Attachment 1 Statement of Work.docx
DOCX document 52 KB Posted
- Attached to
- Install HVAC in BLDGS 3 and 15 - Tifton, GA
- Solicitation number
- 1232SA26Q0879
About this file
This is a Statement of Work for HVAC system replacement at two USDA Agricultural Research Service buildings located at 103 Bermuda Drive, Tifton, Georgia. The contractor must remove existing disjointed mini-split HVAC units and install cohesive multi-zone heating and cooling systems capable of serving all identified spaces. In Building 15, the work includes removing systems in rooms 1, 2, 4, 6, and storage room (estimated capacities ranging from 1.5 to 4 tons) and installing central heating/air conditioning with supply and return ducting. In Building 3, the contractor must remove and replace systems in rooms 1, 2, and 5 (each estimated at 1.5 tons). Both buildings require sealing exterior penetrations, disconnecting/capping electrical and plumbing connections no longer needed, installing drip pans and drainage piping, providing programmable thermostats with heat/cool setpoints and daily scheduling, and delivering system operational training. All work must be completed as turn-key service with the contractor furnishing all personnel, equipment, tools, materials, and quality control.
The project completion timeline is 90 days from the Notice to Proceed, with a detailed project schedule due within 14 days of contract award. Work hours are 8:00 a.m. to 5:00 p.m., Monday through Friday, excluding federal holidays. The contractor must submit a Site Safety Specific Plan/Accident Prevention Plan within 7 days of award and conduct all work inspections with minimum three-day advance written notice. Key requirements include contractor responsibility for hazardous materials assessment, disposal of all removed materials and debris off-site, dust and noise abatement, site cleanup, and three written submittals of shop drawings and specifications. The contractor must verify all dimensions and site conditions prior to commencing work, provide their own restroom facilities, and protect all work and existing property; any damage must be repaired at contractor expense. A pre-bid site visit is encouraged, and the government will conduct final inspection and acceptance prior to payment.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 1232SA26Q0879 Amend 1.pdf | ||
| Attachment 3 Questions from Industry.pdf | ||
| Attachment 2 WD 2015-4517 Rev 34 Dated 13 May 2026.pdf | ||
| 1232SA26Q0879.pdf | ||
| Exhibit A Limitations on Subcontracting Worksheet.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Agricultural Research Service
U.S. DEPARTMENT OF AGRICULTURE
Solicitation Number and Project Title Page 2 of 2
STATEMENT OF WORK
HVAC INSTALLATION
USDA BUILDING 15
USDA BUILDING 3
Southeast Watershed Research Unit 103 Bermuda Dr.
Tifton, Georgia 31793
Asset ID(s):
660200B015 660200B003
1. PROJECT INTRODUCTION
1.1. PROJECT TITLE
USDA-ARS Building 3 & 15 HVAC Replacement
2. PROJECT BACKGROUND AND PURPOSE
The USDA, Agricultural Research Service (ARS), Southeast Watershed Research Unit’s mission is to develop the scientific understanding and associated technologies of watershed systems essential to maintaining/enhancing the environmental and natural resource base upon which a viable, sustainable, and productive agricultural economy depends.
USDA Buildings 3 & 15 have had multiple mini-split HVAC units installed over multiple years in an attempt to solve heating and cooling challenges over the life of the building. This has resulted in disjointed systems that are difficult to maintain. The purpose of this project is to remove the disjointed systems and install cohesive systems that are capable of meeting the heating and cooling needs of the spaces.
3. SCOPE AND OBJECTIVES
3.1. DESCRIPTION OF WORK
The Contractor must furnish all personne1l, equipment, tools, materials, supervision, and quality control necessary to remove the mini-split systems installed and replace with a multi-zone system that can heat/cool the identified spaces.
The Contractor must:
BUILDING 15
· Remove current mini-split/conventional systems in rooms 1, 2, 4, 6, & storage room.
· Install central heating and air conditioning system with supply / return ducting as necessary for system operation.
| ROOM |
| ESTIMATED SF |
| ESTIMATED SIZE |
| Room 1 |
| 300SF |
| 1340SF |
| Room 2 |
| 300SF |
| 3.5 – 4 ton estimated |
| Hall |
| 740SF |
| Storage |
| 500SF |
| 1.5 ton estimated |
| Room 4 |
| 320SF |
| 1.5 ton estimated |
| Room 6 |
| 360SF |
| 1.5 ton estimated |
BUILDING 3
· Remove and replace current systems installed in rooms 1, 2, & 5.
· Install central heating and air conditioning system in rooms 1, 2, & 5.
| ROOM |
| ESTIMATED SF |
| ESTIMATED SIZE |
| Room 1 |
| 600SF |
| 1.5 ton estimated |
| Room 2 |
| 650SF |
| 1.5 ton estimated |
| Room 5 |
| 600SF |
| 1.5 ton estimated |
BOTH BUILDINGS
· Cover/seal no longer needed penetrations in the building exterior.
· Disconnect/cap/secure any electrical / plumbing connections no longer needed
· Install appropriate drip pan / drainage piping / etc to ensure proper system operation.
· Programmable thermostats shall be provided to control zone temperatures -basic programming should include heat/cool set points and daily scheduling capability
· Provide system operational training if applicable.
· Provide all quotes as turn-key completed work.
3.2. The Contractor will verify all dimensions and site conditions prior to beginning work. No Government equipment will be available for use by the Contractor. The Contractor must provide their own restroom facility.
3.3. LOCATION OF WORK
The project is for two buildings located at 103 Bermuda Dr., Tifton, Georgia 31793
3.4. PRE-BID SITE VISIT
Interested vendors are encouraged to visit the site and be escorted by a government representative to confirm locations, dimensions, and conditions of the project before a quote is submitted. The purpose of a site visit is to observe conditions relevant to the completion of this project. No consideration will be given to claims based on lack of knowledge of existing conditions, except where contract documents detail definite provisions for adjustment in cost or extension due to existing conditions not readily foreseeable.
4. PROJECT SCHEDULE
4.1. The completion of this project shall not exceed 90 days from the date of the Notice to Proceed (NTP). A request for time extension must be submitted to the Contracting Specialist/Officer in writing. Each request must include specific and detailed reasons in support of the schedule alteration.
4.2. The Contractor must prepare an overall project schedule including milestone dates for all phases of work and completion date; submit to the COR for approval. This schedule is due fourteen (14) days after contract award. The Contractor must track all work progress to ensure that the project is completed according to the schedule. Include work week schedule with daily starting and stopping time.
4.3. The Contractor must coordinate and confirm the dates for all work with the COR. If necessary, any request for a time extension must be submitted to the Contracting Specialist in writing. Each request must include specific and detailed reasons in support of the schedule alteration and provide an updated schedule for completion. No extension of the period of performance may be given without the written authority of the CO.
4.4. Project work hours are 8:00 am to 5:00 pm, local time, Monday through Friday; federal holidays excluded. The contractor is not required to provide services on recognized Federal holidays established by Federal law (5 U.S.C. 6103). Any changes to work schedule must be submitted to CO for written approval prior to any schedule change.
5. GENERAL REQUIREEMENTS
5.1. PERMITS
No known permits required.
5.2. SAFETY
The Contractor must submit a Site Safety Specific Plan/Accident Prevention Plan (Plan) in industry recognizable format to the COR within seven (7) days of contract award. The Plan must include phone numbers and maps to local physician offices and the nearest hospital. The Government will review and approve the Plan before issuance of the NTP.
5.3. QUALITY CONTROL
Provide quality control to ensure that all components of project work meet the requirements of the contract specifications. Ensure that all work not acceptable or compliant with the specifications is corrected prior to inspection or review by the COR. Quality control is the exclusive responsibility of the Contractor.
5.4. PROTECTION OF WORK AND PROPERTY/SAFETY REQUIREMENTS
5.4.1. The Contractor must protect the work, the site, and all existing property and structures within the limits of the construction activities or that may be affected thereby until acceptance of the work. Any damage to property must be repaired at the Contractor’s expense to pre-damaged condition to the satisfaction of the COR.
5.4.2. Safety and health matters, as they relate to the work, are the exclusive responsibility of the Contractor. The Contractor must furnish, erect, and maintain barricades, warning lights, signs, guards, or take other precautions as may be required by law or local authorities of the protection and security.
5.4.3. Provide continuous noise and dust abatement as required to prevent disturbance and nuisance to the public and workers and to the occupants of adjacent premises and surrounding areas. Dampen or cover areas affected by demolition operations as necessary to prevent dust nuisance.
5.4.4. The contract documents may not represent all surface conditions at the site and adjoining areas. The known surface conditions are as indicated and must be compared with actual conditions before commencement of work and the cost must be included in the Contractor’s quote.
5.4.5. The Government will not furnish any labor or equipment to unload or move materials or supplies.
6. UTILIZATION OF BIOBASED PRODUCTS
The Contractor must utilize products and material based from bio-based materials as applicable, (e.g. bio-based greases; bio-based hydraulic fluids, bio-based absorbents), to the maximum extent possible without jeopardizing the intended end use or detracting from the overall quality delivered to the Government. All supplies and materials must be of a type and quality that conform to the applicable federal specifications and standards. All supplies and materials to be used in the performance of work described herein are subject to the approval of the Contracting Officer Representative (COR). Products can be found at: www.biopreferred.gov.
7. HAZARDOUS MATERIAL
The SEWRU Generators are not suspected to contain asbestos containing materials. Existing conditions are reflected correctly to the best of USDA’s knowledge. The USDA makes no representation, warranty, or guaranty that the conditions indicated either are representative of those conditions existing throughout the area, or that unforeseen developments may not occur, or that materials other than, or proportions different from those indicated may not exist. The Contractor must include costs for hazardous materials assessment in the quote. If hazardous materials are found to be present, it must be reported to the CO & COR for further action.
8. DISPOSAL OF REMOVED MATERIALS AND DEBRIS
8.1. The Contractor must dispose of removed, materials, waste, trash, and debris in a safe, acceptable manner, in accordance with applicable laws and ordinances and as prescribed by authorities having jurisdiction.
8.2. Burying of trash and debris on the site is prohibited. Burning of trash and debris at the site is prohibited.
8.3. Remove trash and debris from the site at frequent intervals so that its presence will not delay the progress of the work or cause hazardous conditions for workers and the public.
8.4. Removed materials, trash, and debris must become the property of the Contractor and must be removed from the project site and be disposed of in a legal manner. Location of disposal site and length of haul are the Contractor's responsibility.
8.5. The contractor should make every effort to recycle as much of the construction debris as possible.
8.6. Any waste materials encountered during the demolition that are found to contain lead, asbestos, polychlorinated biphenyls (PCB), fluorescent lamps, or any hazardous substances are to be handled and removed in accordance with local, state, and federal laws and requirements concerning hazardous waste as well as any specific hazardous waste requirements stated in different sections.
8.7. Comply with hauling and disposal regulations of authorities having jurisdiction, per federal, state, and local requirements.
9. TEMPORARY FACILITIES
There are no temporary facilities available to the contractor for this project.
10. CLEANUP
The work area must be kept clean and free of debris at all times. Restore areas disturbed as nearly as possible to the original appearance and condition. Upon completion of the project, and prior to final inspection, the Contractor must remove from the premises all unused material, trash, and debris resulting from the work to the satisfaction of the COR.
11. SUBMITTALS
Submittals on all material incorporated into the work, including shop drawings and specifications, used on this project must be submitted to the EPM, COR, and Contracting Specialist. Electronic submittals are acceptable, otherwise three (3) written submittals are required.
11.1. Project Schedule within fourteen (14) calendar days of award (see Section 3.2).
11.2. Plan within seven (7) days of award (see Section 4.2).
11.3. Any additional material, including shop drawings and specifications, used on this project.
12. INSPECTION AND ACCEPTANCE
A government representative will inspect and approve the work performed on this project. The Contractor must schedule inspection a minimum of three (3) days in advance, in writing, to the COR and CO.
13. FINAL PAYMENT/CONTRACT CLOSEOUT
The following documents are required prior to final payment (other documents may also be required): Release of Liens, Release of Claims, Employee Payroll\Timesheets, and Invoice.
Last Updated 7/15/2026 image1.jpeg