Attachment 11 - 3WeekLookahead_StrawberryBunkhouses_Template.xlsx

XLSX spreadsheet 69 KB Posted

Attached to
GAOA – Strawberry – Kamas Bunkhouse Renovations on the Uinta/Wasatch/Cache National Forest
Solicitation number
1240LU26Q0003
Issued by

About this file

This is a Three-Week Look Ahead construction schedule template for the Strawberry Bunkhouse Renovations project at Strawberry Reservoir Visitors Center on the Uinta/Wasatch/Cache National Forest. The template serves as a planning tool for contractors to track construction activities across multiple buildings (Buildings 1062, 1063, 1064, and 1065) during a three-week execution period from March 7-28, 2027. The document includes an all-buildings schedule covering pre-construction and priority work activities, with separate detailed schedules for each individual building unit.

The template outlines comprehensive renovation activities across all buildings, including mobilization, asbestos and lead paint testing, mold testing, pest mitigation, window replacement with vinyl windows and screens, flooring installation (LVT and carpet), interior and exterior painting, plumbing fixture replacement with lever-handle faucets, electrical outlet inspection and LED lighting upgrades, water heater replacement, smoke and carbon monoxide detector installation, bathroom and kitchen renovations, appliance replacement (washers, dryers, microwaves, ranges, refrigerators), roof rib cover repairs, soffit and fascia replacement, and mattress replacement. The template includes columns for activity identification, responsible party assignment, original duration, daily scheduling across the three-week period, completion percentage tracking, and notes for project-specific considerations such as Building 1063 not requiring water heater replacement in Room 3. The document also provides a blank template and example template for reference purposes.

View the file

Other files

Show all 11

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ALLStrawberry 3-Week LA

Three-Week Look Ahead Construction Schedule Template
Project NameProject Location
STRAWBERRY BUNKHOUSE RENOVATIONS - ALL BUILDINGSSTRAWBERRY RESERVOIR VISITORS CENTERWork Type 1
Project ManagerStart DateWork Type 2
03/07/26Work Type 3
Project NumberEnd DateWork Type 4
03/28/26Project Milestone
Pre-Construction Phase
Activity IDActivity NameResponsible PartyOriginal DurationSUNMONTUESWEDTHURFRISATSUNMONTUESWEDTHURFRISATSUNMONTUESWEDTHURFRISATCompletion Status
(BY PERCENT)Notes
03/07/2603/08/2603/09/2603/10/2603/11/2603/12/2603/13/2603/14/2603/15/2603/16/2603/17/2603/18/2603/19/2603/20/2603/21/2603/22/2603/23/2603/24/2603/25/2603/26/2603/27/26
011900Mobilization including bonding0
024230Priority Work - Asbestos and lead paint testing and reporting for all buildings prior to beginning work.0
028500Priority Work - Mold testing and reporting for all buildings prior to beginning work.0
017320Priority Work - Bat and mouse contamination treatment and mitigation for all buildings prior to beginning work.0
311000Priority Work - Cut back overgrown shrubs/ underbrush for all buildings prior to beginning work.0
087100Remove all existing interior door knobs and replace with lever type handles. Inspect interior door hardware, and consult COR for necessary repairs or replacements0
017320Remove and dispose of all (4) exterior door screens. Do not replace.
090190Prep, paint, and seal all exterior doors per specifications.
260533Inspect all interior and exterior electrical outlets, and consult COR for repairs or replacements per specifications
74113Repair, replace, and secure metal roof rib covers, endcaps, and gable vent screens & frames per drawings

1062Strawberry 3-Week LA

Three-Week Look Ahead Construction Schedule Template
Project NameProject Location
STRAWBERRY BUNKHOUSE RENOVATIONS - BUILDING 1062Work Type 1
Project ManagerStart DateWork Type 2
03/07/27Work Type 3
Project NumberEnd DateWork Type 4
03/28/27Project Milestone
Pre-Construction Phase
Activity IDActivity NameResponsible PartyOriginal DurationSUNMONTUESWEDTHURFRISATSUNMONTUESWEDTHURFRISATSUNMONTUESWEDTHURFRISATCompletion Status
(BY PERCENT)Notes
03/07/2703/08/2703/09/2703/10/2703/11/2703/12/2703/13/2703/14/2703/15/2703/16/2703/17/2703/18/2703/19/2703/20/2703/21/2703/22/2703/23/2703/24/2703/25/2703/26/2703/27/27
Mobilization and Priority Work0
85313Demo and remove all windows. Provide and install new vinyl windows, screens, and blinds per specifications.0
40322Replace detached brick window sill and seal all penetrations on the brick exterior per drawings0
17320Provide and install exterior dryer vent where missing0
017320Remove and store wood burning stove in garage. Demo and remove protective ceramic layer at floor and ceiling. Remove chimney flue, repair ceiling, and seal roof penetrations.0
96519Demo and remove existing rolled vinyl flooring. Provide and install LVT flooring per specifications.0
96813Demo and remove existing carpet. Provide and install carpet flooring per specifications
99123Prep and paint all interior walls and ceilings per specifications.
223400Demo and remove water heater. Provide and install new water heater per specifications.
224213Provide and install toilet
102819Demo and remove existing shower door. Provide and install new shower door.
267500Provide and install smoke and carbon monoxide detectors.
265000Replace all interior and exterior light fixtures with LED Lights per drawings
62023Provide and install painted baseboard, to match existing as closely as possible.
92900Provide and install wall including sheetrock, framing, paint, double pocket door, and finish trim per drawings.
12500013Replace all bedframes and mattresses (Twin XL) to match existing frames
017320Replace all vent fans in restrooms
224216Demo and remove existing bathroom and kitchen faucets. Provide and install lever handle type faucet per specifications
64113Replace kitchen cabinet hinges, drawer glides, and handles. Deep clean all cabinetry
113100Remove washer and dryer and properly dispose. Provide new washer and dryer with front facing controls per specifications.
113100Provide and replace UL listed electric microwave, range and range hood per specifications
113100Provide and replace Energy Star rated refrigerator/ freezer per specifications
123623Remove and replace kitchen laminate countertops
74293Replace soffit and fascia per drawings

1063Strawberry 3-Week LA

Three-Week Look Ahead Construction Schedule Template
Project NameProject Location
STRAWBERRY BUNKHOUSE RENOVATIONS - BUILDING 1063Work Type 1
Project ManagerStart DateWork Type 2
03/07/27Work Type 3
Project NumberEnd DateWork Type 4
03/28/27Project Milestone
Pre-Construction Phase
Activity IDActivity NameResponsible PartyOriginal DurationSUNMONTUESWEDTHURFRISATSUNMONTUESWEDTHURFRISATSUNMONTUESWEDTHURFRISATCompletion Status
(BY PERCENT)Notes
03/07/2703/08/2703/09/2703/10/2703/11/2703/12/2703/13/2703/14/2703/15/2703/16/2703/17/2703/18/2703/19/2703/20/2703/21/2703/22/2703/23/2703/24/2703/25/2703/26/2703/27/27
Mobilization and Priority Work0
85313Demo and remove all windows. Provide and install new vinyl windows, screens, and blinds per specifications.0
96519Demo and remove existing rolled vinyl flooring. Provide and install LVT flooring per specifications.0
96813Demo and remove existing carpet. Provide and install carpet flooring per specifications0
99123Prep and paint all interior walls and ceilings per specifications.0
223400Demo and remove water heater. Provide and install new water heater per specifications. Room 3 will not need replacement.0
267500Provide and install smoke and carbon monoxide detectors.
265000Replace all interior and exterior light fixtures with LED Lights per drawings
62023Provide and install painted baseboard, to match existing as closely as possible.
12500013Replace all mattresses (Twin XL)
017320Replace all vent fans in restrooms
224216Demo and remove existing faucets. Provide and install lever handle type faucet per specifications
74293Replace soffit and fascia per drawings

1064Strawberry 3-week LA

Three-Week Look Ahead Construction Schedule Template
Project NameProject Location
STRAWBERRY BUNKHOUSE RENOVATIONS - BUILDING 1064Work Type 1
Project ManagerStart DateWork Type 2
03/07/27Work Type 3
Project NumberEnd DateWork Type 4
03/28/27Project Milestone
Pre-Construction Phase
Activity IDActivity NameResponsible PartyOriginal DurationSUNMONTUESWEDTHURFRISATSUNMONTUESWEDTHURFRISATSUNMONTUESWEDTHURFRISATCompletion Status
(BY PERCENT)Notes
03/07/2703/08/2703/09/2703/10/2703/11/2703/12/2703/13/2703/14/2703/15/2703/16/2703/17/2703/18/2703/19/2703/20/2703/21/2703/22/2703/23/2703/24/2703/25/2703/26/2703/27/27
Mobilization and Priority Work0
85313Demo and remove all windows. Provide and install new vinyl windows, screens, and blinds per specifications.0
99123Prep and paint all interior walls, ceilings, and shelving per specifications.0
223400Demo and remove water heater. Provide and install new water heater per specifications.0
267500Provide and install smoke and carbon monoxide detectors.0
265000Replace all interior and exterior light fixtures with LED Lights per drawings0
113100Remove washer and dryer and store in garage. Provide new washer and dryer with front facing controls per specifications.
113100Remove (2) existing fridges and install (2) new Energy Star rated refrigerator/ freezers and (1) freezer per specifciations.
113100Provide and replace UL listed electric microwave, range and range hood per specifications
017320Replace all vent fans in restrooms
64113Replace kitchen cabinet hinges, drawer glides, and handles. Deep clean all cabinetry
74293Replace soffit and fascia per drawings

1065Strawberry 3-week LA

Three-Week Look Ahead Construction Schedule Template
Project NameProject Location
STRAWBERRY BUNKHOUSE RENOVATIONS - BUILDING 1065Work Type 1
Project ManagerStart DateWork Type 2
03/07/27Work Type 3
Project NumberEnd DateWork Type 4
03/28/27Project Milestone
Pre-Construction Phase
Activity IDActivity NameResponsible PartyOriginal DurationSUNMONTUESWEDTHURFRISATSUNMONTUESWEDTHURFRISATSUNMONTUESWEDTHURFRISATCompletion Status
(BY PERCENT)Notes
03/07/2703/08/2703/09/2703/10/2703/11/2703/12/2703/13/2703/14/2703/15/2703/16/2703/17/2703/18/2703/19/2703/20/2703/21/2703/22/2703/23/2703/24/2703/25/2703/26/2703/27/27
Mobilization and Priority Work0
85313Demo and remove all windows. Provide and install new vinyl windows, screens, and blinds per specifications.0
96519Demo and remove existing rolled vinyl flooring. Provide and install LVT flooring per specifications.0
96813Demo and remove existing carpet. Provide and install carpet flooring per specifications0
99123Prep and paint all interior walls and ceilings per specifications.0
223400Demo and remove water heater. Provide and install new water heater per specifications.0
267500Provide and install smoke and carbon monoxide detectors.
265000Replace all interior and exterior light fixtures with LED Lights per drawings
62023Provide and install painted baseboard, to match existing as closely as possible.
12500013Replace all mattresses (Twin XL)
017320Replace all vent fans in restrooms
224216Demo and remove existing faucets. Provide and install lever handle type faucet per specifications
74293Replace soffit and fascia per drawings

- Disclaimer -

Any articles, templates, or information provided by Smartsheet on the website are for reference only. While we strive to keep the information up to date and correct, we make no representations or warranties of any kind, express or implied, about the completeness, accuracy, reliability, suitability, or availability with respect to the website or the information, articles, templates, or related graphics contained on the website. Any reliance you place on such information is therefore strictly at your own risk.

BLANK 3-Week LA

Three-Week Look Ahead Construction Schedule Template
Project NameProject Location
Work Type 1
Project ManagerStart DateWork Type 2
03/07/27Work Type 3
Project NumberEnd DateWork Type 4
03/28/27Project Milestone
Pre-Construction Phase
Activity IDActivity NameResponsible PartyOriginal DurationSUNMONTUESWEDTHURFRISATSUNMONTUESWEDTHURFRISATSUNMONTUESWEDTHURFRISATCompletion Status
(BY PERCENT)Notes
03/07/2703/08/2703/09/2703/10/2703/11/2703/12/2703/13/2703/14/2703/15/2703/16/2703/17/2703/18/2703/19/2703/20/2703/21/2703/22/2703/23/2703/24/2703/25/2703/26/2703/27/27
0
0
0
0
0
0

EXAMPLE 3-Week LA

Three-Week Look Ahead Construction Schedule Template Example
Project NameProject Location
Project AlphaAddress, City, State ZIPWork Type 1
Project ManagerStart DateWork Type 2
Henry McNeal03/07/27Work Type 3
Project NumberEnd DateWork Type 4
001-ABC-DEF03/28/27Project Milestone
Pre-Construction Phase
Activity IDActivity NameResponsible PartyOriginal DurationSUNMONTUESWEDTHURFRISATSUNMONTUESWEDTHURFRISATSUNMONTUESWEDTHURFRISATCompletion Status
(BY PERCENT)Notes
03/07/2703/08/2703/09/2703/10/2703/11/2703/12/2703/13/2703/14/2703/15/2703/16/2703/17/2703/18/2703/19/2703/20/2703/21/2703/22/2703/23/2703/24/2703/25/2703/26/2703/27/27
A10300Prepare/Submit Project Scheduler QualificationsHenry McNeal335
A10301Prepare/Submit Insurance CertificatesBrent Williams522
A10302Prepare/Submit Preliminary Project ScheduleHenry McNeal510
A10303Prepare/Submit Quality Control PlanJason Desjardins37
A10304Review/Approve Health and Safety PlanJason Desjardins380Contact SSHO Manager
A10305Review/Approve List of Proposed ContractorsJason Desjardins530
A10305Mobilization0

CLICK HERE TO CREATE IN SMARTSHEET

http://bit.ly/2ZM77jmhttps://www.smartsheet.com/try-it?trp=10669&utm_source=template-excel&utm_medium=content&utm_campaign=Three-Week+Look+Ahead+Construction+Schedule-excel-10669&lpa=Three-Week+Look+Ahead+Construction+Schedule+excel+10669 image1.png image2.svg

.MsftOfcThm_Accent4_lumMod_75_Stroke_v2 { stroke:#BF9000;

File details come from the government source that posted it. Updated .