ATTACHMENT 1 - Specifications.pdf
PDF 11 MB Posted
- Attached to
- Y1BG--EHRM Infrastructure Upgrades Construction - Bath - Project 528A6-22-700 Federal contract opportunity
- Solicitation number
- 36C77626B0015
About this file
Summary of Bath VAMC EHRM Infrastructure and Data Center Upgrades Bid Documents
This is a comprehensive bid document package for the EHRM Infrastructure and Data Center Upgrades Construction project at Bath VAMC (VA Project 528A6-22-700), prepared by AE Works (Project VBAT-006). The project involves demolishing portions of existing structures, constructing a new standalone data center building in Building 100, upgrading telecommunications rooms throughout the campus, installing fiber optic backbone cabling infrastructure, and upgrading supporting electrical and mechanical systems across multiple buildings. The work is phased into nine distinct phases over an extended construction period, with strict requirements for maintaining 24/7 medical center operations, infection control risk assessments (ICRA), and coordination with ongoing facility activities.
The specifications mandate comprehensive quality control, safety compliance, and specialized contractor qualifications including a CQC System Manager with engineering background, specialized personnel in electrical/mechanical/civil disciplines, and designated Site Safety and Health Officer. Contractor must establish and maintain negative pressure containment systems, decontamination facilities, emergency action plans, and respiratory protection programs. The project requires submittal of detailed project schedules using Critical Path Method with approximately 730 work activities, warranty management plans, as-built drawings, photographic documentation with interactive digital indexing, and systems manuals. Asbestos abatement is required in multiple locations (approximately 3,110 square feet and 40 linear feet identified), with strict compliance to 12 NYCRR Part 56, EPA, and OSHA standards. The contractor must secure pre-construction approvals for design mixes (concrete), shop drawings, testing laboratory qualifications, Environmental Protection Plan, Accident Prevention Plan, and numerous specialized submittals before work commencement.
View the file
Other files for this federal contract opportunity
Show all 27
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
BATH VAMC
EHRM INFRASTRUCTURE AND DATA
CENTER UPGRADES
BATH, NEW YORK
BID DOCUMENTS
SEPTEMBER 26, 2025
VA Project 528A6-22-700
AEW # VBAT-006
Prepared by
418 Beaver St Sewickley, PA 15143
(412) 287-7333
VA Project No. 528A6-22-700 Bath VAMC AE Works Project No. VBAT-006 EHRM Infrastructure and Data Center Upgrades
BID DOCUMENTS
05-10-24
STAMPS PAGE
00 00 01-1
STAMPS PAGE
Section 00 00 01
BID DOCUMENTS
06-01-24
TABLE OF CONTENTS
00 01 10-1
TABLE OF CONTENTS
Section 00 01 10
SECTION NO. DIVISION AND SECTION TITLES DATE
DIVISION 00 - SPECIAL SECTIONS
00 01 10 Stamp Page N/A 00 01 15 List of Drawing Sheets 07-15
DIVISION 01 - GENERAL REQUIREMENTS
01 00 00 General Requirements 11-21 01 32 00 Construction Documentation 09-23 01 32 16.15 Project Schedules (Small Projects – Design/Bid/Build 11-21 01 33 23 Shop Drawings, Product Data, and Samples 02-23 01 35 26 Safety Requirements 09-22 01 42 19 Reference Standards 11-20 01 45 00 Quality Control 02-21 01 45 29 Testing Laboratory Services 11-18 01 45 35 Special Inspections 06-21 01 45 35.01 Schedule of Special Inspections N/A 01 57 19 Temporary Environmental Controls 01-21 01 58 16 Temporary Interior Signage 07-15 01 74 19 Construction Waste Management 04-22 01 81 13 Sustainable Construction Requirements 10-17 01 91 00 General Commissioning Requirements 04-22
DIVISION 02 – EXISTING CONDITIONS
02 21 13 Site Surveys 02-23 02 41 00 Demolition 08-17 02 82 11 Traditional Asbestos Abatement 04-19
DIVISION 03 – CONCRETE
03 30 00 Cast-in-Place Concrete 07-19
DIVISION 04 – MASONRY
04 05 13 Masonry Mortaring 10-17 04 05 16 Masonry Grouting 02-16 04 20 00 Unit Masonry 08-17 04 72 00 Cast Stone Masonry 02-15
DIVISION 05 – METALS
05 31 00 Steel Decking 01-21 05 36 00 Composite Metal Decking 01-21 05 40 00 Cold-Formed Metal Framing 01-21
BID DOCUMENTS
06-01-24
TABLE OF CONTENTS
00 01 10-2
SECTION NO. DIVISION AND SECTION TITLES DATE
05 50 00 Metal Fabrications 08-18
DIVISION 06 – WOOD, PLASTICS AND COMPOSITES
06 10 00 Rough Carpentry 10-17 06 16 00 Sheathing N/A
DIVISION 07 - THERMAL AND MOISTURE PROTECTION
07 13 00 Sheet Waterproofing 01-21 07 14 16.11 Cold Fluid Applied Waterproofing N/A 07 21 13 Thermal Insulation 10-17 07 27 27 Fluid-Applied Membrane Air Barrier, Vapor Retarding 02-16 07 31 13 Asphalt Shingles 01-21 07 60 00 Flashing and Sheet Metal 01-21 07 71 00 Roof Specialties 01-21 07 84 00 Firestopping 02-16 07 92 00 Joint Sealants 10-17 07 95 13 Expansion Joint Covers 02-16
DIVISION 08 - OPENINGS
08 11 13 Hollow Metal Doors and Frames 01-21 08 14 00 Interior Wood Doors 01-21 08 31 13 Access Doors and Frames 04-22 08 71 00 Door Hardware 03-24 08 90 00 Louvers and Vents 01-21
DIVISION 09 – FINISHES
09 05 16 Subsurface Preparation for Floor Finishes 01-21 09 06 00 Schedule of Finishes 01-21 09 22 16 Non-Structural Metal Framing 06-18 09 29 00 Gypsum Board 04-20 09 51 00 Acoustical Ceilings 12-18 09 65 13 Resilient Base and Accessories 01-21 09 65 19 Resilient Tile Flooring 05-18 09 68 00 Carpeting 01-21 09 91 00 Painting 01-21 09 96 13 ESD Control System N/A
DIVISION 10 – SPECIALTIES
10 14 00 Signage 01-21 10 44 13 Fire Extinguisher Cabinets 08-18 10 81 13 Bird Control Devices N/A
DIVISION 21- FIRE SUPPRESSION
BID DOCUMENTS
06-01-24
TABLE OF CONTENTS
00 01 10-3
SECTION NO. DIVISION AND SECTION TITLES DATE
21 13 13 Wet-Pipe Sprinkler Systems 06-15 21 22 00 Clean Agent Fire Suppression Systems 05-15
DIVISION 22 – PLUMBING
22 05 23 General Duty Valves for Plumbing Piping 11-22 22 07 11 Plumbing Insulation 09-19 22 08 00 Commissioning of Plumbing Systems 11-16 22 11 00 Facility Water Distribution 11-19
DIVISION 23 – HEATING, VENTILATING, AND AIR
CONDITIONING (HVAC)
23 05 11 Common Work Results for HVAC 02-20 23 05 12 General Motor Requirements for HVAC Equipment 02-20 23 05 41 Noise and Vibration Control for HVAC Piping and
Equipment 02-20
23 05 93 Testing, Adjusting, and Balancing for HVAC 02-20 23 07 11 HVAC Insulation 02-20 23 08 00 Commissioning of HVAC Systems 02-20 23 09 23 Direct-Digital Control System for HVAC 09-11 23 21 13 Hydronic Piping 02-20 23 21 23 Hydronic Pumps 02-20 23 23 00 Refrigerant Piping 02-20 23 31 00 HVAC Ducts and Casings 02-20 23 34 00 HVAC Fans 02-20 23 37 00 Air Outlets and Inlets 02-20 23 72 00 Air-to-Air Energy Recovery Equipment 05-11 23 81 00 Decentralized Unitary HVAC Equipment 03-20 23 81 23 Computer-Room Air-Conditioners 04-11 23 81 43 Air-Source Unitary Heat Pumps 04-11 23 82 00 Convection Heating and Cooling Units 03-20
DIVISION 25 – INTEGRATED AUTOMATION
25 08 00 Commissioning of Integrated Automation 05-24
DIVISION 26 – ELECTRICAL
26 01 00 Basic Electrical Requirements 11-22 26 02 00 Quality Requirements 11-22 26 05 00 Common Work Results for Electrical 11-22 26 05 11 Requirements for Electrical Installations 11-22 26 05 13 Medium-Voltage Cables 11-22 26 05 19 Low-Voltage Electrical Power Conductors and Cables 11-22 26 05 26 Grounding and Bonding for Electrical Systems 11-22 26 05 33 Raceway and Boxes for Electrical Systems 11-22 26 05 41 Underground Electrical Construction 11-22 26 05 73 Overcurrent Protective Device Coordination Study 11-22
BID DOCUMENTS
06-01-24
TABLE OF CONTENTS
00 01 10-4
SECTION NO. DIVISION AND SECTION TITLES DATE
26 08 00 Commissioning of Electrical Systems 11-16 26 12 19 Medium-Voltage VFI Transformers 11-22 26 13 20 Medium-Voltage Pad-Mounted Switchgear 11-22 26 22 00 Low-Voltage Transformers 11-22 26 24 16 Panelboards 11-22 26 25 11 Busways 11-22 26 25 50 Generator Docking Station 11-22 26 26 00 Power Distribution Units for Static Uninterruptible
Power Systems 11-22
26 27 26 Wiring Devices 11-22 26 29 21 Enclosed Switches and Circuit Breakers 11-22 26 32 13 Engine Generators 11-22 26 33 53 Static Uninterruptible Power Supply 11-22 26 36 23 Automatic Transfer Switches 11-22 26 41 00 Facility Lightning Protection 11-22 26 43 13 Surge Protective Devices 11-22 26 51 00 Interior Lighting 03-24 26 56 00 Exterior Lighting 11-22
DIVISION 27 – COMMUNICATIONS
27 05 26 Grounding and Bonding for Communications Systems 07-23 27 05 33 Conduits and Backboxes for Communications Systems 12-01-
27 05 36 Cable Trays for Communications Systems 12-01-
27 05 53 Identification for Communications Systems 12-01-
27 08 00 Commissioning of Communications Systems 11-16 27 10 00 Structured Cabling 12-01-
27 11 16 Communications Cabinets, Racks, Frames, and Enclosures 12-01-
27 11 19 Communications Termination Blocks and Patch Panels 12-01-
27 11 26 Communications Rack Mounted Power Protection and Power
Strips 05-24
27 13 13 Communications Copper Backbone Cabling 12-01-
27 13 13.13 Communications Copper Cable Splicing and Terminations 12-01-
27 13 23 Communications Optical Fiber Backbone Cabling 08-23 27 13 23.13 Communications Optical Fiber Splicing and Terminations 12-01-
27 15 13 Communications Copper Horizontal Cabling 12-01-
27 16 19 Communications Patch Cords, Station Cords, and Cross-
Connect Wire 12-01-
DIVISION 28 – ELECTRONIC SAFETY AND SECURITY
BID DOCUMENTS
06-01-24
TABLE OF CONTENTS
00 01 10-5
SECTION NO. DIVISION AND SECTION TITLES DATE
28 05 00 Common Work Results for Electronic Safety and Security 04-18 28 05 13 Conductors and Cables for Electronic Safety and
Security 10-18
28 05 26 Grounding and Bonding for Electronic Safety and Security
09-11
28 05 28.33 Conduits and Backboxes for Electronic Safety and Security
09-11
28 08 00 Commissioning of Electronic Safety and Security Systems 11-16 28 13 00 Physical Access Control System 10-11 28 16 00 Intrusion Detection System 10-11 28 23 00 Video Surveillance 09-11 28 31 00 Fire Detection and Alarm 10-11
DIVISION 31 – EARTHWORK
31 20 00 Earthwork 07-16
DIVISION 32 – EXTERIOR IMPROVEMENTS
32 05 23 Cement and Concrete for Exterior Improvements 08-16 32 12 16 Asphalt Paving 09-15 32 31 19 Decorative Metal Fence and Gate 06-18 32 90 00 Plantings 08-16
DIVISION 33 – UTILITIES
33 10 00 Water Utilities 03-17 33 40 00 Storm Sewer Utilities 12-17 33 63 00 Steam Energy Distribution 09-17
BID DOCUMENTS
05-01-20
LIST OF DRAWING SHEETS
00 01 15 - 1
SECTION 00 01 15
LIST OF DRAWING SHEETS
Refer to Drawing G001 for Sheet Index
- - - E N D - - -
BID DOCUMENTS
11-01-21
GENERAL REQUIREMENTS
01 00 00 -1
SECTION 01 00 00
GENERAL REQUIREMENTS
PART 1 - GENERAL
1.1 SAFETY REQUIREMENTS
A. Refer to section 01 35 26, SAFETY REQUIREMENTS for safety and infection control requirements.
1.2 GENERAL INTENTION
A. Data Center/Main Computer Room (MCR) – The main Data Center in Building
37 will be relocated into a new Building 100 meeting the OIT standards for a Medium Campus Support Center (CSC).
B. Facility Fiber Infrastructure – The new CSC serves as the centralized location and distribution point for new single mode and multimode fiber optic backbone cabling to all modified and new Telecommunications
Rooms.
C. Telecommunication Room (TR) – Upgrade new TRs in multiple buildings throughout the campus. new equipment racks, power and lighting, telecommunications bonding, and climate control.
D. Upgrade the existing horizontal cabling from the TRs to the WAOs with
Category 6A.
E. Upgrades of supporting electrical/mechanical systems.
F. Physical Security upgrade of the data center and TRs access control and video surveillance systems are to comply with the Physical Security and
Resiliency Design Manual (PSRDM).
G. Visits to the site by Bidders are scheduled per solicitation only.
H. Offices of AE Works, 418 Beaver Street, Sewickley Pa. as
Architect-Engineers, will render certain technical services during construction. Such services shall be considered as advisory to the
Government and shall not be construed as expressing or implying a contractual act of the Government without affirmations by Contracting
Officer or his duly authorized representative.
I. Before placement and installation of work subject to tests by testing laboratory retained by Department of Veterans Affairs, the Contractor shall notify the COR in sufficient time to enable testing laboratory
BID DOCUMENTS
11-01-21
GENERAL REQUIREMENTS
01 00 00 -2 personnel to be present at the site in time for proper taking and testing of specimens and field inspection. Such prior notice shall be not less than three workdays unless otherwise designated by the COR.
J. All employees of general contractor and subcontractors shall comply with VA security management program and obtain permission of the VA police, be identified by project and employer, and restricted from unauthorized access.
1.3 STATEMENT OF BID ITEM(S)
A. ITEM I, GENERAL CONSTRUCTION: BASE BID: Work includes general construction, demolition, sitework, necessary removal of existing structures and construction.
1.4 SPECIFICATIONS AND DRAWINGS FOR CONTRACTOR
A. Drawings and contract documents may be obtained from the website where the solicitation is posted. Additional copies will be at Contractor's expense.
1.5 CONSTRUCTION SECURITY REQUIREMENTS
A. Security Plan:
1. The security plan defines both physical and administrative security procedures that will remain effective for the entire duration of the project.
2. The General Contractor is responsible for assuring that all sub-contractors working on the project and their employees also comply with these regulations.
B. Security Procedures:
1. General Contractor’s employees shall not enter the project site without appropriate badge. Photo ID equivalent to state issued driver’s license. They may also be subject to inspection of their personal effects when entering or leaving the project site.
2. Before starting work the General Contractor shall give one week’s notice to the Contracting Officer so that security escort arrangements can be provided for the employees. This notice is
BID DOCUMENTS
11-01-21
GENERAL REQUIREMENTS
01 00 00 -3 separate from any notices required for utility shutdown described later in this section.
3. No photography of VA premises and outside of project area is allowed without written permission of the Contracting Officer. Patients and staff are not to be photographed at any time.
4. VA reserves the right to close down or shut down the project site and order General Contractor’s employees off the premises in the event of a national emergency. The General Contractor may return to the site only with the written approval of the Contracting Officer.
5. VA Police have the right to inspect contractor vehicles, toolboxes, trailers, and storage at any times.
C. Key Control:
1. The General Contractor shall provide duplicate keys and lock combinations to the Contracting officers representative (COR) for the purpose of security inspections of every area of project including toolboxes and parked machines and take any emergency action.
2. The General Contractor shall provide all permanent cores at completion of the work turn over lock cylinders to the VA locksmith for permanent installation. See Section 08 71 00, DOOR HARDWARE and coordinate.
D. Document Control:
1. Before starting any work, the General Contractor/Sub Contractors shall submit an electronic security memorandum describing the approach to following goals and maintaining confidentiality of
“sensitive information”.
2. The General Contractor is responsible for safekeeping of all drawings, project manual and other project information. This information shall be shared only with those with a specific need to accomplish the project.
3. Certain documents, sketches, videos or photographs and drawings may be marked “Law Enforcement Sensitive” or “Sensitive Unclassified”.
Secure such information in separate containers and limit the access to only those who will need it for the project. Return the information to the Contracting Officer upon request.
BID DOCUMENTS
11-01-21
GENERAL REQUIREMENTS
01 00 00 -4
4. These security documents shall not be removed or transmitted from the project site without the written approval of Contracting
Officer.
5. All paper waste or electronic media such as CD’s and diskettes shall be shredded and destroyed in a manner acceptable to the VA.
6. Notify Contracting Officer and Site Security Officer immediately when there is a loss or compromise of “sensitive information”.
E. Motor Vehicle Restrictions
1. Vehicle authorization request shall be required for any vehicle entering the site and such request shall be submitted 24 hours before the date and time of access. Access shall be restricted to picking up and dropping off materials and supplies.
2. A limited number of (2 to 5) permits shall be issued for General
Contractor and its employees for parking in designated areas only.
Contractor to coordinate with VA Medical Center Facility Manager.
1.6 OPERATIONS AND STORAGE AREAS (FAR 52.236-10)
A. The Contractor shall confine all operations (including storage of materials) on Government premises to areas authorized or approved by the Contracting Officer. The Contractor shall hold and save the
Government, its officers and agents, free and harmless from liability of any nature occasioned by the Contractor's performance.
B. Temporary buildings (e.g., storage sheds, shops, offices) and utilities may be erected by the Contractor only with the approval of the
Contracting Officer and shall be built with labor and materials furnished by the Contractor without expense to the Government. The temporary buildings and utilities shall remain the property of the
Contractor and shall be removed by the Contractor at its expense upon completion of the work. With the written consent of the Contracting
Officer, the buildings and utilities may be abandoned and need not be removed.
C. The Contractor shall, under regulations prescribed by the Contracting
Officer, use only established roadways, or use temporary roadways constructed by the Contractor when and as authorized by the Contracting
Officer. When materials are transported in prosecuting the work, vehicles shall not be loaded beyond the loading capacity recommended by
BID DOCUMENTS
11-01-21
GENERAL REQUIREMENTS
01 00 00 -5 the manufacturer of the vehicle or prescribed by any Federal, State, or local law or regulation. When it is necessary to cross curbs or sidewalks, the Contractor shall protect them from damage. The
Contractor shall repair or pay for the repair of any damaged curbs, sidewalks, or roads.
D. Working space and space available for storing materials shall be as determined by the COR.
E. Workers are subject to rules of Medical Center applicable to their conduct.
F. Execute work in such a manner as to interfere as little as possible with work being done by others. Keep roads clear of construction materials, debris, standing construction equipment and vehicles at all times.
G. Execute work to interfere as little as possible with normal functioning of Medical Center as a whole, including operations of utility services, fire protection systems and any existing equipment, and with work being done by others. Use of equipment and tools that transmit vibrations and noises through the building structure, are not permitted in buildings that are occupied, during construction, jointly by patients or medical personnel, and Contractor's personnel, except as permitted by COR where required by limited working space.
1. Do not store materials and equipment in other than assigned areas.
2. Schedule delivery of materials and equipment to immediate construction working areas within buildings in use by Department of
Veterans Affairs in quantities sufficient for not more than two workdays. Provide unobstructed access to Medical Center areas required to remain in operation.
3. Where access by Medical Center personnel to vacated portions of buildings is not required, storage of Contractor's materials and equipment will be permitted subject to fire and safety requirements.
H. Utilities Services: Where necessary to cut existing pipes, electrical wires, conduits, cables, etc., of utility services, or of fire protection systems or communications systems (except telephone), they shall be cut and capped at suitable places where shown; or, in absence
BID DOCUMENTS
11-01-21
GENERAL REQUIREMENTS
01 00 00 -6 of such indication, where directed by COR. All such actions shall be coordinated with the COR or Utility Company involved:
1. Whenever it is required that a connection fee be paid to a public utility provider for new permanent service to the construction project, for such items as water, sewer, electricity, gas or steam, payment of such fee shall be the responsibility of the Government and not the Contractor.
I. Phasing:
1. The Medical Center must maintain its operation 24 hours a day 7 days a week. Therefore, any interruption in service must be scheduled and coordinated with the COR to ensure that no lapses in operation occur. It is the CONTRACTOR'S responsibility to develop a work plan and schedule detailing, at a minimum, the procedures to be employed, the equipment and materials to be used, the interim life safety measure to be used during the work, and a schedule defining the duration of the work with milestone subtasks. The work to be outlined shall include, but not be limited to:
2. To ensure such executions, Contractor shall furnish the COR with a schedule of approximate phasing dates on which the Contractor intends to accomplish work in each specific area of site, building or portion thereof. In addition, Contractor shall notify the COR two weeks in advance of the proposed date of starting work in each specific area of site, building or portion thereof. Arrange such phasing dates to ensure accomplishment of this work in successive phases mutually agreeable to COR and Contractor, as follows:
Phase One: Data Center Planning
Phase one primarily consists of the full construction and completion of the new data center including but not limited to, site work, utilities, structural, and finishes. Site work under Phase one shall be to provide utilities and new structure. Site work not directly required for building operations may occur at any time including but not limited to sidewalks, restoration, etc. when best suits the work. Phases one, two, and three may run concurrently if sufficient labor and supervision is provided.
A. Client Tasks:
BID DOCUMENTS
11-01-21
GENERAL REQUIREMENTS
01 00 00 -7
1. Coordinate with system vendors and Service Providers and complete equipment migrations to new equipment cabinets as they become ready for use (rolling cutover) and remove emptied legacy cabinets.
B. Architectural Tasks:
1. Establish and maintain infection control, risk management, and safety measures in compliance with VA guidelines prior to initiating work.
a. ICRA: Contractor to study and follow strictly the template set forth in the VHA Infection Control Risk Assessment for Construction, Renovation and Maintenance guidelines regarding the protocol and procedures required to do work on Data Center. This includes filling out all forms including in the template and obtaining approval prior to starting work.
b. PCRA: Compliance with the ICRA shall be done in conjunction with PCRA (Pre- construction Risk Assessment, for the activity which addresses other activity- related safety concerns (e.g. vibrations, noise) outside of the ICRA.
2. Construct new Data Center building shell, interior partitions, exterior canopies, louver and doors.
3. Complete ceiling finishes, wall finishes, flooring, doors, windows, signage, physical security features, door hardware installation etc. as well as carry out careful protection of completed surfaces before handing project over.
4. Remove infection control, risk management, and safety measures when construction is complete.
C. Mechanical Tasks:
1. Provide water protection and leak detection measures to control water-related risks during construction.
2. Install new computer room air conditioning (CRAC) unit(s).
Prioritize two fully operational CRACs and associated condensing units sized at N. Install remaining cooling unit(s) to satisfy the Data Center cooling requirements (N+1 design).
3. Install ductwork to the return section of the CRAC units, which must remain open to the environment until all telecommunications and electrical infrastructure equipment is installed. Protect new ductwork from dust/debris until
BID DOCUMENTS
11-01-21
GENERAL REQUIREMENTS
01 00 00 -8 new unit(s) is brought online.
4. Install horizontal ductwork to server cabinet chimneys as units become available.
5. Install leak detection devices to new equipment cabinets.
D. Electrical Tasks:
1. Install new uninterruptible power supply (UPS) units, standalone power distribution units (PDUs), battery cabinets, and maintenance bypass cabinets. Bring units online one at a time (2N design).
2. Install new panelboards, circuits, and overhead busways to new PDU units.
3. Install power distribution to equipment cabinets and mechanical equipment as they become available.
4. Install new lighting, exit signage, and receptacle devices.
5. Establish emergency power off (EPO) system, fire alarm system/devices, and connect new clean agent system to fire alarm system.
6. Establish ground ring and lightning protection system.
7. Upon completion of commissioning of the new Data Center, remove existing UPS supporting the existing Data Center in Room 76-G113A. Coordinate timing of this work with VA COR and demolish equipment in place as necessary for complete removal.
E. Telecommunications & Electronic Security Tasks:
1. Install new Main Distribution Area (MDA), Horizontal Distribution Area (HDA), and in-row Equipment Distribution (ED) cabinets as floor space becomes available. Prioritize “A” series MDA and HDA cabinets supporting backbone cabling, followed by redundant “B” series cabinets.
2. Install new permanent link backbone cabling between new equipment cabinets. Prioritize “A” series cabling segments, followed by redundant “B” series segments.
3. Install new cameras, card readers, and other electronic security devices.
4. Remove remaining unnecessary legacy outlets/devices, horizontal/backbone cabling, and pathway infrastructure in their entirety from existing Data Center.
F. Civil Tasks:
1. Install construction fencing, roads, related signage and erosion & sediment control measures as shown on the plans for new Data Center area of construction.
BID DOCUMENTS
11-01-21
GENERAL REQUIREMENTS
01 00 00 -9
2. Verify and document existing underground utility service lines, duct banks and structures for the new Data Center area of construction.
3. Initiate earthworks preparation for new Data Center.
4. Establish proposed grade for the new Data Center and coordinate underground service lines proposed for the Data Center
5. Construct site improvements and underground utility service lines shown on the plan in coordination with building construction.
6. Coordinate mechanical and electrical unit pads and mounting with ground utility locations.
7. Complete sanitary and stormwater systems and tie ins to existing mains as shown on the plans.
G. Structural Tasks:
1. Construct new standalone Data Center per structural drawings, coordinate with other discipline drawings where required. Specific phasing of structural activities for standalone Data Center to be determined by general contractors.
H. Fire Suppression Tasks:
1. Install piping and discharge nozzles in Data Center to provide clean agent protection.
2. Locate and mount clean agent storage tanks and ensure they are secured.
3. Route electrical cabling for clean agent control systems to the fire alarm control panel (FACP).
4. Provide dedicated 120VAC, 20-amp power circuit to serve
RFCP.
5. Provide addressable releasing fire control panel to serve the inert gas suppression within the Data Center. Provide four (4) addressable input modules off the building fire alarm system to transmit releasing system alarm, discharge, supervisory and trouble signals to building fire alarm system.
6. Provide addressable output module to shut down CRAC unit upon releasing of inert gas.
7. Provide maintenance disconnect switch for the inert gas solenoid valve. Provide addressable input module for monitoring of the maintenance disconnect switch.
8. Provide addressable output module to activate emergency power off functions of the Data Center electrical equipment.
BID DOCUMENTS
11-01-21
GENERAL REQUIREMENTS
01 00 00 -10
9. Install the new sprinkler mains and risers in alignment with the Data Center infrastructure.
10. Install branch piping in ceilings of the Data Center.
11. Install standard response fusible link upright sprinklers with guards within the Data Center.
12. The existing sprinkler system will be decommissioned and removed following the successful installation and commissioning of the new clean agent system, ensuring uninterrupted fire protection coverage during the transition.
I. Systems Testing and Commissioning Tasks:
1. Conduct infrastructure testing and labeling as new subsystem installations are completed and ensure ready for use. Conduct commissioning tasks as specified.
Phase Two: Telecommunications Room Planning
Phase two primarily consists of select demolition and construction of new telecommunication rooms throughout the facility including but not limited to, utilities, finishes, and racks. Phases one, two, and three may run concurrently. Phase Two may not occupy more than five active work areas at one time without prior approval from the COR. Telecom Room buildouts include existing spaces being modified, some requiring expansion, and new construction. Work in existing and operational work areas may require escorts from the VA to ensure proper security.
A. Client Tasks:
1. Remove unnecessary network equipment, patch cords, cabinets/racks, inventory, workstations, etc., from each Telecom Room work area to create clear working space.
2. Initiate network equipment migration to new equipment racks and prepare for work area outlet cutover.
B. Architectural Tasks:
1. Establish infection control, risk management, and safety measures in compliance with VA guidelines prior to initiating work in each Telecom Room work area. Maintain infection control, risk management, and safety measures as work progresses.
a. ICRA: Contractor to study and follow strictly the template set forth in the VHA Infection Control Risk Assessment for Construction, Renovation and Maintenance guidelines regarding the protocol and
BID DOCUMENTS
11-01-21
GENERAL REQUIREMENTS
01 00 00 -11 procedures required to do work on Data Center. This includes filling out all forms including in the template and obtaining approval prior to starting work.
b. PCRA: Compliance with the ICRA shall be done in conjunction with PCRA (Pre- construction Risk Assessment, for the activity which addresses other activity- related safety concerns (e.g. vibrations, noise) outside of the ICRA.
c. Contractor to also coordinate with VA COR on mobile temporary ICRA barriers and extent of the occupation of any agreed upon work areas. All offices, exits, utility and MEP spaces, restrooms shall be always kept accessible unless proper approvals were obtained from VA COR. Approvals are to be obtained by the following entities: VA Police, VA Fire Department or others as directed by VA COR.
2. As required, remove Telecom space partitions, ceiling finishes, wall finishes, flooring, doors, windows, signage, physical security features, etc. This work also includes abatement of Asbestos-Containing Material (ACM) and other selective demolition as detailed in the construction documents.
3. Construct partitions, TRs floor finishes and install plywood backer board as required.
4. Construct new Telecommunications Room shells and/or modify existing room partitions as indicated on drawings.
5. Install ceiling finishes, wall finishes, flooring, doors, signage, physical security features, door hardware, etc.
C. Mechanical Tasks:
1. Provide water protection and leak detection measures to control water-related risks during construction.
2. As required, remove designated HVAC and plumbing systems.
Domestic water piping being demolished shall be removed back to the main and capped at the main. Contractor to confirm abandoned in place capping and piping “dead leg” exceptions with the Client due to access restrictions.
3. Prepare designated space for the mini-split indoor unit in the Telecommunications Room.
4. Install mini-split indoor unit, associated exterior condensing unit, and refrigerant piping connections.
5. Connect condensate piping and condensate pump (if
BID DOCUMENTS
11-01-21
GENERAL REQUIREMENTS
01 00 00 -12 required), route to designated location.
6. Provide thermostat with integral temperature and humidity sensor.
D. Electrical Tasks:
1. Remove unnecessary legacy outlets/devices, lighting, wiring, and pathway infrastructure in their entirety.
Ensure remaining infrastructure is properly supported.
2. Install power distribution for new lighting, equipment racks, convenience receptacles, and mechanical equipment.
3. Install fire alarm devices and connect to the existing system.
4. Install new telecommunications secondary bonding busbar and bonding backbone conductor.
5. As new infrastructure is installed and ready for use, remove unnecessary legacy outlets/devices, wiring, and pathway infrastructure in their entirety.
E. Telecommunications & Electronic Security Tasks:
1. Remove unnecessary legacy outlets/devices, horizontal/backbone cabling, and pathway infrastructure in their entirety. Seal empty work area outlets with blank cover plates and ensure remaining infrastructure is properly supported.
2. Prioritize one new rack, followed by redundant racks as floor space becomes available.
3. Initiate new cameras, card readers, and other electronic security devices.
F. Fire Suppression Tasks:
1. Install sprinkler system components, including branch piping and sprinkler heads in completed ceilings.
G. Systems Testing and Commissioning Tasks:
1. Conduct infrastructure testing and labeling as new subsystem installations are completed and ensure ready for use. Conduct commissioning tasks as specified.
Fiber Backbone Pathways
Phase three primarily consists of conduit, duct bank, and other primary pathways between Telecommunications Spaces. Phases one, two, and three may run concurrently. Phase three may not restrict corridors or passage of food carts, patients, cleaning equipment, egress, or access to offices without prior coordination. Some work
BID DOCUMENTS
11-01-21
GENERAL REQUIREMENTS
01 00 00 -13 may require contractors to work outside of normal facility hours to reduce impacts.
A. Architectural Tasks:
1. Establish infection control, risk management, and safety measures in compliance with VA guidelines prior to initiating work. Maintain infection control, risk management, and safety measures as work progresses.
a. ICRA: Contractor to study and follow strictly the template set forth in the VHA Infection Control Risk Assessment for Construction, Renovation and Maintenance guidelines regarding the protocol and procedures required to do work on Data Center. This includes filling out all forms including in the template and obtaining approval prior to starting work.
b. PCRA: Compliance with the ICRA shall be done in conjunction with PCRA (Pre- construction Risk Assessment, for the activity which addresses other activity- related safety concerns (e.g. vibrations, noise) outside of the ICRA.
c. Contractor to also coordinate with VA COR on mobile temporary ICRA barriers and extent of the occupation of any agreed upon work areas. All offices, exits, utility and MEP spaces, restrooms shall be always kept accessible unless proper approvals were obtained from VA COR. Approvals are to be obtained by the following entities: VA Police, VA Fire Department or others as directed by VA COR. What needs to be done concurrently and what needs to be done sequentially including work limited to one area or one building or work involves the whole campus needs to be proposed, discussed and work plan approved by VA COR prior to any work starts.
2. Remove acoustic ceiling tile as necessary where utility work is required. Replace tiles at the end of each shift.
Replace tiles and grid if damaged during removal. For areas with plaster or hard gypsum ceiling, remove portions as required to install new utilities. Repair and paint to match original conditions upon completion of the work.
3. Remove infection control, risk management, and safety measures when work area construction is complete.
BID DOCUMENTS
11-01-21
GENERAL REQUIREMENTS
01 00 00 -14
Fiber Backbone (A) Cabling
Phase four primarily consists of fiber optic backbone cabling segment “A” between Telecommunications Spaces and the new Data Center. Phase four may only commence post completion of prior phases.
Proper coordination may allow Phase seven to occur with Phase four.
A. Telecommunications Tasks:
1. Install new permanent link backbone cabling between the new and existing Datacenter MDA locations, and between the new MDA and Demarc locations.
2. Install new permanent link backbone cabling from new and modified Telecommunications Rooms to the new Data Center.
B. Systems Testing and Commissioning Tasks:
1. Conduct infrastructure testing and labeling as new subsystem installations are completed and ensure ready for use. Conduct commissioning tasks as specified.
Phase Five: Data Center Core (A) Relocation
Phase five primarily consists of relocation and activation of network Core “A” equipment by others. The Contractor shall allow 90 days for Phase five activities.
Phase Six: Telecom Room Cutover
Phase six primarily consists of Telecommunications Room activation and work area outlet cabling cutover. Phase Six may only commence post completion of Phase five and shall include detailed time and location documents, prepared by the contractor, for access to offices and spaces to perform the work. The contractors may be restricted in some areas of the facility to limit impacts to services. Some work may be required to be performed outside normal facility hours to reduce impacts. Phase seven may run concurrently with Phase six in preparation of Phase eight.
A. Client Tasks:
1. Coordinate with end users to facilitate the work in their area.
2. Migrate users to new cabling infrastructure as work area outlets are ready for use.
B. Architectural Tasks:
1. Establish infection control, risk management, and safety measures in compliance with VA guidelines prior to initiating
BID DOCUMENTS
11-01-21
GENERAL REQUIREMENTS
01 00 00 -15 work. Maintain infection control, risk management, and safety measures as work progresses.
a. ICRA: Contractor to study and follow strictly the template set forth in the VHA Infection Control Risk Assessment for Construction, Renovation and Maintenance guidelines regarding the protocol and procedures required to do work on Data Center. This includes filling out all forms including in the template and obtaining approval prior to starting work.
b. PCRA: Compliance with the ICRA shall be done in conjunction with PCRA (Pre- construction Risk Assessment, for the activity which addresses other activity- related safety concerns (e.g. vibrations, noise) outside of the ICRA.
c. Contractor to also coordinate with VA COR on mobile temporary ICRA barriers and extent of the occupation of any agreed upon work areas. All offices, exits, utility and MEP spaces, restrooms shall be always kept accessible unless proper approvals were obtained from VA COR. Approvals are to be obtained by the following entities: VA Police, VA Fire Department or others as directed by VA COR. What needs to be done concurrently and what needs to be done sequentially including work limited to one area or one building or work involves the whole campus needs to be proposed, discussed and work plan approved by VA COR prior to any work starts.
C. Telecommunications Tasks:
1. Install new Horizontal work area outlet cabling from new/modified Telecommunications Rooms (TR) to individual workstations. Terminate cables in the TR, temporarily leaving cable service loops above finished ceilings at workstation locations.
2. Complete the cable installation at individual work area outlets as they become available, replacing legacy cables, and assist the Client with reestablishing Ethernet connection.
3. As new infrastructure is installed and ready for use, remove unnecessary legacy outlets/devices, horizontal cabling, and pathway infrastructure in their entirety.
BID DOCUMENTS
11-01-21
GENERAL REQUIREMENTS
01 00 00 -16
Seal empty/unused outlets with blank cover plates and ensure remaining infrastructure is properly supported.
D. Systems Testing and Commissioning Tasks:
1. Conduct infrastructure testing and labeling as new subsystem installations are completed and ensure ready for use. Conduct commissioning tasks as specified.
Phase Seven: Fiber Backbone (B) Cabling
Phase seven primarily consists of fiber optic backbone cabling segment “B” between Telecommunications Spaces and the new Data Center. Phase seven may run concurrently with Phase six in preparation of Phase eight. Proper coordination may allow Phase seven to occur with Phase four.
A. Telecommunications Tasks:
1. Install new permanent link backbone cabling between the new and existing Datacenter MDA locations, and between the new MDA and Demarc locations.
2. Install new permanent link backbone cabling from new and modified Telecommunications Rooms to the new Data Center.
B. Systems Testing and Commissioning Tasks:
1. Conduct infrastructure testing and labeling as new subsystem installations are completed and ensure ready for use. Conduct commissioning tasks as specified.
Phase Eight: Data Center Core (B) Relocation
Phase eight primarily consists of relocation and activation of network Core “B” equipment by others. The Contractor shall allow 90 days for Phase eight activities. All prior phases must be completed prior to Phase eight. Non-descript work that does not relay on systems operations may occur concurrently to Phase eight if not completed which may include but not limited to, site restoration, punch-list of non-critical items, submission, and review of as-builts, etc.
Phase Nine: Removal of Nonfunctional Legacy Infrastructure
As new infrastructure is installed and ready for use, remove unnecessary legacy outlets/devices, horizontal/backbone cabling, and pathway infrastructure in their entirety. Phase nine also includes any work to be performed in the existing data center including removal of entry ramp, elevated floor, new stairs to exit, etc. If
BID DOCUMENTS
11-01-21
GENERAL REQUIREMENTS
01 00 00 -17 not previously completed, all remaining work shall be completed during phase nine such as civil work to restore the site, punch list items, etc.
J. Contractor shall take all measures and provide all material necessary for protecting existing equipment and property in affected areas of construction against dust and debris, so that equipment and affected areas to be used in the Medical Centers operations will not be hindered. Contractor shall permit access to Department of Veterans
Affairs personnel and patients through other construction areas which serve as routes of access to such affected areas and equipment. These routes whether access or egress shall be isolated from the construction area by temporary partitions and have walking surfaces, lighting etc.
to facilitate patient and staff access. Coordinate alteration work in areas occupied by Department of Veterans Affairs so that Medical Center operations will continue during the construction period.
K. Construction Fence: Before construction operations begin, Contractor shall provide a chain link construction fence, 2.1m (seven feet) minimum height, around the construction area indicated on the drawings.
Provide gates as required for access with necessary hardware, including hasps and padlocks. Fasten fence fabric to terminal posts with tension bands and to line posts and top and bottom rails with tie wires spaced at maximum 375mm (15 inches). Bottom of fences shall extend to 25mm
(one inch) above grade. Remove the fence when directed by COR.
L. When a building and/or construction site is turned over to Contractor, Contractor shall accept entire responsibility including upkeep and maintenance therefore:
1. Contractor shall maintain a minimum temperature of 4 degrees C (40 degrees F) at all times, except as otherwise specified.
2. Contractor shall maintain in operating condition existing fire protection and alarm equipment. In connection with fire alarm equipment, Contractor shall make arrangements for pre-inspection of site with Fire Department or Company (Department of Veterans Affairs or municipal) whichever will be required to respond to an alarm from
Contractor's employee or watchman.
BID DOCUMENTS
11-01-21
GENERAL REQUIREMENTS
01 00 00 -18
M. Utilities Services: Always Maintain existing utility services for
Medical Center. Provide temporary facilities, labor, materials, equipment, connections, and utilities to assure uninterrupted services.
Where necessary to cut existing water, steam, gases, sewer or air pipes, or conduits, wires, cables, etc. of utility services or of fire protection systems and communications systems (including telephone), they shall be cut and capped at suitable places where shown; or, in absence of such indication, where directed by COR.
1. No utility service such as water, gas, steam, sewers or electricity, or fire protection systems and communications systems may be interrupted without prior approval of COR. Electrical work shall be accomplished with all affected circuits or equipment de-energized.
When an electrical outage cannot be accomplished, work on any energized circuits or equipment shall not commence without a detailed work plan, the Medical Center Director’s prior knowledge and written approval. Refer to specification Sections 26 05 11, REQUIREMENTS FOR ELECTRICAL INSTALLATIONS, 28 05 00, COMMON WORK
RESULTS FOR ELECTRONIC SAFETY AND SECURITY for additional requirements.
2. Contractor shall submit a request to interrupt any such services to
COR, in writing, 14 days in advance of proposed interruption.
Request shall state reason, date, exact time of, and approximate duration of such interruption.
3. Contractor will be advised (in writing) of approval of request, or of which other date and/or time such interruption will cause least inconvenience to operations of Medical Center. Interruption time approved by Medical Center may occur at other than Contractor's normal working hours.
4. Major interruptions of any system must be requested, in writing, at least 15 calendar days prior to the desired time and shall be performed as directed by the COR.
5. In case of a contract construction emergency, service will be interrupted on approval of COR. Such approval will be confirmed in writing as soon as practical.
BID DOCUMENTS
11-01-21
GENERAL REQUIREMENTS
01 00 00 -19
6. Whenever it is required that a connection fee be paid to a public utility provider for new permanent service to the construction project, for such items as water, sewer, electricity, gas or steam, payment of such fee shall be the responsibility of the Government and not the Contractor.
N. Abandoned Lines: All service lines such as wires, cables, conduits, ducts, pipes and the like, and their hangers or supports, shall be removed back to their source. Those which are indicated to be abandoned but are not required to be entirely removed, shall be sealed, capped or plugged at the main, branch or panel they originate from. The lines shall not be capped in finished areas, but shall be removed and sealed, capped or plugged in ceilings, within furred spaces, in unfinished areas, or within walls or partitions; so that they are completely behind the finished surfaces.
O. To minimize interference of construction activities with flow of
Medical Center traffic, comply with the following:
1. Keep roads, walks and entrances to grounds, to parking and to occupied areas of buildings clear of construction materials, debris and standing construction equipment and vehicles. Wherever excavation for new utility lines cross existing roads, at least one lane must be open to traffic at all times with approval.
2. Method and scheduling of required cutting, altering and removal of existing roads, walks and entrances must be approved by the COR.
P. Coordinate the work for this contract with other construction operations as directed by COR. This includes the scheduling of traffic and the use of roadways, as specified in Article, USE OF ROADWAYS.
1.7 ALTERATIONS
A. Survey: Before any work is started, the Contractor shall make a thorough survey with the COR and a representative of VA Supply Service, of buildings areas of buildings in which alterations occur and areas which are anticipated routes of access, and furnish a report, signed by both, to the Contracting Officer. This report shall list by rooms and spaces:
BID DOCUMENTS
11-01-21
GENERAL REQUIREMENTS
01 00 00 -20
1. Existing condition and types of resilient flooring, doors, windows, walls and other surfaces not required to be altered throughout affected areas of buildings.
2. Existence and conditions of items such as plumbing fixtures and accessories, electrical fixtures, equipment, venetian blinds, shades, etc., required by drawings to be either reused or relocated, or both.
3. Shall note any discrepancies between drawings and existing conditions at site.
4. Shall designate areas for working space, materials storage and routes of access to areas within buildings where alterations occur, and which have been agreed upon by Contractor and COR.
B. Any items required by drawings to be either reused or relocated or both, found during this survey to be nonexistent, or in opinion of COR and/or Supply Representative, to be in such condition that their use is impossible or impractical, shall be furnished and/or replaced by
Contractor with new items in accordance with specifications which will be furnished by Government. Provided the contract work is changed by reason of this subparagraph B, the contract will be modified accordingly, under provisions of clause entitled "DIFFERING SITE
CONDITIONS" (FAR 52.236-2) and "CHANGES" (FAR 52.243-4).
C. Re-Survey: Thirty days before expected partial or final inspection date, the Contractor and COR together shall make a thorough re-survey of the areas of buildings involved. They shall furnish a report on conditions then existing, of resilient flooring, doors, windows, walls and other surfaces as compared with conditions of same as noted in first condition survey report:
1. Re-survey report shall also list any damage caused by Contractor to such flooring and other surfaces, despite protection measures; and will form basis for determining extent of repair work required of
Contractor to restore damage caused by Contractor's workers in executing work of this contract.
D. Protection: Provide the following protective measures:
BID DOCUMENTS
11-01-21
GENERAL REQUIREMENTS
01 00 00 -21
1. Wherever existing roof surfaces are disturbed they shall be protected against water infiltration. In case of leaks, they shall be repaired immediately upon discovery.
2. Temporary protection against damage for portions of existing structures and grounds where work is to be done, materials handled, and equipment moved and/or relocated.
3. Protection of interior of existing structures at all times, from damage, dust and weather inclemency. Wherever work is performed, floor surfaces that are to remain in place shall be adequately protected prior to starting work, and this protection shall be maintained intact until all work in the area is completed.
1.8 DISPOSAL AND RETENTION
A. Materials and equipment accruing from work removed and from demolition of buildings or structures, or parts thereof, shall be disposed of as follows:
1. Reserved items which are to remain property of the Government are identified by attached tags as items to be stored as indicated on drawings. Items that remain property of the Government shall be removed or dislodged from present locations in such a manner as to prevent damage which would be detrimental to re-installation and reuse. Store such items where directed by COR.
2. Items not reserved shall become property of the Contractor and be removed by Contractor from Medical Center.
3. Items of portable equipment and furnishings located in rooms and spaces in which work is to be done under this contract shall remain the property of the Government.