Attachment 1 - Technical Specifications.pdf

PDF 11 MB Posted

Attached to
External Staircase Removal and Replacement Federal contract opportunity
Solicitation number
191T7025Q0025
Issued by
Department of State

About this file

This document is a detailed Statement of Work (SOW) for replacing an old spiral staircase connecting Apartment 4 to the attic at the U.S. Embassy's Pinciana Residence in Rome, Italy. The project involves removing the existing narrow spiral staircase and installing a new steel staircase with improved design and functionality, including widening the steps, creating a more comfortable walking surface, and ensuring better structural integrity. Key technical requirements include using S275 steel for the primary structural components, welding steps to UPN beams and a central axis, and incorporating hot-dip galvanized anti-slip steel steps with a false overhang design.

The SOW specifies comprehensive civil works accompanying the staircase replacement, such as removing floor strips and roof coverings, creating niches for support beams, relocating a potable water pipe, removing wall protrusions, extending upper roof covering, and restoring masonry and plaster. The project has a 60-solar-day completion timeline from the Notice to Proceed, with the contractor responsible for submitting detailed shop drawings, safety plans, and maintaining strict safety protocols consistent with U.S. Army Corps of Engineers safety standards. The work must preserve existing pathways, electrical devices, and maintain the current aesthetic of the building while significantly improving the staircase's functionality and safety.

View the file

Other files for this federal contract opportunity

Other files attached to External Staircase Removal and Replacement, newest first.
File Type Posted
Questions and Answers 191T7025Q0025.pdf PDF
Amendment no. 0001.pdf PDF
Attachment 2 - Bill of Quantities.pdf PDF
SF-1442 - 191T7025Q0025.docx DOCX document
Cover Letter.pdf PDF
RFQ 191T7025Q0025.docx DOCX document

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Embassy of the United States of America

Rome, Italy

ROME – PINCIANA RESIDENCE

Replacement of Old and Narrow Spiral Staircase to Connect Pinciana 4 to the Attic

Facility Engineering Office

Summary

1. GENERALITY'

1.1. SUBJECT OF THE SCOPE OF WORK 4

1.2. GENERAL REQUIREMENTS OF THE SOW 4

1.3. OFFER AND ALL-INCLUSIVE PRICES 4

2. CURRENT EXISTING CONDITIONS

NEW STEEL STAIRCASE

WORKS FORESEEN IN THE PROJECT;

INTERFERENCES IN GENERAL

WORK IN GENERAL

CONSTRUCTION SITE SAFETY

3. PHOTOGRAPHIC DOCUMENTATION

4. PROCEDURE FOR EXECUTING THE WORKS

4.1. MATERIAL ACCEPTANCE RULES 22

4.2. GENERAL RULES 22

4.3. QUALITY OF MATERIALS 22

5. TECHNICAL REQUIREMENTS FOR THE EXECUTION OF RENTALS AND TRANSPORT

5.1. PROVISIONAL WORKS 23

5.2. RENTALS 23

5.3. TRANSPORTATION 23

5. TECHNICAL REQUIREMENTS FOR THE EXECUTION OF THE WORKS

5.1. LAYING OF THE MATERIALS 23

6. SITE ORGANIZATION AND SAFETY

6.1. DAMAGE 26

7. CONSTRUCTION SPECIFICATIONS

7.1. STEEL FOR METALLIC STRUCTURES 27

8. SOLICITATION CHARACTERISTICS

8.1. CONTRACT PHASE 35

8.2. IMPLEMENTATION PHASE 35

8.3. CONCLUSION PHASE 36

8.4. PERFORMANCE TIME AND PENALTIES FOR DELAYS 36

8.5. SUBCONTRACTING AND PIECEWORK 36

8.6. MATERIAL EQUIVALENTS 37

8.7. WORK PROGRESS 37

8.8. PARKING 37

9. MATERIAL SPECIFICATION

10. REGISTRY OF SUBMISSION

11. DRAWING

1. GENERALITY'

1.1. Subject of the scope of work

The subject of this SOW pertains to the following works:

• Replacement of the old spiral staircase and associated civil works.

For a comprehensive identification of the work, please refer to the technical conditions indicated in this SOW and the accompanying drawings. A complete maintenance booklet for each individual component must be delivered to ensure proper upkeep and longevity of the installations.

1.2. General requirements of the SOW

All works described in the descriptive and graphic documents must be carried out in strict compliance with current laws, rules, and regulations, and executed in a workmanlike manner. The Contractor is responsible for obtaining all necessary access permits or temporary occupation permits for the external area from the competent authorities.

• Disposal of Non-Reusable Materials: All non-reusable removal materials will be transported to public landfills or designated locations by the Client at the Contractor's expense. Suitable transport documentation must be provided, and delivery to authorized landfills must be ensured.

• Site Inspections and Surveys: The Contractor must include all costs related to site inspections and surveys deemed necessary during the construction site or temporary site inspection in the lump-sum prices referred to in this contract.

Prior to the start of work, the Contractor must provide the Client with:

• Construction Site and Assembly Project: A detailed project plan, complete in every detail, within 30 calendar days from the date of the Notice to Proceed.

• Detailed Work Schedule: A comprehensive schedule outlining the timeline and sequence of the work.

Upon delivery of the works, the Contractor will organize and set up the site within the area dedicated to the works, being responsible for the custody of means and materials. All charges related to demolitions, removals, and preparation of temporary works are included and compensated in the lump-sum prices.

1.3. Offer and all-inclusive prices

The works referred to in this deed are "lump sum contract." By accepting this contract, the Contractor declares that it has taken into account all particular and general situations inherent in the contract and has evaluated all obligations and charges indicated or referred to, including new prices if present.

The Contractor agrees to carry out the works according to the conditions and methods established or referred to in this Deed. The Contractor acknowledges that the consideration for the contract is inclusive of all works and furniture required for the perfect execution of the contract in its entirety and functionality, including charges of all kinds.

2. Current Existing Conditions

Currently, to reach the Attic from apartment no. 4, one must use a spiral staircase installed several years ago on one of the external terraces. Unfortunately, this spiral staircase presents several issues:

• The width of the steps, defined as the space between the railings, does not allow people of robust build or those carrying packages and bags to go up comfortably.

• The significant floor-to-floor distance, approximately 4.21 meters, forces the staircase to make more than one complete turn on its axis, causing inconvenience. Additionally, the step is height 20 cm.

However, It should be noted that the available space to build a staircase is very limited, mainly due to several existing interferences, such as a window, a balcony, protruding external perimeter curbs, and an external potable water pipe.

Photo 1 – Territorial Plan, in the red circle the Area in question

New steel staircase

The new staircase shall have a completely different design, focusing primarily on comfort. As shown in the attached floor plans, the footprint will be different and significantly larger. However, all existing pathways will be maintained, such as access to the balcony leading to the external terrace, the existing window, and all currently installed electrical devices, including lights, switches, and the intercom.

Picture 2 – Existing plan

Picture 3 – project Plan

The contractor, without increasing the projected costs, may also propose a valid alternative solution. The planned staircase will primarily consist of two knee beams (UPN 240), which will serve as the main supporting beams for the entire staircase. These steel beams will extend from the floor to a certain height, where two niches shall be created to support the beams on appropriately sized steel padstones.

As shown in the drawings, particularly the axonometric views, from step 16 onwards to the landing, the staircase will pivot around a central axis made of an S275 steel tubular beam, which shall be welded or bolted to the UPN beams. Steps 17 to 21 shall be welded to this central axis and anchored to the load-bearing walls using HILTI

M12 anchor bolts, at least 15 cm long, through steel plates with a minimum thickness of 10 mm, connected to the steps. For more details, refer to the axonometric drawings.

The steps shall be made from a single sheet that includes both the tread and the riser, using hot-dip galvanized anti-slip steel for outdoor use, with a geometric section that includes a false overhang (see detail "A" on drawing

03.A102). All steps will be welded to the two UPN beams and, from the 16th step onwards, to the central axis and the wall. Additionally, each step must be reinforced with two "L" shaped steel bar, at least 40*40*4 mm, and for larger steps, two or three bars may be required. The contractor must provide shop drawings of the steel staircase for final approval by the COR.

The new staircase must be equipped with metal railing according to the geometry shown in the attached drawings. The railing should also be made of steel, with the handrail welded to the two vertical tubular support elements labeled "B" and "C" to reinforce them (see drawings attached). The color should match the existing one.

Picture 4 – Elevation and Section new staircase

Regarding the civil works planned and connected to the staircase, in more detail:

• Removal of Floor strip and Screed: The floor strip and associated screed will be removed to position the steel plate with a minimum thickness of 15mm, type S275. This steel plate, which shall be professionally welded to the two UPN beams, will serve as a load distributor to prevent overloading or stressing the base floor. The plate must be supported and embedded into the two load-bearing perimeter walls, as shown in the drawings. The plate should extend at least 20 cm into the walls, and the created niches must be restored with controlled shrinkage thixotropic concrete (type R3 or R4) and previously removed brick pieces to recreate the initial conditions.

• Removal of Roof Covering: The roof covering affected by the new staircase footprint shall be removed.

Starting with the dismantling of Plexiglass sheets, secondary wooden beams, and then the main wooden beams. The holes left by the main beams must be filled with masonry pieces and concrete. Refer to drawing 05.A-104. Note that some rigid pipes and an electrical box will need to be relocated to the remaining roof area, using new materials and cables if necessary. The new rigid pipes must be painted to match the existing color. The removal also includes the downspout and associated flashing for rainwater collection.

• Creation of Niches for UPN Beams: Niches shall be created to support the two UPN beams on the wall. The demolition must be controlled, using a hammer and chisel to avoid stressing or damaging the existing wall. The niche must be large enough to accommodate the base support steel plate (padstone), at least 300*200*20mm. The two UPN beams shall be welded to the plates. The niches shall then be restored using the same masonry material previously removed and low-shrinkage thixotropic concrete

(type R3 or R4).

• Relocation of Potable Water Pipe: A potable water pipe running externally along the wall has been found in the intervention area. This pipe makes a significant interference that must be managed to install the new staircase. The plan includes embedding the pipe within the existing masonry, including installing an inspection box for the existing valve. The new pipe can be made of different material as long as it has the same section and is suitable for potable use. Once the pipe is embedded, the masonry and plaster must be restored.

• Removal of Wall Protrusions: Various masonry protrusions in the staircase area must be removed, as highlighted in drawing 05.A-104. After the work, the plaster must be restored to ensure continuity with the existing wall.

• Extension of Upper Roof Covering: The existing upper roof covering must be extended to the end of the building housing the external elevator, as shown in the photographic documentation and drawing

05.A-105. The supporting structure must match the existing one, including the main and secondary beams with the same section, Plexiglass sheet, and all necessary hardware, such as aluminum joint covers, nails, anchors, holes in the floor, cementitious thixotropic mortar for beam anchoring, and plaster finishing.

• Restoration of Masonry and Plaster: The work includes restoring masonry and plaster to a perfect finish, both for areas directly affected by the work and other deteriorated areas within the construction site. The plaster must be suitable for exterior use, complete with smoothing, and ready for wall painting.

• Concrete Elevation Step: To meet the dimensional requirements of the staircase steps, which must not exceed a certain height, a false platform measuring 1m x 0.7m x 0.07m shall be built at the beginning of the staircase, as shown in the project plan. This platform must be covered with the same tiles as the existing floor, using special corner pieces at the edges

• Painting: Upon completion of the work, the affected walls must be painted with two coats, using the same colors as the existing ones, for both vertical facades and other protruding curbs.

Picture 5 – Axonometrics

Picture 6 - Axonometrics

Works foreseen in the project;

The works shall include:

1. Site Preparation;

2. Removal of floor strip and screed

3. Removal of roof covering

4. Dismantling of existing spiral staircase

5. Creation of niches for UPN beams

6. Relocation of potable water pipe

7. Removal of protruding curb

8. Installation of new staircase

9. Extension of upper roof covering

10. Restoration of masonry and plaster

11. Concrete elevation step

12. Painting

INTERFERENCES IN GENERAL

In the photo below, all external interferences that need to be removed, demolished, and/or rebuilt to construct the new staircase are highlighted and summarized.

Picture 7 – Interferences To Be Removed

WORK IN GENERAL

All civil, electrical, hydraulic, and temporary safety works must be supported by plans and executive drawings approved by the COR. At the end of the work, the Contractor must provide original format files (e.g., dwg, word, excel) of the As-Builts.

CONSTRUCTION SITE SAFETY

The safety of the construction site, including all charges foreseen by current legislation, is crucial. This includes:

• Fencing of the construction site area.

• Protection of existing window, balcony and any electronics device.

• Necessary small scaffolding for the planned works.

In addition, all the work shall comply with the US Army Corps of Engineers (USACE) Safety and Health

Requirements Manual (EM-385-1-1) for contractor safety.

3. PHOTOGRAPHIC DOCUMENTATION

Photo 8

Photo 9

Photo 10

Photo 11

Photo 12

Photo 13

Photo 14

4. PROCEDURE FOR EXECUTING THE WORKS

4.1. Material acceptance rules

The materials required for the construction of the works, whatever their origin, shall be of the best quality, and will be considered accepted only when, at the unquestionable judgment of the COR, they correspond to those designated below in terms of nature, quality, durability, suitability and application. Except for special materials, all the works must come from quarries, factories, refineries, etc., deposits. chosen exclusively by the Contractor, which cannot make any exceptions.

4.2. General rules

The items below must establish the execution rules for the various works contemplated in the Contract, as well as the technical specifications of the materials used.

By rule of thumb, in the execution, the Contractor shall have to comply with the best rules of the art as well as with the following works. For the categories of works that are not found in this SOW, and for which no special rules have been prescribed, in particular for any work to be carried out economically, the Contractor must follow the best procedures dictated by the technique and comply with the orders that for this purpose, the COR will issue.

Works which, for any reason, immediately or subsequently prove to be badly performed, must be redone at the Contractor's expense, without the need for a formal request from the COR; the possible presence on site of an overseer of the Principal cannot be invoked by the Contractor in discharge of its liability.

For the works on the networks and for the construction of artifacts and works of art, the Contractor, having received the delivery, referring to the project cornerstones, will first carry out the tracing of the work by affixing the stakes and modifiers for the axis, for the sections and for the works of art; at his care and expense the pickets will be maintained until completion.

4.3. Quality of materials

All the works envisaged by this SOW can be performed in perfect working order and with materials that meet the technical specifications indicated and/or referred to in this SOW.

The quality of the material used in the execution of these works must meet, when not otherwise specified by Contractor rules or regulations, the requisites required by the laws in force and by the official standards of good construction techniques.

The Client, during construction and at any time, may take material samples from the manufactured articles used to verify their perfect correspondence with the approved types.

In this case, the Contractor will have to make an operating team available to the client to carry out the activities necessary for the execution of these checks, carried out with the help of a specific specialized

Contractor. These charges will be charged to the Contractor, including any demolition and reconstruction of the works found to be non-compliant.

The Contractor must promptly report any defect or anomaly found on the materials supplied.

5. TECHNICAL REQUIREMENTS FOR THE EXECUTION OF RENTALS AND

TRANSPORT

5.1. Provisional works

The main regulations concerning scaffolding and scaffolding, fixed metal scaffolding, mobile scaffolding, etc., are contained in Legislative Decree 81/08 and subsequent Legislative Decree No. 106 of 08/03/2009.

5.2. Rentals

The machines and tools given for hire must be in perfect working order and be equipped with all the accessories necessary for their operation. The maintenance of tools and machines is the exclusive responsibility of the Contractor so that they are in constant efficiency.

The lump sum price includes transport from the place of origin to the construction site and vice versa, assembly and disassembly, labour, fuel, lubricants, consumables, electricity, scrap and everything for the necessary functioning of the means. They also include general expenses and the entrepreneur's profit in the freight rates.

5.3. Transportation

If the size of the material to be transported is less or more than the payload of the vehicle requested for hire, no price reductions or increasing are envisaged.

The supply of consumables and the driver's labor are included in the transport prices.

5. TECHNICAL REQUIREMENTS FOR THE EXECUTION OF THE WORKS

5.1. Laying of the materials

The Contractor shall follow what is include the technical sheets of the materials that we use, after approval by COR.

6. SITE ORGANIZATION AND SAFETY

The safety of the construction site, including all charges foreseen by the current legislation, will be an important aspect for the planned works. The item includes the following:

- Fencing of the construction site area, temporary walkways, construction site bathroom.

- All types of scaffolding possibly necessary for carrying out the planned works.

In addition to the provisions of the SOW, the following remains established:

1. upon delivery of the works, the Contractor must designate by name a technical assignment employed by or registered in a specific professional register with the task of directing the organization of the site and supervising the conditions of safety and use of the manpower, equipment and materials. Said technician is required to always be present on site.

2. The Contractor is required, during the preparation of the site, the execution of the works to observe the rules on accident prevention and occupational hygiene referred to in Presidential Decree 27.04.1955, n.547, to Presidential Decree 07.01.1956, n.164, to Presidential Decree 03.19.1956, n.303, to Legislative

Decree 81/2008 and subsequent amendments. mod. and supplement and subsequent provisions even if issued during the course of the works.

3. The Contractor has the obligation to comply with the "safety plan" or the one amended following the supplementary proposals formulated by him and to comply with the related implementing provisions that will be issued during the works by the "safety coordinator during the execution of the works"; the Contractor must also draw up and promote to the COR, in the manner established by the combined provisions of the aforementioned Legislative Decree 81/2008, an operational safety plan that takes into account the organizational, technical, procedural and technological reality of the Contractor itself. In the event of a temporary association of companies, the above applies to the agent Contractor or Contractor designated as group leader. In the event that the drafting of the safety and coordination plan is not envisaged, the

Contractor must draw up and deliver its own replacement safety plan to the COR within the terms established by the Rule. It should be noted that the amount of the charges deriving from the implementation of the provisions of the aforementioned construction site safety documents, expressly indicated in the specifications, are understood to be offset and included in the unit and/or bulk prices of the various items of the estimate. Having established that the percentage safety incidence of the safety charges of each individual estimate item is conventionally assumed to be equal to the ratio between the global work costs and the gross amount of the safety charges, the portion of the amount not to be subject to a discount will be equal to product of the aforementioned incidence by the gross amount booked.

4. The Contractor is obliged to adapt the working hours to the User's needs, with the obligation to obtain the information in advance.

5. The Contractor, through its manager, will have to keep a register updated on the construction site, to be shown for inspection by the Project Manager himself or someone on his behalf, such as in the work itself or to be noted on a daily basis materials and inflows on site to be used in the works, those used in the execution of the works themselves and those removed from the site, with the resultant of the materials stored there. He must keep the packing slips/supply of materials in absolute order in special catalogues/binders prepared for this purpose.

6. It is absolutely forbidden to access the site for Contractor personnel who, where requested, refuse to submit to personal checks or checks on things in tow. The contracting station declines any responsibility if the refusal referred to in this paragraph causes delays, hindrances or even the impossibility of executing the contract.

7. The Contractor must maintain discipline on construction sites and is obliged to observe and away from his agents and his agents, the regulations and provisions in general issued by the contracting station and by the competent authorities for the good order and discipline of the works. The Contractor must employ suitable persons for his agents, foremen and workers. The construction manager has the right to order the change of duties of the Contractor's personnel in cases of ineptitude and the removal of personnel from the works in cases of insubordination and bad faith. In any case, the Contractor remains liable for damages caused by the inexperience, negligence or bad faith of the personnel themselves.

8. To guarantee the execution of the works, maintain personal surveillance compliance in all construction sites, even if external to the places of work, on all the means used by the Contractor, as well as in the production and material processing workshops. When this is established by the regulations, by the specifications and by the contract and when the contracting station, in warning of any regulatory or contractual requirement, signifies to the contracting party that it wants to make use of this right, the contracting station itself has the obligation to inform the station in good time Contractor of the start of processing of objects related to the works and to give it all the information it deems necessary for the exercise of supervision. He must also indicate, if requested, the establishments from which he intends to order the materials necessary for the execution of the contract.

9. The works must be carried out in a workmanlike manner and the materials to be used must be of the best quality available on the market, free from any general and special defect, meet all the other requirements indicated in the technical specifications and in the specifications as well as in the Decrees bearing the conditions mandatory general techniques. When it comes to national products, the Contractor is free to procure materials where he deems the best, provided that they have requirements where prescribed by the contract, unless in these general conditions, in the special chapter or in the price tariff, special requirements are prescribed on origins some materials. The Contractor must justify, with the presentation of suitable documents, the actual origin of the materials, and lend himself to subjecting them to all the tests that the project manager deems appropriate to ascertain their quality and resistance. The materials cannot be used if they have not been previously accepted by the construction manager who has the right to refuse those he does not recognize as suitable for the goodwill of the works. The rejected materials must be removed from the construction sites within the term established by the construction manager and at a convenient distance; failing the Contractor to comply with the relevant provision, the site manager has the right to do so directly, charging the Contractor the related expense, which will be deducted from the first advance certificate. Acceptance does not affect the right of the contracting station to refuse, at any time until testing, the works performed with materials that do not comply with the contractual conditions, materials to proceed, pursuant to art. 18 of DM 145/2000, in the case of construction defects. When the

Contractor presents concrete for and the relative samples, the contracting station may examine proposals to replace the quality of the materials and their origin, if prescribed, however reserving the full right to accept and reject said proposals. If, even without opposition from the site manager, the Contractor has on his own initiative used materials of a better prescribed excess weight and size, or of a more accurate quality or mastery, he is not entitled to any price increase, whatever the the advantages that can derive from the contracting station; and in this case the accreditation of the Contractor is done as if the materials found the weight and dimensions, the qualities and the mastery established in the contract. Conversely, objects or materials of weight, characteristics and/if smaller than those prescribed, or of lower quality or less accurate workmanship are used, they will be counted by reducing in proportion to the lower weight, smaller dimensions and different quality and processing the corresponding prices. All general and specific charges, in any case connected to the obligations listed above, are to be paid in full and at the expense of the

Contractor, having taken them into account in determining the individual unit prices, by measure or as a whole of the tender specifications.

6.1. DAMAGE

1. The Contractor is responsible for all measures, including provisional works and all obligations to avoid the occurrence of damage to the works, the environment, people and things in the execution of the contract pursuant to art. 14 of the DM n. 145/2000.

2. No compensation is due for damage caused by force majeure to temporary works, scaffolding or site vehicles and equipment .

7. CONSTRUCTION SPECIFICATIONS

7.1. STEEL FOR METALLIC STRUCTURES

• Typology

For the construction of metal structures, steels compliant with the harmonized standards of the UNI EN

10025 series (for rolled steel), UNI EN 10210 (for seamless pipes), and UNI EN 10219-1 (for welded pipes) shall be used. These steels must bear the CE marking as required by Directive 89/106/EEC – Construction

Products (CPD), implemented in Italy by Presidential Decree 21/04/1993 n. 246, as amended by

Presidential Decree 10/12/1997 n. 499, and must be certified with a system of attestation of conformity as defined in point 11.3 of the NTC 2018.

For the verification of mechanical characteristics, the sampling of specimens, the position in the piece from which they must be taken, the preparation of test tubes, and the test methods must comply with the requirements of UNI EN ISO 377/1999, UNI 552/1986, EN 10002-1/2004, and UNI EN 10045-1/1992 standards.

For the construction of all primary metal parts, the use of S275 steel is prescribed as indicated in the executive tables and as defined in point 11.3.4.1 - Generalities of the NTC 2018.

All steels must have a chemical composition that complies with the applicable harmonized European standards, as defined in point 11.3.2.6 of the NTC 2018. As provided in point 11.3.4.5 - Welding Process of the NTC 2018, the welding of steels must follow the procedures codified by the UNI EN ISO 4063/2001 standard. Welders using manual and semi-automatic procedures must be qualified according to the UNI

EN 287-1/2004 standard. Welders making fillet tee joints must be specifically qualified and may not be qualified by making butt joints only.

During welding, the UNI EN 1011/2005 standards parts 1-2 must be adhered to. Bolts used must comply with the UNI EN ISO 4016/2002 and UNI 5592/1968 standards. The use of bolts consisting of class 8.8 screws and class 8 nuts according to the UNI EN ISO 898-1/2001 standard

• Identification

The product supplied by the Contractor must have branding that clearly shows the reference to the manufacturing company, the production plant, the type of steel, and its quality grade. The trademark must be filed with the Ministry of Public Works, Central Technical Service. Failure to mark or illegibility, even partial, will result in the refusal of the supply. The Contractor shall provide the COR with certificates relating to the qualification tests and periodic quality verification tests; these certificates must clearly show:

• The name of the manufacturing company, the plant, and the place of production

• The test certificate according to UNI EN 10204:2005

• The identification mark of the product filed with the Central Technical Service

• The details of the last deposit certificate obtained for the theoretical quality verification tests

• The date of sampling, the place where the tests were carried out, and the date of issue of the certificate (not earlier than three months from the date of the site inspection)

• The nominal and actual dimensions of the product

• The results of tests carried out in the factory or in an official laboratory

• The chemical analysis, which for weldable products, must satisfy the composition limits recommended by UNI 5132

• The statistical processing required by the attachments of the Ministerial Decree of 14.01.2018

The COR may request to take samples of materials for further tests.

• Marking

The Contractor shall mark and document all materials to ensure they are used as specified.

• Location of Markings

The markings must be positioned so as not to be hidden by other materials after installation.

• Stamping

If the steel is to be sandblasted, acid-treated, sprayed, or galvanized, it must be marked with low-pressure marking. Marks must be of adequate depth to avoid deletion. Sandblasting, where necessary, must be done according to the American standards.

• Length

Members having both ends prepared for compressive contact, such as struts or columns, should not deviate from the intended length by more than 1mm. Elements that do not have the ends prepared for compression contacts, and which must be connected to other metal parts of the structure, must not deviate from the pre-established length by more than 2mm if the total length is equal to or less than 10m, and 4mm for elements longer than 10m.

• Compression Joints

The gap between joints whose performance, when assembled during manufacture, depends on compressive contact, must not exceed 0.75 mm and must be less than 0.25 mm over 50% of the contact section length.

• Storage and Handling on Site

Steel structures will be placed in a separate storage area from other site materials. This area will be kept clean. The Contractor will ensure that there are no earthy residues or other impurities/slag on the surface of the profiles before assembly. If there is dirt, it must be removed by brushing. All steel structural elements brought to the construction site and stored before installation must be adequately protected and supported to be lifted off the ground. Part markings must be visible when parts are stored. The Contractor must use the utmost care in packing the material and in handling and transporting the metal structures to avoid any damage to the structures themselves and to the protective layers.

• Pre-assembly on Site

All pre-assembly of the structures will be carried out on benches raised off the ground, suitably prepared by the Contractor. The pre-assembly areas, unless otherwise agreed with the COR, must be outside the perimeter of the finished building. Upon delivery of the works, the COR will indicate to the Contractor the areas envisaged for pre-assembly. The pre-assemblies must be carried out according to the assembly program, and all pre-assembled material must be stored in appropriately prepared buffer areas. All material stored in the buffer areas shall be sequenced according to the installation schedule. If it is not possible to provide site areas sufficient to allow the pre-assembly of the structures on site, this operation must be performed by the Contractor at its workshops or another place agreed upon and accessible to the Works

Manager. The material must arrive on site already sequenced according to the assembly schedule.

• On-site Assembly

Before drawing up the tender offer, the Steel Works Contractor is required to carry out a site visit to ascertain the operating conditions associated with assembly. On this occasion, a "Report of the Visit" must be drawn up. During the preliminary site visit, the following areas will be identified:

• Storage area

• Pre-assembly area

• Assembly area (lift)

All in relation to effective general operations. The Contractor is required to check the tracing of the anchors to the reinforced concrete structures before starting the assembly phase. Under no circumstances will claims relating to tracking errors be accepted by the executor of the civil works.

• Cutting

Steel must be cut with an automatic or semi-automatic system. Manual or flame cutting will be used only when the use of automatic or semi-automatic machinery is not possible, and only with the approval of the

COR. The use of hot device cutting equipment is not permitted without prior approval. If flame cuts are made, the edges of all the cut plates must be smoothed to remove scale, marks, deposits, irregularities, and excessive hardening. Burrs, sharp edges, and irregular edges must also be removed by grinding.

• Bearing Contacts for Joints Subjected to Compression

Joints subjected to compression will have contact surfaces prepared to obtain an adequate joint plane. It will be possible to use filing, cutting, or other equivalent systems approved by the COR. The surfaces intended for contact joints must be at right angles to the nominal axis of the element itself. Different angles will be accepted only if indicated and annotated in the carpentry drawings. It is not necessary to carry out any additional preparation on surfaces intended to be incorporated in mortar beds, such as foundation plates, or those of attachment of metal structures to concrete structures.

• Stiffeners

The stiffener gussets will be cut and sanded to ensure precise contact along the edges of the flanges.

• Straightening

No straightening of the material must be carried out that could cause alterations of its physical or chemical characteristics and consequently non-compliance with the requirements specified for the material at the time of supply. Before starting work, the Contractor must provide the COR for approval and include in its

Method Statement the procedures it intends to adopt for any straightening interventions on structural elements.

• Heating

No heating of the material must be carried out that could cause an alteration of its characteristics and consequently non-compliance with the requirements specified for the material at the time of supply.

• Temporary Connections

After their use, the Contractor must remove any temporary connections that may have been necessary to implement their method of manufacture or implementation. The removal of any temporary element must take place in compliance with the relevant regulations and with a procedure agreed upon and approved by the COR.

• Assembly

Whatever the assembly sequences, the Contractor must take into account the static behavior of the structure in the partial configurations and the stresses produced during the lifting phase by drawing up a specific calculation report. It will also be necessary to define the type of substrate suitable both for the passage of vehicles and for the correct pre-assembly of the structures.

• Alignment of Structures

All structural parts will be aligned as soon as possible after their assembly. Permanent connections between the various members will not be made until the structure has been sufficiently aligned, leveled, plumbed, and temporarily connected. The Contractor shall ensure that the various components do not go out of square when setting up or aligning the rest of the structure. Due consideration should be given to the effects of temperature on the structure and measuring instruments when taking measurements for layout, siting, and construction, and for all subsequent dimensional checks.

• Pillar Leveling

The leveling and plumbing of the pillars will be done using flat wedge-shaped steel plates of adequate size, strength, and stiffness. Where leveling plates are left in place for later incorporation into mortar, they should be positioned so that they are completely enclosed and covered by the casting.

• Theoretical Design Counter-arrows

The geometry shown in the drawings of the Executive Project corresponds to the undeformed structure and net of preforming; the Construction design will have to consider the appropriate strategies for a possible pre-camber.

• Counter-arrows for the Settlement of the Joints

A further and adequate preforming may be envisaged to cope with irreversible settlements, taking into consideration the cumulative settlement of the joints present in the roofing structure.

• Baseplate Bolts in Sleeves

The anchor bolts of the base plates must be placed at a suitable distance from the surfaces that laterally limit the reinforced concrete structure to which they are anchored. The anchorage length must comply with the provisions of the DM 14.01.2018. The plan position of the base bolts positioned in sleeves, which will eventually be concreted in, must not deviate from the position specified on the drawings by more than 5 mm.

• Welded Joints

Welds and steels for welded structures must comply with the recommendations contained in UNI 5132.

Welds must be done under the direction of welder technicians who have appropriate qualifications and who have procedure certification according to UNI 4634.

• Welding Procedure

The welding procedures must comply with the recommendations of UNI 5132. For the execution of the welded joints on site and/or at the foot of the work, an approach of the parts must be guaranteed within the tolerances allowed for each type of welding. The necessary supports of the filler material must therefore be provided in accordance with the preparation of the flaps. All necessary precautions must be taken for perfect alignment of the parts to be welded. As a general rule, welds should not be smoothed unless explicitly indicated on the drawings. Welding procedures and fabrication sequences should be such as to minimize distortion.

• Temporary Welds and Temporary Connections

Temporary welds and those relating to temporary joints, necessary for manufacturing and/or installation, must comply with the aforementioned regulations and must be removed so as not to damage the permanent works. The removal method must be submitted for the approval of the COR.

• Butt Welds

Where possible, backplates will be used to ensure full thickness/fill of the groove at the ends. These plates must meet the following requirements:

✓ The mechanical and physical characteristics for the plates must be identical to those of the material to be welded.

✓ The plates must be prepared in the same way as the parts to be joined.

✓ After completion of the weld, the plates must be removed by cutting. The surfaces to which they were attached should be chamfered, ground, and inspected for cracks.

• Welds of Pins or Connectors

Where foreseen, the rotation or sliding pins must be installed according to the manufacturer's prescriptions both for the materials and for the accessory procedures and devices.

• Welding Test

Before starting work, the Contractor must conduct a series of welding tests on pins/connectors to verify the adequacy of the welding system and the proposed equipment. The tests must be carried out using the same material and the procedures foreseen for the works. At least ten percent of the connectors must be tested in trials. In the hypothesis of in situ welding of the connectors, at the beginning of each shift, at least two welding tests must be carried out for each welder.

• Slag Removal

The slag will be removed with light hammering, metal brushes, or other methods that do not deform the weld surface.

• Holes for Bolted Connections

All holes will be punched and reamed unless otherwise agreed with the COR. Unless otherwise indicated on the drawings, the holes for normal bolts must have a diameter equal to that of the bolt, increased by 1.0 mm up to diameter 20 mm, and by 1.5 mm for diameters greater than 20 mm, except for foundation plates where a slightly larger tolerance is acceptable. In the event that the holes move out of alignment between two flanges, it is not permissible to enlarge the holes or distort the metal to achieve alignment. For bolts and vent holes in hollow sections, the holes shall be sealed to prevent moisture ingress. If the methodologies to be used are not specified in the project documents, they will be defined by the Contractor who will illustrate them in their method declaration.

• Preparation of the Elements to be Bolted

For all bolted assemblies, the degree of resistance of the bolt-nut-washer combination must comply with the provisions or recommendations in the relevant Standards.

• Condition of the Bolts

The bolt assembly immediately prior to installation must be in such a condition that the nut rotates freely on the bolt.

• Washers

Each bolted connection must contain at least one washer placed under the part being rotated.

• Variable Thickness Washers

These washers shall be used under bolt heads or nuts that rest on surfaces inclined 3 or more degrees from the plane at right angles to the bolt axis.

• Locking Bolts

Nuts used in joints subject to vibration or reverse stress will be suitably locked. If the methodologies to be used are not specified in the project documents, they will be defined by the Contractor, who will illustrate them in their method declaration.

• Length Limits

The length of the bolt must be such that at least one thread is visible above the nut after pulling, and at least one thread other than the final thread is free between the nut and the non-threaded part of the bolt.

• Bolt Pull

The tightening torques will comply with the recommendations contained in Eurocode 3. The tightening must never be pushed beyond the nominal limit to avoid compromising the capacity of the joint. The tightening torque tolerance is 10%.

• Connections that Allow Movement - Slots

If slotted holes are indicated on the drawings to allow movement, the joint must be assembled in such a way as to allow the desired or prescribed movement. Slotted connections will be made using the following method:

• The slotted hole must be of a larger diameter than the non-slotted one.

• A bolt of the large head type must be used, with a spring washer under the head, which rests on the contact surface of the non-slotted part.

• A flat washer must be placed under the nut, and this must be tightened on the non-slotted side.

The Contractor is strictly prohibited from making slots in the connections where they are not specifically prescribed by the project. In the event that this prohibition is not respected, the DL will order the immediate replacement of the pieces in question.

• Chemical Connectors

Where specified in the project documents, the use of connectors that use chemical resins is permitted, provided that the specifications and methods required by the manufacturer are scrupulously followed. The choice of the appropriate type of chemical connector, if not indicated in the project documents, will be made by the Contractor based on the loads and functions that the connector must perform, subject to approval by the Works Manager.

• Anchor Bolts

All base bolts should be securely in place during installation. During all stages of construction, all bolts, threads, and nuts shall be protected to prevent damage, corrosion, and contamination. The cavities formed to house the base bolts must be kept free and clean of foreign bodies.

• Corrosion Protection - Galvanizing

For the metal members (steel), a protection system for galvanizing by hot immersion is foreseen according to UNI 5744/66. The protection systems must be preceded by the preparation of the surfaces, consisting of:

• Degreasing

• Washing

• Pickling

• Washing

• Flushing

• Desiccation

Furthermore, the preparation must include:

• Preparation of the metal support with sandblasting cleaning to Sa21/2 degree according to SSPC-

SP10/63; procedure to be carried out exclusively with initial state of steel A, B, C, D according to photographic standard SIS 055900/67. Reach proficiency level A21/2, B21/2, C21/2, D21/2. If the metal support does not meet the above photographic standard, it must be brought to that state before the subsequent preparation.

• Preparation of the metal support with Sa3 grade white metal sandblasting cleaning according to

SSPC-SP5/63; procedure to be carried out exclusively with initial state of steel A, B, C, D according to photographic standard SIS 055900/67.

8. SOLICITATION CHARACTERISTICS

8.1. Contract phase

Within 15 calendar days of the date of award, the Contractor shall submit the following documentation to the Embassy’s Technical Office:

· A final and detailed work schedule of the various interventions and relative length of time required to carry out all the work requested in the contract.

· A final Safety Plan as set forth in the General chapter, finalized with the names of all actors and with the results of the discussions with the POSHO.

· A list of the names, complete with bio-data, of all the employees, as well as possible suppliers and sub-

Contractors for specific work, who will require access to the work-site. Furthermore, the Contractor shall submit a complete list of vehicles to be used during the project, indicating the make, model and license number.

· Designation of someone who will be in charge of the project on behalf of the Contractor and who will be fully authorized to discuss and decide together with the COR any variations during the course of the project, both concerning methodology of the work and the supplies.

· Designation of a Safety Manger who will address all safety issues and will monitor the daily operations.

· The register of submittals.

8.2. Implementation phase

· The implementation phase starts with the Notice to proceed (NTP).

· No work shall be performed before the submission of the shop drawings and relevant approval.

· No materials shall be installed prior the relevant submission and approval.

· Normal working hours are from 08:00-08:30 up to 17:30 during weekdays. Any work to be carried out after normal working hours or during the week-end shall be agreed upon in advance with the COR in order to obtain all the necessary authorizations and approvals.

· Demolitions, perforations and other high noise operations shall be carried out no earlier than 09.30. The quiet rule shall apply even during the time 12.30 to 15.30, during work days.

· The work-site shall be kept as clean as possible.

· Areas for storing material shall be agreed upon, together with the COR, based on logistical-operative criteria.

· Any temporary interruptions of utilities shall be scheduled at least 5 days in advance and shall be subject to approval from the COR.

· Tests on the correct operation of the systems and consignment of parts of completed work shall be carried out in the presence of the person designated by the Contractor and someone authorized by the Embassy.

The Contractor shall be responsible for drawing up the necessary delivery reports for the work and systems carried out and shall be subject to verification and acceptance by the COR.

8.3. Conclusion phase

· Once the project is completed a final inspection shall be carried out with representatives of the Contractor and the Embassy, in order to verify that the project has been carried out correctly, that it is in compliance with the technical specifications and that the systems operate correctly.

· When the work has been completed and accepted by the COR, the Contractor shall submit the following documents to the COR:

· detailed “as-built” drawings showing the new constructions, both the architectural/structural aspects as well as all the systems. The drawings shall be submitted on paper and software in ".dwg" format.

· technical cards of the most important materials used in the project, with a list indicating the location of the vendors and local suppliers.

· certification of conformity and tests carried out by the manufacturers for materials, as well as guarantee of the correct installation of all the materials by the Contractor with regard to the project realization and law requirements.

8.4. Performance time and penalties for delays

The contract performance time and the methods with which these times will be calculated are fully described in the solicitation package and here listed for convenience.

The Registry of Submission, at the following of this document, shall, (but shall not be limited to), indicate the kind of material samples and the number of them for selection and approval by the COR.

Period of time the complete execution of the project, from mobilization to final cleaning:

60 solar days from the "Notice to proceed".

Penalties for delays in completing the project are those described in the tender documents.

8.5. Subcontracting and piecework

In the subcontracting authorization request and in the subcontracting agreement, the Contractor shall promptly indicate the operational scope of the subcontract, in terms of performance, and specify in unambiguously, in particular, the name of the sub-Contractor, the description of the work or services to be subcontracted – indicating the relative quantities or dimensional parameters referred to each execution area and process phase and referring to the project - the individual areas the individual process phases in which the subcontracted work or services will be performed.

In any case, the Contractor remains responsible towards the contracting authority for the execution of the works subject to subcontracting, relieving…

This is the start of the file's text. The full file is on GovTribe.