This Statement of Work (SOW) details a furniture replacement project for the U.S. Embassy Consular Section in Madrid, Spain. The project involves removing existing furniture, supplying and installing new furniture including electrically powered sit-stand desks, storage cabinets, lateral files, shelving, meeting tables, and guest seating. Key requirements include using low-VOC, durable finishes, ensuring USB outlets in cubicles, and complying with EU, Spanish, and U.S. building and safety codes.
The project will be executed in three installation phases, with each phase lasting 7 days, and a total production time of 45 days from order confirmation. Contractors must submit detailed documentation including design drawings, electrical load plans, and a phased work schedule. Security protocols require background checks for personnel and embassy staff escort. The embassy will hold a mandatory site visit/pre-proposal conference on September 10, 2025, and contractors must provide name and ID of attendees 48 hours in advance. The project includes a minimum 3-year warranty on furniture components and electrical installation, with all work subject to strict security and safety regulations.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Attachment 4 - Technical sheets.pdf | ||
| Solicitation 19SP5025Q0021.pdf | ||
| Invitation letter.pdf | ||
| Attachment 3 Total cost breakdown Solicitation 19SP5021Q0021.xlsx | XLSX spreadsheet | |
| Attachment 2 Drawings.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATEMENT OF WORK
Attachment 1. SPECIFICATIONS
U.S. Embassy Madrid Spain
Purchase Request: PR15537183
1. INTRODUCTION / SUMMARY OF WORK PROJECT
The U.S. Embassy in Madrid seeks to replace office furniture in the Consular Sec�on. The objec�ve is to improve opera�onal efficiency, ensure compliance with ergonomic and safety standards, and maintain a professional appearance in alignment with Department of State guidelines.
The project includes the removal and disposal of exis�ng furniture, the supply and installa�on of new furniture, and adjustments to ensure that all consular worksta�ons are properly oriented, preven�ng computer screens from being visible to visa applicants or through external windows.
Furniture must comply with the specifica�ons outlined in Atachment 4 – Technical Sheets. The brands and models listed in the atachment are provided for reference only. Proposals must include furniture that meets the requirements and characteris�cs detailed in Atachment 4.
The project will be located at:
U.S. Embassy Consular Sec�on Calle de Serrano, 75, 28006 Madrid, Spain
2.SCOPE OF WORK
2.1 PRIOR TO IMPLEMENTATION
Site Visit and Survey: The contractor is responsible for researching existing conditions and factors that may impact the cost or performance of the services. Attendance at a site visit is recommended to verify all measurements and survey the existing layout prior to submitting the Bill of Materials (BOM) and quotation. Measurements provided by the U.S. Embassy are approximate, and the Embassy will not be held liable for any inaccuracies in dimensions
The Government intends to hold a site visit/preproposal conference on September 10, 2025 at 12:00.
Participants will meet at the Embassy, Calle Serrano, 75, Madrid.
Offerors planning to attend the site visit must submit Name and IDs of the attendees 48 hours prior to the site visit to Maria Jose Moyano: moyanomx@state.gov
DOCUMENT SUBMITTAL PACKAGE. Submit before awarding process, document submittal package that includes:
1. Product Data: Manufacturer's data sheets on each product to be used, including:
1. Create concept and sample of material.
2. Submit manufacturer’s installation instructions, including preparation, storage, and handling requirements.
2. Shop Drawings:
1. Show complete layout and location of the area, including required clearances. Include site layout drawings or any other plans required for this project.
2. Show typical details of assembly, erection, and anchorage.
3. Selection Samples: For each finished product specified, provide one complete set of color chips representing manufacturer's full range of available colors and patterns.
4. Verification Samples: For each finished product specified one sample, minimum size 1-3/4” x 2-1/4”, representing actual product, color, and patterns.
5. Design, bill of materials to be installed, materials provided by the contractor must be approved before prefabrication and installation.
6. Complete finalized Work Plan including Critical Path Method (CPM) schedule.
2.2 IMPLEMENTATION
1. Works must only be carried out by staff with technical knowledge to do so, and always complying with the security rules.
2.3 PROJECT DETAILS
2.3.1 Design & Planning
• Develop a furniture layout in compliance with Drawings provided in Atachment 2:
• EU, Spain, and U.S. building and safety codes, including EM 385-1-1, OSHA, and NEC standards.
• Provide layout drawings and specifica�ons for COR review and approval prior to procurement.
2.3.2 Furniture Supply & Installa�on
• Supply all new furniture, including but not limited to:
o Electrically powered sit-stand desks.
o Storage cabinets, lateral files, and shelving.
o Mee�ng tables and guest sea�ng as required.
• All furniture finishes to be durable, low-VOC.
• All cubicles must have a USB outlet for charging electrical devices.
2.3.3 Removal & Disposal
• Safely dismantle and remove exis�ng furniture for disposal or recycling in accordance with local environmental regula�ons.
• Coordinate with Consulate GSO/FAC for disposi�on of any salvageable items.
2.3.4 Execu�on Constraints
• Turnkey Delivery – Contractor to provide all labor, materials, tools, equipment, transport, and supervision.
2.3.5 Security & Access Control
• All personnel entering the Consulate compound must submit required personal informa�on to the Contrac�ng Officer’s representa�ve (COR) for background checks at least 10 business days in advance.
• All contractor staff must be always escorted by designated Embassy staff with escort authority while on U.S. Government property.
2.4 Deliverables
• Pre-installa�on:
o Final design drawings and furniture specifica�ons.
o Electrical load plan for sit-stand desks.
o Phased work schedule coordinated with Consular Sec�on leadership.
• Post-installa�on:
o As-built drawings.
o Equipment manuals and warranty documenta�on.
o Staff training for sit-stand desk opera�on and maintenance.
2.5 Standards & References
• European & Spanish Standards:
o EN building and safety codes
Crosson, Andrew D (Madrid) Is this just a standard requirement? Interesting. Haven't seen that before. Not really necessary, but sure.
Plikerd, Jordan S (Madrid) I have gone in and modified so many office cubes in Baku & Guangzhou to add USB chargers/outlets to have chargers so that people are less likely to try to plug their phone into the PC to charge and DT gets involved. This can be cut.
Crosson, Andrew D (Madrid) I defer to you. I guess I don't care either way, was more curious than anything.
Qin, Xiangli @Plikerd, Jordan S (Madrid) Please include references to OBO FIRE Code Chapter 8, Section 805.4 on Upholstered Furniture, as well as 15 FAM 761(b) regarding UL and CE certification marking requirements.
Plikerd, Jordan S (Madrid) will do o Spanish occupa�onal safety regula�ons (Prevención de Riesgos Laborales)
2.6. Warranty
• Minimum 3-year warranty on furniture components.
• Minimum 3-year warranty on electrical installa�on and workmanship.
2.7. Period of Performance
The contractor shall sustain a Kick-off meeting to review the SOW, detailed schedule, execution, selection of finishes and safety plan.
Furniture installation will take place in three phases:
Phase 1 – CLIN no. 1 – Contractor shall install furniture in 7 days
Phase 2 – CLLIN no. 2 – Contractor shall install furniture in 7 days
Phase 3 – CLIN no. 3 and 4 – Contractor shall install furniture in 7 days
Production time:
The contractor must deliver furniture within 45 days of order confirmation. Order confirmation will occur once the Government selects final finishes for all furniture pieces following contract award.
• CLIN 1: 45 days
• CLIN 2: 45 days
• CLIN 3: 45 days
• CLIN 4: 45 days If all CLINs are awarded simultaneously, the contractor will have a total of 45 days to produce and deliver all furniture.
The contractor is responsible for storing the furniture and ensuring it is ready for delivery and installation in accordance with the furniture installation schedule agreed upon by both parties after contract award.