contractor shall be authorized travel expenses IAW the Joint Travel Regulation (JTR) and the limitation of funds specified in this contract.
2014CMRANSP5.1.3TBDNot Seperately Priced (NSP)
2015CDRLsNSP5.1.1, 5.1.2, 5.1.7.1, 5.2.1, 5.2.5.1, 5.2.5.3, 5.2.5.6, 5.2.6.1, 5.2.7.1, 5.2.8, 5.2.9,TBDThe following list represents deliverables that the Contractor shall provide per the instructions specified in DD Form 1423
2016Customer SupportFFP5.5TBDCustomer Support Mission Requirements represent tasks to support or customers through the life of the contract based on mission requirements and available funding.
2013Phase OutFFP1.6.17.2TBDTransition to full development and support capability. (1) Non-recurring labor and travel unique to Transition Phase-In, including hiring and training of personnel to staff the LVC-IA Development facility (JDIF) and the PDSS facility (contractor); and (2) Non-recurring labor for set-up of computing equipment, network infrastructure, GFP, software and associated ODC required to transition to contractor's PDSS facility. 60 day transition period.