Attachment 1- Statement of Work.pdf
PDF 1 MB Posted
- Attached to
- Base Cameras, Columbus AFB, MS
- Solicitation number
- FA302225Q0320
About this file
This Statement of Work (SOW) details a security camera purchase and installation project for Columbus Air Force Base in Mississippi, scheduled for August 2025. The project requires replacing fourteen existing cameras and installing eleven new cameras across multiple buildings, totaling 25 cameras. The contractor must provide and integrate a new Video Management System (VMS), install servers or cloud-based storage capable of storing 30 days of video recordings, and set up three workstations or virtual access points. The system must support integration of up to 40 existing Axis cameras with specific firmware requirements, connect to the Air Force Network, and comply with UFC standards.
Key technical requirements include advanced Artificial Intelligence capabilities for license plate recognition, tracking vehicles and individuals across multiple video feeds, and object detection. The installation must be completed within 60 calendar days of contract award, with cameras positioned at various strategic locations including gates, vehicle inspection areas, and building perimeters. Some cameras may require wireless operation. The contractor must perform cybersecurity hardening, submit comprehensive documentation, conduct a training session, and provide all necessary software licensing. The contract includes a base year from September 2025-2026 with four additional 12-month option years extending through September 2030.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATEMENT OF WORK (SOW)
FOR
SECURITY FORCES CAMERA
PURCHASE AND INSTALL
AT
COLUMBUS AIR FORCE BASE, MISSISSIPPI
05 August 2025
Attachment 1 - FA302225Q0320
1. DESCRIPTION OF SERVICES:
Unless otherwise specified, the contractor shall furnish all personnel, transportation, equipment, tools, materials, and other resources required to:
• Provide, install, configure, and integrate a new Video Management System
(VMS)
• Install servers or provide cloud base storage capable of storing at least 30 days of video recordings
• Install three (3) workstations or provide capability for administrators to log into the system virtually
• Replace fourteen (14) cameras and install an additional eleven (11) cameras at designated locations, as outlined in Attachment 1
• Supply and install all necessary equipment and perform required configurations to integrate up to 40 existing Axis cameras into the operating system. The specific Axis camera models to be integrated are:
Camera Model Name Minimum Firmware Supported Axis 211 D2110-VE 11.10.61
Axis M3027-PVE M3027 5.55.1 Axis P-1448-LE P1448-LE 11.10.61
Axis P3346 P3346 11.10.61 Axis M3007-PVE M3007-PV 5.70.1 & 6.50.5.2
Axis P3301 P3301 5.40.9.2 Axis Q6000-E Mk II Q6000-E Mk II 6.50.5.7
Axis Q60 PTZ NFI NFI Axis Q1765-LE Q1765-LE 11.10.61
All equipment shall be connected to the Air Force Network and must comply with UFC requirements. The contractor shall become familiar with the security and network architecture of Columbus AFB to ensure an optimized and efficient system implementation.
1.1. Place of Performance: Columbus AFB, Columbus, MS
1.2. Contractor Required Deliverables
The Contractor shall provide, deliver, install, configure, update, and connect the items listed in Attachment 1 of this Statement of Work
1.3. Hours of Operation
1.3.1. Normal Working Hours.
The Contractor shall perform services under this SOW between the hours of 07:30 to 16:30 local time, Monday through Friday, except on Federal Holidays or when the government facility is closed due to local or national emergencies, administrative closings, or similar government-directed facility closings.
1.3.2. Federal Holidays
The Contractor is not required to perform services on Federal holidays below:
a. 1 January (New Year’s Day)
b. 3rd Monday in January (Martin Luther King, Jr. Day)
c. 3rd Monday in February (Presidents Day)
d. Last Monday in May (Memorial Day)
e. 4 July (Independence Day)
f. 1st Monday in September (Labor Day)
g. 2nd Monday in October (Columbus Day)
h. 11 November (Veterans Day)
i. 4th Thursday in November (Thanksgiving Day)
j. 25 December (Christmas Day)
k. Any other day designated by federal statute, executive order or presidential proclamation
1.3.3. Principal Period of Maintenance: Contractor must notify Government Representative via email 48 hours prior to service; response not required
1.4. Equipment Requirements
1.4.1. The preferred connection type will be hardwired, however, the use of wireless components can be considered only after pre-coordination with both Security Forces and the base Communications Squadron.
1.4.2. The use of cloud-based storage shall meet or exceed all cybersecurity standards required by the DoD.
1.4.3. The system will interface with the base-wide NIPRNet, maintaining logical separation of data through a Closed Restricted Network (CRN). While data will traverse the existing infrastructure, safeguards will remain in place to preserve its integrity. All components involved must be selected from historically validated Department of Defense technology sources, and the Contractor is responsible for ensuring that all equipment runs a DoD-approved Operating System (OS).
1.4.4. The Contractor shall provide the software license covering all cameras and associated components. Cameras must be accessible from designated network locations via web browser, secured through common access card, PIV, or username and password authentication.
1.4.4.1. Software Licensing Period of Performance (PoP):
One Base Year of 12 months and four12-month option years. The PoP reads as follows:
Base Year: September 2025- September 2026 Option Year 1: September 2026 – September 2027 Option Year 2: September 2027 – September 2028 Option Year 3: September 2028 – September 2029 Option Year 4: September 2029 – September 2030
1.4.5. The software solution shall incorporate advanced Artificial Intelligence (AI) capabilities to enhance situational awareness and operational efficiency. Core functionalities must include real-time license plate recognition, automated tracking of vehicles and individuals across multiple video feeds. The ability for object detection, re-identification, and trajectory prediction is also preferred.
1.4.6. The cost of all required camera mounting brackets shall be factored into the Contractor’s bid.
1.4.7. Project scope includes work on facilities up to the height of the tallest building on base. The cost of any necessary Skylift rentals shall be included in the bid.
1.4.8. All equipment provided must comply with Section 889 of the National Defense Authorization Act (NDAA). BANNED Equipment or components include, but are not limited to, products manufactured by the following plus any affiliate brands:
• Huawei Technologies Company
• ZTE Corporation
• Hytera Communications Corporation
• Hangzhou Hikvision Digital Technology Company
• Dahua Technology Company
2. QUALITY CONTROL
The contractor shall develop and maintain an effective quality control program to ensure all work is performed in accordance with commonly accepted commercial practices. The contractor shall develop and implement procedures to identify, prevent, and ensure non-recurrence of defective work. The Contracting Officer may request this plan as deemed necessary.
3. INSTALLATION
3.1. The Contractor shall furnish all labor, tools, equipment, and materials necessary to install and maintain new cameras, servers, patch cables (fiber or copper), software, and associated components as directed by the 14th Security Forces Squadron. Work shall include removal of all debris, foreign object damage (FOD), tools, and excess materials from the work areas upon completion.
3.2. If requested, the Contractor shall conduct a site survey, coordinate with all relevant stakeholders, collect site-specific data, test existing equipment, and identify any operational constraints that could influence system design or recommendations. The
Contractor shall also identify any required existing documentation, such as As-Built Drawings.
3.3. The Contractor shall submit manufacturers’ data sheets for all materials, equipment, and software required for implementation of the complete system.
3.4. The Contractor shall perform all cybersecurity hardening tasks in accordance with the most current standards. This includes, but is not limited to, applying patches and updates, implementing Security Technical Implementation Guides (STIGs) and Security Requirements Guides (SRGs), and configuring systems securely.
3.5. Prior to installation at Government facilities, the Contractor shall submit the following documentation for approval:
• System descriptions and manufacturers’ data
• Network diagrams
• Data flow diagrams
• Hardware and software inventories (per eMASS template requirements)
• Ports, Protocols, and Services (PPS) list
• ACAS vulnerability and SCAP/SCC scan summaries and raw results
• Completed STIG/SRG checklists with comments
• Configuration files for all network devices
• Plan of Action and Milestones (POA&M) or deviations documentation for any unresolved vulnerabilities
3.6. The system shall achieve 100% compliance with ACAS/Nessus and SCAP/STIG requirements. Any deviations must be fully documented and approved by the Government prior to installation.
3.7. Responsibility for system accreditation resides with the Government once cybersecurity hardening is complete and all required documentation has been accepted.
3.8. All personnel requiring base access to perform work shall undergo background checks by Security Forces. The Contractor shall submit the list of installers at least two
(2) weeks prior to the scheduled start date.
3.9. The Contractor shall install the Video Management System (VMS), servers, workstations, and cameras in accordance with the specifications outlined in this Statement of Work.
3.10. All installation activities, including deployment of cameras, servers, workstations, and the VMS, shall be completed within sixty (60) calendar days from the contract award effective date.
3.11. The Contractor shall ensure all system software is updated and that installed cameras are fully configured and integrated with the servers and VMS. A comprehensive performance test shall be conducted with designated representatives from the 14th Security Forces Squadron to verify functionality.
3.12. Prior to final acceptance of the installation, the Contractor shall conduct one (1) training session for up to ten (10) personnel. All access credentials—such as usernames, passwords, and authentication codes—shall be provided at that time to support operational readiness.
4. CONTRACTOR RESPONSIBILIITES.
4.1. Points of Contact The Contractor shall provide a current list of designated points of contact available during standard business hours (Monday through Friday, 07:30–16:30).
This list shall be continuously updated and submitted to the 14th Security Forces Squadron via email at 14SFS.S5.ALL@us.af.mil throughout the life of the contract.
4.2. Scope of Limitations Maintenance and support services outlined in this Statement of Work shall apply solely to the equipment specified herein.
4.3. Access and Equipment Coordination The Contractor shall coordinate all lift access required for elevated camera servicing. When necessary to minimize disruption to base operations, the Contractor may be required to schedule after-hours work.
ATTACHMENT 1
Video Management System (VMS), Servers, Workstations, Existing Camera Replacement and New Camera Installation
• Building 95/98 Commercial Vehicle Inspection (CVI): A total of two (2) cameras will be installed, replacing existing cameras, at this location. Two (2) outdoor IP cameras in opposite corners covering the inspection area.
• Building 99 Visitor Control Center (VCC): A total of one (1) IP indoor 360-degree view camera with sound will be installed, replacing an existing camera, at this location.
• Building 110 East Gate: A total of three (3) outdoor cameras will be installed, replacing existing cameras, at this location. Two (2) IP cameras, one (1) facing inside the base for inbound/outbound traffic, one (1) facing outside the base for inbound/outbound traffic, one (1) IP outdoor 360-degree view camera.
• Building 1130 South Gate: A total of three (3) outdoor cameras will be installed, replacing existing cameras, at this location. Two (2) IP cameras, one (1) facing inside the base for inbound/outbound traffic, one (1) facing outside the base for inbound/outbound traffic, one (1) IP outdoor 360-degree view camera.
• Building 2006: A total of two (2) cameras will be installed, replacing existing cameras, at this location. One (1) camera will be an outdoor IP camera facing North towards the North Gate. This will need to be able to process precise video approximately 800 meters from mounting location. One (1) camera will be an outdoor IP camera facing West towards the Hot Cargo Pad. This will need to be able to process precise video approximately 1500 meters from mounting location.
• Building 926: Total of one (1) camera will be installed, replacing existing cameras, at this location. One (1) indoor 360-degree cameras with sound with clear view of the SFS armory door and the SFS clearing barrel.
• Building 998: Total of one (1) camera will be installed, replacing existing cameras, at this location. One (1) outdoor IP camera capable of viewing both the SFS ARMAG & flightline ECP.
• Building 1805: Total of two (2) cameras will be installed at this location (no previous camera in place). Two (2) outdoor IP camera capable of viewing up to 1600 meters.
• Building 2005: A total of one (1) camera will be installed, replacing existing cameras, at this location. One (1) camera will be an outdoor IP camera. This will need to be able to process precise video approximately 1600 meters from mounting location.
• Building 958: A total of one (1) camera will be installed at this location. The camera will be an outdoor wide angle camera mounted in the parking lot facing towards the East side of the building. This camera may be required to operate wireless.
• Building 964: A total of one (1) camera will be installed at this location. The towards the West side of the building. This camera may be required to operate
• Building 966: A total of one (1) camera will be installed at this location. The
• Building 972: A total of one (1) camera will be installed at this location. The towards the East side of the building. This camera may be required to operate
• Building 972: A total of one (1) camera will be installed at this location. The
• Building 958: A total of one (1) camera will be installed at this location. The camera will be an outdoor camera mounted in the open area between buildings 958, 964, & 966. This camera may be required to operate wireless.
• Building 543: A total of one (1) camera will be installed at this location. One (1) outdoor camera in the Northwest corner of the building. This camera may be required to operate wireless.
• Building 9113: A total of one (1) camera will be installed at this location. One (1) outdoor camera in the center of the building. This camera may be required to operate wireless.
• Building 348: A total of one (1) camera will be installed at this location. One (1) outdoor IP camera at the center of the building on the West side. This camera may be required to operate wireless.
| 1. DESCRIPTION of Services: |
| 1.1. Place of Performance: Columbus AFB, Columbus, MS |
| 1.2. Contractor Required Deliverables |
| 1.3. Hours of Operation |
| 1.3.1. Normal Working Hours. |
| 1.3.2. Federal Holidays |
| 2. Quality control |
| 3. installation |
| 4. Contractor responsibiliites. |
| 4.3. Access and Equipment Coordination The Contractor shall coordinate all lift access required for elevated camera servicing. When necessary to minimize disruption to base operations, the Contractor may be required to schedule after-hours work. |