This Statement of Work (SOW) details the procurement, installation, integration, and testing of backup power equipment for Building 70 at the Mississippi Air National Guard Combat Readiness Training Center in Gulfport, Mississippi.
The contractor must procure and install one 125kW diesel backup generator (208/120V, 3-Phase, 4-Wire, 60 Hz, 1800 RPM) with an integrated double-walled sub-base fuel tank of minimum 250-gallon capacity, Level 1 sound and weather attenuation enclosure, and radiator cooling system. The contractor must also procure and install one 1200-Amp Automatic Transfer Switch (ATS) rated NEMA 3R for exterior installation with service entrance rating, fully automatic operation with programmable exerciser timers, voltage/frequency sensing, and manual bypass capability. Additional requirements include four runs of #500kCM copper conductors routed in PVC-coated rigid conduit over approximately 30 feet to connect the generator to the ATS. All materials must comply with the Buy American Act and federal procurement guidelines.
The contractor's specific tasks include: conducting a detailed site survey with submittal package approval (including manufacturer data sheets, site layout diagram, and single-line electrical diagram) within 15 calendar days of Notice to Proceed; procuring and delivering all equipment with responsibility for offloading and staging; performing complete turnkey installation including concrete equipment pads with seismic-rated anchor bolts, electrical integration with NEC and military standard compliance, and control wiring; executing comprehensive commissioning including pre-start checks, minimum 2-hour load bank testing per NFPA 110 at 25%, 50%, 75%, and 100% loads, and automatic transfer testing; providing site restoration and hands-on operator training covering startup/shutdown procedures, manual bypass operation, fault diagnostics, and maintenance intervals. The total period of performance is 180 calendar days from award, with submittals due within 15 days, procurement within 135 days of submittal approval, and on-site installation and testing completed within 30 days of equipment delivery. The contractor must provide a minimum two-year comprehensive manufacturer's warranty on the generator and ATS and guarantee all installation workmanship for one year following final military acceptance. All work must comply with the National Electrical Code, NEMA standards, and local Base Civil Engineering requirements.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATEMENT OF WORK (SOW)
PROCUREMENT AND INSTALLATION OF BACKUP GENERATOR & AUTOMATIC
TRANSFER SWITCH (ATS) FOR BLDG 70
MISSISSIPPI AIR NATIONAL GUARD
COMBAT READINESS TRAINING CENTER (CRTC)
GULFPORT, MISSISSIPPI
1.0 PROJECT TITLE & OBJECTIVE
The objective of this contract is the procurement, delivery, installation, integration, and testing of one (1) 125kW Diesel Backup Generator, one (1) 1200Amp Automatic Transfer Switch (ATS), and associated copper conductors to support emergency power requirements for Building 70 (BLDG 70) at the Mississippi Air National Guard Combat Readiness Training Center (CRTC), Gulfport, Mississippi.
2.0 BACKGROUND
The Gulfport Combat Readiness Training Center (CRTC) serves as a critical training site for the Total Force Special Warfare Airmen. Building 70 requires a highly reliable emergency backup power system to ensure continuous operations during utility outages. To meet this operational need, the Base Civil Engineer (CRTC/CEO) has established requirements to procure and install a 125kW generator and a service-entrance-rated ATS to automatically transfer critical loads during power anomalies.
3.0 SCOPE OF WORK
The Contractor shall provide all labor, supervision, materials, equipment, transportation, and coordination necessary to perform the following:
• Procure and deliver one (1) 125kW Diesel Generator (meeting all specific requirements).
• Procure and deliver one (1) 1200Amp Automatic Transfer Switch (ATS).
• Procure and deliver four (4) #500kCM Copper Conductors for connection between the generator and the ATS. The approximate distance from the Generator to the ATS is 30 ft.
• Provide complete turnkey installation, including any required site preparation, equipment mounting, electrical conduit routing, utility connection, and control wiring integration.
• Conduct pre-commissioning inspections, system testing, load bank testing, and training for local Base Civil Engineering personnel.
• Provide operation and maintenance manuals, and warranty documentation.
4.0 TECHNICAL SPECIFICATIONS
4.1 Backup Generator
The backup generator system must meet or exceed the following specifications:
• Manufacturer/Model: 125kW Backup Generator
• Electrical Characteristics: 208/120V, 3-Phase, 4-Wire, 60 Hz, operating at
1800 RPM.
• Fuel Type: Diesel.
• Cooling System: Radiator cooled, sized to maintain safe operating temperatures under full rated load at maximum ambient site conditions.
• Acoustic & Weather Enclosure: Level 1 Sound and Weather Attenuation
Enclosure.
• Fuel Storage: Integrated sub-base fuel tank with a minimum capacity of 250 gallons, double-walled.
4.2 Automatic Transfer Switch (ATS)
The ATS must meet or exceed the following specifications:
• Amperage Rating: 1200 Amps.
• Enclosure Type: NEMA 3R rated (suitable for secure exterior/outdoor installation).
• Service Entrance Rating: Service Entrance Rated (must include a main utility disconnect breaker integral to the ATS).
• Operation: Fully automatic initiation with programmable exerciser timers, voltage/frequency sensing on both utility and generator sources, and manual bypass/override capability.
4.3 Cabling & Conductors
• Specification: Four (4) runs of #500kCM Copper Conductors.
• Application: Specifically designated for the critical electrical connection between the backup generator and the ATS.
• Conduit: Conductors shall be routed in appropriately sized PVC-coated rigid conduit where exposed to outdoor weathering.
5.0 SPECIFIC CONTRACTOR TASKS
Task 1: Site Survey & Engineering Submittals Site Inspection: The Contractor shall perform a detailed site survey to verify the physical footprint, routing path for the copper conductors, structural foundation requirements, and electrical tie-in locations at BLDG 70.
Submittal Package: Prior to purchasing any equipment, the Contractor shall submit a comprehensive technical submittal package to the Base Civil Engineer for review and approval. The package must include:
• Manufacturer data sheets for the Generator, ATS, Enclosures, and Conductors.
• Detailed site layout diagram indicating generator placement, ATS mounting location, and conduit run path.
• Single-line electrical diagram of the proposed integration.
Task 2: Procurement & Delivery The Contractor shall procure all approved materials, ensuring strict adherence to the Buy American Act and federal procurement guidelines.
The Contractor shall coordinate delivery to the Gulfport CRTC. The Contractor is solely responsible for offloading, hoisting, rigging, and staging the heavy equipment.
Task 3: Installation & Electrical Integration Demolish:
• Demo and dispose of existing manual transfer switch
Civil/Structural Work:
• Install a reinforced concrete equipment pad of sufficient thickness and dimensions to support the generator and sub-base fuel tank weight, preventing vibration transfer.
• Securely anchor the generator and ATS to their respective concrete pads using seismic-rated anchor bolts.
Electrical Installation:
• Install the 1200A ATS on the exterior of equipment enclosure at the designated service entrance point.
• Run conduit and pull the four (4) #500kCM copper conductors from the generator breaker to the ATS.
• Route control wiring between the generator control panel and the ATS to facilitate automatic start/stop and utility sensing.
• Ensure all grounding and bonding comply with the National Electrical Code (NEC) and local military standards.
Task 4: Testing & Commissioning Upon completing physical installation, the Contractor shall execute a comprehensive commissioning plan witnessed by the Base Civil Engineer (or designated representative):
Pre-Start Checks: Verify fuel, coolant, lubrication levels, phase rotation, and insulation resistance.
Load Bank Test: Conduct a minimum 2-hour resistive load bank test of the generator system (complying with NFPA 110 requirements) to verify output performance at 25%, 50%, 75%, and 100% load capacities.
Automatic Transfer Test: Perform a simulated utility power outage test to verify:
• Loss-of-utility sensing.
• Generator startup and stabilization timing.
• Automatic transfer switch actuation.
• Load pickup and steady-state voltage/frequency under actual building load.
• Automatic re-transfer to utility power upon restoration, including generator cool-down cycle.
Task 5: Cleanup & Training Site Restoration: The Contractor shall remove all packaging, excess materials, excavated soil, and construction debris from the site, returning the surrounding area to its original or improved state.
Operations Training: Provide hands-on operations and maintenance training to designated Base Civil Engineering personnel. Training shall cover:
• Basic system startup and shutdown procedures.
• Manual bypass operation of the ATS.
• Fault code diagnostics, fuel management, and routine maintenance intervals.
6.0 PERIOD OF PERFORMANCE
The total period of performance for this project shall be 180 calendar days from the Date of Award/Notice to Proceed (NTP).
• Submittals: Within fifteen (15) calendar days after NTP.
• Procurement Lead Time: Within 135 calendar days after submittal approval.
• On-Site Installation & Testing: To be completed within thirty (30) calendar days of equipment delivery to the site.
7.0 QUALITY ASSURANCE & WARRANTY
• Code Compliance: All materials and installations must conform to the latest editions of the National Electrical Code (NEC/NFPA 70), National Electrical Manufacturers Association (NEMA) standards, and local Base Civil Engineering requirements.
• Warranty: The Contractor shall provide a minimum of a two (2) year comprehensive manufacturer's warranty on the Generator and the Automatic Transfer Switch. Additionally, the Contractor shall guarantee all installation workmanship for a period of one (1) year following final military acceptance.
| STATEMENT OF WORK (SOW) |
| 1.0 PROJECT TITLE & OBJECTIVE |
| 2.0 BACKGROUND |
| 3.0 SCOPE OF WORK |
| 4.0 TECHNICAL SPECIFICATIONS |
| 4.1 Backup Generator |
| 4.2 Automatic Transfer Switch (ATS) |
| 4.3 Cabling & Conductors |
| 5.0 SPECIFIC CONTRACTOR TASKS |
| Task 1: Site Survey & Engineering Submittals |
| Task 2: Procurement & Delivery |
| Task 3: Installation & Electrical Integration |
| Task 4: Testing & Commissioning |
| Task 5: Cleanup & Training |
| 6.0 PERIOD OF PERFORMANCE |
| 7.0 QUALITY ASSURANCE & WARRANTY |