This is a production schedule template for a 60' Dive Support Boat contract (N6426725Q415, Attachment 10) that outlines key milestone events in the boat's construction timeline. The schedule tracks major events from Design Maturity Review through final delivery, including ordering and receiving major items, hull fabrication, engine installation, Technical Data Package (TDP) submission, and Pre-Delivery Inspection Tests (PDITs).
The template indicates delivery will be to Groton, CT with a Government Notional Delivery of 545 days after contract award (DAC). Major items are specified to include engines, generators, and raw materials like aluminum. The document is marked as "DRAFT" and requires contractors to fill in the planned number of days after contract award or option exercise for each milestone event, with the Design Maturity Review noted as a one-time event.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Attachment 2 - Specification Response Matrix.pdf | ||
| Attachment 7 - DS Boat Spare Parts List.pdf | ||
| Attachment 11 - Technical Data Rights Assertion.pdf | ||
| Attachment 12 - Past Performance and Experience.pdf | ||
| Draft SOW.pdf | ||
| Attachment 5 - Electrical Load Analysis AC Distribution.pdf | ||
| Attachment 6 - Unique Item Identification.pdf | ||
| Attachment 9 - Warranty Terms.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DRAFTDesign Maturity Review
Order Major Items
Receipt of Major Items
Start Hull Fabrication
Install Engines
Submit
TDP
Conduct PDITs
Deliver Boat
Delivery Location
Gov't Notional Delivery
Boat 1 (CLIN 0001) Groton, CT 545 DAC
Notes:
4. DAC – Days after contract award Add additional column(s) if needed
N6426725Q415 Attachment 10
Production Schedule (Days After Contract Award (DAC) or Option Exercise (AOE))
1. Add the planned number of days after contract or option award for each of the events in the cells above.
2. Design Maturity Review is a one time event.
3. Major Items include engines, generators, and raw material suppliers (e.g. aluminum);