Attachment 1 - Statement Of Work.pdf

PDF 393 KB Posted

Attached to
HVAC Repair, Bldg. J01164, JBLM, WA
Solicitation number
W911S8-21-B-0003
Issued by

About this file

This is an invitation for bid for HVAC repair services at Building J01164 located at Joint Base Lewis-McChord in Washington. The solicitation requires repairing the climate control units, installing additional exhaust fans, repairing air handling units and exhaust units, and repairing controls. A mandatory site visit and pre-bid conference will be held on May 20, 2021 and all questions are due by May 24, 2021. Bids must be submitted electronically by June 11, 2021 at 1:00 PM PDT to the Contracting Officer. The work must be completed within 180 calendar days of notice to proceed.

View the file

Other files

Show all 14

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATEMENT OF WORK

January 13, 2021

CONSTRUCTION

RFP Final Date: January 25, 2021

1. GENERAL DISCUSSION:

1.1. Project Identification

1.1.1. Project Title: Repair HVAC Hangar 7

1.1.2. IJO Number(s): MCD001883J

1.1.3. Project Package Number(s): PS 2116

1.2. Description of Work

1.2.1. The contractor shall supply all supervision, labor, equipment, and materials to perform all work in strict accordance with the contract, this statement of work, and identified drawings to repair HVAC at J01164.

1.3. Area Description

1.3.1. Location

1.3.1.1. Building J01164 (Hangar 7) is a fuels system maintenance dock used for C-17 aircraft. The building is located on B St. in between Levitow Blvd. and 8th St. on McChord Field.

1.3.2. Known Existing Site Condition

1.3.3. Hangar 7 has two climate control units (CCU) that are used to control temperature and humidity for C-17 fuel cell maintenance purposes. These units have control panels for summer and winter modes, purge, cure, etc. These units are failing and are not able to provide enough purge air or temperature control for proper fuels maintenance. The CCUs are suspended from the hangar’s roof truss system approximately 20’ above finished floor (AFF); one on each side of the west wall. Additionally, the two air handlers serving the hangar bay area are failing and cannot provide adequate heat to the space. This directly affects the ability to control the temperature in the hangar for curing purposes when conducting maintenance. The existing exhaust units are failing and will be replaced, as well as adding two more exhaust units.

1.4. Principal Items To Be Accomplished

1.4.1. The following applies to all CLINs:

1.4.1.1. Hangar 7 is classified as a Class I, Division I hazardous location up to 18” AFF. Additionally, perimeter walls up to 4’ AFF are classified as Class I, Division I for all switches and receptacles.

Electrical work in the hangar shall comply with National Electric Code (NEC) hazardous location requirements.

1.4.1.2. Wall penetrations for conduit, ducting, etc. shall be sealed properly and be watertight and fire stopped.

1.4.1.3. Interior conduit shall be EMT; exterior conduit shall be RGS. All new conduit shall be ¾” minimum and be installed using compression fittings (watertight where exposed to elements) and be properly installed and secured per NEC.

1.4.1.4. Any flexible conduit runs used shall be limited to 3’ maximum in length per component and shall be properly supported. Cable ties/zip ties are not permitted for conduit support. Contractor shall update panel schedules for any panel that is altered during construction.

1.4.1.5. If any insulation materials used are listed in the following website, the materials shall meet the recycled content percentage listed: https://sftool.gov/greenprocurement/green-products/1/construction-materials/22/building-insulation/0

1.4.1.6. All recycled materials and waste shall be documented and submitted to the Government per the DPW CD diversion and disposal reporting instructions. All piping and materials not to be reused for the new system shall be removed and disposed of with no abandoned material left on site. The contractor shall broom clean the area to include all construction/demolition debris after demo is complete. Before Government final inspection the area shall be wet cleaned with cleaning agent and no abandoned materials or trash left on site.

1.4.1.7. Contractor shall conduct a modified Performance Verification Test (PVT) on new equipment with DPW BMS system manager. Provide a PVT checklist submittal before scheduling PVT. Any non-functioning equipment that is not part of this contract will be noted by the Government.

Complete seven day trend after PVT.

1.4.1.8. Contractor shall follow JBLM DDC specification 23 09 23 to include DDC Phase I & II trainings and a 14 day notice when requesting PVT.

1.4.1.9. Contractor shall install a laminated warranty tag on all new equipment stating contractor’s name, point of contact with phone number, date of install, warranty dates, and Government PM name and email. Attach with zip tie on equipment in noticeable location and complete before government final inspection.

1.4.1.10. Contractor shall install O&M’s for all new equipment in a clear plastic container near existing O&M’s in the fire pump room properly labeled “BLDG J01164 O&M’s”. Contractor shall install a label on the plastic tote that provides an itemized list of which O&M’s it contains; label shall be waterproof (cover with tape, laminate, etc.). Contractor shall supply DPW PM with an electronic copy of new O&M’s on a CD as a submittal.

1.4.2. Base Item CLIN 0001: Repair Climate Control Units, Bldg. J01164, IJO: MCD001883J, Equipment

1.4.2.1. Contractor shall clean and flush existing water heating piping (entire building) using a blend of polymeric and chelating agents that will preferentially remove iron oxides and will assist in softening light calcium deposits prior to installing new equipment; an example being CH2O Clean-N-Flush. Existing equipment may remain connected during flush. Flush shall be performed prior to the installation of new CCUs and AHUs. Follow manufacturer’s instructions for cleaning https://sftool.gov/greenprocurement/green-products/1/construction-materials/22/building-insulation/0 https://sftool.gov/greenprocurement/green-products/1/construction-materials/22/building-insulation/0 and length of time. Flush the system until the discharge water is running clear; contractor shall notify the Government QAR and PM at the beginning and conclusion of the system flush so that the Government may observe the clarity of the water. Attach fittings/blanks as required to perform the flushing. Obtain sewage discharge permit; take a sample of water to be discharged and estimate pH and chlorine PPM for sewage permit. Discharge shall be into the sanitary sewer system unless directed otherwise by DPW personnel (see section 15.3.3). Note: discharge permits are typically valid for one day at a time. Separate permits may be required depending on the number of discharges required. Contractor shall provide a submittal on the cleaning agent to be used.

1.4.2.2. Contractor shall demo steam supply, condensate return, and associated steam components from the CCUs steam humidifier section back to nearest tee. Tees shall be replaced with elbows and/or any other fittings as required to delete the CCU humidifier sections and allow the remainder of the steam/condensate system to operate as intended. Match existing pipe size and type.

1.4.2.3. Contractor shall remove all ducting from existing CCUs to include supply side duct, damper, etc.

to wall opening, discharge ducting, and supports. Contractor shall protect wall openings from the elements until the new duct and inlet damper is installed. Contractor shall remove existing flex duct from CCUs. Contractor shall take care to not damage flex duct as it is removed. Flex duct shall remain on site for occupant inspection. Any flex duct not secured by the occupants after inspection shall be disposed of accordingly by the contractor.

1.4.2.4. Contractor shall remove and dispose of the existing CCUs to include supports, piping, valves, drains, electrical, etc. as required to install new CCUs per this SOW and attachments. Note: the new CCUs will be installed at ground level on an elevated platform. Demo existing CCU electrical disconnects/motor starters. Demo conductors and conduit as required to route the new CCU electrical service. Existing conduit may be reused if it is the appropriate size for the new CCU electrical service. Conductors and circuit breakers may be reused if they are serviceable and are the appropriate size for the new CCUs.

1.4.2.5. Contractor shall demo CCU cooling system (DX unit) to include all refrigerant lines, drain lines, condensing units, and electrical to include motor/starter disconnects. Condenser units circuit breakers may be reused for the new exhaust fans (EF-2 and EF-3) if they are serviceable, the correct size for the new equipment, and are rated for use with the new units. Contractor shall fill holes using fire stop caulking as required due to demo of refrigerant lines, electrical lines, etc.

Paint exterior wall to match existing as required for removal of condenser motor/starter disconnects. Refrigerant evacuation and recovery shall be IAW 40 CFR 82, Subpart F. Air program POC: Diane Roberts @ 253-966-1770.

1.4.2.6. Contractor shall provide shop drawings for new CCU equipment platforms. Platforms shall be a minimum of 2’ tall. Drawings shall illustrate the construction of the platforms to include materials used, thickness/gauge, securing/mounting information, and dimensions. Contractor shall provide calculations or similar showing that the new platforms can properly support the weight of the new CCUs. Provide shop drawings to the Government as a submittal.

1.4.2.7. Contractor shall provide and install the new equipment platforms per the Government accepted shop drawings. The platforms shall be secured to the hangar floor in a similar fashion as the existing AHUs. The platforms shall be installed on the ground level below where the existing CCUs are hung from the ceiling. The new platforms shall be positioned such that there is a minimum of 3’ of clearance on all sides of the platform and new equipment. The platforms and new equipment shall not be more than 4’ from the west wall. The platform and equipment on the north side of the hangar shall not block the existing eye wash station.

1.4.2.8. Contractor shall provide and install new CCUs meeting the requirements of Attachment #2. New CCUs shall be mounted on new equipment platforms and be properly installed and secured per manufacturer instructions/recommendations (mounting, vibration isolation, etc.). Contractor shall install new piping, fittings, valves, strainers, etc. as required to provide complete and usable new CCUs. Supply and return piping shall have full port ball isolation valves with stainless steel trim for CCU isolation purposes. New piping shall match existing size and type. Use dielectric unions for dissimilar metals where required.

1.4.2.9. Contractor shall install new ductwork for new CCUs. Install new power inlet damper IAW manufacturer instructions. Inlet dampers shall be closed when the CCUs are powered off. See Attachment #2 for additional ductwork requirements.

1.4.2.10. Contractor shall install new smoke detector on each CCU duct. New smoke detectors shall be connected to new DDC and building’s fire alarm panel per NFPA 72. Smoke detectors shall be located downstream of the supply air filters and prior to any branch connection IAW NFPA 72.

Provide UL listed or FM approved detectors for duct installation. Provide duct detectors with an approved duct housing, mounted exterior to the duct, and with perforated sampling tubes extending across the width of the duct. Detectors shall have a test port with test switch or remote keyed test device. Activation of the detector shall cause shutdown of the associated equipment and issue an alarm to the DDC.

1.4.2.11. Contractor shall install electrical to include but not limited to conductors, conduit, and circuit breakers as required powering all equipment. Electrical components that are not reused from the existing service must be new. Contractor shall install new motor starter/fused disconnect combination units for new CCUs.

1.4.2.12. Contractor shall perform new equipment start up by manufacturer’s representative with DPW present for safety checks in accordance with the manufacturer documentation. Contractor shall give DPW a minimum of 48 hour notice prior to startup.

1.4.2.13. Contractor shall perform a test and balance (TAB) on the new CCUs after equipment startup by manufacturer’s representative but prior to PVT. The TAB shall include the balancing of the hot water coils in the new CCUs as well as an air balance on the new CCUs. The contractor shall provide the TAB results as a submittal.

1.4.2.14. Contractor shall perform heating water testing by a 3rd party qualified water treatment contractor and develop a water treatment plan. Add chemicals per the treatment plan. Provide testing results, treatment plan, and chemicals added as a submittal to the Government. Once the submittal is approved, secure a laminated copy of the treatment plan and chemicals added documentation near the chemical pot. Clean all strainers (entire building) after system startup by manufacturer representative but prior to chemical addition and final inspection. Contractor shall notify DPW QAR a minimum of 24 hours prior to cleaning strainers so that DPW QAR may observe. This work (testing, treatment, cleaning, etc.) to be competed after new CCUs and AHUs are installed and have been started up by manufacturer rep.

1.4.2.15. Contractor shall insulate new supply/return heating piping with mineral fiber insulation meeting ASTM C547 or cellular glass insulation meeting ASTM C552. Insulation thickness shall match existing and have a factory applied protective jacket. Corners shall have PVC jacket. Seal the ends of pipe insulation with brush coat of waterproof vapor barrier coating. Sections of insulated piping where support hangers are installed shall have calcium silicate insulation meeting ASTM C533 under the support hangers. Calcium silicate insulation sections shall have a metal guard between insulation jacket and support hanger and insulation section shall be a minimum width of four times the width of the support hanger. All piping shall be properly supported.

1.4.2.16. Contractor shall install name and directional labeling on each type and size of piping and label all mechanical equipment with durable identification tags. Name and directional labeling color shall match building’s existing labeling for that type of service. Name and directional labeling shall be installed every 10’ or 270° in bends, whichever is less. Match naming in new DDC graphics.

1.4.2.17. Contractor shall modify the CCU TCP’s as called out in Attachment #3.

1.4.3. Base Item CLIN 0002: Install Additional Exhaust Bldg. J01164, IJO: MCD001883J, Equipment

1.4.3.1. Contractor shall install concrete equipment pads as required for new exhaust fans. New equipment pads shall be installed neighboring the existing EU equipment pads and shall match the height of the existing EU equipment pads. New equipment pads shall have chamfered edges with a minimum chamfer of ¾”. Equipment pads shall be reinforced with rebar or a galvanized wire mesh such that the new equipment pads can properly support the new equipment. Contractor shall provide the Government with a submittal showing that the new equipment pads meet the requirements of ACI 301.

1.4.3.2. Contractor shall provide and install new exhaust fans and fan motors on new equipment pads.

New exhaust fans and fan motors shall be rated for the system temperature and pressure requirements. Each unit shall be able to exhaust approximately 6,000 CFM. New equipment shall be secured to the equipment pads per manufacturer recommendations. New equipment shall be rated for hazardous locations (similar to existing EU’s).

1.4.3.3. Contractor shall reconfigure wall duct box for both EU’s such that the existing EU’s and new exhaust fans (EF-2 and EF-3) are able to utilize the same existing wall penetrations. Contractor shall install new ductwork for new exhaust fans to include but not limited to ductwork, fittings, stacks, etc. Contractor shall install ductwork from wall duct box to new exhaust fan inlet and new exhaust stack from exhaust fan outlet for each new EF. New exhaust ductwork and stack shall be sized appropriately per manufacturer recommendations. New exhaust stacks shall approximately match the height of the existing stacks. Exhaust stacks shall have no-loss stackheads (a.k.a zero pressure weather cap) installed. No-loss stackheads shall be installed IAW manufacturer recommendations/instructions and be properly supported. Exhaust stacks shall be supported similar to existing stacks. Contractor shall install protective covers for new fans/motors similar to existing EU protective covers. Paint new equipment/equipment covers and stack to match existing.

1.4.3.4. Contractor shall install new interior exhaust ductwork from wall duct box to flex drop location.

Ductwork shall be sized appropriately per the system temperatures, pressures, and CFM requirements. See Attachment #2 for additional requirements.

1.4.3.5. Contractor shall install new electrical for new EF’s as required to provide complete and useable exhaust units. New electrical to include conduit, conductors, circuit breakers (see section 1.4.2.5), etc. Contractor shall install new motor starter/fused disconnect combination units for new EF’s;

units shall be installed similar to starter/disconnects for EU’s. Contractor to coordinate exact location with Government PM.

1.4.3.6. Contractor shall conduct performance testing with Government Quality Assurance. Testing shall be conducted IAW manufacturer procedures for system startup. Contractor shall submit startup reports prior to final inspection with DPW personnel.

1.4.4. Base Item CLIN 0003: Repair AHUs and Exhaust, Bldg. J01164, IJO: MCD001883J, Repair

1.4.4.1. Contractor shall remove ductwork as required to demo existing AHU-1 and AHU-2. Note: AHU- 3 serves the office areas and is not being replaced. Undamaged ductwork is to be reused.

1.4.4.2. Contractor shall clean all ductwork associated with AHU-1 & 2 to include grilles, registers, diffusers, etc.

1.4.4.3. Contractor shall remove and dispose of existing AHU-1 & 2 to include supports, piping, valves, drains, electrical, etc. as required to install new AHUs per this SOW and attachments. Demo existing CCU electrical disconnects/motor starters. Demo conductors and conduit as required to route the new AHU electrical service. Existing conduit may be reused if it is the appropriate size for the new AHU electrical service. Conductors and circuit breakers may be reused if they are serviceable and are the appropriate size for the new AHUs.

1.4.4.4. Contractor shall provide and install new AHU-1 and AHU-2; replacement shall be in kind. Note:

As-builts indicate that original 7.5 HP motors were replaced with 10 HP motors. New AHUs shall be mounted on existing equipment platforms and be properly secured; modify platforms if required to ensure they can properly support the weight of the new AHUs. Contractor shall provide calculations or similar showing that the platforms can properly support the weight of the new AHUs. Contractor shall install new piping, fittings, valves, strainers, etc. as required to provide complete and usable new AHUs. Supply and return piping shall have full port ball isolation valves with stainless steel trim for AHU isolation purposes. New piping shall match existing size and type. Use dielectric unions for dissimilar metals where required.

1.4.4.5. Contractor shall install new ductwork for new AHUs as required. See Attachment #2 for additional ductwork requirements.

1.4.4.6. Contractor shall install new smoke detector on each AHU duct. New smoke detectors shall be connected to new DDC and building’s fire alarm panel per NFPA 72. Smoke detectors shall be located downstream of the supply air filters and prior to any branch connection IAW NFPA 72.

Provide UL listed or FM approved detectors for duct installation. Provide duct detectors with an approved duct housing, mounted exterior to the duct, and with perforated sampling tubes extending across the width of the duct. Detectors shall have a test port with test switch or remote keyed test device. Activation of the detector shall cause shutdown of the associated equipment and issue an alarm to the DDC.

1.4.4.7. Contractor shall install electrical to include but not limited to conductors, conduit, and circuit breakers as required powering all equipment. Electrical components that are not reused from the existing service must be new. Contractor shall install new motor starter/fused disconnect combination units for new AHUs.

1.4.4.8. Contractor shall perform new equipment start up on new AHUs by manufacturer’s representative with DPW present for safety checks in accordance with the manufacturer documentation.

Contractor shall give DPW a minimum of 48 hour notice prior to startup.

1.4.4.9. Contractor shall perform a TAB on the new AHUs after equipment startup by manufacturer’s representative but prior to PVT. The TAB shall include the balancing of the hot water coils in the new AHUs as well as an air balance on the new AHUs. The contractor shall provide the TAB results as a submittal.

1.4.4.10. Contractor shall insulate new supply/return heating piping with mineral fiber insulation meeting ASTM C547 or cellular glass insulation meeting ASTM C552. Insulation thickness shall match existing and have a factory applied protective jacket. Corners shall have PVC jacket. Seal the ends of pipe insulation with brush coat of waterproof vapor barrier coating. Sections of insulated piping where support hangers are installed shall have calcium silicate insulation meeting ASTM C533 under the support hangers. Calcium silicate insulation sections shall have a metal guard between insulation jacket and support hanger and insulation section shall be a minimum width of four times the width of the support hanger. All piping shall be properly supported.

1.4.4.11. Contractor shall install name and directional labeling on each type and size of piping and label all mechanical equipment with durable identification tags. Name and directional labeling color shall match building’s existing labeling. Name and directional labeling shall be installed every 10’ or 270° in bends, whichever is less. Match naming in new DDC graphics.

1.4.4.12. Contractor shall modify the AHU TCP’s. Include filter alarm indicator light and manual reset button for filter and smoke. Include indicator light showing occupancy status (occupied or unoccupied). Include occupancy override button (4 hours).

1.4.4.13. Contractor shall demo EU-1 & 2 electrical as required to install new EU’s per this SOW and attachments. Demo existing EU electrical disconnects/motor starters. Demo conductors and conduit as required to route the new EU electrical service. Existing conduit may be reused if it is the appropriate size for the new EU electrical service. Conductors and circuit breakers may be reused if they are serviceable and are the appropriate size for the new EU’s.

1.4.4.14. Contractor shall demo EU-1 and EU-2 motor and fan to include fan inlet ductwork (wall duct box reconfigured in CLIN 0002). Contractor shall demo EU protective coverings as required.

1.4.4.15. Contractor shall clean EU equipment pads with cleaning agent removing any dirt, moss, etc.

Contractor shall refer to instructions in section 15.6 if using hazardous materials.

1.4.4.16. Contractor shall install new EU-1 and EU-2 fan and motor to include new inlet ductwork.

Contractor shall connect new fan to existing stack. Contractor shall install new fan and motor protective covers similar to existing. Contractor shall paint new covers/equipment to match existing. EU-1 and EU-2 fan and motor replacement shall be in kind and shall be appropriate for the system temperatures and pressures.

1.4.4.17. Contractor shall install new electrical for new EU’s as required to provide complete and useable exhaust units. Electrical to include conduit, conductors, circuit breakers, etc. Electrical that is not reused from existing service shall be new. Contractor shall install new motor starter/fused disconnect combination units for new EU’s. Contractor to coordinate exact location with Government PM.

1.4.4.18. Contractor shall conduct performance testing on new EU’s with Government Quality Assurance.

Testing shall be conducted IAW manufacturer procedures for system startup. Contractor shall submit startup reports prior to final inspection with DPW personnel.

1.4.5. Base Item CLIN 0004. Repair Controls, Bldg. J01164, IJO: MCD001883J, Repair

1.4.5.1. Contractor shall provide new DDC shop drawings for BLDG J01164 to achieve HVAC sequence of operations. Existing ASI controls are to be replaced with Tridium based N4 controls. Shop drawings shall conform to JBLM DDC specification 23 09 23. See Attachment #3 for DDC as-builts/points list, additional changes, and DDC specifications. DDC shop drawings shall include at a minimum:

a. An updated sequence of operations for mechanical equipment to include but not limited to:

1. AHU-1 through AHU-3, CCU-1 and CCU-2 (to include control panels), EF-1, EU-1 and EU-2, UH-1 and UH-2, steam/condensate system (heat exchanger, condensate pumps, etc.), hot water heating pump, and new exhaust fans EF-2 and EF-3. Include additional sensors called out in as-built control drawings and SOW. Modify sequence of operations to reflect the following:

i. CCU-1 and CCU-2 shall operate using 100% outside air (OSA). New CCUs shall incorporate a temperature sensor on the leaving face of the heating coil. If the temperature after the coil is sensed at 35°F or below, the DDC shuts off the CCU fan and closes the OSA damper. The heating coil is then opened to full flow and an alarm is issued. This sequence shall be hard-wired. Manual reset is required. CCU fan shall not start until its respective OSA damper is proved 100% open and the OSA damper shall not close until the fan wheel stops turning (preset period of time). See additional comments for CCU and TCP sequence of operations in Attachment #3.

ii. EF-2 and EF-3 shall be controlled by an on/off position toggle switch in the temperature control panel (TCP) for the respective CCU.

iii. UH-1 and UH-2 shall be controlled by a space temperature sensor and shall provide freeze protection.

iv. PIR Occupancy sensors (see below).

2. Modify control drawings to reflect the following:

i. New CCU-1 and CCU-2.

ii. New CCU-1 and CCU-2 TCP’s.

iii. New AHU-1 and AHU-2.

iv. New AHU-1 and AHU-2 TCP’s.

v. New EU-1 and EU-2.

vi. New EF-2 and EF-3.

vii. Add UH-1 and UH-2 to include space temperature sensor.

viii. New thermostats and occupancy sensors.

3. Unoccupied, warm-up, and occupied modes. Since J01164 is an alternate fuels hangar, there is no consistent occupancy schedule. The new DDC shall control the space temperatures as follows; all set points shall be adjustable at DDC workstation:

i. The building shall have two thermostats communicating with the DDC.

Thermostats shall be located in the office/admin area and the hangar bay area; coordinate exact location with Government PM.

ii. The office/admin area and hangar bay shall each have an occupancy sensor;

coordinate exact location with Government PM. The occupancy sensors shall be IAW UFGS 23 09 13 (see Attachment #1). Contractor shall make adjustments to sensor sensitivity as required. Once a sensor relays occupancy to the DDC for a period of two minutes or longer (delay timer, etc.), the DDC shall be placed into occupied mode for a period of 4 hours. The office/admin space temperature shall be set to 68°F heating and unoccupied heating temperature set point shall be 55°F. The hangar bay temperature shall be set to 60°F heating and unoccupied heating temperature set point shall be 45°F.

b. DDC floor plans showing locations and communication plan of sensors (outside air, thermostat, etc.), controllers, and switch.

c. Mechanical equipment field wiring schematic showing all required controllers, switch, and sensors to meet sequence of operation. Ensure command and status of all mechanical equipment listed in [a.; 1.] above. See as-builts and [a.; 3.] above for schedule of equipment.

Include bill of materials with part numbers.

d. DDC panel wiring schematics. Show landing location of all control wiring. The JACE shall be compatible with Tridium N4 with open license. Size and number of JACE shall be determined by the contractor.

1.4.5.2. Contractor shall demo existing ASI controls to include but not limited to: control cabinets, conductors, relays, thermostats, etc. as required to install new DDC. Contractor shall patch and paint walls as required where cabinets, conduit, thermostats/temperature sensors, etc. were demoed or relocated. Contractor to sequence the construction as not to have the heating / ventilation off for an extended period of time (8 hours or more) when the outside air temperature is below 45°F. Coordinate outages with DPW. Contractor may operate equipment in manual mode during controls work if needed to maintain heat.

1.4.5.3. Contractor shall install new DDC per the Government accepted shop drawings, attachments, and this SOW. The DDC installation shall have/be:

a. Integrated into the JBLM’s Tridium N4 based Energy Monitoring System (EMS) to achieve full operational control of HVAC equipment per the accepted sequence of operation.

b. New DDC equipment and components/controls (sensors, actuators, thermostats, CT’s, panels, controllers etc.). New controllers shall be Tridium N4 compatible.

c. New control wiring. Do not reuse any existing control wiring. Plenum rated wire is acceptable above ACT ceilings. Wiring shall be in conduit when not above ACT ceilings.

Fire stop all conduit penetrations through walls. Existing ASI controls conduit may be reused if new control wiring does not exceed conduit fill percentages. Install new conduit where required for control wiring. Paint conduit to match existing if required.

d. Provide new 8 port NEC switch. Switch shall be similar to Cisco catalyst 2960-CX 8. Exact make/model switch to be verified by NEC. Switch will be installed by others.

e. Labeled communication line from JACE to NEC switch. Coordinate with DPW for port number.

f. Enclosed JACE and controllers in communication room in a NEMA 2 enclosure. Enclosure shall be mounted in the same area as the demoed enclosure for existing controls.

g. Generate new N4 graphics per JBLM DDC spec 23 09 23.

h. DDC shop drawings uploaded in .pdf format to work bench software.

i. JACE archived to Tridium N4 work bench software in BLDG 2012.

j. Laminated warranty tags and control drawings at DDC enclosure. Warranty tags shall meet requirements listed in section 1.4.1.9. Control drawings shall be 11x17.

1.4.5.4. Contractor shall provide revised shop drawings (if required) to reflect any modifications to the system/sequence of operations to achieve the desired operating parameters. Submit revisions after PVT is complete.

2. PERFORMANCE AND SCHEDULING:

2.1. Performance Period Requirements

2.1.1. The Contractor is required to commence work under this Contract within ten (10) calendar days after the date of issuance of the Notice to Proceed (NTP) for the Base Item(s), prosecute the work diligently, and complete all work on all Base Item(s) no later than 180 calendar days after the date of issuance of the Notice to Proceed for the Base Item(s). The time stated for completion includes final cleanup of the premises and submission of all required close-out documentation.

2.1.2. Blank copies of Government forms required by this SOW will be provided to the Contractor within 14 calendar days of award issuance. Examples of these forms include: daily reports, ENG Form 4025-R, HJB 229, etc.

2.2. Award of Options

2.2.1. N/A

2.3. Construction Phasing Requirements

2.3.1. Contractor shall coordinate all shut downs/outages with DPW.

2.3.2. Contractor shall minimize heating outage due to AHU/CCU replacement if replacement is conducted during heating season. Heating outage (if required) shall be conducted when outside air temperatures are 45°F or higher for the duration of the outage.

2.4. Perform other work necessary

2.4.1. The contractor shall be responsible for providing a complete and useable product/system and shall be responsible for accomplishing all tasks incidental to the completion of the project requirements. Requirements for a complete and useable product which are not explicitly called out in the SOW but are reasonably discernable via any other method than destructive testing shall be considered a requirement of the project/contract.

2.4.2. For purposes of this project, replace in kind refers to an item that meets the design specifications of the item it is replacing. This can be an identical replacement or any other alternative specifically provided for in the design specification, as long as the alternate does not in any way adversely affect the use of the item or associated items.

3. SUBMITTAL PROCEDURES:

3.1. Project Submittal Requirements: All submittals shall be submitted electronically (emailed) to the government Project Manager (PM) in Adobe Acrobat .pdf format. An ENG Form 4025 shall accompany each submittal. These forms will be furnished to the Contractor by the PM. The submittal file name shall be in the format “Contract # – submittal #, submittal name” for example;

“0020-001 RTU”. Properly complete this form by filling out all the heading blank spaces and identifying each item submitted. Drawings if required by the SOW shall be in ACAD format and a second electronic copy in PDF format. The Government reserves the right to request submittals not listed in this SOW; any submittals not listed in this SOW but requested by the Government shall become a requirement of the project. Submittals requiring Government approval are to be scheduled and made prior to the acquisition of the material or equipment covered thereby. Each submittal is to be complete and in sufficient detail to allow ready determination of compliance with contract requirements. Contractor shall check and approve all items prior to submittal and stamp, sign, and date indicating action taken. Proposed deviations from the contract requirements are to be clearly identified.

3.1.1. The Government reserves the right to require the contractor to resubmit any item found not to comply with the contract. This does not relieve the contractor from the obligation to furnish material conforming to the plans and specifications; will not prevent the KO from requiring removal and replacement of nonconforming material incorporated in the work; and does not relieve the contractor of the requirements to furnish samples for testing by the Government laboratory or for check testing by the Government in those instances where the technical specifications so prescribe.

3.1.2. Government Approval. Government approval is required for critical materials, deviations, equipment whose compatibility with the entire system must be checked, safety requirements, and other items as designated by the KO. Government approval is required for any deviations from the solicitation or accepted proposal and other items as designated by the KO. These deviations must contain proper documentation stating why this deviation is necessary and why it is beneficial to the government.

3.1.3. Information Only. Submittals not requiring Government approval will be for information only. The approving authority will not provide approval of information only submittals but shall provide acknowledgement of receipt.

3.1.4. Variations. Variations from contract requirements require Government approval pursuant to contract Clause FAR 52.236-21 and will be considered where advantageous to Government and/or overall project. Discussion with KO or their representative (DPW PM, MICC CS, etc.)

prior to submission will help ensure functional and quality requirements are met and minimize rejections and resubmittals. Specifically point out variations from contract requirements in transmittal letters. Failure to point out variations may result in the Government requiring rejection and removal of such work at no additional cost to the Government. When proposing a variation, deliver written request to the KO, with documentation of the nature and features of the variation and why the variation is desirable and beneficial to Government. In addition to documentation required for variation, include the submittals required for the item. Clearly mark the proposed variation in all documentation. Check the column "variation" of ENG Form 4025 for submittals that include proposed variations requested by the contractor. Set forth in writing the reason for any variations and annotate such variations on the submittal. The Government reserves the right to rescind inadvertent approval of submittals containing unnoted variations.

3.1.5. Approval. When approving authority is KO or the designated representative, the Government will:

Note date on which submittal was received. Review submittals for approval within scheduling period specified and only for conformance with project design concepts and compliance with contract documents. Identify returned submittals with one of the actions defined in paragraph entitled "Review Notations" and with markings appropriate for action indicated. Upon completion of review of submittals requiring Government approval, stamp and date approved submittals. The transmittal form (4025-R) showing approval of the submittal will be retained by the KO and one copy of the transmittal form will be returned to the contractor electronically. The KO's approval or acceptance of submittals is not to be construed as a complete check, and indicates only that the general method of construction, materials, detailing and other information are satisfactory.

Approval or acceptance will not relieve the contractor of the responsibility for any error that may exist, as the contractor is responsible for the satisfactory construction of all work. After submittals have been approved or accepted by the KO, no resubmittal for the purpose of substituting materials or equipment will be considered unless accompanied by an explanation of why a substitution is necessary.

3.1.6. Disapproval. Contractor shall make corrections required by the KO. If the contractor considers any correction or notation on the returned submittals to constitute a change to the contract drawings or specifications, notice as required under the clause entitled, "Changes" is to be given to the KO.

Failure to point out deviations may result in the Government requiring rejection and removal of such work at the contractor's expense. If changes to submittals are necessary, the contractor shall make such revisions and submission of the submittals in accordance with the procedures above within 7 calendar days. No item of work requiring a submittal change is to be accomplished until the changed submittals are approved.

3.1.7. Duration for submittal review: The Government shall have up to 14 calendar days to review each submittal starting when the Government receives the electronic submission. Longer review times may be required on a case-by-case basis.

3.2. Project Schedule:

3.2.1. Prepare for approval a Project Schedule, as specified herein, pursuant to the contract clause, SCHEDULE FOR CONSTRUCTION CONTRACTS. Show in the schedule the sequence in which the contractor proposes to perform the work and dates on which the contractor contemplates starting and completing all schedule activities. The scheduling of the entire project, including construction sequences, is required. The scheduling of construction is the responsibility of the contractor. Contractor management personnel shall actively participate in its development.

Subcontractors and suppliers working on the project shall also contribute in developing and maintaining an accurate Project Schedule. Provide a schedule that is a forward planning as well as a project monitoring tool.

3.2.1.1. Approved Project Schedule. Use the approved Project Schedule to measure the progress of the work and to aid in evaluating time extensions. Make the schedule cost loaded and activity coded.

The schedule will provide the basis for all progress payments. If the contractor fails to submit any schedule within the time prescribed, the Contracting Officer (KO) may withhold approval of progress payments until the contractor submits the required schedule.

3.2.1.2. Default Terms. Failure of the contractor to comply with the requirements of the contract shall be grounds for a determination, by the KO, that the contractor is not prosecuting the work with sufficient diligence to ensure completion within the time specified in the contract. Upon making this determination, the KO may terminate the contractor's right to proceed with the work, or any separable part of it, in accordance with the default terms of the contract.

3.2.2. BASIS FOR PAYMENT AND COST LOADING: Use the schedule as the basis for determining contract earnings during each update period and therefore the amount of each invoice payment.

Lack of an approved schedule update, or qualified scheduling personnel, will result in the inability of the KO to evaluate contractor percentage complete for the purposes of payment.

Failure of the contractor to provide all required information will result in the disapproval of the preliminary, initial, and subsequent schedule updates. In the event schedule revisions are directed by the KO and those revisions have not been included in subsequent revisions or updates, the KO may hold retainage up to the maximum allowed by contract, each payment period, until such revisions to the Project Schedule have been made. Activity cost loading shall be reasonable, as determined by the KO. The aggregate value of all activities coded to a contract line item number (CLIN) shall equal the value of the CLIN on the Project Schedule. The Government will withhold 5% of the project amount for submission and acceptance of any and all closeout documents as specified in each project and this shall be shown on the project schedule.

3.2.3. PROJECT SCHEDULE DETAILED REQUIREMENTS: The computer software system utilized to produce and update the Project Schedule shall be capable of meeting all requirements of this specification. Failure of the contractor to meet the requirements of this specification will result in the disapproval of the schedule.

3.2.3.1. Critical Path Method. Use the Critical Path Method (CPM) of network calculation to generate the Project Schedule. Prepare the Project Schedule using the Precedence Diagram Method (PDM).

3.2.3.2. Level of Detail Required. Develop the Project Schedule to an appropriate level of detail. Failure to develop the Project Schedule to an appropriate level of detail, as determined by the KO, will result in its disapproval. The KO will consider, but is not limited to, the following characteristics and requirements to determine appropriate level of detail:

a. Activity Durations. Reasonable activity durations are those that allow the progress of ongoing activities to be accurately determined between update periods. Procurement activities are defined herein.

b. Permit Activities. Include permit activities, when required, with the necessary conferences and follow-up actions and dates. Include the permitting schedule in the Project Schedule, showing the sequence of events involved in carrying out the project permit tasks within the specific contract period. This shall be at a detailed level of scheduling sufficient to identify all major permitting tasks, including those that control the flow of work.

c. Procurement Activities. Tasks related to the procurement of long lead materials or equipment shall be included as separate activities in the project schedule. Long lead materials and equipment are those materials that have a procurement cycle of over 30 days. Examples of procurement process activities include, but are not limited to: submittals, approvals, procurement, delivery, start-up, and testing.

d. Mandatory Tasks. The following tasks (as required) must be included and properly scheduled:

1. Submission of closeout submittals, equipment commissioning, controls testing plan submission, controls testing, performance verification testing, other systems testing, Contractor’s internal project inspection, correction of punchlist from the Contractor’s pre-final inspection, final inspection.

2. Government Activities. Show Government and other agency activities that could impact progress. These activities include, but are not limited to: approvals, environmental permit approvals by State regulators, inspections, utility tie-in, Government Furnished Equipment (GFE) and Notice to Proceed (NTP) for phasing requirements.

3. Contract Line Item Number (CLIN) Coding. Code all activities to the CLIN on the CLIN Schedule to which the activity belongs. An activity shall not contain more than one CLIN code. CLIN code all activities, even when an activity is not cost loaded (to include preconstruction and post construction activities).

3.2.4. Scheduled Project Completion and Activity Calendars. The schedule interval shall extend from Notice to Proceed (NTP) date to the required contract completion date. The contract completion activity (End Project) shall finish based on the required contract duration in the accepted contract proposal, as adjusted for any approved contract time extensions. The first scheduled work period shall be the day after NTP is received by the contractor. Schedule activities on a calendar to which the activity logically belongs. Activities may be assigned to a 7-day calendar when the contract assigns calendar day durations for the activity such as a Government Acceptance activity. Assign the Category of Work Code - Weather Sensitive Installation to those activities that are weather sensitive. Original durations must account for anticipated normal adverse weather. The Government will interpret all work periods not identified as non-work periods on each calendar as meaning the contractor intends to perform work during those periods.

3.2.4.1. Project Start Date. The schedule shall start no earlier than the date on which the NTP was acknowledged. Include as the first activity in the project schedule an activity called “NTP”.

3.2.4.2. Project Completion Date. Constrain completion of the last activity in the schedule by the contract completion date. Schedule calculations shall result in a negative float when the calculated early finish date of the last activity is later than the contract completion date. Include as the last activity in the project schedule an activity called "Project Completion”.

3.2.5. PROJECT SCHEDULE SUBMISSIONS: The contractor shall provide the submissions as described below:

3.2.5.1. Project Schedule Submission. Submit the Project Schedule for approval within 7 calendar days after NTP. The schedule shall demonstrate a reasonable and realistic sequence of activities which represent all work through the entire contract performance period. The Project Schedule shall be at a reasonable level of detail as determined by the KO. This requirement is in addition to any required schedules or submittals submitted in response to a Request for Proposal (RFP).

3.2.5.2. Project Schedule Updates. At the request of the KO, the contractor shall provide and submit an updated Project Schedule. These submissions will enable the KO to assess the contractor's progress. If the contractor fails or refuses to furnish the information and Project Schedule data, which in the judgment of the KO or authorized representative is necessary for verifying the contractor's progress, the contractor shall be deemed not to have provided an estimate upon which progress payment may be made.

3.2.6. REQUESTS FOR TIME EXTENSIONS: In the event the contractor believes they are entitled to an extension of the contract performance period, completion date, or any interim milestone date, furnish the following for a determination by the KO: justification, project schedule data, and supporting evidence (Ex: daily reports showing delays) as the KO may deem necessary.

Submission of proof of excusable delay, based on revised activity logic, duration, and costs (updated to the specific date that the delay occurred) is a condition precedent to any approvals by the Government. In response to each RFP issued by the Government, the contractor shall submit a schedule impact analysis demonstrating whether or not the change contemplated by the Government impacts the critical path.

3.2.6.1. Justification of Delay. The Project Schedule shall clearly display that the contractor has used, in full, all the float time available for the work involved with this request. The KO's determination as to the number of allowable days of contract extension shall be based upon the Project Schedule updates in effect for the time period in question, and other factual information. Actual delays that are found to be caused by the contractor's own actions, which result in a calculated schedule delay, will not be a cause for an extension to the performance period, completion date, or any interim milestone date.

3.2.6.2. Unexcused Delays. Unexcused delays will result in a disapproval of any time extension request and the Contractor will be required to complete the work within the original period of performance. If the Contractor cannot complete the work within the original period of performance, the Contractor will be required to provide consideration to the Government in order to receive a time extension. Consideration will be established on a case by case basis but examples include but are not limited to extended warranty period, upgraded materials, etc.

3.3. Accident Prevention Plan:

3.3.1. Use a qualified person to prepare the written site-specific APP. Prepare the APP in accordance with the format and requirements of USACE EM 385-1-1 and as supplemented herein. Cover all paragraph and subparagraph elements in USACE EM 385-1-1, Appendix A, "Minimum Basic

Outline for Accident Prevention Plan". Specific requirements for some of the APP elements are described below. The APP shall be job-specific and address any unusual or unique aspects of the project or activity for which it is written. The APP shall interface with the contractor's overall safety and health program. Include any portions of the contractor's overall safety and health program referenced in the APP in the applicable APP element and made site specific. The Government considers the prime contractor to be the "controlling authority" for all work site safety and health of the subcontractors.